Question Set 2

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions for W91ZLK-18-R-0036 |

Page # Section/

Paragraph # Section/Paragraph

Title/Subject Question

Section C, PWS para 3.2

1st sentence, re: Secret Clearance

“All contractor resources supporting this contract shall be … capable of obtaining a Secret Clearance; …”

Will the contractor be required to obtain a Secret Clearance?

C.1.3 Objective, Last sentence states, “Task orders may be classified up to the SECRET level.” Since a number of task orders from other organizations maybe using this contract, their task order may require Secret Clearance. The current Task Order for Evaluation has No Secret Requirement as per Para. 4.3 Security. “The highest clearance required will be NAC background check.”

If so, will the Government provide a Form 254?

56-57 Section L,

(ii) Volume II – Past Performance

Last paragraph on page, PPQ

Sentence states: “The information that is required to be supplied is identified on the form provided below entitled “Past Performance Questionnaires (Attachment 2).”

1. The PPQ (Attachment 7) does not require the contractor fill out scope-specific information. Please clarify.

(ii) Volume II Section L, Past Performance

The proposal must demonstrate satisfactory past performance and contractual completion of relevant projects. Relevant projects are recent projects that are similar to the solicited project in scope, size, and/or complexity. Scope relevancy is defined as those projects that demonstrate past performance in the management of facilities and related logistics for complex government entities and/or large corporations.

Attachment 7, PART 1. In the last bullet asks “Nature of the Contractual Effort” this where we would like the offer to fill out the scope-specific effort

2. Attachment 7 is the PPQ, rather than Attachment 2. (This is a correct statement)

Answer provided in Red

Questions for W91ZLK-18-R-0036 |

56-57 Section L,

(ii) Volume II – Past Performance

1st paragraph The first paragraph states “The Offeror will submit information on at least three (3) but not more than five (5) similar projects.

Other than the PPQ, does the Government require the Offeror to provide relevant projects narratives? If so, can the Government please provide more specific instructions as to what information they require for the relevant contracts?

Yes, offerers must submit relevant project narratives. Relevant projects are recent projects that are similar to the solicited project in scope, size, and/or complexity.

Scope relevancy is defined as those projects that demonstrate past performance in the management of facilities and related logistics for complex government entities and/or large corporations.