This Basis of Estimates document is prepared for Broward County, Florida's Transportation Department and provides a comprehensive unit cost framework for the Transit Bus Stop ADA Improvements project funded through the Federal Transit Administration (FTA). The project involves an open-end contract for furnishing labor, materials, equipment, and services required to install Americans with Disabilities Act compliant landing pads and transit amenities at multiple bus stop sites throughout Broward County. The scope of work encompasses installation of transit amenities including benches, trash cans, and bike racks, along with construction of sidewalks, bus stop landing areas, curbs, and related site improvements. The document establishes 29 line items with standardized unit definitions and detailed descriptions to guide cost estimation for various construction activities, including clearing and grubbing, concrete work, asphalt paving, detectable warning installations, sodding, sign relocation, and labor supplementation.

The basis of estimates utilizes standard FDOT (Florida Department of Transportation) item numbers and commodity codes to ensure consistency and facilitate pricing across the project locations. Compensation is structured on a unit-price basis, with payments made according to measurable quantities of work completed, such as linear feet for curb and gutter installation, square yards for concrete sidewalks and clearing work, cubic yards for excavation and fill, each for equipment and amenity installations, and hours for additional labor supplementation. Key cost considerations include mobilization and maintenance of traffic requirements specific to both general work zones and bus bay closures, which are critical for minimizing public inconvenience during construction. The contract requires county surtax funding, adherence to county and state licensing requirements, compliance with FTA regulations, and bonding as specified in the full solicitation documents.

View the file

Other files

File Type Posted
17-Specifications and Requirements - TRN2132943B1.pdf PDF
8-FTA Buy America Certification Iron, Steel, Non-Rolling Stock.pdf PDF
18-Additional Technical Specifications - TRN2132943B1.pdf PDF
16-Criminal History Screening Practices Certification.docx DOCX document
15-Insurance Requirement - TRN2132943B1.pdf PDF
21-Summary of Vendor Rights for Broward County Competitive Solicitations.docx DOCX document
3-Subcontractors-Subconsultants-Suppliers Requirement.docx DOCX document
23-Special Instructions to Vendors - TRN2132943B1.pdf PDF
22-FTA Funding Supplement 2026 - TRN2132943B1.pdf PDF
11-Vendor Questionnaire - Quotes and Bids.docx DOCX document
1-Anti-Human Trafficking Affidavit.docx DOCX document
5-Surtax-Funded Agreement Contract Terms.docx DOCX document
7-FTA Funding Supplement Acknowledgement.pdf PDF
9-FTA Restrictions on Lobbying Certification (Loan Guarantees and Loan Insurance).pdf PDF
12-Bid Bonds, Performance and Payment Bonds, and Surety Qualification Requirements.pdf PDF
4-Litigation History.docx DOCX document
10-FTA Restrictions on Lobbying Certification.pdf PDF
2-Insurance Requirements - Quotes Bids.docx DOCX document
14-Wage Determination - Construction 2026 - TRN2132943B1.pdf PDF
19-Construction Activities - TRN2132943B1.pdf PDF
20-General Conditions - Quotes Bids.docx DOCX document
6-FTA Government-Wide Debarment Certification.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASIS OF ESTIMATES

TRANSIT BUS STOP ADA IMPROVEMENTS (FTA)

A. UNIT DEFINITIONS

• AS Assembly

• CY Cubic Yard

• EA Each

• HR Hour

• LB Pound

• LF Lump Sum

• SF Square Foot

• SY Square Yard

• TN Ton

B. ITEM DESCRIPTIONS/DETAILS

Item No.

FDOT Item No. Commodity Code Description Unit

1 104 12 STAKED SILT FENCE, TYPE III LF

Installation per plans or per County direction as needed.

2 110 1 CLEARING & GRUBBING SY

Includes removal of top soil and all vegetation stems/trunks smaller than 2” diameter.

Limits per plans.

3 110 4 10 REMOVAL OF EXISTING CONCRETE PAVEMENT SY

Includes concrete pavement, concrete sidewalks, slope pavement, ditch pavement, curb and gutter, and asphalt surfaces.

4 120 1 REGULAR EXCAVATION CY

Includes all excavation as required to complete work except sign foundations.

5 120 6 EMBANKMENT (FILL) CY

Includes material delivered to the site for proper grading per plans. Does not include limerock used for base courses.

6 160 4 STABILIZED SUBBASE SY

Included stabilizing areas (per plan) to provide a firm and unyielding subgrade.

Stabilizing material shall be existing material.

7 210 1 1 REWORKING LIMEROCK BASE, 6” SY

Includes reworking the existing rock base per the plans. Includes compaction to density per plans and specifications.

8 210 2 LIMEROCK (FURNISHING,SPREADING, SHAPING, AND COMPACTING) CY

Includes the delivery, placement, grading, shaping, and compacting of new lime rock material. Also includes material proctor and density testing per plans and specifications.

9 339 1 MISCELLANEOUS ASPHALT PAVEMENT TN

Consists of construction of asphalt pavement in areas which will not be subjected to vehicular traffic, such as pavement under guardrail, bicycle paths, median pavement, sidewalks, etc.

Item No. FDOT Item No. Commodity Code Description Unit

10 400 1 CONCRETE CLASS I, RETAINING WALLS CY

Includes formwork, and material, delivery, and placement of concrete for retaining walls, culverts, and pipe end walls per plans. Item not to be used for bus stop shelter foundations. Steel reinforcement to be paid under Item #11.

11 425 6 VALVE BOXES, ADJUST EA

Consists of changing the vertical placement of an existing box so that it will conform to the finished grade as designated in the plans. Existing box to be reused.

12 515 1 1 PIPE HANDRAIL - GUIDERAIL, STEEL LF

To be used as detailed on FDOT Standard Plans 515-080. Includes manufacturing, installation, and hardware.

13 520 1 10 ADDITION OF CURB AND GUTTER TYPE "F" LF

Includes construction of concrete curb, and all forming, contraction joint forming, expansion joint construction, finishing, and backfilling and compaction. Length measured along face of curb.

14 520 2 4 ADDITION OF CURB TYPE "D" LF

Includes construction of concrete curb, and all forming, contraction joint forming, expansion joint construction, finishing, and backfilling and compaction. Length measured along face of curb.

15 522 2 CONCRETE, MATERIAL AND INSTALLATION (6”) THICK SY

Consists of construction of plain sidewalk. Includes all materials, joint forming (or sawing), placing, and finishing. Specifically excludes excavation and steel reinforcement.

16 527 2 DETECTABLE WARNING – NEW CONSTRUCTION PRECAST TILE (Furnish & Install) SF

This pay item is to be used for Detectable Warnings applied to walking surfaces, used in coordination with Index 522-002. For standard size detectable warnings, use the quantity shown on the Index. For all custom sizes, estimate the quantity to the nearest square foot.

17 570 1 2 SODDING (Typical Bahia or St. Augustine) SY

Includes rough grading, debris removal, materials, installation, and watering until established. Watering only for non-irrigated installations.

18 700 20 11 SINGLE POST SIGN, RELOCATE AS

Includes removal of existing sign and foundation, and reinstallation of sign and foundation as shown in plans. Also includes restoration of initial location.

19 700 20 40 SINGLE POST SIGN, REMOVE AS

Includes removal of existing sign and foundation, and restoration of site.

20 101 1 MOBILIZATION (CONSTRUCTION ONLY) Per Work Order

Consists of work and operations necessary to begin work on a project. Includes moving in equipment and personnel, establishing temporary offices, safety equipment and sanitary facilities, permitting with local agencies (except actual permit fees), preconstruction meetings. Only one Mobilization per Work Order.

Item No.

FDOT Item No. Commodity Code Description Unit

21 102 1 MAINTENANCE OF TRAFFIC (Refer to SPECIFICATIONS AND REQUIREMENTS) SITE

Includes all items required to safely maintain pedestrian, bicycle, and vehicular traffic throughout a transportation work zone with minimal inconvenience to the public. Item is specific to the need to close lanes adjacent to the work zones.

22 102 1 MAINTENANCE OF TRAFFIC - BUS BAY

(Refer to SPECIFICATIONS AND REQUIREMENTS) SITE

Includes all items required to safely maintain pedestrian, bicycle, and vehicular traffic throughout a transportation work zone with minimal inconvenience to the public. Item is specific to the need to close the bus bay associated with the impacted job site.

23 BOLTED BIKE RACK INSTALLATION ONLY INCLUDING MANUFACTURER APPROVED

HARDWARE EA

Includes installation of county-provided bike rack. Includes cost of hardware for installation on concrete slab and delivery of materials from the County warehouse.

24 BOLTED BIKE RACK RELOCATION INCLUDING MANUFACTURER APPROVED

Includes removal and reinstallation of existing bike rack. Includes cost of hardware for reinstallation on concrete slab, and delivery to proposed site.

25 BOLTED BENCH INSTALLATION ONLY INCLUDING MANUFACTURER APPROVED

Includes installation of county-provided bench. Includes cost of hardware for installation on

26 BOLTED BENCH RELOCATION INCLUDING MANUFACTURER APPROVED HARDWARE EA

Includes removal and reinstallation of existing bench. Includes cost of hardware for

27 BOLTED/IN GROUND TRASH CAN INSTALLATION ONLY INCLUDING MANUFACTURER

APPROVED HARDWARE EA

Includes installation of county-provided trash can. Includes cost of hardware for installation on

28 BOLTED/IN GROUND TRASH CAN RELOCATION INCLUDING MANUFACTURER

APPROVED HARDWARE EA

Includes removal and reinstallation of existing trash can. Includes cost of hardware for

29 ADDITIONAL LABORER (INCLUDING ALL PAY/FRINGE BENEFITS) HR

Labor hours to be used to supplement installation/relocation items above for the purpose of corrections, cleaning, and other findings found not to be the fault of the Contractor.