JMEC_Jemez_Mountain_Electric_COOP_Requirements.docx
DOCX document 13 KB Posted
- Attached to
- Jemez RD Office Construction Project Federal contract opportunity
- Solicitation number
- 12837919R0002
About this file
JMEC Requirements
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jemez Mtn. Electric COOP Requirements
1. JMEC will designate an existing pole as a “Riser” pole to allow the distribution line to go underground.
1. JMEC will designate a second existing pole as a “Riser” pole to allow the distribution line to return to its existing Overhead route.
1. The distance between these two poles will be approximately 1,000 800 feet. At some point along this 1,000 800 foot underground route (location undetermined at this time) there will be a junction box installed.
1. The contractor will need to provide and install the conduit and stub ups from the first riser pole to the junction box, and from the junction box to the second riser pole. The conduit should be 6” schedule 40 PVC. The 90’s should be rigid.
1. The contractor will need to provide and install another conduit and stub ups from the junction box to the new service transformer. The requirements for the conduit and stub ups are the same as above.
1. The contractor will need to provide and install the transformer pad. JMEC will provide to the contractor the specification for this pad.
1. The contractor will need to provide and install the conduit from the transformer secondary to the meter location as designated by the Forest Service’s Engineer.
1. JMEC will provide the cable, junction box, service transformer, meter, miscellaneous materials and connectors, as well as all labor to install this material.