12639523R0014-0005.pdf

PDF 943 KB Posted

Attached to
HVAC Equipment Replacement, Memphis Federal contract opportunity
Solicitation number
12639523R0014
Issued by
Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services

About this file

This federal contract solicitation seeks proposals to replace certain HVAC equipment within a USDA building in Memphis, Tennessee. Offerors are asked to submit pricing and equipment specifications for multiple proposal packages, including one to three 200-ton chillers, one to three 2821 MBH steam boilers, a plate frame heat exchanger, one to three 200-ton cooling towers, and one or two 40-50HP air compressors. Chiller selections will be evaluated on a life cycle cost basis considering first cost, efficiency, energy cost, maintenance cost, and lead time. Other equipment will be selected based on first cost, efficiency, and lead time. Proposals should include performance data, dimensions, electrical requirements, and maintenance costs for all recommended equipment. Award will be made to the offerors providing the best value based on the selection criteria.

View the file

Other files for this federal contract opportunity

Other files attached to HVAC Equipment Replacement, Memphis, newest first.
File Type Posted
12639523R0014-0007.pdf PDF
12639523R0014-0006.pdf PDF
12639523R0014-0004.pdf PDF
Amendment 0003_Equipment Present Worth Analysis 2023May18.xlsx XLSX spreadsheet
12639523R0014-0003.pdf PDF
USDA Memphis Mechanical Mod pre bid attendance sheet.pdf PDF
Memphis TN Mechanical Mod pre-bid site visit.xlsx XLSX spreadsheet
12639523R0014-0002.pdf PDF
12639523R0014-0001.pdf PDF
Atch 6_Equipment Present Worth Analysis.xlsx XLSX spreadsheet
Atch 4_ proposal package schedule.pdf PDF
Atch 2_Specifications.pdf PDF
Atch 5_Structural Drawings.pdf PDF
Atch 1_federal construction wage rates_Shelby County.pdf PDF
Atch 3_Drawings.pdf PDF
12639523R0014.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12639523R0014 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

APHIS-MN-126395

05/24/20230005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

USDA APHIS

250 MARQUETTE AVE

SUITE 410

MINNEAPOLIS MN 55401

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/25/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Tax ID Number: Not Available

DUNS Number: Not Available

This amendment is written to clarify requirements.

- Refer to the specifications, section 23 90 00 Temperature Regulation. Paragraph 1.3 is deleted in its entirety. The scope of work for temperature controls under this project is described in paragraph 1.1. Note that the sequences in paragraph 2.5 describe existing sequences of operation, which shall be maintained. EK Automation shall integrate any and all equipment furnished under this project into the existing temperature controls systems for full control of the equipment in accordance with the sequences of operation.

- Refer to the specifications, section 23 95 00 Building Automation Systems. Paragraph 1.6 is deleted in its entirety. The scope of work for temperature controls under this project is Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JAMES G. ROLOFF

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

05/25/2023

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12639523R0014/0005 described in paragraph 1.1. EK Automation shall integrate any and all equipment furnished under this project into the existing Building Automation Systems for full control of the equipment in accordance with the sequences of operation.

- Both sections 23 90 00 and 23 95 00 are a guideline for EK Automation / Siemens to integrate new equipment into the existing systems, and generally describe what has already been installed by EK Automation in the past when the Landis and Gyr system was replaced.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

FFA22025 TEMPERATURE REGULATION 23 90 00 - 1

04/2023

SECTION 23 90 00 - TEMPERATURE REGULATION

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes control equipment for HVAC systems and components furnished under this project.

B. Refer to 23 00 00 for bid package and bid form requirements. Generally, all existing chillers, boilers, plate heat exchangers are connected to the existing building automation system, Seimens Talon by EK Automation of Memphis Tennessee. For each item of equipment to be replaced, reconnect existing actuators, and all microprocessor control interfaces for the equipment to the building automation system. Note that for Bid Package 4, VFDs are being added for the cooling tower fans. Modify the sequence for the cooling tower condenser water temperature control to incorporate fan speed control prior to dump valve operations.

C. Note that EK Automation is required to provide controls and connection to the existing system, no exception.

1.2 SUBMITTALS

A. Submit manufacturer's data on all materials and equipment. Include system schematics indicating all devices, electrical wiring and sequence of operation. Sequence of operation shall reference each component device by designation used on schematics. Submittal must be approved prior to beginning any work. All wiring shall be installed to meet Division 26 specifications.

A.

12639523R0014, Amendment 0005

FFA22025 TEMPERATURE REGULATION 23 90 00 - 2

PART 2 – PRODUCTS

2.1 CONTROL VALVES, WATER

A. All modulating 3-way water valves shall be provided with equal-percentage contoured throttling plugs. They shall remain closed against full system pressure.

B. Valves 3" and smaller shall be screwed type, valves 4" and larger shall be flanged. Valves shall be factory-rated to withstand the pressures encountered. Valves shall have stainless-steel stems and spring-loaded teflon packing.

C. Water valves shall be sized for a pressure drop equal to the coil they serve but not to exceed 5 psi. Valves shall have replaceable seats and discs. Refer to the schedule for valve control valves ranges.

D. It shall be acceptable to reuse the existing valve bodies and replace the actuators if the valves are in good condition and are functional. Note that any valves that fail during the life of the lease period shall be replaced at no cost to the government.

2.2 CONTROL VALVES, STEAM

A. Steam valves shall be high quality valves equipped with stainless steel trim and characterized throttling plugs to insure practically straight line gradual operation. Refer to the schedule for valve control valves ranges.

B. It shall be acceptable to reuse the existing valve bodies and replace the actuators if the valves are in good condition. Note that any valves that fail during the life of the lease period shall be replaced at no cost to the government.

2.3 ELECTRIC ACTUATORS

A. Electric operators shall be sized to operate their appropriate dampers or valves with sufficient reserve power to provide smooth modulating action, electric/hydraulic actuators or potentiometer feedback positioners shall be used.

B. Where sequencing of actuators is called for such sequencing shall be accomplished by spring ranges adequate for the application.

C. Where critical application controllers are used, or where actuators are controlled from pressure sensors, electric/hydraulic actuators or potentiometer feedback positioners shall be used.

2.4 CONTROL SYSTEM DESCRIPTION

A. The main control station is located in the penthouse electrical room, and consist of a monitor, keyboard, and ISP connection device, connected to and accessing all control points described in the point schedule. The following paragraphs describe the existing equipment and sequences, which shall be maintained under this project.

B. The main control station shall be capable of access from a remote location via web (internet) access, utilizing layers of password protection. Arrange for and provide independent, outside access to cable company service for use by the temperature control system. Temperature control operator workstation shall not be connected to the government computer network. System features shall be provided such that remote visual access to

FFA22025 BUILDING AUTOMATION SYSTEM 23 95 00 - 4

communication protocols to a Network Area Controller (NAC), provided under Division 17.

1.7 RELATED WORK SPECIFIED ELSEWHERE

A. Drawings and general provisions of the Contract, including General and supplementary Conditions and Division-1 specification sections, apply to work of this section.

B. Products furnished but installed by mechanical contractor:

1. VFD’s (if selected by the owner as an add)

2. Valves and Actuators

3. Flow switches, flow sensors, thermowells and pressure taps

4. Automatic dampers to be installed under section 23 00 00.