Summary of Special Provisions for Utility Extension Program 07
This document contains the special provisions for a water and wastewater utility extension project administered by the City of Midland, Texas. The project scope encompasses removal, replacement, relocation, and installation of water improvements, wastewater improvements, and associated utility structures throughout the contract term. Work includes mobilization, excavation, pavement removal and repair, sidewalk repair, concrete sealing, erosion control, traffic control, and coordination with OSHA, franchise utilities, and One Call (Texas 811) notifications. The contract is structured as a master program with individual work orders assigned throughout the project period, with the initial contract term set to expire on September 30, 2027. The contract may be renewed for up to two additional one-year terms by mutual written agreement between the City and Contractor. The project is not to exceed $2,000,000.00 total, with the same spending limit applying to each renewal term should they be exercised.
Bidders must submit complete proposals with all bid items filled out and include documentation proving possession of active Water Operator D licenses and either Wastewater D or Class 1 Collections licenses, which must be maintained throughout the contract. Payment is issued only upon 100% completion of work orders and inspection by City personnel, with payment made for materials installed rather than delivered. The Contractor bears responsibility for construction staking, survey work, all required material and workmanship testing, erosion control measures, waste disposal, traffic control plan submissions and maintenance, and maintaining continuous access and utility service to adjacent properties. Special requirements include specific pressure and testing protocols for water and wastewater systems, restrictions on concrete placement temperature ranges, pavement mixture standards, and strict compliance with OSHA trenching requirements and Texas Manual on Uniform Traffic Control Devices standards.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP 1
SPECIAL PROVISIONS
ATTENTION: All Bidders are directed to pay special attention to the NOTICE TO BIDDERS section of the bid packet. Bidders have sole responsibility for complying with the current bid process requirements. Bidders also have sole responsibility for verifying that any bid submitted is completed correctly and includes all of the required documentation, including addendums.
1. SCOPE OF WORK:
Included in this Utility Extension Program 07 will be the removal, replacement, relocation, placement, and installation of existing and proposed water improvements, wastewater improvements, and other assorted utility structures and appurtenances including all necessary mobilization, saw-cutting, pavement removal, excavation, embankment, embedment, backfill, compaction, form work, pavement repair, sidewalk repair, concrete joint sealing, erosion control, traffic control, utility cover adjustments, as well as coordination with City of Midland staff and organizations such as OSHA, franchise utilities, etc. as needed, One Call (Texas 811) notifications for pending work, notifications to adjacent property owners as directed by City of Midland Staff, and all other work to be performed as outlined in the Construction Drawings and Specifications, which are necessary to satisfactorily complete the work.
The Owner reserves the right to abandon, without obligation to the Contractor, any part of the program, or the entire program, at any time before the Contractor begins any construction work authorized by the Owner. This applies to the individual projects assigned throughout the course of this program, and does not refer to the start of work for the program as a whole.
Standard Specifications for Construction of the City of Midland will govern all construction, except as modified by these Special Provisions.
2. ORDER OF PRECEDENCE:
The Special Provisions take precedence over the General Conditions in this bid packet anywhere these two sections are not in agreement.
The Special Provisions take precedence over the City of Midland Specifications in this bid packet anywhere these two sections are not in agreement.
The Contractor is to bid the quantities in the Proposal section of the bid packet even if there is a discrepancy between the Proposal quantities and those noted or measured in the construction drawing set.
In the construction drawing set any written or noted dimension takes precedence over dimensions measured based on the drawing scale unless otherwise directed by the Engineer.
Any changes or revisions made as part of an Addendum for this project take precedence over the original bid packet and construction drawing set where the documents are in conflict.
If a Bidder submits both a hard-copy bid submittal and a digital bid submittal, the digital bid submittal will be considered the official bid for this project and the hard-copy submittal will not be considered as a legitimate bid submittal for this project.
SP 2
If a Bidder submits a digital bid for this project, the information entered directly into the City of Midland’s online procurement portal will take precedence over any attached documents even if there is a discrepancy between the directly entered information and the attachment documents.
3. EXAMINATION OF SITE:
Prospective bidders are to make a careful examination of the entire site of the project and are to make such explorations as may be necessary to determine the subsoil and/or water conditions to be encountered;
improvements and obstructions which may be encountered; methods of providing ingress-egress to private as well as public property; methods of handling traffic during construction and maintenance of the entire project as well as any section thereof, protection of all existing structures both above and below ground; and how the plans fit the proposed project and especially if any discrepancies exist.
4. PAYMENT:
The Contractor will receive full payment from the Owner for each work order when the work order is 100% complete. Payment will not be made prior to a work order being 100% complete, and payment will be made for material installed, not for material delivery. This will apply to all Bid Items.
Only one (1) Open Trench Depth bid item will apply at a time to any given length of open trench excavation.
These bid items are not stacked when determining payment for open trench excavation.
5. SAFETY REQUIREMENTS:
It is the responsibility of the Contractor to follow and comply at all times with Occupational Safety and Health Administration (OSHA) and all other applicable safety regulations and requirements throughout the course of the project’s work. The City of Midland reserves the right to require additional safety measures on the project site at any time if they are needed in the opinion of the Engineer for the safety of the work crews or public.
6. SAFETY RESTRICTIONS – WORK NEAR HIGH VOLTAGE LINES:
The following procedure will be followed regarding the subject item on this contract:
1) A warning sign painted yellow with black letters that are legible at twelve feet shall be placed inside and outside vehicles such as cranes, derricks, power shovels, drilling rigs, pile drivers, hoisting equipment or similar apparatus. The warning sign shall read as follows:
“WARNING – UNLAWFUL TO OPERATE THIS EQUIPMENT WITHIN SIX FEET OF HIGH VOLTAGE LINES”
2) Equipment that may be operated within ten feet of high voltage lines shall have an insulation cage-type of guard about the boom or arm, except back hoes or dippers, and insulator links on the lift hook connections.
3) When necessary to work within six feet of high voltage electric lines, notification shall be given to the power company of who will erect temporary mechanical barriers, de-energize the line, or raise or lower the line. The notifying department shall maintain an accurate log of all such calls to the Power Company, and shall record action taken in each case.
SP 3
4) The Contractor is required to make arrangements with the Power Company for the temporary relocation or raising of high voltage lines at the Contractor’s sole cost and expense.
5) No person shall work within six feet of a high voltage line without protection having been taken as outlined in Paragraph (3).
7. TRAFFIC CONTROL:
All proposed traffic control shall be approved by the City where applicable. All traffic control plans must be submitted to and approved by the Construction Manager no less than two (2) business days prior to starting the construction work. Traffic control for each phase of work must be approved prior to starting that work.
Generic traffic control plans or typical details may be submitted for shoulder work on any class of roadway, or for work on local or collector streets that does not require the closure of any travel lanes (i.e., all lanes are open to traffic on striped roadways, or adequate width remains available for two-way traffic on unstriped roadways).
Once a generic traffic control plan or typical detail for a certain type of setup has been approved one time, the Contractor shall only be responsible for notifying the Construction Manager of the location, type of setup, and dates on which they intend to utilize the pre-approved traffic control for the duration of the contract. No additional plan submittals will be required in these cases, except that the City reserves the right to suspend this exception at its discretion. For any work not fitting the above exception, or in the event that the exception is suspended by the City, a site-specific traffic control plan will be required for each work location and time period.
1. All temporary traffic control shall be in general conformance with the Texas Manual on Uniform Traffic Control Devices (TMUTCD) (latest edition as adopted by the Texas Department of Transportation), except as specifically directed by the City Engineer or City Traffic Engineer.
2. All temporary traffic control shall be designed, installed, and maintained by competent and qualified personnel with adequate experience in traffic control.
3. All temporary traffic control involving multiple lane closures or traffic shifts, full closures of collector or arterial streets, traffic control extending through a railroad crossing, or any setup reasonably determined by the City to be “complex”, shall be implemented only by a contractor with specific experience and expertise in the field of traffic control (i.e., a qualified “barricade company”).
4. A Traffic Control Plan (TCP) shall be submitted to the Engineering Services Department, Construction Manager, in advance of any work in the right-of-way that impacts traffic. No work shall occur until an approved TCP has been returned to the Contractor.
5. A copy of the approved TCP shall be kept in the possession of the person responsible for supervising the traffic control at all times while working in the right-of-way. The approved TCP shall be presented to City staff or law enforcement upon demand at any time.
6. Depending on site conditions and the nature of the work, temporary traffic control may be approved by the City for either of the following:
a. All Times – All traffic control, including closures, may remain in place 24 hours per day until expiration of the approved TCP.
b. Off-Peak Only – Lane or road closures are NOT permitted from 6:00-9:00 AM and 4:00-7:00 PM on weekdays (Monday through Friday). Other traffic control not related to lane or road closures may remain in place 24 hours per day until expiration of the approved TCP.
SP 4
7. The contractor setting the temporary traffic control shall be responsible for the maintenance and upkeep of all signs, barricades, and other devices, at all times.
a. All temporary traffic control setups shall be maintained at least one time per day, including weekends and holidays.
b. More frequent maintenance shall be performed as needed, with particular emphasis to following up after severe weather events or during times of high winds.
c. Maintenance shall include:
i. Verifying and correcting the location and orientation of all signs, barricades, and other devices;
ii. Keeping signs and reflective areas of barricades and other devices clean and free of dirt buildup so as to maintain appropriate visibility and legibility; and
iii. Ensuring the proper location, orientation, and operation of arrow boards or message boards, if present.
8. Arrow boards shall be required for lane closures under the following conditions:
a. On roadways with a posted speed limit of 55 MPH or greater, for closures lasting more than one
(1) hour;
b. On roadways with a posted speed limit of 45 MPH or greater, for closures lasting more than four
(4) hours;
c. On any roadway if lanes will remain open to traffic travelling in the same direction on both sides of a closed lane during any overnight hours (from 7:00 PM to 6:00 AM); and
At other times as shown on the approved TCP, or as otherwise directed by the City.
8. COMPLETION OF WORK:
Any work assigned to the Contractor is to be considered part of a work order, and completion of the assigned work occurs when the work order is 100% complete. A work order may only be completed after all utility, paving, sidewalk, erosion control, traffic control, and site cleanup work has been completed. All work must be inspected by the City’s Inspector or Engineer before being accepted, and the City’s inspector or Engineer and the Contractor must sign or initialize the finalized work order before it is considered 100% complete.
Work orders that are considered 100% complete and are signed or initialized are final and no subsequent changes, additional, reductions, or corrections will be made to the quantities listed on the work orders. The only exception that may occur will be at the sole discretion of the Engineer, who may add quantities to the work order for work that was performed but not accounted for in the original signed or initialized work order.
Errors in the unit prices used to calculate totals for work orders may be corrected by the City’s Inspector or Engineer after work orders are signed and initialized so long as no change is made to the original work order quantities – OR – the Contractor may request that a new work order with the correct unit prices be provided for fresh signatures or initials. Quantities for work orders will remain fixed after the original work order is signed or initialized regardless of whether or not corrections are made to the unit prices and returned for a second round of signatures or initials, except as stated in the previous paragraph.
SP 5
9. DETOURS:
The Contractor is to prosecute his work in such a manner as to create a minimum of interruption to traffic and pedestrian facilities and to the flow of vehicular and pedestrian traffic within the project area.
10. PROPERTY AND RIGHT-OF-WAY ACCESS:
Access to adjacent properties must be maintained at all times unless otherwise directed by the Engineer. If the contractor will not be working in an area for a period of one week or more, special care is to be taken to address any unsafe conditions such as excavated areas or obstructions outside the worked area that could be tripping hazards, etc. Contractor must notify affected properties no less than two (2) business days prior to any planned access interruptions.
Contractor must coordinate with the City of Midland regarding any planned access interruptions for public Right-of-Way, or to restore any public infrastructure damaged during construction activities.
Steel plates or equivalent means must be used as needed to enable vehicle access across a trench that would otherwise prevent access to a private property unless construction work is actively taking place at this location.
These temporary measures are to be kept in place any time construction activity is not actively taking place, or until the trench pavement repair is complete.
11. PROPERTY AND RIGHT-OF-WAY SERVICE:
Service to adjacent properties must be maintained at all times unless otherwise directed by the Engineer.
Such services include water, wastewater, fiber, cable, electric, and gas. Contractor must notify affected properties no less than two (2) business days prior to any planned service interruption.
Contractor must coordinate with the City of Midland regarding any planned service interruptions for public water or wastewater, or to restore any public infrastructure damaged during construction activities.
Contractor must coordinate with private service providers for any necessary service interruptions to their infrastructure or to restore service to their infrastructure in the event that a private service is disrupted, damaged, etc. during construction.
12. CONSTRUCTION SCHEDULE:
It is the responsibility of the Contractor to furnish the Construction Engineer, prior to construction, with a schedule outlining the anticipated time each phase of construction will begin and be completed, including sufficient time being allowed for clean-up.
13. CONSTRUCTION STAKING:
The Contractor has sole responsibility for construction staking.
It is the responsibility of the Contractor to provide the project construction staking at fifty-foot (50’) intervals along the entire length of the project as well as at such control points as the Contractor deems necessary for proper execution of the work. Construction staking is to include grading and cuts as well as horizontal alignments and construction control points. Cut sheets are to be provided to the Engineer by the Contractor for review and approval.
SP 6
14. SURVEY:
The Contractor has sole responsibility for construction survey.
The Contractor is to provide GPS survey shots for all meters replaced to the City of Midland with each completed work order submittal. Survey data is to be shot in Texas Central Zone with 1983 NAD at 1.0' accuracy or better.
Survey data is to be provided in Excel csv. file format with all rounding functions turned off.
15. CONSTRUCTION MATERIALS:
The Contractor is to only provide new materials for permanent installation in any and all parts of this project, and all such materials must comply with the General Conditions, the Bid Packet Specifications, and all applicable City of Midland Standards and Specifications.
For this project, the Standard Specification is hereby amended to read:
Qualifications of Material Sources – Contractor is only to use pavement mixtures that have a proven record of acceptance by the City of Midland, or another Texas municipality, or have a proven record of meeting similar standards for state highway projects.
Concrete is only to be placed when the ambient temperature is between 40 degrees and 95 degrees Fahrenheit and the ambient temperature in the shade is higher than 40 degrees Fahrenheit or is 40 degrees Fahrenheit and rising.
All concrete pavement joints are to be sealed with Texas Department of Transportation (TxDOT) DMS-6310 SL-2 sealant, an American Society for Testing and Materials (ASTM) D 1190 Hot-Applied Single Component Joint Sealant, or a City of Midland approved equal. This will not apply to curb or sidewalk joints.
No construction materials are to be placed or installed during rain events unless they are necessary to resolve an emergency situation or to facilitate the project site erosion control measures.
16. EROSION CONTROL:
Erosion control is the responsibility of the Contractor and erosion control measures are to be implemented so as to prevent sediment erosion from wind, rain, and other elements from the project site. Should the Owner feel that supplementary erosion control measures are required in addition to those implemented by the Contractor then the Contractor will include additional erosion control measures within reason to the Owner’s satisfaction and/or TCEQ requirements.
Reasonable erosion control measures include but are not limited to: construction entrance(s), concrete washout(s), perimeter silt fence or fiber wattle, rock rip-rap dams for concentrated runoff control, gutter and inlet protection measures such as sand bags, and stabilization of the construction area surfaces when construction work is not actively occurring by means of vegetative cover or seeded erosion control blankets.
Supplemental erosion control measures are ancillary to the project and not paid as a separate item, unless otherwise noted in the Proposal or Pay Notes.
Site cleanup work is to be done for this project as soon as possible as per the General Conditions and will be ancillary to the project and not paid as a separate item, unless otherwise noted in the Proposal or Pay Notes.
SP 7
Site cleanup is to take place throughout the project’s construction as needed to maintain a clean and professional looking work area. No more than three calendar days are to elapse after completion of construction before the final roadway and right-of-way cleanup has been completed to the satisfaction of the Engineer.
17. WASTE MATERIAL:
Excess material from excavation and other construction or demolition activity will become the property of the Contractor. Excess excavation will be disposed of at locations secured by the Contractor and if necessary, approved by the Engineer. No material is to be placed on private property or City property without the approval of the Engineer and the property owner. Removal of excess material, excavation, and waste material are ancillary to the project and not paid as a separate item, unless otherwise noted in the Proposal or Pay Notes.
Excess concrete material must be washed out in a concrete washout within the project’s job site area, or else any and all other concrete material washout must occur away from the job site area in the Contractor’s or concrete Supplier’s own operation yards or properties. Under no circumstances are concrete trucks allowed to washout in any job site excavations, channels, public right-of-way, or on private property.
Existing fire hydrants and existing water meters indicated for removal as part of the project are to be returned to the City of Midland by the Contractor and remain City property. These are ancillary to the project and will not be paid as separate items.
18. TESTING:
It is the Contractor’s responsibility to perform all required testing for any and all materials and workmanship performed or installed as part of the project’s work. The cost of all such testing is to be borne solely by the Contractor unless required by the Engineer for work or materials that had previously been tested and approved and had not experienced any change in condition since that time as a result of the Contractor’s work or actions;
or unless additional testing outside of the project scope is performed at the request of the Engineer.
Required testing includes:
Concrete Pavement For Trench Repair – A Slump Test is required only if directed by the Engineer for pavement patches that are equal to or greater than 50 cubic yards (roughly equal to an 8’ wide by 340’ long by 6” thick pavement section). The slump test is to be performed once for every cylinder set (3 cylinders) taken, and no less than 1 cylinder set per day is to be taken for testing when concrete is placed. Test results are to be given to the engineer upon completion of each test. There will be no testing for curb, ramps, and sidewalks.
Asphalt Hot-Mix Pavement For Trench Repair – A Nuclear Gauge Density Test is required only if directed by the Engineer for pavement patches that are equal to or greater than 620 square yards (roughly equal to an 8’ wide by 700’ long pavement section). The laboratory density limits will be a minimum limit of 96%, a maximum limit of 98%, and an optimum limit of 97%. The acceptable field density limit will be a minimum limit of 93%, a maximum limit of 98%, and an optimum limit of 95%. Test results are to be given to the Engineer upon completion of each test.
Water Pipes & Fittings – Perform Pressure Testing and Bacterial Testing (Bac T)/Chlorination testing for all water mains and fire hydrants.
• Pressure Test – Perform test as described in the City of Midland Water Line Specifications, PART 10, Hydrostatic Tests, with the sole difference being that a continuous pressure of 180 pounds per square
SP 8
inch (psi) must be maintained over a continuous period of not less than four (4) hours rather than eight
(8) hours. The acceptable field pressure limit will be a minimum 180 psi and a maximum 185 psi. A 2-3 psi drop in the measured pipe pressure during the first two (2) hour period will be acceptable to account for the compression of air within the pipe so long as the minimum and maximum allowed field pressure limits are not exceeded. There can be no variation in the measured pipe pressure during the last two (2) hours of the pressure test.
• Bac T/Chlorination Testing – Perform disinfection and test as described in the City of Midland Water Line Specifications, Part 9, Disinfection Of Pipe Lines.
Wastewater Gravity Pipes/Manholes – Perform air testing, mandrel testing, hydrostatic testing, and closed circuit televising (CCTV) for all wastewater mains and manholes.
• Air Test – Perform test as described in the City of Midland Gravity Flow Pipe Sewers And Fittings For Wastewater And Storm Water, Part 3.14, Testing Gravity Mains And Manholes.
• Mandrel Test – A successful mandrel pull is required for all wastewater pipes installed.
• Hydrostatic Testing – Perform test as described in the City of Midland Gravity Flow Pipe Sewers And Fittings For Wastewater And Stormwater Specifications, Part 3.14, Hydrostatic Testing.
• Closed Circuit Televising (CCTV) – Provide CCTV video of the wastewater mains for the full length of the wastewater system installed, including through all wastewater structures. CCTV video is not required for wastewater laterals unless directed by the Engineer.
Force Mains & Fittings (Wastewater & Storm Drain) – Perform pressure testing for all wastewater and storm drain force mains.
• Pressure Test – Perform test as described in the City of Midland Water Line Specifications, PART 10, Hydrostatic Tests, with the sole difference being that a continuous pressure of 180 pounds per square inch (psi) must be maintained over a continuous period of not less than four (4) hours rather than eight
(8) hours. The acceptable field pressure limit will be a minimum 180 psi and a maximum 185 psi. A 2-3 psi drop in the measured pipe pressure during the first two (2) hour period will be acceptable to account for the compression of air within the pipe so long as the minimum and maximum allowed field pressure limits are not exceeded. There can be no variation in the measured pipe pressure during the last two (2) hours of the pressure test.
19. COMPLIANCE:
The said Contractor further agrees to comply with all applicable provisions of the laws and building and construction codes of the City of Midland and the State of Texas, and with any regulations for the protection of workers which may be promulgated by the Government, and will protect such work with all necessary lights, barriers, safeguards, and warnings as provided for in said specifications and the Ordinance regulations.
Contractor is to comply with all acceptable industry standards for means, methods, and details of work to be performed, as well as with any specific requirements of the City of Midland.
Contractor is to comply with any specific order of construction as directed by the City of Midland, but is otherwise free to conduct the work in the order which the Contractor sees fit.
SP 9
Contractor agrees to comply with any specific direction or requirement of the City of Midland for the construction of this project, but is otherwise free to perform the work in its own way.
20. PERSONNEL:
It is the Contractor’s responsibility to have a supervising representative of the Contractor on the construction site any time that construction work is taking place. The Contractor’s representative must be on the Contractor’s direct payroll. Sub-contractors or paid consultants will not satisfy this requirement.
It is also the Contractor’s responsibility to provide the City with a reliable contact for issue escalation coordination. Such contacts would include the Contractor’s site foreman, the Contractor’s construction project manager, etc.
21. INTENT OF THE PROPOSAL:
The intent of the proposal is to determine the lowest responsible bidder based on the total of the quantities and unit prices. Once the lowest responsible bidder is selected, the project will be awarded based on the terms and requirements of the contract outlined in the bid packet and in an amount not to exceed $2,000,000.00. The initial term of the contract will expire on September 30, 2027.
22. RENEWAL OF CONTRACT:
If the Owner and Contractor agree in writing, the contract may be renewed for up to two (2) additional one (1) year terms (for an amount not to exceed $2,000,000.00 per term).
All renewal time periods will begin on October 1st of the calendar year the renewal is agreed to and will end on September 30th of the following calendar year.
If the Owner and Contractor do not agree to renew the existing contract then the contract will expire at the end of the term for either the first award period or, if applicable, the first period of contract renewal.
23. WARRANTY PERIOD:
There is no warranty period for this program as all work performed is to be subject to City inspection prior to acceptance. Any work performed without City inspection is subject to re-excavation for inspection, removal, replacement, reinstallation, or any other work deemed necessary by the City Inspector or Engineer to address the failure by the Contractor to have the required inspection performed at the Contractor’s sole expense.
24. BID PACKET COMPLETION ITEMS OF NOTE:
Bidders must be willing to sign the Contract as is if a bid is submitted. Revisions, alterations, deletions, additions, or any other changes of any kind by the bidder to the bid packet or other bid documents (such as the construction drawing set, addendums, etc.) will result in the bid submittal being deemed ‘Non-Responsive’ and the bid will not be accepted.
Bidders are reminded to make sure that the Conflict of Interest forms are completed if applicable before submitting a bid.
SP 10
All bid items in the Proposal section must be completed for a bid submittal to be considered complete. Any bid item left blank, only partially completed, or that the bidder indicates they chose to not provide a bid for will be considered incomplete, and the entire bid submittal will also be deemed incomplete, the bid submittal will be deemed ‘Non-Responsive’, and the bid will not be accepted. Bidders bear sole responsibility for making sure that the Proposal is complete and in accordance with the instructions provided to bidders in the bid packet.
All acknowledgement forms for all addendums that are issued during the bid process for this project must be filled out and be included with any bid submittal for that bid submittal to be considered complete. Any bid submittal lacking these completed addendum acknowledgement forms will be deemed ‘Non-Responsive’ and the bid will not be accepted. Bidders bear sole responsibility for making sure that they have obtained all addendums issued prior to submitting their bid.
Bidders must provide documentation as part of the bid packet submittal proving that they possess active licenses that are equivalent to or a higher class than a Water Operator D license and also equivalent to or a higher class than either a Wastewater D license or a Class 1 Collections license, and the Contractor must maintain both of these active licenses for the entirety of the project. Any bid submittal that does not include this required documentation for both licenses will be rejected as a non-responsive bid. If a Contractor allows either or both of the required licenses to lapse at any time during the course of the project then all work under this project will be halted and the City of Midland will have sole discretion to either allow the Contractor to renew both of their active licenses before resuming work or to end the project immediately.
All trenching and excavation operations are to comply with current OSHA requirements at all times, including 29 CFR Part 1926 Subpart P. Contractor is to provide proper trench protection systems, including shoring, shielding, or sloping as required by soil conditions and trench depth.
All open trenches, excavations, and work zones adjacent to traffic or pedestrian areas are to be protected with approved crashworthy barricades, channelizing devices, and traffic control devices in accordance with applicable current Texas MUTCD and TxDOT standards. Contractor is to maintain safe access and egress at all times unless otherwise approved by the City. Where steel plates or similar trench safety measures are utilized for open trenching, crashworthy barricades, channeling devices, and traffic control devices are still required unless otherwise approved by the City.
| Special Provisions |
| 1. Scope of work: |
| 2. Order of precedence: |
| 3. examination of site: |
| 4. payment: |
| 5. SAFETY REQUIREMENTS: |
| 6. Safety restrictions – work near high voltage lines: |
| 7. Traffic control: |
| 8. Completion of work: |
| 9. detours: |
| 10. property and right-of-way access: |
| 11. PROPERTY AND RIGHT-OF-WAY SERVICE: |
| Service to adjacent properties must be maintained at all times unless otherwise directed by the Engineer. Such services include water, wastewater, fiber, cable, electric, and gas. Contractor must notify affected properties no less than two (2) busin... |
| Contractor must coordinate with the City of Midland regarding any planned service interruptions for public water or wastewater, or to restore any public infrastructure damaged during construction activities. |
| 12. Construction schedule: |
| 13. CONSTRUCTION STAKING: |
| 14. survey: |
| 15. Construction Materials: |
| 16. EROSION CONTROL: |
| 17. Waste material: |
| 18. TESTING: |
| 19. Compliance: |
| 20. PERSONNEL: |
| 21. INTENT OF THE PROPOSAL: |
| 22. RENEWAL OF CONTRACT: |
| 23. WARRANTY PERIOD: |
| 24. Bid Packet Completion Items of Note: |