0. DRAFT - SOW-FY22. IOT RD_PN89902_CSDC Charleston_2022.08.05.docx

DOCX document 895 KB Posted

Attached to
Charleston Consolidated Storage Distribution Center Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

This is a special notice for an initial outfitting project at the Charleston Consolidated Storage and Distribution Center. The USACE Little Rock District will issue a request for quote under simplified acquisition procedures and commercial items procedures. The requirement is set aside for small businesses with a NAICS code of 337127 and size standard of 500 employees. The estimated contract value is $1.5 million to $2 million. The quote due date is September 2, 2022 with a site visit scheduled for August 23, 2022. Draft documents are subject to change prior to solicitation issuance. The potential beneficial occupancy date is January 19, 2023 and potential open for business date is March 19, 2023. The notice provides advance information on an upcoming solicitation and invites feedback through ProjNet until August 25, 2022.

View the file

Other files for this federal contract opportunity

Other files attached to Charleston Consolidated Storage Distribution Center, newest first.
File Type Posted
31. DRAFT - Template-Inventory Report-Hardware-Software.pdf PDF
6. DRAFT - JBC CSDC - DP2 FINAL_drawings.pdf PDF
10. DRAFT - JB Charleston CSDC_DOR-Provided Final Furniture-Equipment Package_17Jan22.pdf PDF
22. DRAFT - DHA Privacy Impact Assessment PIA_Processes and Procedures.docx DOCX document
21. DRAFT - DHA MDE Categorization Memo.pdf PDF
11. DRAFT - JSN U0060 Electric Swivel Seated-Narrow-Isle 33' Vertical Swing Reach 3K Fork Lift.pdf PDF
32. DRAFT - Template-Ports-Protocols-Services Management Registry Update.xlsx XLSX spreadsheet
28. DRAFT - Template_Program of Record_DHA Info Sys Contingency Plan.docx DOCX document
2. Real ID TRI-Fold (15Sep20-V42).pdf PDF
27. DRAFT - Template_Information System_Incident Response Plan.docx DOCX document
24. DRAFTExample_IP Network External to Control System_Generic ICS Med-COI Boundary Diagram v4 (1).pdf PDF
18. DRAFT - DHA 27 52 33 Refrigerator Monitoring Systems.pdf PDF
7. DRAFT - CSDC GC Schedule 30Jun22.pdf PDF
11. DRAFT - JSN U0096 3-phase 480 VAC Powered Battery Charger For JSN U0060 Electric Forklift.pdf PDF
2. Base Access WORKSHEET V9_Dec20_ACC (002).pdf PDF
30. DRAFT - Template-DHA-FE FRCS Vendor Risk Assessment_v2.0.docx DOCX document
17. DRAFT - DHA 27 41 43 Audio Video Conferencing.pdf PDF
16. DRAFT - Checklist_Control System Factory Acceptance Test and Site Acceptance Test.pdf PDF
9. DRAFT - JB Charleston CSDC_Existing Inventory_ 23Mar22.pdf PDF
29. DRAFT - Template-DHA RMF System Enterprise and Information Security Architecture.pdf PDF
26. DRAFT - Template_DHA RMF System Authorization Boundary.pdf PDF
23. DRAFT - DHA RMF Information Flow Diagram.pdf PDF
14. DRAFT - JBCHS IDEA FONSI-FONPA_A7 Signed (2).pdf PDF
33. DRAFT - Template-System Level Configuration Management Plan.doc DOC document
3. DRAFT - Charleston CSDC IOT Project Status Report (PSR).xlsx XLSX spreadsheet
19. DRAFT - DHA ACAS-NESSUS Scanning Guide-CUI.pdf PDF
12. DRAFT - DHA FE Wayfinding Guidelines-Signage Standards (Draft)_01Mar22.pdf PDF
11. DRAFT - JSN U1021 Wall-MountedWireGuidanceSystemLineDriverandGuidanceControlWire-Forklift(JSN U0060).pdf PDF
5. DRAFT - Interiors_JBC CSDC - DP2 FINAL_drawings.pdf PDF
1. DRAFT - Drawings Installation Map - CSDS and ACC.pdf PDF
8. DRAFT - JB Charleston CSDC_PRCL_v.2_21Jan21.pdf PDF
20. DRAFT - DHA FRCS Baseline Categorization Memorandum-1 Oct 2020.pdf PDF
0. DRAFT FY22 IOT CSDC_Div 00_CLIN BID Schedule.xlsx XLSX spreadsheet
15. DRAFT - JB Charleston CSDC_Facility Site Approval.pdf PDF
13. DRAFT - JB Charleston CSDC_Program for Design_5Feb22.pdf PDF
Draft Solicitation_Special Notice_Charleston CSDC.pdf PDF
25. DRAFT - Template_DHA RMF Security Control Plan_Implementation Guidance.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IO&T REQUIREMENTS: FY22 Charleston CSDC (OM-IOT) PROJECT NO 89902 DATE: 24 June 22 (v.02)

Table of Contents

Table of Contents2
1General Requirements4
1.1General Requirements4
1.1.1Overview4
1.1.2Project Information4
1.1.3Work Restrictions5
1.1.4Progress & Completion Photos5
1.1.5Meetings & Reporting5
1.1.6Schedule7
1.1.7Submittals10
1.1.1Acceptance & Transfer Documentation10
1.2Initial Outfitting12
1.2.1General12
1.2.2Qualifications: Initial Outfitting Personnel15
1.2.3Submittals: FFE-LVS16
1.2.4Furniture, Fixtures, Equipment (FFE) Package16
1.2.5Low Voltage System (LVS) Package17
1.2.6FFE-LVS Execution Plan18
1.3Transition18
1.3.1General18
1.3.2Qualifications: Transition Personnel24
1.3.3Submittals: Transition Plan25
1.4Acceptance & transfer of property27
2Functional Requirements27
3Interior Design Requirements27
3.1General27
3.1.1Qualifications: Interior Design27
3.1.2Submittals: Furniture & Fixtures28
3.2Division 10: Specialties28
3.2.1New Signage-Interior (PP)28
3.2.2New Storage & Lockers (PP)28
3.2.3New Fire Protection Items (PP)29
3.3Division 12: Furnishings (Furniture, Accessories, Casework, Artwork, etc.)29
3.3.1New Furnishings (PP)30
4Equipment Requirements31
4.1General31
4.1.2Qualifications: Equipment32
4.1.3Submittals: Equipment33
4.2Division 11: Equipment (Medical, Institutional, Office, Etc.)33
4.2.1New Equipment (PP)34
4.2.2Reused Equipment34
5Communication Requirements34
5.1General35
5.1.1Order Criteria Applies36
5.1.2Site Investigation Report: Communication Systems36
5.2Qualifications: Communications36
5.2.1Communications Systems Engineer (CSE)36
5.2.2Registered Communications Distribution Designer (RCDD)36
5.2.3Cybersecurity Consultant36
5.3Submittals: Communications (Design)37
5.3.1Order of Applicability37
5.3.2Distribution & Medium37
5.3.3LVS (RPIE vs PP)37
5.3.4LVS Package38
5.4Submittals: Communications38
5.4.1LVS Submittals38
5.4.2Building Equipment Rooms & Structures: Communications39
5.4.3Commissioning39
6Division 25: Integrated Automation (Cybersecurity)40
6.1Risk Management Framework (RMF)40
6.2Submittals: Cybersecurity41
6.2.1Design Submittals42
6.3Schedule Constraints: Cybersecurity45
7Division 27: Communications (Infrastructure, Phone, Data, etc.)45
7.1Telecommunications Interior Infrastructure45
7.2Classified Telecommunication Infrastructure45
7.3Telecommunications Pathways & Cabling45
7.4Backbone Cabling – Optical (RPIE)46
7.5Cabling System - Building Telecommunications (RPIE)46
7.6Work Areas46
7.7Grounding Bonding, and Static Protection46
7.8Telecommunications System Administration46
7.9Telecommunication System Testing46
7.10Service Specific Requirements46
7.11System Infrastructure46
7.12Real Property Installed Equipment (RPIE)46
7.13Personal Property (PP)46
7.14Data Communications Wireless Access Points (IS-PP)47
7.15Wireless Local Area Network (WLAN) Heat Mapping47
7.16Data Communications Network Equipment (IS-PP)47
7.17Sound Masking Systems (FRCS-PP)48
8Division 28: Electronic Safety & Security (Fire Alarm & Electronic Security System)48
8.1Fire Alarm & Detection (RPIE)48
8.2Electronic Security Systems (ESS) (PP)48
9Division 33: Utilities (Telecommunications Outside Plant)48
10REFERENCES48
11Attachments50

General Requirements General Requirements Overview The Defense Health Agency-Facilities Enterprise (DHA-FE) requires Initial Outfitting and Transition (IO&T) services for the FY22 MILCON Warehouse Replacement Project at Charleston AFB, SC.

Initial Outfitting means to provide new furniture, fixtures, equipment, and low voltage systems (FFE-LVS) classified as Personal Property[footnoteRef:1] in new or newly renovated facilities. [1: Personal Property = non-fixed modular, moveable furniture, fixtures, equipment, & low voltage systems (FFE-LVS). It is not Real Property Installed Equipment (RPIE)]

Transition services generally includes (1) relocating reuse FFE-LVS, (2) disposing of non-reuse FFE-LVS, (3) public relations (PR) support, (4) staff orientation & training, and (5) cleaning prior to occupancy of the new or newly renovated space.

Project Information

PROJECT INFORMATION

A
Real Property Jurisdiction
Department of the Air Force
B
Location
JB Charleston, Charleston, South Carolina
C
Project Delivery Method
IOT Stand-Alone
#
FACILITY INFORMATION
FACILITY 1
FACILITY 2
FACILITY 3
1
Project Number
89902
89902
89902
2
Project Title
CSDC Charleston
CSDC Charleston
CSDC Charleston
3
Facility Number
00697
N/A
4
Facility Name
Warehouse
Leased Building
New Bldg
5
Square Footage
10,000
75,000
95,474
6
Real Property Categorization
5306
5306
5306
7
Medical Treatment Facility Type
Medical Warehouse
Medical Warehouse
Medical Warehouse
8
Facility Function
Warehouse
Warehouse
Warehouse
9
Scope Description
Demolish
Transfer Only
New Construction
10
Fund Sources
MILCON
N/A
MILCON
11
Level of Construction
Demo

Permanent

12
Department Name(s)

Materiel Receiving/Processing, Materiel Staging, Materiel Storage, and Biomedical Equipment Repair

13
Current Use (Occupancy)
Storage
Storage
N/A
14
New Use (Occupancy)
N/A
N/A
Storage
15
Historical Status
No
N/A
No
16
Archeological Site
No
No
No
17
Defense Medical Information System Identifier (DMIS ID)
0356
N/A
0356

The existing Joint Base (JB) Charleston Medical Readiness mission is supported by Building 697 and a leased building off base. The Air Force Surgeon General (SG) approved Consolidated Storage and Distribution Center (CSDC) for CONUS-based War Readiness Material (WRM) so Building 697 will be replaced and the lease for the building off base will end.

Work Restrictions Continued Occupancy All departments within the existing facility will remain in operation during the entire Period of Performance (POP) unless specifically stated herein. Permission to interrupt operations must be submitted in writing within the timelines outlined in the section titled Schedule Constraints.

Base Access & Work Hours When arranging access to Charleston AFB, there is a minimum of 72hrs pre-notice to process Form 74. COR and Project officer will assist in processing base access and provide further details on what documents and forms are required.

Work hours within the existing facility, and on and around the site, are outlined in the following table. Work outside these hours requires approval and must be requested within the time outlined in the section titled Schedule Constraints.

DAYS
WORK PERIOD
START
END
Monday-Friday
10 hours
7:00 am
5:00 pm
Saturday
10 hours
7:00 am
5:00 pm
Sunday
0 hours
0
0

Contractor Access and Use of Premises Contractor installation access instructions are defined in the Attachment: Installation Contractor Requirements.

Concurrent Projects

#
PROJECT
GENERAL WORK DECRIPTION
GENERAL AREA/ LOCATION AFFECTED
ESTIMATED COMPLETION/ DURATION
1
ACC Modernization
Modernization and reorganization of select MTF departments.
Main MTF around the corner from the CSDC Site
March 2025
2
HAAMS
Storage facility for Specialized Training
Adjacent to the MTF
May 2022
3
Temporary Passenger Terminal
30ft South of the CSDC site
July 2022 – Sept 2022

Progress & Completion Photos Provide pre-work, progress, and completion photos for the spaces outlined in the following table.

#
SPACE
1
Primary & Secondary Entrances
2
High Bay Storage
3
Loading Dock
4
Office Space
5
Conference Room
6
Vault
7
Walk In Cooler

Meetings & Reporting Meeting Logistics Coordinate Agendas and meeting arrangements with the government prior to the meeting date. Notify the government of workspace requirements necessary to conduct the meeting (e.g., required number of meeting rooms, tables, chairs, presentation boards, teleconferencing ability, wi-fi connectivity, etc.). Provide equipment, accessories, and documents necessary to conduct the meeting. Include the meeting address, building, and room number on all agendas.

Potential Changes Documentation At the close of each meeting identify Potential Changes that may impact the project cost, scope, schedule, or safety. Document it as a risk on the IOT Project Status Report (PSR), circumstance or individual driving the change, and, if approved, government individual approving the change. Refer to section Project Status Report.

Government Representatives Coordinate agenda, meetings, activities, and deliverables with the government representatives listed in the table below. The IOT Contractor is not permitted to meet with CSDC representatives (aka “Users”) unless the DHA-FE Project Officer/Lead or IOT Planner (or their designee) can attend.

#
AGENCY
REPRESENTATIVE
ROLE
1
Contracting Activity (aka Agent)
Contracting Officer
Responsible for entering a contract on behalf of the Government
Contracting Officer Representative
Responsible for administering the contract on behalf of the Contracting Officer
Project Manager
Manages the project scope on behalf of the Contracting Activity/Agent
Quality Assurance Evaluator/Representative
Assures products and work complies with government quality standards
5
DHA-FE
Project Officer/Project Lead (PO/PL)
Leads DHA-FE project team; project’s primary point of contact (POC)
Facility/Clinical Planner
DHA-FE project team members (referred to as the “Integrated Project Team” (IPT); supports PO/PL for project’s life cycle; develops project requirements on behalf of the project sponsor (DHA-FE); reviews submittals for compliance/conformance; serves as healthcare subject experts for their respective discipline.

Interior Design Planner

Equipment Planner

Communications Rep (aka IM-IT Planner)

Architectural Planner/Representative

IOT Planner

Transition Coordinator
Coordinate property management & transition service activities
13
CSDC
Facility Manager (FM)
Manages Facilities environment of care, safety, ops, maintenance
Logistics
Oversees property management and procurement activities
Information Systems (IM-IT)
Maintains information management/technology Systems
Medical Equipment Maintenance
Maintains Medical Devices and Equipment on behalf of the facility
Safety & Security
Provides safety and security oversight on behalf of facility
Equipment Custodian
Responsible for all property located within assigned department
Infection Control
Responsible for infection control compliance
Department Representatives
Serves as department’s representative to support the transition
Information Systems Security Manager (ISSM)
Responsible for the development, implementation, assessment, and monitoring of common controls.
GOV Site Information System Owner (ISO)
Responsible for the overall procurement, development, integration, modification, operation, maintenance, and disposal of an information system
GOV Information System Security Officer (ISSO)
Responsible for developing and enforcing security policies for the information system, managing/controlling changes to the information system and assessing the security impacts of those changes.
24
Installation
Installation Rep
Represents installation’s security, site, and comm requirements
Authority Having Jurisdiction (AHJ)
Refer to UFCs

Weekly Progress Meetings Conduct Weekly Progress Meetings with the government representatives. Provide agendas, meeting minutes, action items, and attendance records. At a minimum, include agenda items outlined in the table below.

#
AGENDA ITEM
TOPIC
DISCUSSION
1
IOT Project Status Report (PSR)
IOT Project Status Report (PSR)
Overarching risks and changes
Overview
Changes
Cost
Changes and potential exposure
Schedule
Changes to milestones and Impact on project schedule and critical path
Scope
Changes in scope for all disciplines
Risk
Review risks, strive for resolution, assign a point of contact to work issues
Requests for Information (RFI)
RFIs’ that require resolution and/or action
Distribution
Determine if distribution requirements changed
9
Meeting Minutes
Previous meeting minutes and corrections; upcoming meetings & site visits
10
Submittals
Upcoming and outstanding submittals

IOT Project Status Report (PSR) Maintain the Attachment: IOT Project Status Report (PSR). Document project status, information, and issues. The PSR (also known as the Weekly [Risk] Report) outlines submittal distribution requirements. The purpose of the PSR is to keep senior leadership and the project team informed of risks related to cost, schedule, scope, and safety. The PSR serves as a repository of relevant and historical information and is used extensively for studies, analysis, and senior-level reporting. It enables team members to proactively manage issues and minimize risks real time.

Update the PSR weekly until receipt of the final DD Form 1354: Transfer and Acceptance of Real Property and final set of DD Form 250 is the Material Inspection and Receiving Report (MIRR).

Review the PSR during weekly progress meetings. Highlight changes, updates, and edits. It is critical the PSR reflect accurate and current information and all fields are complete. Failure to maintain this document could adversely impact the project, funding, programming decisions, prompt resolution, change management, and ultimately affect the contractor’s performance rating.

Tracking Potential Changes Use the IOT Project Status Report (PSR) to clearly identify any adjustments which may have a potential cost, schedule, scope, safety, or quality change. Should one be identified, notify the Contracting Officer (KO) in accordance with the Contract Clauses. The PSR is the mechanism used to inform the project team of potential risks.

Meeting Minutes and Written Records Prepare detailed and accurate written records of each site visit and meeting. Refer to the IOT Project Status Report (PSR) Distribution List for distribution requirements. Include agenda, subject, names of participants, relevant details, action items, responsible team member, and required resolution date. Illustrate and/or include contract documents reflecting scope additions and deletions. Summarize work the contractor believes is outside the contract scope. Number written records in consecutive order. Provide electronic copies of all written records, agendas, presentations, and meeting minutes in each submittal.

File Naming Conventions, Electronic Submittals, & Distribution Provide standardized electronic naming conventions to ensure timely government responses. Include numerical date (i.e., 20220330 for 30 Mar 2022), fiscal year (FY), installation name, submittal/RFI/ASI number, and project number. Do not exceed thirty (30) characters or include special characters (e.g., 20220301_FY24_FtBragg_DS4_PNXXX). Distribute electronic submittals to the government via a publicly accessible site (such as Microsoft® SharePoint® or equivalent). Provide electronic submittals in accordance with the IOT Project Status Report (PSR). Provide electronic submittals with a single file structure with proper bookmarks. Each file size may not exceed 50 megabytes (MB).

Review & Resolution Conferences Review and resolution conferences are to be held following each submittal. Review open issues or actions from the last meeting, what occurred, and what is planned to occur before next meeting. Reviews should focus on critical path items and activities that may impact the project’s schedule/scope. The objective of the review or resolution conference is to resolve any outstanding compliance or conformance deficiencies identified by the government. No comment should be left unresolved before moving forward to the next submittal.

Schedule Project Schedule (Detailed Requirements) & Period of Performance (POP) The Period of Performance (POP) includes the activities and deliverables outlined in the tables below. Beneficial Occupancy Date (BOD) is determined by the Construction schedule. Open for Business (OFB) should occur within 60 days of BOD.

Current BOD is 19 Jan 2023

A
INITIAL OUTFITTING/FFE-LVS INSTALLATION
INCLUDED POP/SCHEDULE
1
Notice to Proceed
Yes, prior to install date schedule asap after award to reflect these dates
2
FFE-LVS Submittals 1-2
3
Procurement
4
Delivery/Storage
5
Installation of Personal Property
Yes, prior to Transition Start
6
Testing
7
Certifications
8
Cleaning
9
Inspections
10
Acceptance
11
Train Staff
12
Property Transfers
B
TRANSITION
INCLUDED POP/SCHEDULE
1
Transition Submittals
Yes
2
Orient Staff Members
Yes, upon completion of FFE-LVS install, prior to each phased move
3
Property Moves

Yes, 2-workdays by phase

4
De and Re-Installations
5
Testing
6
Certifications
7
Inspections
8
Acceptance
9
Temporary Signage
10
Move Occupants
11
Clean (Aseptic)
12
Dispose
Yes, shall not impede critical path
13
Survey (Lessons Learned)
Yes

Schedule Constraints Due to DHA-FE and the CSDC operational constraints, schedules must account for the constraints outlined in the table below. These schedule constraints take precedence over those listed in the attached documents and/or specifications.

NO
ACTIVITY/DELIVERABLE
SCHEDULE CONSTRAINTS (CALENDAR DAYS)
1
Acceptance Docs: Reuse FFE-LVS (Interim)
45 days prior to Conditional Acceptance
2
Acceptance Docs: Reuse FFE-LVS (Revised)
21 days prior to Conditional Acceptance
3
Acceptance Docs: Reuse FFE-LVS (Final)
21 days to Final Acceptance
4
Acceptance Forms: New FFE-LVS (Interim)
45 days prior to Conditional Acceptance
5
Acceptance Forms: New FFE-LVS (Revised)
21 days prior to Pre-Final Acceptance
6
Acceptance Forms: New FFE-LVS (Final)
21 days prior to Final Acceptance
7
Acceptance Inspections (Notice)
45 days prior
8
Acceptance Submittals (O&M Manuals)
At time of installations
9
Disposition Plan (& Notice Date to Begin) DD Form 1348-1A Disposal Turn-In Form
Coordinate deliveries w/ Logistics & DLA-DS NLT 90 days prior to disposition
10
Documentation (Warranty & Maintenance)
15 days post acceptance; 21-day Govt review
11
Inspection (Punch Lists & Inspection Findings)
7 days following government inspection
12
Inspection Docs: Corrected Final Documents
14 days prior to Final Inspection
13
Inspection Docs: Notification: Inspection
21 days prior to inspection
14
Inspection Docs: Systems & Equipment Testing List
90 days prior to testing
15
Lessons Learned Survey (Distribute Reports)
NLT 45 days following survey distribution
16
Lessons Learned Survey (Transition & PR) (Distribute Surveys)
NLT 14 days following moves by phase
17
Meeting (Kick-Off)
7 days following Notice to Proceed (NTP)
18
Meeting Agendas (Draft)
45 days prior to meeting date
19
Meeting Agendas (Final) & Attendee Confirmation
10 days prior to meeting
20
Meeting Minutes & Written Records
5 days following meeting/conference
21
Meeting: Comm/LVS Coordination Meeting
Bi-Weekly; commence NLT 120 prior to moves
22
Meeting: FFE-LVS Third-Party Vendor Coordination
Coordination with facility NLT 6 mos. prior to start
23
Meeting: IOT Project Status Report (Risk Identification)
Within 14 days of identification
24
Meeting: IOT Project Status Report (Risk Resolution)
30 days of identification
25
Meeting: Transition Planning
Minimum Bi-Weekly; commence NLT 90 days prior to moves
26
Notice: Disruption of Utility Services
14 days prior to shutdown
27
Notice: Facility Cleaning
120 days prior to moves
28
Notice: FFE-LVS Installation
21 days prior to installation
29
Notice: Installation Security Notification
60 days prior to mobilization
30
Notice: Preliminary Moves - Notification
60 days prior to target move date by phase
31
Notice: Street Closings
30 days prior to closure
32
Notice: Traffic Disruptions/Traffic Control Plan
14 days prior to work commencement
33
Notice: Work holidays, weekends, after hours
14 days prior to commencing work
34
Notice: Final Moves Notification
21 days prior to Conditional Acceptance by phase
35
Notice: Request for Time Extensions
Refer to Contract Clauses
36
Performance Forms: Contractor Address/Resolve Rating
Contractor 7 days to respond to rating; Govt 7 days to confirm
37
Provide Attic Stock
Within 30 days of Govt acceptance of each phase
38
Public Relations (Coordinate Ceremony Materials/Postings)
Review w/facility a min of 45 days prior to release
39
Public Relations (Distribute materials /postings & handouts)
Min of 90 days prior to move or ceremony
40
Record Documents (Draft/Final)
21 days for review
41
Request for Information (RFI)
Govt 14 days to respond
42
Resumes (Key Personnel-Revisions)
Project kick-off meeting
43
Resumes (Updated Key/FFE-LVS Personnel)
Provide to Govt at time of project kick-off meeting
44
Schedule (Closeout & Warranty)
60 days prior to inspection; govt review = 21 days
45
Schedule (Updates on PSR)
7 days of meeting date or major shift in schedule
46
Submittal (Initialed PRC room drawings)
7 days following conditional inspections
47
Submittal (O&M Data Changes)
14 days of Govt notification
48
Submittal 1: Comm/LVS Binder (Draft)
NLT 12-mos prior to Conditional Acceptance Date (PH1 if project is phased)
49
Submittal 1: Department Transition Plan (Draft)
50
Submittal 1: FFE Binder (Draft)
51
Submittal 1: FFE-LVS Execution Plan Binder (Draft)
52
Submittal 1: Transition Plan (Draft)
53
Submittal 2: Comm/LVS Binder (Corrected Final)
NLT 6-months prior Conditional Acceptance Date (PH1 if project is phased)
54
Submittal 2: Department Transition Plan (Corrected Final)
55
Submittal 2: FFE Binder (Corrected Final)
56
Submittal 2: FFE-LVS Execution Plan Binder (Corrected Final)
57
Submittal 2: Transition Plan (Corrected Final)
58
Submittal 2: FFE-LVS Training Schedule, Testing & Certification Schedule (new & reuse) (Corrected Final)
Distribute revisions 60 days prior to move commencement by phase
59
Submittal 2: Transition Plan: Final Activity Schedules, Move Guides, Move Spreadsheets & “Day in the Life” (Corrected Final)
Distribute handouts 14 days prior to move commencement by phase
60
Submittals: Final Corrected
21 days of correction; govt review = 15 workdays
61
Submittals: Government Review Period
21-day review period
62
Submittal: O&M Manuals (to include Facility Data)
At time of RP, RPIE, PP Conditional Acceptance
63
Testing & Certification: Comm/LVS Coordination
Coordinate with installation security NLT 120 days prior to system install

Operational Time Constraints The tables below outline functional, operational, and phasing time constraints. Consider these constraints during development of proposals, phasing/transition plans, and project schedules.

#
CONSTRAINT
1
Contractor work must not negatively impact facility operations
2
Contractor must work within the time constraints outlined in the section titled Schedule Constraints
3
Departments may not be closed for more than 2-work days during the transition period.
4
All existing security systems are to remain fully operational (i.e., Duress, IDS, Card Access, etc.)

Submittals Quantity of Submittals Provide the number of submittals outlined on the Attachment: IOT Project Status Report (PSR) (Distribution List).

Submittal Register Within 30-days of contract award, provide a Submittal Register listing required submittals in the table below.

NO
SUBMITTAL REQUIREMENTS
SUBMITTAL REGISTER REQUIRED
1
FFE-LVS Submittals (IO)
Yes
2
Transition Submittals (T)
Yes
3
Activation Submittals (A)
Yes
4
Cybersecurity Submittals
Yes (Refer to section titled Division 25)

Submittal Deviations Documents submitted with the solicitation, and proposals accepted by the government, are considered the contract documents and must be used to track cost, scope, and schedule adjustments for the project duration. During the project, document any deviations to the contract documents by highlighting changes to the (1) PRC quantity, (2) CID, (3) specifications, (4) additional accessories to a particular JSN or system, (5) PRC deletions or additions of a JSN or system, and/or (6) PRC changes from a JSN or system from “reuse” to “new” or vice versa. The contractor is not authorized to execute changes, or exceed the contract price, without a contract modification. Summarize and highlight all deviations on the awarded or modified contract documents and provide with each submittal. Use a different color to highlight submittal revisions or deviations. Document deviations in the government accepted CLIN Schedule.

0. Acceptance & Transfer Documentation Acceptance Milestones & Terminology The following figure illustrates acceptance milestones, terminology, and associated documentation. Include transition, activation, real property, and personal property acceptance milestones in project schedules and the IOT Project Status Report (PSR). Incorporate this terminology in all project schedules.

Submit property transfer documentation (e.g., DD Form 1354: Transfer and Acceptance of Real Property and DD Form 250 is the Material Inspection and Receiving Report (MIRR). The following table outlines the project phase and deliverables related to work acceptance[footnoteRef:2] and property type transfers. Refer to UFC 1-300-08 Criteria for Transfer & Acceptance of DoD Real Property. [2:

#
PHASE DUE
RESPONSIBILITY
PROPERTY
MILESTONE
ACCEPTANCE DOCUMENTATION
1
Design (PH5)
Designer of Record (DOR)
New RP/RPIE/EIP
Draft Transfer Documents
Draft DD Form 1354s (as part of Final Design Submittal)
DOR/PP Contractor
New PP

Draft DD Form 250s (as part of Final Design Submittal)

3
Construction (PH6)
Construction Contractor
New RP/RPIE/EIP
Conditional Acceptance
Interim DD Form 1354, Punchlist, AHJ & ATO Docs
4
Initial Outfit (PH7)
IO/T Sub/Contractor
New PP

Interim DD Form 250s, Punchlist, AHJ & ATO Docs

5
Transition (PH7)

Activation (PH8)

Construction Contractor
New RP/RPIE/EIP
Final Acceptance
Final DD Form 1354, Punchlist, AHJ & ATO Docs
IO/T Sub/Contractor
New PP

Final DD Form 250s, Punchlist, AHJ & ATO Docs

Reuse

Reuse Property Transfer Documentation: (1) PRC (2) Existing Inventory List of Reuse Items; (3) Room-By-Room Drawings

The following table outlines who are authorized to take acceptance of the property.

No
Document
Section
Authorized Government Rep
1
DD Form 1354 (Real Property & Real Property Installed Equipment (RPIE))
27 Transferred By
Contracting Officer Representative (COR)
28 Accepted By
Facility Manager (FM)
3
DD Form 250 (Personal Property)
21a. Origin
Prime/IOT Contractor
21 c. Destination
DHA-FE IO/T Coordinator (if assigned). PO/PL if no IO/T Coordinator
22 Receiver’s Use
Logistics Representative (Property Book Custodian)
6
Existing Inventory/PRC (Reuse FFE-LVS)
All
Logistics Representative (Property Book Custodian)
7
Punchlist (RP/RPIE/PP)
All
Contracting Officer Representative (COR)/Project Officer/Project Lead
8
AHJ Documentation
All
AHJ/Fire Protection Engineer
9
ATO Documentation (Communications)
All
Chief Information Officer (CIO)/ISSM

Acceptance Classifications All inspection and acceptance items specified for correction via the “punch list” will be assigned an acceptance classification to include (1) Counterfeit, (2) Critical Non-Conformance, (4) Major Non-Conformance or (5) Warranty.

a. Counterfeit Item means an unlawful or unauthorized reproduction, substitution, or alteration that has been knowingly mismarked, misidentified, or otherwise misrepresented to be an authentic, unmodified item from the original manufacturer, or a source with the express written authority of the original manufacturer or current design activity, including an authorized aftermarket manufacturer (e.g., used items represented as new, or the false identification of grade, serial number, lot number, date code, or performance characteristics).

b. Critical Nonconformance means a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services; or is likely to prevent performance of a vital agency mission.

c. Major Nonconformance means a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose.

Acceptance Terms

a. Conditional Acceptance is when the government accepts the contractor’s work even though it is not yet complete and/or does not conform to the contract quality requirements. It includes a specified date to correct or otherwise complete the work[footnoteRef:3] and occurs once the Contracting Officer notifies the project sponsor (i.e., DHA-FE) that the work has reached Substantial Completion. Construction Conditional Acceptance is synonymous with Placed in Service (PIS) date and Beneficial Occupancy Date (BOD). [3: FAR 46.5 Acceptance, UFC 1-300-08 Criteria and Transfer and Acceptance of Real Property, FAR 46.101 Quality Assurance

b. Final Acceptance means an authorized government representative assumes ownership of the property, determines services rendered are complete, in accordance with the contract. Final acceptance includes Authority to Operate (ATO) documentation. Final Acceptance is synonymous with Construction Complete and Open for Business (OFB).

Initial Outfitting General Provide new Furniture & Fixtures outlined in the section titled Interior Design Requirements. Provide the Equipment outlined in the section titled Equipment Requirements. Provide the Low Voltage Systems (LVS) outlined in the section titled Communication Requirements.

There are two types of Furniture, Fixtures, Equipment and Low Voltage Systems (FFE-LVS) (1) Real Property Installed Equipment (RPIE) and (2) Personal Property (PP). The table below outlines (1) the property types, (2) nomenclature, (3) appropriation or fund source, (4) definitions, and (5) which set of criteria typically applies. Attachment: Project Room Contents (PRC) outlines what FFE is considered RPIE versus PP. MIL-STD-1691 Military Medical & Dental Facilities: Policy Document (FFE-LVS) outlines what LVS is considered RPIE versus PP.

Comply with referenced criteria and standards outlined in the table below unless otherwise explicitly stated. Exceptions: Some equipment or systems such as Electronic Security Systems (ESS) must comply with both and . Other exceptions are noted throughout this document.

#
PROPERTY TYPE
ALSO KNOWN AS
APPROPRIATION/

FUND SOURCE

DEFINITION[footnoteRef:4] [4: Reference: UFC 1-300-008 Criteria for Transfer and Acceptance of DoD Real Property]

APPLICABLE CRITERIA & STANDARDS*

1
Real Property Installed Equipment
RPIE or Installed Building Equipment (IBE)
MILCON or Operations & Maintenance (O&M)

Also known as “Project Funds”

Property affixed and built into the facility as an integral part of the facility; necessary to make facility complete, and if removed, would destroy, or severely reduce the usefulness of the facility
and
2
Personal Property
Expense Equipment

(1-year money)

Initial Outfitting & Transition (OM-IOT)
Property (systems and equipment, materials, and supplies) except real property
and

Investment/Expense Equipment (2-year money)

Research, Development, Evaluation & Training (RDT&E)
Property (except real property/ Property that consists of capital and other nonexpendable equipment

Equipment in Place (EIP) or Investment Equipment (3-year money)

Procurement (P)
Property that consists of capital and other nonexpendable equipment of a movable nature that has been fixed in place or attached to the real property but is not an integral part of the facility

Space Planning & Document Updates Prior to Submittal 1 conduct a detailed Survey and Existing Inventory of FFE-LVS for all departments and spaces impacted by construction or moves. Based on these findings, markup[footnoteRef:5] the DOR or government-provided (“G”) documents to reflect field-verified conditions; prior to FFE-LVS procurement date, and 6-months prior to expected installation. The scope of this effort includes: [5: Markup = colored highlights, clouds, etc. ]

a. Field Verification (field verify room configuration, infrastructure, structural conditions, and impact on FFE-LVS)

b. Project Room Contents (PRC) (confirm new versus reuse and logistical responsibility)

c. MEP/Architectural Drawings (new and reuse FFE-LVS)

d. FFE/Equipment Drawings (new and reuse FFE)

e. Communication Drawings (new and reuse LVS)

f. Specifications/Cutsheets (new equipment and LVS)

g. Room Data/Illustration Sheets (new furniture and fixtures)

h. Change Summary (Document summarizing required changes to infrastructure/structural)

i. Existing Inventory List (C): All existing property must be documented on an updated and contractor-maintained Existing Inventory List (C) derived from the Attachment: Existing Inventory List(s) (also referred to as the Defense Medical Logistics Standard Support (DMLSS) Accountable Medical Device Equipment (MDE) List and DMLSS RPIE List). In addition to what is listed as reuse on the contractual PRC, incorporate findings from the Existing Inventory List (C) on a sortable Microsoft® Excel® spreadsheet. Include information found in the table below.

j. Space Planning. Prior to the placement of the FFE-LVS, field verify existing site conditions to include architectural, mechanical, electrical, communications, fire protection, and civil-structural conditions. Contractor updated FFE space plans (drawings) must show all electrical, communications, mechanical (i.e., fume/exhaust hoods), and plumbing interface (i.e., sinks, water connections, medical gas) on the same drawing.

k. Reuse FFE. Reuse is defined as property with 24-months of useful life remaining at the time of re-installation. As part of the submittal review process, the Biomedical Equipment Technician (BMET) will verify if equipment meets this definition and is scheduled for reuse or disposition.

#
EXISTING INVENTORY CONTENT
1
Confirm what property is to be moved, relocated, and reinstalled (reuse)
2
Include room level information for current, interim, and final locations
3
Confirm reuse items planned for the project meet the operability, durability, and safety requirements
4
Determine reuse items will fit within allowable space in new facility; notify project leadership if they will not
5
Confirm items will have necessary utilities to function in accordance with manufacturer specifications
6
Determine if reuse items can be delivered into the new facility via corridors, doors, etc.
7
Determine which items should be denoted for excessing and disposition
8
Include utilities, dimensions, and photographs for all Medical Device Equipment (MDE)
9
Include JSN, Nomenclature, quantities, Equipment Control Numbers (ECNs)
10
Include existing artwork
11
Coordinate reuse vs. disposal with facility FM, BMETs, Logistics, Property Custodians

Storage & Staging Provide an FFE-LVS Execution Plan: Storage & Staging Plan. Prior to each submittal coordinate plan details with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Government provided storage space is not available. Staging requirements must be coordinated and approved by the Facility Manager prior to need date. Provide warehousing and storage necessary to deliver, move, stage, and install property. Replace in-kind all property damaged during moves or transport. Store property in environmentally controlled spaces and provide water line shock treatment in accordance with manufacturer recommendations.

Delivery & Installation Provide an FFE-LVS Execution Plan: Delivery & Installation Plan. Prior to each submittal coordinate plan details with project representatives from facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Deliver and install all new FFE-LVS. Protect areas and equipment from damage during moves and installation. Provide drop cloths and other coverings necessary to protect all surfaces. Mask and cover wall fixtures, plaques, pictures, bulletin boards, communication equipment, and cables. Move furniture, equipment, or other items necessary to install the property. Return areas to the original condition or as directed by the Contracting Officer.

Prior to installation, confirm placement of commodities with Government Representatives. Ensure installation and placement of FFE-LVS complies with the American Disability Act (ADA) and does not block access to sinks, doors, etc. All Government installed/provided FFE-LVS (e.g., paper towels, hand soap, hand sanitizer, etc.) must be installed and operational prior to inspections. Provide labels for users to distinguish apart hand soap and hand sanitizer dispensers if JSNs are the same.

Mock-Ups (Interior) Not applicable.

Testing & Certification Provide an FFE-LVS Execution Plan: Testing & Certification Plan. Prior to each submittal, coordinate plan details with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Test and certify new FFE-LVS. Test and certify all property in accordance with manufacturer instructions. Certify that testing, measurement, and diagnostic equipment complies with calibration certifications and National Institute of Standards and Technology (NIST) requirements. Provide operational and safety results to the government prior to acceptance and use. Provide qualified Biomedical Equipment Technicians (BMETs) to perform safety checks, inspections, and calibrations on relocated medical equipment.

Security Provide an FFE-LVS Execution Plan: Security Plan. Prior to each submittal coordinate plan details with facility management and safety and security personnel. Secure new FFE-LVS and existing department property. Provide necessary security provisions to keep property safe, secure, and in its designated location. The government is not responsible for the property until formal acceptance. Provide security measures to guard against damage and theft. Employ procedures to track product movement until time of acceptance.

Cleaning/Cleanup Develop the FFE-LVS Execution Plan: Cleaning Plan and coordinate cleaning protocols with project representatives from the facility management and infection control point of contact(s) in advance of cleaning. Include measures to take to ensure a clean work area and compliance with site-specific trash disposal and recycling policies. Provide cleaning services for all areas impacted by installation of new property.

Inspections & Acceptance Provide an FFE-LVS Execution Plan: Inspection & Acceptance Plan. Prior to each submittal, coordinate plan details, inspections, and acceptance activities with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Include copies of all required property transfer forms. Acceptance cannot occur until all property is installed, tested, and certified. Provide deliverables at time of the conditional and final acceptance to ensure the process is efficient and well organized.

Prior to inspections provide (1) a Punch List stating what activities are yet to be accomplished, (2) a Pending JSN & LVS List of FFE-LVS not yet installed to include nomenclature, ECNs, a brief explanation of the issue, and a (3) date it will be resolved.

At time of inspection, provide a current PRC and LVS List and post at the entrance/door of all areas where FFE-LVS is required. The PRC must include all current RPIE and PP JSNs, nomenclature, and ECNs. Update each ECN with the ECN of the item it replaces. This is not required for items not replaced. The current PRC will serve as a checklist for inspections and acceptance.

Upon inspection completion submit (1) Inspected Commodities List in Microsoft® Excel® format, and (2) a scanned copy of the PRC with Government inspectors’ initials and signatures.

The Logistics Officer, or an officially designated representative, must sign all DD Form 250s and DD Form 1354s at time of acceptance.

Operations & Maintenance Data Provide Operations & Maintenance Data for all new FFE-LVS in accordance with the and the .

Training Provide an FFE-LVS Plan: Training Plan and coordinate with project representatives from the facility management, information systems, logistics, equipment maintenance, and department point of contact(s). Train designated personnel to properly operate and maintain new FFE-LVS.

Warranty Provide Warranty Documents in accordance with the and the .

Government Furnished Equipment & Communication Systems Coordinate all Schedules with project delivery team on government-furnished procurement efforts and government managed third-party installations. For each project phase, provide and maintain a Microsoft® Excel® Government Furnished Equipment List (GFE) of all FFE-LVS the facility is responsible to procure (i.e., soap dispensers, information technology gear and equipment, etc.). Indicate required delivery dates. Refer to the section titled Schedule Constraints.

Cybersecurity Provisions Refer to section titled Communication Requirements, Division 25: Integrated Automation (Cybersecurity).

Qualifications: Initial Outfitting Personnel Project Manager Provide an IO/T Project Manager (PM) responsible for the overall life-cycle management and coordination of FFE-LVS and transition services. They serve as the central point of contact for government personnel for all FFE-LVS correspondence, activities, and deliverables. The FFE-LVS PM must have an intimate knowledge of the project requirements, be able to anticipate and control risks related to (1) trades and third-party contractor coordination, (2) space planning of interim and final locations, (3) utilizing reuse property, and (4) transition. They are responsible for adequate internal controls and to minimize operational risks, conflicts, and misunderstandings. The table below outlines the required qualifications.

#
QUALIFICATIONS
REQUIRED
#
QUALIFICATIONS
REQUIRED
(Experience in this role)
Y/N
# YRS
(Experience in this role)
Y/N
# YRS
1
Total Years of Transition Experience
Yes
3
11
Budget & Procurement Documentation
Yes
3
2
DoD Criteria & Standards
Yes
3
12
Proficient in reading design documents
Yes
3
3
On-site construction management
Yes
3
13
Proficient in reading construction docs
Yes
3
4
Well-Versed in Healthcare Operations
Yes
2
14
Risk Management: Quality & Safety
Yes
3
5
Initial Outfit/Supply FFE-LVS
Yes
3
15
Proficient of & understanding of DoD healthcare PP IM-IT systems
Yes
3
6
Transition Services
Yes
3
16
Procurement, delivery, installation
Yes
3
7
New Construction Work
Yes
3
17
Testing, certification, commissioning
Yes
3
8
Multi-Phased Alterations (occupied)
Yes
3
18
Training related to property
Yes
3
9
Demolition & Disposition Work
Yes
3
19
Proficient in reading project schedules
Yes
3
10
Risk Management: Quality & Safety
Yes
3

IOT Personnel Contractor personnel involved with FFE-LVS services are to be present on-site during all moves, installation, testing, certifications, inspections, and acceptance. The Contractor is responsible for coordinating all FFE-LVS activities. Refer to section titled Qualifications: Equipment, Qualifications: Interior Design, Qualifications: Communications.

Submittals: FFE-LVS Submittal Procedures Provide the submittals within the time constraints outlined in Schedule Constraints. Include content listed below. Submittals must comply with applicable , , and . Refer to the Attachment: IOT Project Status Report (PSR) for distribution requirements. Refer to DHA-FE Examples for expected level of submittal development. In addition to electronic updates, provide hard copy updates since the last submittal. Provide a cover sheet for each binder section summarizing the changes within that section.

Prior to mobilization include provisions required in the Health Insurance Portability and Accountable Act (HIPAA). NOTE: If there are submittal discrepancies between what is listed in the table(s) and the then requirements listed in the UFCs apply.

Government Furnished Documents Any government-furnished PRC or Existing Inventory List is designated with a (G). Documentation updated and maintained by the contractor is designated with a (C).

Furniture, Fixtures, Equipment (FFE) Package Provide and/or update the Furniture, Fixtures, and Equipment (FFE) Package in a single binder, and in accordance with the criteria and deliverables outlined in the table below. Include narratives, lists, color boards, forms, and specifications/product data. Large presentation boards and drawings may be provided under separate cover. For additional information refer also to Division 10: Specialties, Division 11: Equipment, and Division 12: Furnishings.

DOR-provided the following deliverables. The following table outlines whether they apply to this project.

· Drawings: Furniture Schedule (with quantities), Furniture & Equipment Plan (placement) (Drawing IF101, IF101A, IF101B)

· Room/Product Data Sheets & Samples (with Manufacturer)

· Drawings: Finishes, Signage, Furniture & Equipment Plan,

· Specifications Project Room Contents (PRC) list (Dated 21 Jan 21):

#
CONTENT
REFERENCE
DELIVERABLE
1
Table of Contents (3-Level)

IOT Contractor to Provide

2
Narrative: Design Analysis (Furniture & Fixtures)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
3
List: Point of Contacts (Project Team)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
4
List: Cost Data (FFE)
UFC 3-120-10 Interior Design; UFC 4-510-01 Design: Military Medical Facilities
IOT Contractor to Provide
5
List: Item Code Legend (aka PP JSN Summary)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
6
List: Project Room Contents (FFE) (Temp/Final Spaces)
UFC 4-510-01 Design: Military Medical Facilities
IOT Contractor to Provide
7
List: Manufacturer Source List
UFC 3-120-10 Interior Design
IOT Contractor to Provide
8
Documents: Best Value Determination (BVD)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
9
Color Boards: Furniture Material Boards (8-1/2 x 11)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
10
Color Boards: Large Scale Presentations
UFC 3-120-10 Interior Design
IOT Contractor to Provide
11
Drawings: Equipment Drawings (FFE)
UFC 4-510-01 Design: Military Medical Facilities
IOT Contractor to Provide
12
Drawings: Architectural Plans w/ FFE
UFC 3-120-10 Interior Design
IOT Contractor to Provide
13
Drawings: Room-by-Room Plans (FFE)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
14
Drawings: Typical (FFE)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
15
Drawings: Systems Furniture (large scale w/ electrical, comm, panels)
UFC 3-120-10 Interior Design; UFGS 12 59 00 Systems Furniture
IOT Contractor to Provide
16
Drawings: Artwork Placement Plans
UFC 3-120-10 Interior Design
IOT Contractor to Provide
17
Specifications: Data Sheets (per Item JSN, Contract & Manufacturer, Make/Model Info, Qty, Cost)
UFC 3-120-10 Interior Design
IOT Contractor to Provide
18
Specifications: Equipment Data & Catalog Cut Sheets
UFC 4-510-01 Design: Military Medical Facilities
IOT Contractor to Provide
20
Specifications: Warranty Information, Contact Information for Repairs, Qualification of Installers and Inspectors, Performance Verification & Acceptance Testing Docs, Operations & Maintenance Data
and UFGS 12 50 00.13 10 Furniture Installation
IOT Contractor to Provide
25
Forms: Property Transfer Documentation (i.e., DD Form 250s)
DD Form 250 Material Inspection & Receiving Report
IOT Contractor to Provide
26
Documentation: Cybersecurity (Equipment Related)
Refer to section titled Division 25: Integrated Automation (Cybersecurity)
IOT Contractor to Provide

Low Voltage System (LVS) Package Provide and/or update LVS Package (i.e., Communication Package) in a single binder in accordance with UFC 4-510-01 Design: Military Medical Facilities, (PP), DD Form 250 Material Inspection & Receiving Report. Include the deliverables listed in the table below. Refer also to the sections titled Division 25: Integrated Automation (Cybersecurity), Division 27: Communications, and Division 28: Electronic Safety & Security. LVS Drawings may be provided under separate cover.

#
CONTENT
DELIVERABLE
1
Table of Contents (3-Level)
IOT Contractor to Provide
2
Narrative: Design Analysis (LVS)
IOT Contractor to Provide
3
List: Point of Contacts (Project Team)
IOT Contractor to Provide
4
List: Cost Data (LVS)
5
List: Item Code Legend (aka LVS Summary)
6
List: Project Room Contents (to include LVS)
7
List: Manufacturer Source List (LVS)
8
Documents: Best Value Determination Forms (LVS)
IOT Contractor to Provide
9
Drawings: Communication Drawings
IOT Contractor to Provide
10
Drawings: Room-by-Room Plans (LVS)
IOT Contractor to Provide
11
Drawings: Typical (LVS)
IOT Contractor to Provide
12
Data/Cut Sheets (per Item, Contract & Manufacturer/Make/Model Info, Qty, Cost)
IOT Contractor to Provide
13
Specifications (LVS) to include Warranty Information, Contact information for repairs, Qualification of Installers and Inspectors, Installation Instructions, Performance Verification & Acceptance Testing Docs, Operations & Maintenance Data

IOT Contractor to Provide

14
Forms: Property Transfer Documentation (i.e., DD Form 250s)
IOT Contractor to Provide
15
Documentation: Cybersecurity (LVS Related)
IOT Contractor to Provide

Content: LVS Package FFE-LVS Execution Plan Provide an FFE-LVS Execution Plan that describes how the contractor will plan, coordinate, and execute the work. Include content outlined in the table below. Include narratives, schedules, and supporting documents. Do not include pricing. List all activities in the order they are to be performed. Coordinate all plans and schedules with the project’s most current schedule. Refer to Attachment: Drawing: Installation Map in the development of the FFE-LVS Execution Plan. Provide in electronic form and one hard copy (2” 3-ring binder) for facility use. Provide cut sheets and specifications in electronic form only.

FFE-LVS EXECUTION PLAN

#
CONTENT
0
Table of Contents
Provide a 3-level Table of Contents
1
FFE-LVS Schedule
Comprehensive schedule outlining the IO execution plan from award, and procurement activities through final acceptance by phase.
2
Existing Inventory List (C)
Refer to section titled Space Planning & Document Updates
3
Plan: Storage & Staging
How property will be insured, stored, transported; include installation access
4
Plan: Delivery & Installation
How property installation process will be planned and executed; include how mock-ups will be planned and scheduled
5
Plan: Testing & Certification
How testing & certification will be planned, coordinated, executed; provide a test & certification schedule, refer to DHA-FE Examples: PP Plan (Test & Certification Schedule)
6
Plan: Security
How areas/rooms and property will remain secure from delivery thru acceptance
7
Plan: Training
How staff will be trained on new property (to include FFE and IM-IT/LVS); provide a training schedule, refer to DHA-FE Examples: PP Plan (Training Schedule)
8
Plan: Inspections & Acceptance
How inspections and acceptance will be planned, coordinated, executed
9
Plan: Cleaning
How cleaning will be planned, coordinated, and conducted in accordance with cited criteria
10
List: Govt Furnished Equipment

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .