IO&T REQUIREMENTS: FY22 Charleston CSDC (OM-IOT) PROJECT NO 89902 DATE: 24 June 22 (v.02)
Table of Contents
| Table of Contents | 2 | |
| 1 | General Requirements | 4 |
| 1.1 | General Requirements | 4 |
| 1.1.1 | Overview | 4 |
| 1.1.2 | Project Information | 4 |
| 1.1.3 | Work Restrictions | 5 |
| 1.1.4 | Progress & Completion Photos | 5 |
| 1.1.5 | Meetings & Reporting | 5 |
| 1.1.6 | Schedule | 7 |
| 1.1.7 | Submittals | 10 |
| 1.1.1 | Acceptance & Transfer Documentation | 10 |
| 1.2 | Initial Outfitting | 12 |
| 1.2.1 | General | 12 |
| 1.2.2 | Qualifications: Initial Outfitting Personnel | 15 |
| 1.2.3 | Submittals: FFE-LVS | 16 |
| 1.2.4 | Furniture, Fixtures, Equipment (FFE) Package | 16 |
| 1.2.5 | Low Voltage System (LVS) Package | 17 |
| 1.2.6 | FFE-LVS Execution Plan | 18 |
| 1.3 | Transition | 18 |
| 1.3.1 | General | 18 |
| 1.3.2 | Qualifications: Transition Personnel | 24 |
| 1.3.3 | Submittals: Transition Plan | 25 |
| 1.4 | Acceptance & transfer of property | 27 |
| 2 | Functional Requirements | 27 |
| 3 | Interior Design Requirements | 27 |
| 3.1 | General | 27 |
| 3.1.1 | Qualifications: Interior Design | 27 |
| 3.1.2 | Submittals: Furniture & Fixtures | 28 |
| 3.2 | Division 10: Specialties | 28 |
| 3.2.1 | New Signage-Interior (PP) | 28 |
| 3.2.2 | New Storage & Lockers (PP) | 28 |
| 3.2.3 | New Fire Protection Items (PP) | 29 |
| 3.3 | Division 12: Furnishings (Furniture, Accessories, Casework, Artwork, etc.) | 29 |
| 3.3.1 | New Furnishings (PP) | 30 |
| 4 | Equipment Requirements | 31 |
| 4.1 | General | 31 |
| 4.1.2 | Qualifications: Equipment | 32 |
| 4.1.3 | Submittals: Equipment | 33 |
| 4.2 | Division 11: Equipment (Medical, Institutional, Office, Etc.) | 33 |
| 4.2.1 | New Equipment (PP) | 34 |
| 4.2.2 | Reused Equipment | 34 |
| 5 | Communication Requirements | 34 |
| 5.1 | General | 35 |
| 5.1.1 | Order Criteria Applies | 36 |
| 5.1.2 | Site Investigation Report: Communication Systems | 36 |
| 5.2 | Qualifications: Communications | 36 |
| 5.2.1 | Communications Systems Engineer (CSE) | 36 |
| 5.2.2 | Registered Communications Distribution Designer (RCDD) | 36 |
| 5.2.3 | Cybersecurity Consultant | 36 |
| 5.3 | Submittals: Communications (Design) | 37 |
| 5.3.1 | Order of Applicability | 37 |
| 5.3.2 | Distribution & Medium | 37 |
| 5.3.3 | LVS (RPIE vs PP) | 37 |
| 5.3.4 | LVS Package | 38 |
| 5.4 | Submittals: Communications | 38 |
| 5.4.1 | LVS Submittals | 38 |
| 5.4.2 | Building Equipment Rooms & Structures: Communications | 39 |
| 5.4.3 | Commissioning | 39 |
| 6 | Division 25: Integrated Automation (Cybersecurity) | 40 |
| 6.1 | Risk Management Framework (RMF) | 40 |
| 6.2 | Submittals: Cybersecurity | 41 |
| 6.2.1 | Design Submittals | 42 |
| 6.3 | Schedule Constraints: Cybersecurity | 45 |
| 7 | Division 27: Communications (Infrastructure, Phone, Data, etc.) | 45 |
| 7.1 | Telecommunications Interior Infrastructure | 45 |
| 7.2 | Classified Telecommunication Infrastructure | 45 |
| 7.3 | Telecommunications Pathways & Cabling | 45 |
| 7.4 | Backbone Cabling – Optical (RPIE) | 46 |
| 7.5 | Cabling System - Building Telecommunications (RPIE) | 46 |
| 7.6 | Work Areas | 46 |
| 7.7 | Grounding Bonding, and Static Protection | 46 |
| 7.8 | Telecommunications System Administration | 46 |
| 7.9 | Telecommunication System Testing | 46 |
| 7.10 | Service Specific Requirements | 46 |
| 7.11 | System Infrastructure | 46 |
| 7.12 | Real Property Installed Equipment (RPIE) | 46 |
| 7.13 | Personal Property (PP) | 46 |
| 7.14 | Data Communications Wireless Access Points (IS-PP) | 47 |
| 7.15 | Wireless Local Area Network (WLAN) Heat Mapping | 47 |
| 7.16 | Data Communications Network Equipment (IS-PP) | 47 |
| 7.17 | Sound Masking Systems (FRCS-PP) | 48 |
| 8 | Division 28: Electronic Safety & Security (Fire Alarm & Electronic Security System) | 48 |
| 8.1 | Fire Alarm & Detection (RPIE) | 48 |
| 8.2 | Electronic Security Systems (ESS) (PP) | 48 |
| 9 | Division 33: Utilities (Telecommunications Outside Plant) | 48 |
| 10 | REFERENCES | 48 |
| 11 | Attachments | 50 |
General Requirements General Requirements Overview The Defense Health Agency-Facilities Enterprise (DHA-FE) requires Initial Outfitting and Transition (IO&T) services for the FY22 MILCON Warehouse Replacement Project at Charleston AFB, SC.
Initial Outfitting means to provide new furniture, fixtures, equipment, and low voltage systems (FFE-LVS) classified as Personal Property[footnoteRef:1] in new or newly renovated facilities. [1: Personal Property = non-fixed modular, moveable furniture, fixtures, equipment, & low voltage systems (FFE-LVS). It is not Real Property Installed Equipment (RPIE)]
Transition services generally includes (1) relocating reuse FFE-LVS, (2) disposing of non-reuse FFE-LVS, (3) public relations (PR) support, (4) staff orientation & training, and (5) cleaning prior to occupancy of the new or newly renovated space.
Project Information
PROJECT INFORMATION
| A |
| Real Property Jurisdiction |
| Department of the Air Force |
| B |
| Location |
| JB Charleston, Charleston, South Carolina |
| C |
| Project Delivery Method |
| IOT Stand-Alone |
| # |
| FACILITY INFORMATION |
| FACILITY 1 |
| FACILITY 2 |
| FACILITY 3 |
| 1 |
| Project Number |
| 89902 |
| 89902 |
| 89902 |
| 2 |
| Project Title |
| CSDC Charleston |
| CSDC Charleston |
| CSDC Charleston |
| 3 |
| Facility Number |
| 00697 |
| N/A |
| 4 |
| Facility Name |
| Warehouse |
| Leased Building |
| New Bldg |
| 5 |
| Square Footage |
| 10,000 |
| 75,000 |
| 95,474 |
| 6 |
| Real Property Categorization |
| 5306 |
| 5306 |
| 5306 |
| 7 |
| Medical Treatment Facility Type |
| Medical Warehouse |
| Medical Warehouse |
| Medical Warehouse |
| 8 |
| Facility Function |
| Warehouse |
| Warehouse |
| Warehouse |
| 9 |
| Scope Description |
| Demolish |
| Transfer Only |
| New Construction |
| 10 |
| Fund Sources |
| MILCON |
| N/A |
| MILCON |
| 11 |
| Level of Construction |
| Demo |
Permanent
Materiel Receiving/Processing, Materiel Staging, Materiel Storage, and Biomedical Equipment Repair
| 13 |
| Current Use (Occupancy) |
| Storage |
| Storage |
| N/A |
| 14 |
| New Use (Occupancy) |
| N/A |
| N/A |
| Storage |
| 15 |
| Historical Status |
| No |
| N/A |
| No |
| 16 |
| Archeological Site |
| No |
| No |
| No |
| 17 |
| Defense Medical Information System Identifier (DMIS ID) |
| 0356 |
| N/A |
| 0356 |
The existing Joint Base (JB) Charleston Medical Readiness mission is supported by Building 697 and a leased building off base. The Air Force Surgeon General (SG) approved Consolidated Storage and Distribution Center (CSDC) for CONUS-based War Readiness Material (WRM) so Building 697 will be replaced and the lease for the building off base will end.
Work Restrictions Continued Occupancy All departments within the existing facility will remain in operation during the entire Period of Performance (POP) unless specifically stated herein. Permission to interrupt operations must be submitted in writing within the timelines outlined in the section titled Schedule Constraints.
Base Access & Work Hours When arranging access to Charleston AFB, there is a minimum of 72hrs pre-notice to process Form 74. COR and Project officer will assist in processing base access and provide further details on what documents and forms are required.
Work hours within the existing facility, and on and around the site, are outlined in the following table. Work outside these hours requires approval and must be requested within the time outlined in the section titled Schedule Constraints.
| DAYS |
| WORK PERIOD |
| START |
| END |
| Monday-Friday |
| 10 hours |
| 7:00 am |
| 5:00 pm |
| Saturday |
| 10 hours |
| 7:00 am |
| 5:00 pm |
Contractor Access and Use of Premises Contractor installation access instructions are defined in the Attachment: Installation Contractor Requirements.
Concurrent Projects
| # |
| PROJECT |
| GENERAL WORK DECRIPTION |
| GENERAL AREA/ LOCATION AFFECTED |
| ESTIMATED COMPLETION/ DURATION |
| 1 |
| ACC Modernization |
| Modernization and reorganization of select MTF departments. |
| Main MTF around the corner from the CSDC Site |
| March 2025 |
| 2 |
| HAAMS |
| Storage facility for Specialized Training |
| Adjacent to the MTF |
| May 2022 |
| 3 |
| Temporary Passenger Terminal |
| 30ft South of the CSDC site |
| July 2022 – Sept 2022 |
Progress & Completion Photos Provide pre-work, progress, and completion photos for the spaces outlined in the following table.
| 1 |
| Primary & Secondary Entrances |
Meetings & Reporting Meeting Logistics Coordinate Agendas and meeting arrangements with the government prior to the meeting date. Notify the government of workspace requirements necessary to conduct the meeting (e.g., required number of meeting rooms, tables, chairs, presentation boards, teleconferencing ability, wi-fi connectivity, etc.). Provide equipment, accessories, and documents necessary to conduct the meeting. Include the meeting address, building, and room number on all agendas.
Potential Changes Documentation At the close of each meeting identify Potential Changes that may impact the project cost, scope, schedule, or safety. Document it as a risk on the IOT Project Status Report (PSR), circumstance or individual driving the change, and, if approved, government individual approving the change. Refer to section Project Status Report.
Government Representatives Coordinate agenda, meetings, activities, and deliverables with the government representatives listed in the table below. The IOT Contractor is not permitted to meet with CSDC representatives (aka “Users”) unless the DHA-FE Project Officer/Lead or IOT Planner (or their designee) can attend.
| # |
| AGENCY |
| REPRESENTATIVE |
| ROLE |
| 1 |
| Contracting Activity (aka Agent) |
| Contracting Officer |
| Responsible for entering a contract on behalf of the Government |
| Contracting Officer Representative |
| Responsible for administering the contract on behalf of the Contracting Officer |
| Project Manager |
| Manages the project scope on behalf of the Contracting Activity/Agent |
| Quality Assurance Evaluator/Representative |
| Assures products and work complies with government quality standards |
| 5 |
| DHA-FE |
| Project Officer/Project Lead (PO/PL) |
| Leads DHA-FE project team; project’s primary point of contact (POC) |
| Facility/Clinical Planner |
| DHA-FE project team members (referred to as the “Integrated Project Team” (IPT); supports PO/PL for project’s life cycle; develops project requirements on behalf of the project sponsor (DHA-FE); reviews submittals for compliance/conformance; serves as healthcare subject experts for their respective discipline. |
Interior Design Planner
Equipment Planner
Communications Rep (aka IM-IT Planner)
Architectural Planner/Representative
IOT Planner
| Transition Coordinator |
| Coordinate property management & transition service activities |
| 13 |
| CSDC |
| Facility Manager (FM) |
| Manages Facilities environment of care, safety, ops, maintenance |
| Logistics |
| Oversees property management and procurement activities |
| Information Systems (IM-IT) |
| Maintains information management/technology Systems |
| Medical Equipment Maintenance |
| Maintains Medical Devices and Equipment on behalf of the facility |
| Safety & Security |
| Provides safety and security oversight on behalf of facility |
| Equipment Custodian |
| Responsible for all property located within assigned department |
| Infection Control |
| Responsible for infection control compliance |
| Department Representatives |
| Serves as department’s representative to support the transition |
| Information Systems Security Manager (ISSM) |
| Responsible for the development, implementation, assessment, and monitoring of common controls. |
| GOV Site Information System Owner (ISO) |
| Responsible for the overall procurement, development, integration, modification, operation, maintenance, and disposal of an information system |
| GOV Information System Security Officer (ISSO) |
| Responsible for developing and enforcing security policies for the information system, managing/controlling changes to the information system and assessing the security impacts of those changes. |
| 24 |
| Installation |
| Installation Rep |
| Represents installation’s security, site, and comm requirements |
| Authority Having Jurisdiction (AHJ) |
| Refer to UFCs |
Weekly Progress Meetings Conduct Weekly Progress Meetings with the government representatives. Provide agendas, meeting minutes, action items, and attendance records. At a minimum, include agenda items outlined in the table below.
| # |
| AGENDA ITEM |
| TOPIC |
| DISCUSSION |
| 1 |
| IOT Project Status Report (PSR) |
| IOT Project Status Report (PSR) |
| Overarching risks and changes |
| Cost |
| Changes and potential exposure |
| Schedule |
| Changes to milestones and Impact on project schedule and critical path |
| Scope |
| Changes in scope for all disciplines |
| Risk |
| Review risks, strive for resolution, assign a point of contact to work issues |
| Requests for Information (RFI) |
| RFIs’ that require resolution and/or action |
| Distribution |
| Determine if distribution requirements changed |
| 9 |
| Meeting Minutes |
| Previous meeting minutes and corrections; upcoming meetings & site visits |
| 10 |
| Submittals |
| Upcoming and outstanding submittals |
IOT Project Status Report (PSR) Maintain the Attachment: IOT Project Status Report (PSR). Document project status, information, and issues. The PSR (also known as the Weekly [Risk] Report) outlines submittal distribution requirements. The purpose of the PSR is to keep senior leadership and the project team informed of risks related to cost, schedule, scope, and safety. The PSR serves as a repository of relevant and historical information and is used extensively for studies, analysis, and senior-level reporting. It enables team members to proactively manage issues and minimize risks real time.
Update the PSR weekly until receipt of the final DD Form 1354: Transfer and Acceptance of Real Property and final set of DD Form 250 is the Material Inspection and Receiving Report (MIRR).
Review the PSR during weekly progress meetings. Highlight changes, updates, and edits. It is critical the PSR reflect accurate and current information and all fields are complete. Failure to maintain this document could adversely impact the project, funding, programming decisions, prompt resolution, change management, and ultimately affect the contractor’s performance rating.
Tracking Potential Changes Use the IOT Project Status Report (PSR) to clearly identify any adjustments which may have a potential cost, schedule, scope, safety, or quality change. Should one be identified, notify the Contracting Officer (KO) in accordance with the Contract Clauses. The PSR is the mechanism used to inform the project team of potential risks.
Meeting Minutes and Written Records Prepare detailed and accurate written records of each site visit and meeting. Refer to the IOT Project Status Report (PSR) Distribution List for distribution requirements. Include agenda, subject, names of participants, relevant details, action items, responsible team member, and required resolution date. Illustrate and/or include contract documents reflecting scope additions and deletions. Summarize work the contractor believes is outside the contract scope. Number written records in consecutive order. Provide electronic copies of all written records, agendas, presentations, and meeting minutes in each submittal.
File Naming Conventions, Electronic Submittals, & Distribution Provide standardized electronic naming conventions to ensure timely government responses. Include numerical date (i.e., 20220330 for 30 Mar 2022), fiscal year (FY), installation name, submittal/RFI/ASI number, and project number. Do not exceed thirty (30) characters or include special characters (e.g., 20220301_FY24_FtBragg_DS4_PNXXX). Distribute electronic submittals to the government via a publicly accessible site (such as Microsoft® SharePoint® or equivalent). Provide electronic submittals in accordance with the IOT Project Status Report (PSR). Provide electronic submittals with a single file structure with proper bookmarks. Each file size may not exceed 50 megabytes (MB).
Review & Resolution Conferences Review and resolution conferences are to be held following each submittal. Review open issues or actions from the last meeting, what occurred, and what is planned to occur before next meeting. Reviews should focus on critical path items and activities that may impact the project’s schedule/scope. The objective of the review or resolution conference is to resolve any outstanding compliance or conformance deficiencies identified by the government. No comment should be left unresolved before moving forward to the next submittal.
Schedule Project Schedule (Detailed Requirements) & Period of Performance (POP) The Period of Performance (POP) includes the activities and deliverables outlined in the tables below. Beneficial Occupancy Date (BOD) is determined by the Construction schedule. Open for Business (OFB) should occur within 60 days of BOD.
Current BOD is 19 Jan 2023
| A |
| INITIAL OUTFITTING/FFE-LVS INSTALLATION |
| INCLUDED POP/SCHEDULE |
| 1 |
| Notice to Proceed |
| Yes, prior to install date schedule asap after award to reflect these dates |
| 5 |
| Installation of Personal Property |
| Yes, prior to Transition Start |
| B |
| TRANSITION |
| INCLUDED POP/SCHEDULE |
| 1 |
| Transition Submittals |
| Yes |
| 2 |
| Orient Staff Members |
| Yes, upon completion of FFE-LVS install, prior to each phased move |
Yes, 2-workdays by phase
| 4 |
| De and Re-Installations |
| 12 |
| Dispose |
| Yes, shall not impede critical path |
| 13 |
| Survey (Lessons Learned) |
| Yes |
Schedule Constraints Due to DHA-FE and the CSDC operational constraints, schedules must account for the constraints outlined in the table below. These schedule constraints take precedence over those listed in the attached documents and/or specifications.
| NO |
| ACTIVITY/DELIVERABLE |
| SCHEDULE CONSTRAINTS (CALENDAR DAYS) |
| 1 |
| Acceptance Docs: Reuse FFE-LVS (Interim) |
| 45 days prior to Conditional Acceptance |
| 2 |
| Acceptance Docs: Reuse FFE-LVS (Revised) |
| 21 days prior to Conditional Acceptance |
| 3 |
| Acceptance Docs: Reuse FFE-LVS (Final) |
| 21 days to Final Acceptance |
| 4 |
| Acceptance Forms: New FFE-LVS (Interim) |
| 45 days prior to Conditional Acceptance |
| 5 |
| Acceptance Forms: New FFE-LVS (Revised) |
| 21 days prior to Pre-Final Acceptance |
| 6 |
| Acceptance Forms: New FFE-LVS (Final) |
| 21 days prior to Final Acceptance |
| 7 |
| Acceptance Inspections (Notice) |
| 45 days prior |
| 8 |
| Acceptance Submittals (O&M Manuals) |
| At time of installations |
| 9 |
| Disposition Plan (& Notice Date to Begin) DD Form 1348-1A Disposal Turn-In Form |
| Coordinate deliveries w/ Logistics & DLA-DS NLT 90 days prior to disposition |
| 10 |
| Documentation (Warranty & Maintenance) |
| 15 days post acceptance; 21-day Govt review |
| 11 |
| Inspection (Punch Lists & Inspection Findings) |
| 7 days following government inspection |
| 12 |
| Inspection Docs: Corrected Final Documents |
| 14 days prior to Final Inspection |
| 13 |
| Inspection Docs: Notification: Inspection |
| 21 days prior to inspection |
| 14 |
| Inspection Docs: Systems & Equipment Testing List |
| 90 days prior to testing |
| 15 |
| Lessons Learned Survey (Distribute Reports) |
| NLT 45 days following survey distribution |
| 16 |
| Lessons Learned Survey (Transition & PR) (Distribute Surveys) |
| NLT 14 days following moves by phase |
| 17 |
| Meeting (Kick-Off) |
| 7 days following Notice to Proceed (NTP) |
| 18 |
| Meeting Agendas (Draft) |
| 45 days prior to meeting date |
| 19 |
| Meeting Agendas (Final) & Attendee Confirmation |
| 10 days prior to meeting |
| 20 |
| Meeting Minutes & Written Records |
| 5 days following meeting/conference |
| 21 |
| Meeting: Comm/LVS Coordination Meeting |
| Bi-Weekly; commence NLT 120 prior to moves |
| 22 |
| Meeting: FFE-LVS Third-Party Vendor Coordination |
| Coordination with facility NLT 6 mos. prior to start |
| 23 |
| Meeting: IOT Project Status Report (Risk Identification) |
| Within 14 days of identification |
| 24 |
| Meeting: IOT Project Status Report (Risk Resolution) |
| 30 days of identification |
| 25 |
| Meeting: Transition Planning |
| Minimum Bi-Weekly; commence NLT 90 days prior to moves |
| 26 |
| Notice: Disruption of Utility Services |
| 14 days prior to shutdown |
| 27 |
| Notice: Facility Cleaning |
| 120 days prior to moves |
| 28 |
| Notice: FFE-LVS Installation |
| 21 days prior to installation |
| 29 |
| Notice: Installation Security Notification |
| 60 days prior to mobilization |
| 30 |
| Notice: Preliminary Moves - Notification |
| 60 days prior to target move date by phase |
| 31 |
| Notice: Street Closings |
| 30 days prior to closure |
| 32 |
| Notice: Traffic Disruptions/Traffic Control Plan |
| 14 days prior to work commencement |
| 33 |
| Notice: Work holidays, weekends, after hours |
| 14 days prior to commencing work |
| 34 |
| Notice: Final Moves Notification |
| 21 days prior to Conditional Acceptance by phase |
| 35 |
| Notice: Request for Time Extensions |
| Refer to Contract Clauses |
| 36 |
| Performance Forms: Contractor Address/Resolve Rating |
| Contractor 7 days to respond to rating; Govt 7 days to confirm |
| 37 |
| Provide Attic Stock |
| Within 30 days of Govt acceptance of each phase |
| 38 |
| Public Relations (Coordinate Ceremony Materials/Postings) |
| Review w/facility a min of 45 days prior to release |
| 39 |
| Public Relations (Distribute materials /postings & handouts) |
| Min of 90 days prior to move or ceremony |
| 40 |
| Record Documents (Draft/Final) |
| 21 days for review |
| 41 |
| Request for Information (RFI) |
| Govt 14 days to respond |
| 42 |
| Resumes (Key Personnel-Revisions) |
| Project kick-off meeting |
| 43 |
| Resumes (Updated Key/FFE-LVS Personnel) |
| Provide to Govt at time of project kick-off meeting |
| 44 |
| Schedule (Closeout & Warranty) |
| 60 days prior to inspection; govt review = 21 days |
| 45 |
| Schedule (Updates on PSR) |
| 7 days of meeting date or major shift in schedule |
| 46 |
| Submittal (Initialed PRC room drawings) |
| 7 days following conditional inspections |
| 47 |
| Submittal (O&M Data Changes) |
| 14 days of Govt notification |
| 48 |
| Submittal 1: Comm/LVS Binder (Draft) |
| NLT 12-mos prior to Conditional Acceptance Date (PH1 if project is phased) |
| 49 |
| Submittal 1: Department Transition Plan (Draft) |
| 50 |
| Submittal 1: FFE Binder (Draft) |
| 51 |
| Submittal 1: FFE-LVS Execution Plan Binder (Draft) |
| 52 |
| Submittal 1: Transition Plan (Draft) |
| 53 |
| Submittal 2: Comm/LVS Binder (Corrected Final) |
| NLT 6-months prior Conditional Acceptance Date (PH1 if project is phased) |
| 54 |
| Submittal 2: Department Transition Plan (Corrected Final) |
| 55 |
| Submittal 2: FFE Binder (Corrected Final) |
| 56 |
| Submittal 2: FFE-LVS Execution Plan Binder (Corrected Final) |
| 57 |
| Submittal 2: Transition Plan (Corrected Final) |
| 58 |
| Submittal 2: FFE-LVS Training Schedule, Testing & Certification Schedule (new & reuse) (Corrected Final) |
| Distribute revisions 60 days prior to move commencement by phase |
| 59 |
| Submittal 2: Transition Plan: Final Activity Schedules, Move Guides, Move Spreadsheets & “Day in the Life” (Corrected Final) |
| Distribute handouts 14 days prior to move commencement by phase |
| 60 |
| Submittals: Final Corrected |
| 21 days of correction; govt review = 15 workdays |
| 61 |
| Submittals: Government Review Period |
| 21-day review period |
| 62 |
| Submittal: O&M Manuals (to include Facility Data) |
| At time of RP, RPIE, PP Conditional Acceptance |
| 63 |
| Testing & Certification: Comm/LVS Coordination |
| Coordinate with installation security NLT 120 days prior to system install |
Operational Time Constraints The tables below outline functional, operational, and phasing time constraints. Consider these constraints during development of proposals, phasing/transition plans, and project schedules.
| 1 |
| Contractor work must not negatively impact facility operations |
| 2 |
| Contractor must work within the time constraints outlined in the section titled Schedule Constraints |
| 3 |
| Departments may not be closed for more than 2-work days during the transition period. |
| 4 |
| All existing security systems are to remain fully operational (i.e., Duress, IDS, Card Access, etc.) |
Submittals Quantity of Submittals Provide the number of submittals outlined on the Attachment: IOT Project Status Report (PSR) (Distribution List).
Submittal Register Within 30-days of contract award, provide a Submittal Register listing required submittals in the table below.
| NO |
| SUBMITTAL REQUIREMENTS |
| SUBMITTAL REGISTER REQUIRED |
| 1 |
| FFE-LVS Submittals (IO) |
| Yes |
| 2 |
| Transition Submittals (T) |
| Yes |
| 3 |
| Activation Submittals (A) |
| Yes |
| 4 |
| Cybersecurity Submittals |
| Yes (Refer to section titled Division 25) |
Submittal Deviations Documents submitted with the solicitation, and proposals accepted by the government, are considered the contract documents and must be used to track cost, scope, and schedule adjustments for the project duration. During the project, document any deviations to the contract documents by highlighting changes to the (1) PRC quantity, (2) CID, (3) specifications, (4) additional accessories to a particular JSN or system, (5) PRC deletions or additions of a JSN or system, and/or (6) PRC changes from a JSN or system from “reuse” to “new” or vice versa. The contractor is not authorized to execute changes, or exceed the contract price, without a contract modification. Summarize and highlight all deviations on the awarded or modified contract documents and provide with each submittal. Use a different color to highlight submittal revisions or deviations. Document deviations in the government accepted CLIN Schedule.
0. Acceptance & Transfer Documentation Acceptance Milestones & Terminology The following figure illustrates acceptance milestones, terminology, and associated documentation. Include transition, activation, real property, and personal property acceptance milestones in project schedules and the IOT Project Status Report (PSR). Incorporate this terminology in all project schedules.
Submit property transfer documentation (e.g., DD Form 1354: Transfer and Acceptance of Real Property and DD Form 250 is the Material Inspection and Receiving Report (MIRR). The following table outlines the project phase and deliverables related to work acceptance[footnoteRef:2] and property type transfers. Refer to UFC 1-300-08 Criteria for Transfer & Acceptance of DoD Real Property. [2:
| # |
| PHASE DUE |
| RESPONSIBILITY |
| PROPERTY |
| MILESTONE |
| ACCEPTANCE DOCUMENTATION |
| 1 |
| Design (PH5) |
| Designer of Record (DOR) |
| New RP/RPIE/EIP |
| Draft Transfer Documents |
| Draft DD Form 1354s (as part of Final Design Submittal) |
Draft DD Form 250s (as part of Final Design Submittal)
| 3 |
| Construction (PH6) |
| Construction Contractor |
| New RP/RPIE/EIP |
| Conditional Acceptance |
| Interim DD Form 1354, Punchlist, AHJ & ATO Docs |
| 4 |
| Initial Outfit (PH7) |
| IO/T Sub/Contractor |
| New PP |
Interim DD Form 250s, Punchlist, AHJ & ATO Docs
Activation (PH8)
| Construction Contractor |
| New RP/RPIE/EIP |
| Final Acceptance |
| Final DD Form 1354, Punchlist, AHJ & ATO Docs |
| IO/T Sub/Contractor |
| New PP |
Final DD Form 250s, Punchlist, AHJ & ATO Docs
Reuse
Reuse Property Transfer Documentation: (1) PRC (2) Existing Inventory List of Reuse Items; (3) Room-By-Room Drawings
The following table outlines who are authorized to take acceptance of the property.
| No |
| Document |
| Section |
| Authorized Government Rep |
| 1 |
| DD Form 1354 (Real Property & Real Property Installed Equipment (RPIE)) |
| 27 Transferred By |
| Contracting Officer Representative (COR) |
| 28 Accepted By |
| Facility Manager (FM) |
| 3 |
| DD Form 250 (Personal Property) |
| 21a. Origin |
| Prime/IOT Contractor |
| 21 c. Destination |
| DHA-FE IO/T Coordinator (if assigned). PO/PL if no IO/T Coordinator |
| 22 Receiver’s Use |
| Logistics Representative (Property Book Custodian) |
| 6 |
| Existing Inventory/PRC (Reuse FFE-LVS) |
| All |
| Logistics Representative (Property Book Custodian) |
| 7 |
| Punchlist (RP/RPIE/PP) |
| All |
| Contracting Officer Representative (COR)/Project Officer/Project Lead |
| 8 |
| AHJ Documentation |
| All |
| AHJ/Fire Protection Engineer |
| 9 |
| ATO Documentation (Communications) |
| All |
| Chief Information Officer (CIO)/ISSM |
Acceptance Classifications All inspection and acceptance items specified for correction via the “punch list” will be assigned an acceptance classification to include (1) Counterfeit, (2) Critical Non-Conformance, (4) Major Non-Conformance or (5) Warranty.
a. Counterfeit Item means an unlawful or unauthorized reproduction, substitution, or alteration that has been knowingly mismarked, misidentified, or otherwise misrepresented to be an authentic, unmodified item from the original manufacturer, or a source with the express written authority of the original manufacturer or current design activity, including an authorized aftermarket manufacturer (e.g., used items represented as new, or the false identification of grade, serial number, lot number, date code, or performance characteristics).
b. Critical Nonconformance means a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services; or is likely to prevent performance of a vital agency mission.
c. Major Nonconformance means a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose.
Acceptance Terms
a. Conditional Acceptance is when the government accepts the contractor’s work even though it is not yet complete and/or does not conform to the contract quality requirements. It includes a specified date to correct or otherwise complete the work[footnoteRef:3] and occurs once the Contracting Officer notifies the project sponsor (i.e., DHA-FE) that the work has reached Substantial Completion. Construction Conditional Acceptance is synonymous with Placed in Service (PIS) date and Beneficial Occupancy Date (BOD). [3: FAR 46.5 Acceptance, UFC 1-300-08 Criteria and Transfer and Acceptance of Real Property, FAR 46.101 Quality Assurance
b. Final Acceptance means an authorized government representative assumes ownership of the property, determines services rendered are complete, in accordance with the contract. Final acceptance includes Authority to Operate (ATO) documentation. Final Acceptance is synonymous with Construction Complete and Open for Business (OFB).
Initial Outfitting General Provide new Furniture & Fixtures outlined in the section titled Interior Design Requirements. Provide the Equipment outlined in the section titled Equipment Requirements. Provide the Low Voltage Systems (LVS) outlined in the section titled Communication Requirements.
There are two types of Furniture, Fixtures, Equipment and Low Voltage Systems (FFE-LVS) (1) Real Property Installed Equipment (RPIE) and (2) Personal Property (PP). The table below outlines (1) the property types, (2) nomenclature, (3) appropriation or fund source, (4) definitions, and (5) which set of criteria typically applies. Attachment: Project Room Contents (PRC) outlines what FFE is considered RPIE versus PP. MIL-STD-1691 Military Medical & Dental Facilities: Policy Document (FFE-LVS) outlines what LVS is considered RPIE versus PP.
Comply with referenced criteria and standards outlined in the table below unless otherwise explicitly stated. Exceptions: Some equipment or systems such as Electronic Security Systems (ESS) must comply with both and . Other exceptions are noted throughout this document.
| # |
| PROPERTY TYPE |
| ALSO KNOWN AS |
| APPROPRIATION/ |
FUND SOURCE
DEFINITION[footnoteRef:4] [4: Reference: UFC 1-300-008 Criteria for Transfer and Acceptance of DoD Real Property]
APPLICABLE CRITERIA & STANDARDS*
| 1 |
| Real Property Installed Equipment |
| RPIE or Installed Building Equipment (IBE) |
| MILCON or Operations & Maintenance (O&M) |
Also known as “Project Funds”
| Property affixed and built into the facility as an integral part of the facility; necessary to make facility complete, and if removed, would destroy, or severely reduce the usefulness of the facility |
| and |
| 2 |
| Personal Property |
| Expense Equipment |
(1-year money)
| Initial Outfitting & Transition (OM-IOT) |
| Property (systems and equipment, materials, and supplies) except real property |
| and |
Investment/Expense Equipment (2-year money)
| Research, Development, Evaluation & Training (RDT&E) |
| Property (except real property/ Property that consists of capital and other nonexpendable equipment |
Equipment in Place (EIP) or Investment Equipment (3-year money)
| Procurement (P) |
| Property that consists of capital and other nonexpendable equipment of a movable nature that has been fixed in place or attached to the real property but is not an integral part of the facility |
Space Planning & Document Updates Prior to Submittal 1 conduct a detailed Survey and Existing Inventory of FFE-LVS for all departments and spaces impacted by construction or moves. Based on these findings, markup[footnoteRef:5] the DOR or government-provided (“G”) documents to reflect field-verified conditions; prior to FFE-LVS procurement date, and 6-months prior to expected installation. The scope of this effort includes: [5: Markup = colored highlights, clouds, etc. ]
a. Field Verification (field verify room configuration, infrastructure, structural conditions, and impact on FFE-LVS)
b. Project Room Contents (PRC) (confirm new versus reuse and logistical responsibility)
c. MEP/Architectural Drawings (new and reuse FFE-LVS)
d. FFE/Equipment Drawings (new and reuse FFE)
e. Communication Drawings (new and reuse LVS)
f. Specifications/Cutsheets (new equipment and LVS)
g. Room Data/Illustration Sheets (new furniture and fixtures)
h. Change Summary (Document summarizing required changes to infrastructure/structural)
i. Existing Inventory List (C): All existing property must be documented on an updated and contractor-maintained Existing Inventory List (C) derived from the Attachment: Existing Inventory List(s) (also referred to as the Defense Medical Logistics Standard Support (DMLSS) Accountable Medical Device Equipment (MDE) List and DMLSS RPIE List). In addition to what is listed as reuse on the contractual PRC, incorporate findings from the Existing Inventory List (C) on a sortable Microsoft® Excel® spreadsheet. Include information found in the table below.
j. Space Planning. Prior to the placement of the FFE-LVS, field verify existing site conditions to include architectural, mechanical, electrical, communications, fire protection, and civil-structural conditions. Contractor updated FFE space plans (drawings) must show all electrical, communications, mechanical (i.e., fume/exhaust hoods), and plumbing interface (i.e., sinks, water connections, medical gas) on the same drawing.
k. Reuse FFE. Reuse is defined as property with 24-months of useful life remaining at the time of re-installation. As part of the submittal review process, the Biomedical Equipment Technician (BMET) will verify if equipment meets this definition and is scheduled for reuse or disposition.
| # |
| EXISTING INVENTORY CONTENT |
| 1 |
| Confirm what property is to be moved, relocated, and reinstalled (reuse) |
| 2 |
| Include room level information for current, interim, and final locations |
| 3 |
| Confirm reuse items planned for the project meet the operability, durability, and safety requirements |
| 4 |
| Determine reuse items will fit within allowable space in new facility; notify project leadership if they will not |
| 5 |
| Confirm items will have necessary utilities to function in accordance with manufacturer specifications |
| 6 |
| Determine if reuse items can be delivered into the new facility via corridors, doors, etc. |
| 7 |
| Determine which items should be denoted for excessing and disposition |
| 8 |
| Include utilities, dimensions, and photographs for all Medical Device Equipment (MDE) |
| 9 |
| Include JSN, Nomenclature, quantities, Equipment Control Numbers (ECNs) |
| 10 |
| Include existing artwork |
| 11 |
| Coordinate reuse vs. disposal with facility FM, BMETs, Logistics, Property Custodians |
Storage & Staging Provide an FFE-LVS Execution Plan: Storage & Staging Plan. Prior to each submittal coordinate plan details with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Government provided storage space is not available. Staging requirements must be coordinated and approved by the Facility Manager prior to need date. Provide warehousing and storage necessary to deliver, move, stage, and install property. Replace in-kind all property damaged during moves or transport. Store property in environmentally controlled spaces and provide water line shock treatment in accordance with manufacturer recommendations.
Delivery & Installation Provide an FFE-LVS Execution Plan: Delivery & Installation Plan. Prior to each submittal coordinate plan details with project representatives from facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Deliver and install all new FFE-LVS. Protect areas and equipment from damage during moves and installation. Provide drop cloths and other coverings necessary to protect all surfaces. Mask and cover wall fixtures, plaques, pictures, bulletin boards, communication equipment, and cables. Move furniture, equipment, or other items necessary to install the property. Return areas to the original condition or as directed by the Contracting Officer.
Prior to installation, confirm placement of commodities with Government Representatives. Ensure installation and placement of FFE-LVS complies with the American Disability Act (ADA) and does not block access to sinks, doors, etc. All Government installed/provided FFE-LVS (e.g., paper towels, hand soap, hand sanitizer, etc.) must be installed and operational prior to inspections. Provide labels for users to distinguish apart hand soap and hand sanitizer dispensers if JSNs are the same.
Mock-Ups (Interior) Not applicable.
Testing & Certification Provide an FFE-LVS Execution Plan: Testing & Certification Plan. Prior to each submittal, coordinate plan details with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Test and certify new FFE-LVS. Test and certify all property in accordance with manufacturer instructions. Certify that testing, measurement, and diagnostic equipment complies with calibration certifications and National Institute of Standards and Technology (NIST) requirements. Provide operational and safety results to the government prior to acceptance and use. Provide qualified Biomedical Equipment Technicians (BMETs) to perform safety checks, inspections, and calibrations on relocated medical equipment.
Security Provide an FFE-LVS Execution Plan: Security Plan. Prior to each submittal coordinate plan details with facility management and safety and security personnel. Secure new FFE-LVS and existing department property. Provide necessary security provisions to keep property safe, secure, and in its designated location. The government is not responsible for the property until formal acceptance. Provide security measures to guard against damage and theft. Employ procedures to track product movement until time of acceptance.
Cleaning/Cleanup Develop the FFE-LVS Execution Plan: Cleaning Plan and coordinate cleaning protocols with project representatives from the facility management and infection control point of contact(s) in advance of cleaning. Include measures to take to ensure a clean work area and compliance with site-specific trash disposal and recycling policies. Provide cleaning services for all areas impacted by installation of new property.
Inspections & Acceptance Provide an FFE-LVS Execution Plan: Inspection & Acceptance Plan. Prior to each submittal, coordinate plan details, inspections, and acceptance activities with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Include copies of all required property transfer forms. Acceptance cannot occur until all property is installed, tested, and certified. Provide deliverables at time of the conditional and final acceptance to ensure the process is efficient and well organized.
Prior to inspections provide (1) a Punch List stating what activities are yet to be accomplished, (2) a Pending JSN & LVS List of FFE-LVS not yet installed to include nomenclature, ECNs, a brief explanation of the issue, and a (3) date it will be resolved.
At time of inspection, provide a current PRC and LVS List and post at the entrance/door of all areas where FFE-LVS is required. The PRC must include all current RPIE and PP JSNs, nomenclature, and ECNs. Update each ECN with the ECN of the item it replaces. This is not required for items not replaced. The current PRC will serve as a checklist for inspections and acceptance.
Upon inspection completion submit (1) Inspected Commodities List in Microsoft® Excel® format, and (2) a scanned copy of the PRC with Government inspectors’ initials and signatures.
The Logistics Officer, or an officially designated representative, must sign all DD Form 250s and DD Form 1354s at time of acceptance.
Operations & Maintenance Data Provide Operations & Maintenance Data for all new FFE-LVS in accordance with the and the .
Training Provide an FFE-LVS Plan: Training Plan and coordinate with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Train designated personnel to properly operate and maintain new FFE-LVS.
Warranty Provide Warranty Documents in accordance with the and the .
Government Furnished Equipment & Communication Systems Coordinate all Schedules with project delivery team on government-furnished procurement efforts and government managed third-party installations. For each project phase, provide and maintain a Microsoft® Excel® Government Furnished Equipment List (GFE) of all FFE-LVS the facility is responsible to procure (i.e., soap dispensers, information technology gear and equipment, etc.). Indicate required delivery dates. Refer to the section titled Schedule Constraints.
Cybersecurity Provisions Refer to section titled Communication Requirements, Division 25: Integrated Automation (Cybersecurity).
Qualifications: Initial Outfitting Personnel Project Manager Provide an IO/T Project Manager (PM) responsible for the overall life-cycle management and coordination of FFE-LVS and transition services. They serve as the central point of contact for government personnel for all FFE-LVS correspondence, activities, and deliverables. The FFE-LVS PM must have an intimate knowledge of the project requirements, be able to anticipate and control risks related to (1) trades and third-party contractor coordination, (2) space planning of interim and final locations, (3) utilizing reuse property, and (4) transition. They are responsible for adequate internal controls and to minimize operational risks, conflicts, and misunderstandings. The table below outlines the required qualifications.
| # |
| QUALIFICATIONS |
| REQUIRED |
| # |
| QUALIFICATIONS |
| REQUIRED |
| (Experience in this role) |
| Y/N |
| # YRS |
| (Experience in this role) |
| Y/N |
| # YRS |
| 1 |
| Total Years of Transition Experience |
| Yes |
| 3 |
| 11 |
| Budget & Procurement Documentation |
| Yes |
| 3 |
| 2 |
| DoD Criteria & Standards |
| Yes |
| 3 |
| 12 |
| Proficient in reading design documents |
| Yes |
| 3 |
| 3 |
| On-site construction management |
| Yes |
| 3 |
| 13 |
| Proficient in reading construction docs |
| Yes |
| 3 |
| 4 |
| Well-Versed in Healthcare Operations |
| Yes |
| 2 |
| 14 |
| Risk Management: Quality & Safety |
| Yes |
| 3 |
| 5 |
| Initial Outfit/Supply FFE-LVS |
| Yes |
| 3 |
| 15 |
| Proficient of & understanding of DoD healthcare PP IM-IT systems |
| Yes |
| 3 |
| 6 |
| Transition Services |
| Yes |
| 3 |
| 16 |
| Procurement, delivery, installation |
| Yes |
| 3 |
| 7 |
| New Construction Work |
| Yes |
| 3 |
| 17 |
| Testing, certification, commissioning |
| Yes |
| 3 |
| 8 |
| Multi-Phased Alterations (occupied) |
| Yes |
| 3 |
| 18 |
| Training related to property |
| Yes |
| 3 |
| 9 |
| Demolition & Disposition Work |
| Yes |
| 3 |
| 19 |
| Proficient in reading project schedules |
| Yes |
| 3 |
| 10 |
| Risk Management: Quality & Safety |
| Yes |
| 3 |
IOT Personnel Contractor personnel involved with FFE-LVS services are to be present on-site during all moves, installation, testing, certifications, inspections, and acceptance. The Contractor is responsible for coordinating all FFE-LVS activities. Refer to section titled Qualifications: Equipment, Qualifications: Interior Design, Qualifications: Communications.
Submittals: FFE-LVS Submittal Procedures Provide the submittals within the time constraints outlined in Schedule Constraints. Include content listed below. Submittals must comply with applicable , , and . Refer to the Attachment: IOT Project Status Report (PSR) for distribution requirements. Refer to DHA-FE Examples for expected level of submittal development. In addition to electronic updates, provide hard copy updates since the last submittal. Provide a cover sheet for each binder section summarizing the changes within that section.
Prior to mobilization include provisions required in the Health Insurance Portability and Accountable Act (HIPAA). NOTE: If there are submittal discrepancies between what is listed in the table(s) and the then requirements listed in the UFCs apply.
Government Furnished Documents Any government-furnished PRC or Existing Inventory List is designated with a (G). Documentation updated and maintained by the contractor is designated with a (C).
Furniture, Fixtures, Equipment (FFE) Package Provide and/or update the Furniture, Fixtures, and Equipment (FFE) Package in a single binder, and in accordance with the criteria and deliverables outlined in the table below. Include narratives, lists, color boards, forms, and specifications/product data. Large presentation boards and drawings may be provided under separate cover. For additional information refer also to Division 10: Specialties, Division 11: Equipment, and Division 12: Furnishings.
DOR-provided the following deliverables. The following table outlines whether they apply to this project.
· Drawings: Furniture Schedule (with quantities), Furniture & Equipment Plan (placement) (Drawing IF101, IF101A, IF101B)
· Room/Product Data Sheets & Samples (with Manufacturer)
· Drawings: Finishes, Signage, Furniture & Equipment Plan,
· Specifications Project Room Contents (PRC) list (Dated 21 Jan 21):
| # |
| CONTENT |
| REFERENCE |
| DELIVERABLE |
| 1 |
| Table of Contents (3-Level) |
IOT Contractor to Provide
| 2 |
| Narrative: Design Analysis (Furniture & Fixtures) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 3 |
| List: Point of Contacts (Project Team) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 4 |
| List: Cost Data (FFE) |
| UFC 3-120-10 Interior Design; UFC 4-510-01 Design: Military Medical Facilities |
| IOT Contractor to Provide |
| 5 |
| List: Item Code Legend (aka PP JSN Summary) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 6 |
| List: Project Room Contents (FFE) (Temp/Final Spaces) |
| UFC 4-510-01 Design: Military Medical Facilities |
| IOT Contractor to Provide |
| 7 |
| List: Manufacturer Source List |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 8 |
| Documents: Best Value Determination (BVD) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 9 |
| Color Boards: Furniture Material Boards (8-1/2 x 11) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 10 |
| Color Boards: Large Scale Presentations |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 11 |
| Drawings: Equipment Drawings (FFE) |
| UFC 4-510-01 Design: Military Medical Facilities |
| IOT Contractor to Provide |
| 12 |
| Drawings: Architectural Plans w/ FFE |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 13 |
| Drawings: Room-by-Room Plans (FFE) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 14 |
| Drawings: Typical (FFE) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 15 |
| Drawings: Systems Furniture (large scale w/ electrical, comm, panels) |
| UFC 3-120-10 Interior Design; UFGS 12 59 00 Systems Furniture |
| IOT Contractor to Provide |
| 16 |
| Drawings: Artwork Placement Plans |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 17 |
| Specifications: Data Sheets (per Item JSN, Contract & Manufacturer, Make/Model Info, Qty, Cost) |
| UFC 3-120-10 Interior Design |
| IOT Contractor to Provide |
| 18 |
| Specifications: Equipment Data & Catalog Cut Sheets |
| UFC 4-510-01 Design: Military Medical Facilities |
| IOT Contractor to Provide |
| 20 |
| Specifications: Warranty Information, Contact Information for Repairs, Qualification of Installers and Inspectors, Performance Verification & Acceptance Testing Docs, Operations & Maintenance Data |
| and UFGS 12 50 00.13 10 Furniture Installation |
| IOT Contractor to Provide |
| 25 |
| Forms: Property Transfer Documentation (i.e., DD Form 250s) |
| DD Form 250 Material Inspection & Receiving Report |
| IOT Contractor to Provide |
| 26 |
| Documentation: Cybersecurity (Equipment Related) |
| Refer to section titled Division 25: Integrated Automation (Cybersecurity) |
| IOT Contractor to Provide |
Low Voltage System (LVS) Package Provide and/or update LVS Package (i.e., Communication Package) in a single binder in accordance with UFC 4-510-01 Design: Military Medical Facilities, (PP), DD Form 250 Material Inspection & Receiving Report. Include the deliverables listed in the table below. Refer also to the sections titled Division 25: Integrated Automation (Cybersecurity), Division 27: Communications, and Division 28: Electronic Safety & Security. LVS Drawings may be provided under separate cover.
| 1 |
| Table of Contents (3-Level) |
| IOT Contractor to Provide |
| 2 |
| Narrative: Design Analysis (LVS) |
| IOT Contractor to Provide |
| 3 |
| List: Point of Contacts (Project Team) |
| IOT Contractor to Provide |
| 5 |
| List: Item Code Legend (aka LVS Summary) |
| 6 |
| List: Project Room Contents (to include LVS) |
| 7 |
| List: Manufacturer Source List (LVS) |
| 8 |
| Documents: Best Value Determination Forms (LVS) |
| IOT Contractor to Provide |
| 9 |
| Drawings: Communication Drawings |
| IOT Contractor to Provide |
| 10 |
| Drawings: Room-by-Room Plans (LVS) |
| IOT Contractor to Provide |
| 11 |
| Drawings: Typical (LVS) |
| IOT Contractor to Provide |
| 12 |
| Data/Cut Sheets (per Item, Contract & Manufacturer/Make/Model Info, Qty, Cost) |
| IOT Contractor to Provide |
| 13 |
| Specifications (LVS) to include Warranty Information, Contact information for repairs, Qualification of Installers and Inspectors, Installation Instructions, Performance Verification & Acceptance Testing Docs, Operations & Maintenance Data |
IOT Contractor to Provide
| 14 |
| Forms: Property Transfer Documentation (i.e., DD Form 250s) |
| IOT Contractor to Provide |
| 15 |
| Documentation: Cybersecurity (LVS Related) |
| IOT Contractor to Provide |
Content: LVS Package FFE-LVS Execution Plan Provide an FFE-LVS Execution Plan that describes how the contractor will plan, coordinate, and execute the work. Include content outlined in the table below. Include narratives, schedules, and supporting documents. Do not include pricing. List all activities in the order they are to be performed. Coordinate all plans and schedules with the project’s most current schedule. Refer to Attachment: Drawing: Installation Map in the development of the FFE-LVS Execution Plan. Provide in electronic form and one hard copy (2” 3-ring binder) for facility use. Provide cut sheets and specifications in electronic form only.
FFE-LVS EXECUTION PLAN
| 0 |
| Table of Contents |
| Provide a 3-level Table of Contents |
| 1 |
| FFE-LVS Schedule |
| Comprehensive schedule outlining the IO execution plan from award, and procurement activities through final acceptance by phase. |
| 2 |
| Existing Inventory List (C) |
| Refer to section titled Space Planning & Document Updates |
| 3 |
| Plan: Storage & Staging |
| How property will be insured, stored, transported; include installation access |
| 4 |
| Plan: Delivery & Installation |
| How property installation process will be planned and executed; include how mock-ups will be planned and scheduled |
| 5 |
| Plan: Testing & Certification |
| How testing & certification will be planned, coordinated, executed; provide a test & certification schedule, refer to DHA-FE Examples: PP Plan (Test & Certification Schedule) |
| 6 |
| Plan: Security |
| How areas/rooms and property will remain secure from delivery thru acceptance |
| 7 |
| Plan: Training |
| How staff will be trained on new property (to include FFE and IM-IT/LVS); provide a training schedule, refer to DHA-FE Examples: PP Plan (Training Schedule) |
| 8 |
| Plan: Inspections & Acceptance |
| How inspections and acceptance will be planned, coordinated, executed |
| 9 |
| Plan: Cleaning |
| How cleaning will be planned, coordinated, and conducted in accordance with cited criteria |
| 10 |
| List: Govt Furnished Equipment |