Amendment 0001.pdf
PDF 505 KB Posted
- Solicitation number
- W912WJ21B0001
About this file
This document contains an amendment to a solicitation and responses to request for information questions regarding a federal contract for the Boston Harbor Navigation Improvement Project-Phase 3 Rock Removal. The solicitation is to remove material from the Main Ship Channel, Reserved Channel, and President Roads Anchorage in Boston Harbor to authorized project depths of -49 feet or -42 feet in one limited area, with a 2-foot overdepth allowance. Test pit data to estimate overburden depths in the turning basin is shown on an attached figure, with material types expected to be ordinary overburden as described in the solicitation. Responses to requests for additional geotechnical reports reference where digital copies can be accessed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0014.pdf | ||
| Amendment 0013.pdf | ||
| Amendment 0013 Attachment 01 - RFI Letter.pdf | ||
| Amendment 0012.pdf | ||
| Amendment 0011.pdf | ||
| Amendment 0010.pdf | ||
| Amendment 0010 - Boston XYZ - Avg File.zip | ZIP file | |
| AMendment 0010 - Boston XYZ - Min File.zip | ZIP file | |
| Amendment 0009.pdf | ||
| Amendment 0008_BOS XYZ.zip | ZIP file | |
| Amendment 0008.pdf | ||
| Amendment 0007.pdf | ||
| Amendment 0006.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Specs - Boston Harbor Phase 3 Rock Removal.pdf | ||
| Drawings - Boston Harbor Phase 3 Rock Removal.pdf | ||
| W912WJ21B0001_Solicitation.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is issued to provide responses to Request for Information (RFIs). All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Nov-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21B0001
X 9B. DATED (SEE ITEM 11)
14-Oct-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Nov-2020
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ21B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001 RFIs
1. Document 00 32 00 Geotechnical Data, Page 3, Section 1.4 - Existing Reports and Historical Data states:
“…existing reports and historical data, relative to the dredging of Boston Harbor are available. Contact the Contract Specialist if you would like to view any of the below listed reports.”
Please make available for download the all of the Geotechnical reports and historical data listed in Section
1.4 - Existing Reports and Historical Data.
GOVERNMENT RESPONSE:
Boston Harbor Rock Report 2014and Boston 1927 Report can be downloaded from the following site:
https://www.nae.usace.army.mil/Missions/Projects-Topics/Boston-Harbor/Boston-Harbor-Rock-Report-2014/
Due to the size of the report files. Geologic Reports Resulting from Contract no. W912WJ-18-C-0010 will be made available to bidders via the DoD SAFE (Secure Access File Exchange). Interested bidders must email the Contract Specialist, Elizabeth Glasgow at elizabeth.k.glasgow@usace.army.mil to receive a download code for the requested report(s).
2. Section 01 11 00 Summary of Work, Page 6, Section 1.5e – Physical Data: Conditions of Channel states the following: “Materials removed as a part of this contract include both ordinary and hard materials, removed by mechanical means only. In a limited area located within the Turning Basin, ordinary or hard overburden material remains above the rock to be blasted. In order to estimate the depths of the overburden, test pits were performed in February 2020. Location of Test pits and results of test pits are included in Figure TP-1 attached to the end of the specifications.”
Please provide any and all relevant data and results in regard to the test pit geotechnical exploration noted above. We have located Plan Drawing TP-1 on page 390 of the specifications which shows the locations of 26 Test Pits in the Turning Basin, however no results of the test pits have been included.
GOVERNMENT RESPONSE:
"Per Spec Section 01 11 00 SUMMARY OF WORK, Subpart 1.5e Physical Data, test pits were performed to estimate the depths of overburden. Location and depth of overburden achieved is shown in the top left table, "Test Pit Data," located on figure TP-1 attached to the Contract specifications. Detailed material data was not collected as part of this effort. Potential bidders should expect the overburden material types to be those as described in SECTION 01 11 00 SUMMARY OF WORK, Subpart 1.5.e Physical Data, Contract
no. W912WJ-18-C-0010 (expected to be complete by November 2020)."
(End of Summary of Changes)