SPECS.pdf

PDF 37 MB Posted

Attached to
Mechanical Remediation Dredging in the Lower Harbor
Solicitation number
W912WJ-17-R-0003
Issued by

About this file

SPECS

View the file

Other files

File Type Posted
LHCC_PILES.XLSX XLSX spreadsheet
Amendment_W912WJ-17-R-0003-0005.pdf PDF
Core_Photos_a.pdf PDF
Dredge_Area_33B.DWG DWG drawing
Dredge_Area_35G.DWG DWG drawing
Dredge_Area_37B.DWG DWG drawing
Dredge_Area_35C.DWG DWG drawing
Dredge_Area_33C.DWG DWG drawing
Phase_2_CAD_Cell_20170206_20FT_SMOOTH_SHEET-actual.pdf PDF
Dredge_Area_34B.DWG DWG drawing
Dredge_Area_35F.DWG DWG drawing
Dredge_Area_37A.DWG DWG drawing
20170206_3ft_MIN_MLLW_Depth.xyz XYZ file
Dredge_Area_35E.DWG DWG drawing
Amendment_W912WJ-17-R-0003-0004.pdf PDF
Amendment_W912WJ-17-R-0003-0003.pdf PDF
Amendment_W912WJ-17-R-0003-0002.pdf PDF
33B_Target Elevations_XYZ.txt TXT text file
33C_Target Elevations_XYZ.txt TXT text file
Lower_Harbor_Pre_Dredge_Bathy_2014-2015_XYZ.txt TXT text file
34B_Target Elevations_XYZ.txt TXT text file
37B_Target Elevations_XYZ.txt TXT text file
34B_Boundary.dwg DWG drawing
33B_Boundary.dwg DWG drawing
35G_Target Elevations_XYZ.txt TXT text file
35C_Target Elevations_XYZ.txt TXT text file
35F_Target Elevations_XYZ.txt TXT text file
37B_Boundary.dwg DWG drawing
33C_Boundary.dwg DWG drawing
37A_Boundary.dwg DWG drawing
35E_Boundary.dwg DWG drawing
35E_Target Elevations_XYZ.txt TXT text file
Amendment_W912WJ-17-R-0003-0001.pdf PDF
35G_Boundary.dwg DWG drawing
35C_Boundary.dwg DWG drawing
35F_Boundary.dwg DWG drawing
37A_Target Elevations_XYZ.txt TXT text file
PLANS_.pdf PDF
Solicitation_W912WJ-17-R-0003.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912WJ-17-R-0003

Lower Harbor Dredging

New Bedford Harbor Superfund Site New Bedford, Massachusetts

Construction Solicitation and Specifications

DECEMBER 2016

New Bedford Harbor - Lower Harbor Mechanical Dredging

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 32 00

GEOTECHNICAL DATA

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 29 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 CONTRACTOR QUALITY CONTROL

01 45 01 QUALITY CONTROL SYSTEM (QCS)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES

01 54 50 DREDGING PLANT AND EQUIPMENT

01 57 20 ENVIRONMENTAL PROTECTION

01 72 30 FIELD ENGINEERING FOR DREDGING

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 24 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SCOW -

MONITORING PROFILE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

ATTACHMENTS:

ATTACHMENT A - LH PCB DATA

ATTACHMENT B - POC LIST

ATTACHMENT C - CORE L OGS

ATTACHMENT D - UTILITIES AND PERMITS

ATTACHMENT E - DEBRIS SURVEY

ATTACHMENT F - CAD CELL MAXIMUM FILL ELEVATIONS

ATTACHMENT G - LIST OF CONTRACT DRAWINGS

ATTACHMENT H - SILT CURTAIN SPECIFICATIONS

ATTACHMENT I - PHASE II SIDE SLOPE SECTIONS

ATTACHMENT J - USACE SURVEY

ATTACHMENT K - EXAMPLE CONTOUR DREDGING APPROACH

New Bedford Harbor Lower Harbor Dredging

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 32 00

GEOTECHNICAL DATA

11/12

PART 1 GENERAL

1.1 SUMMARY

1.2 SOIL CLASSIFICATION

1.3 INTERPRETATION

1.4 LABORATORY TESTS

-- End of Section Table of Contents --

DOCUMENT 00 32 00 Page 1

DOCUMENT 00 32 00

GEOTECHNICAL DATA

11/12

PART 1 GENERAL

1.1 SUMMARY

The subsurface conditions in the dredge areas indicated in the specifications are the result of laboratory testing of samples from different reaches of the harbor. Attachment A is included as an attachment to these specifications. Attachment A includes data collected for the characterization of the lower harbor. Sample locations are presented on the contract drawings. The Contractor is responsible for reviewing the information contained in above documentation. Information is made available to Contractor for information purposes only and shall not be taken as warranty of site conditions.

The materials that exist in New Bedford / Fairhaven Harbor include both marine sediments and sediments and soils related to the last glacial period of the regions history and material related to the last post-glacial period of the regions history. As such, materials that exist in the harbor include:

o Marine Sediments (upper layer);

o Post-glacial sediments and soils (underlying the marine sediments); and o Glacial sediments and soils, which could include glacio-fluvial deposits as well as glacial till(deepest layers).

The materials to be dredged in the lower harbor are predominantly soft marine sediments consisting of organic silts (dark to light colored);

inorganic silts, clay, and some sand, pebbles, and cobbles. These sediments are contaminated with Toxic Substances Control Act (TSCA) level PCBs (50 ppm or greater). The deeper underlying sediments contain gravels, cobbles (75-305 millimeters), boulders (greater than 305 millimeters), and stiff, hard, gravely clays, which are not likely to be encountered.

An independent government contractor has conducted debris removal , however some debris may remain at or below the bottom of the harbor.

The contractor shall be prepared to excavate the full range of materials possible, including any remaining debris. Failure of the contractor to anticipate or be prepared for the varying subsurface conditions that exist within the Harbor shall not be cause for a claim of change in conditions of any kind.

1.2 SOIL CLASSIFICATION

The soil classification of the soil samples were performed by visual observation (ASTM D2488, Unified Soil Classification System). Core logs are provided in Attachment C.

1.3 INTERPRETATION

Subsurface investigation data are provided only for information purposes

DOCUMENT 00 32 00 Page 2 and for the convenience of the Contractor. No assurance is given that these conditions are representative of conditions in the dredge areas or areas adjacent thereto. The responsibility lies with the Contractor to interpret subsurface conditions that may affect his work.

1.4 LABORATORY TESTS

Laboratory tests of the samples were generally performed in accordance with the following test methods:

PCBs: SW846 8082A PCBs: Immunoassay (on-site lab analysis)

Note: Immunoassay was used for all samples collected since April 2014.

Approximately 10-20% of the samples were submitted to an off-site lab for verification.

-- End of Section --

DOCUMENT 00 32 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

11/12

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Quantity Determination and Breakdown

1.2 SUBMITTALS

1.3 PROJECT/SITE CONDITIONS

1.3.1 Physical Data

1.3.2 Coordination with Other Work

1.4 SEQUENCING AND SCHEDULING

1.4.1 Hours of Operations

1.4.2 Work Sequence

1.4.2.1 General

1.4.2.2 Progress Schedule

1.4.2.3 Periodic Schedule Updates

1.4.3 Organization at the Site

1.4.3.1 General

1.4.3.2 Rate of Dredging Progress

1.5 CONTRACTOR USE OF PREMISES

1.5.1 Work Limits

1.5.2 Contractor's Receipt of Supplies

1.5.3 Access to Work Site

1.6 COORDINATION

1.6.1 Warnings to Shippers and Other Users of the Harbor

1.6.2 Points-of-Contact

1.6.3 Archaelogy

1.6.3.1 Archaelogical and Paleontological Salvage

1.6.3.2 Salvaged Item

1.6.4 Aids to Navigation

1.7 PRECONSTRUCTION CONFERENCE

1.8 Meetings

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

11/12

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

Major work features include environmental dredging of polychlorinated biphenyl (PCB)-contaminated sediment (and metals, and hydrogen sulfide may be present in the sediment), transportation of sediment, and disposal of the sediment into an existing Confined Aquatic Disposal (CAD) cell. The cell was constructed in two phases as shown on the contract drawings. The Phase 2 portion of the cell will be used for this contract. Optional work items include the removal and disposal of the existing turbidity curtain at the CAD cell.

The work of this project consists of environmental dredging of the Lower Harbor of the New Bedford Harbor/Acushnet River in New Bedford, Massachusetts. Dredging in the Harbor shall be performed in portions of Dredge Areas 33, 34, 35, and 37, which have been subdivided into smaller areas as shown on the contract drawings. Expected dredged materials are described in section 00 32 00. Objects that cannot be removed with the environmental bucket shall be left in place and their position documented on Record Drawings. The government has completed debris removal (see Attachment E); however, some debris may still be present. It is the responsibility of the contractor to remove all debris encountered which can be removed with the environmental bucket. Typical debris encountered by the government in the lower harbor includes rocks, timbers, tires, anchors, concrete blocks, and steel pieces. Dredging will be conducted as outlined in Section 35 20 23. Dredge equipment requirements are detailed in Section 01 54 50.

The work includes temporary storage of dredged material in bottom-dump scows, transportation of the scows to the EPA CAD cell, decanting and carbon-filtering of standing water prior to discharge into the harbor, and placement of dredge material within the EPA CAD Cell, as outlined in Section 35 20 23. The Contractor must not allow the sediment in the scows to dry out, thus preventing an airborn dust problem.

The contractor shall conduct daily bathymetric surveys to confirm all target elevations have been met and to update the DBPS matrix file and will report to the government the amount of required material removed, overdepth material removed, and material removed below the allowable overdepth shown on the contract drawings in CY. No sounding information will be gathered from underneath existing structures (i.e. piers, wharfs). An independent government contractor will be conducting final acceptance surveys and payment surveys within ten days of the Contractor notification that an area will be completed.

See paragraph "1.3" in SECTION 00 80 00 - SPECIAL CONTRACT REQUIREMENTS for details regarding project schedule. The time stated for completion

SECTION 01 11 00 Page 2 shall include demobilaztion. See Paragraph "Work Sequence" in Section

01 11 00 SUMMARY OF WORK

Capping or other backfilling of the CAD cell is not included in this contract.

1.1.1 Quantity Determination and Breakdown

Volumes of material to be removed for each dredge area to reach the required dredge depths and the estimated total volume with 6" allowable overdepth volume are provided in the table below. This breakdown is furnished only to show the approximate distribution of material to be removed. The actual volume of dredge material removed will be calculated by comparing the pre-dredge bathymetric survey to the final post-dredge bathymetric survey. Contractor will be allowed to place the removed material and allowable overdepth volume in the CAD cell within the limitations spelled out in this subsection.

Dredge Verification Surveys will be performed by the Government to determine the accuracy of the contractor's dredging including the required dredge depth, allowable 6" overdepth, and dredging below the allowable overdepth.

Overdepth volume is generated when dredging extends more than 6 inches below the required dredge depth for any location in a dredge area.

Off-site disposal of the remainder of the sediment may be triggered at the discretion of the Contracting Officer if at any point the dredge verification survey shows the "Estimated Total Voume with 6" Allowable Overdepth (cubic yards)" is exceeded for any of the Dredge Areas listed in the table below, and upon such exceedance, the contractor shall prepare a Corrective Action Plan within two calendar days of notification by the Contracting Officer.

The Corrective Action Plan shall include proposed changes to operations required to remedy future over-depth dredging. The Contracting Officer may require the contractor to stop work at no expense to the Government if the plan is not submitted within one week or the plan is determined to be incomplete or unacceptable to the Government.

An Offsite Disposal Plan is included in the list of Preconstruction Submittals, Section 01 33 00. Details of the plan are addressed in Section 35 20 23, 1.5, SD-01 Preconstruction Submittals. Any plan that includes the use of contractor owned treatment facilities at the NBHSS site or Government property shall be approved in advance by the Government.

The following table lists estimated dredge volumes for each area based on cut depth. The volume quantities in the table below include both the required volume and a total allowable volume including six inches of overdepth volume for each of the dredge areas. A slope of 3H:1V has been assumed for overdepth transitions between differing elevations within a dredge area, based on observations from prior dredging in the harbor.

Dredge Area

Estimated Total Required Volume (cubic yards)

Estimated Total Volume with 6" Allowable Overdepth (cubic yards)

33B 7,191 8,859

SECTION 01 11 00 Page 3

Dredge Area

Estimated Total Required Volume (cubic yards)

Estimated Total Volume with 6" Allowable Overdepth (cubic yards)

33C 17,535 22,019

34B 44,613 55,068

35C 26,456 31,987

35E 7,725 9,058

35F 19,130 22,954

35G 5,515 7,142

37A 6,728 8,384

37B 2,860 3,572

Total 137,753 169,043

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Progress Schedule; G, RO

In accordance with the contract clauses, the Contractor shall, within 15 days after receipt of notice to proceed or as otherwise determined by the Contracting Officer, submit for approval a practicable progress schedule. When changes are authorized that result in contract time extensions, Contractor shall submit a modified chart for approval by the Contracting Officer.

Notice to Mariners

Submit a copy of Notice to Mariners to the Contracting Officer.

Aids to Navigation

Submit proof of coordination with the USCG for any necessary relocation or movement of aids to navigation.

Safe Harbor Plan; G, RO

The Contractor shall submit a Safe Harbor Plan to the Contracting Officer for approval prior to the start of on-site work. The Safe Harbor Plan shall include a written description of the Contractor's plan to provide for the safety and security of

SECTION 01 11 00 Page 4 floating plant, equipment, and personnel in the event of a storm or other site emergency. The location for the docking of floating plant and the off-loading of equipment and crews shall be clearly indicated.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Physical Data

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. Additional detail on the site history, site conditions, and project activities are referenced in Section 01 42 00 (Foster Wheeler- 1990, 2002; Jacobs- 2015; EPA-2015)

a. Site Conditions: The indication of physical conditions on the contract drawings and in the specifications are the result of site investigations and surveys. The conditions represented prevailed at the time the investigations and surveys were made. A pre-dredge bathymetric survey will be performed by the Government prior to the start of Contractor dredging operations at the site. Before commencing work at the site, the Contractor shall verify the existing conditions indicated on the drawings and in the specifications. See CONTRACT CLAUSE entitled "SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK".

b. Tide Conditions: The Acushnet River is oriented north-south. The river is tidally influenced and the mean range of tide for the Acushnet River is 1.2 meters (3.9 feet) MLW to MHW. The site of the work is largely protected from wind and wave attack. The maximum current in New Bedford Harbor during flood and ebb is approximately 3.5 knots.

c. Conditions of Federal Channel: The Government will not restrict vessels from the existing channel, except to the extent specified in the specifications and to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such a manner as to obstruct navigation as little as possible. In those instances where the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under the contract in navigable water or on the shore.

d. Channel Traffic: The traffic in New Bedford Harbor and through the barrier and bridges consists of pleasure boats, passenger and dry cargo vessels, tankers, motor vessels and fishing vessels. This traffic is not expected to cause unreasonable interference with the work.

e. Weather Conditions: The Contractor shall expect sub-freezing temperatures, adverse weather conditions at times during the performance period, and ice formations on the river in areas to be dredged. The contractor will be expected to break up any skim ice.

f. Turbidity Curtain Piles: The new turbidity curtain shall be anchored to the existing 12" wood Greenheart piles which are spaced

SECTION 01 11 00 Page 5 approximately 100' apart.

g. Debris removal has been performed by the government, however some debris may remain at the site (see Attachment E).

h. A double wall HDPE pipeline is routed at the surface from the Upper Harbor to the west side of the 195 bridge where it becomes submerged and anchored to the harbor bottom. The pipeline is 12-inch Schedule 80 SDR 13.5 HDPE x 18-inch Schedule 40 SDR 26 HDPE. The majority of this pipeline was permanently anchored to the bottom of the Harbor using a dual anchor system (one anchor on each side of the pipe connected by a nylon strap) at 42 foot spacing. ) The pipeline is located on the east side of the dredge work and crosses under the dredge work perpendicular to the navigation channel near the north end of the channel as shown on the contract drawings. The target sediment in the crossing of the work area shown on the drawings will be removed in the fall of 2016 by the Remedial Action Contract (RAC)contractor and the pipeline subsequently buried below final target elevation. The Contractor will not be impeded by the pipeline which will be in use by the (RAC) contractor working in the Upper Harbor. The P&S Contractor must not damage the pipeline under the pipeline corridor or the floating sections of the pipeline located to the east of the work area, see contract drawings.

i. Utilities in the harbor include water, sewer, gas, electric, and telecom. Available record information and utility drawings are provided in Attachment D.

j. Hardwood piles are used to anchor the turbidity curtain that surrounds the CAD Cell. Ten of these piles are inside of dredge area 35C which will require dredging around the piles, as described in Section 35 20 23, 3.1.2.

1.3.2 Coordination with Other Work

The Contractor for this work shall coordinate his construction activities with the other private entities conducting business operations in or adjacent to the harbor See Attachment B point-of-contact list for private entities and refer to contract drawings showing locations of private entities. The major ongoing activities by private businesses include scow island and the associated working docks owned by Tisbury Towing, docking of fishing vessels at Area D and along property south of Area D (Eastern Fisheries and Seawatch International), and any others. Scow Island consists of two derelict scows filled with junk and debris, located in the middle of the harbor just north of the phase 2 CAD Cell. The integrity of the scows is unknown; however, one of the scows does appear compromised as it lists to one side. Both scows have live vegetation growing on them. These scows will need to be moved in order to dredge the material beneath them. Area D is the dewatering facility used by the government to remove water from hydraulically dredged sediment from the upper Harbor, which is located opposite Dredge Area 35E. The City of New Bedford may also be using the Phase 1 or Phase 2 portion of the CAD cell to dispose of 27,000 cubic yards of sediment from another area in the harbor. Local government contacts are provided in 1.6.2 below.

The government will initiate coordination measures with the local governments regarding areas with ongoing activities that could interfere

SECTION 01 11 00 Page 6 with dredging, such as moorings (local harbor masters) and work on Route 6 (MassDOT). In case of dispute regarding work operations or the use of work areas, resolution will be by the Contracting Officer and his decision shall be final. No direct or extra compensation will be allowed on account of the coordination or cooperation required (see CONTRACT CLAUSE entitled

"OTHER CONTRACTS").

The Route 6 New Bedford-Fairhaven Bridge is a swing bridge that opens for traffic hailing VHF Ch. 13. The bridge opens daily at the top of the hour from 6:00 AM to 10:00AM and 15 minutes after the hour from 11:15 AM to 6:15 PM. After 6:15 PM the bridge is opened only on demand.

1.4 SEQUENCING AND SCHEDULING

1.4.1 Hours of Operations

The Contractor will be allowed to perform dredging operations 24 hours per day and may initiate sediment disposal from 6:00 AM to 10:00 PM , Monday - Saturday, excluding holidays, for the entire performance period.

Maintanence activities will be permitted on Sundays.

Work will not be performed on December 31 or July 4 as the harbor will be closed due to the holiday celebrations.

The exclusion of work on legal holidays has been considered in computing the performance of time in this contract. The following legal holidays are observed:

January 1st Third Monday in January Third Monday in February Last Monday of May July 4th First Monday of September Second Monday of October Fourth Thursday of November December 25th

When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as the legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Requests to perform work during holidays shall be made in writing to the Contracting Officer. Work cannot be performed on December 31 or July 4 as the Harbor will be closed for the holiday celebrations.

1.4.2 Work Sequence

1.4.2.1 General

There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. See Section 35 20 23 DREDGING for the required order of work. The Contractor shall dredge from higher elevation and progress toward the lower elevations in order to avoid sloughing into previously dredged areas. Isolated elevation peaks of a few inches or feet do not need to be dredged first. The high-to-low approach is intended to ensure dredging is progressing down the slopes rather than up the slopes. Dredging from top of slope down is intended as a residuals management practice. Some variations to this

SECTION 01 11 00 Page 7 top-down approach are acceptable depending on water depths, depth of cut, and number of passes.

Minor variations in the sequence of the items of work as approved may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS." Variations shall be approved by the Contracting Officer prior to implementation.

1.4.2.2 Progress Schedule

The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised.

1.4.2.3 Periodic Schedule Updates

An updated schedule showing actual progress shall be submitted monthly or with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.

1.4.3 Organization at the Site

1.4.3.1 General

The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Paragraph 1.

1.4.3.2 Rate of Dredging Progress

Should the Contractor fail to maintain an average rate of 20,000 in-situ cubic yards per month, the Contracting Officer may require that additional personnel and equipment be placed on the job, in order that the work be brought up to schedule and maintained.

1.5 CONTRACTOR USE OF PREMISES

1.5.1 Work Limits

The limits of work consist of the Dredge Areas and CAD cell and any onshore staging areas procured by the Contractor as needed, as shown on the contract drawings and the navigable waters.

1.5.2 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt of

SECTION 01 11 00 Page 8 materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

1.5.3 Access to Work Site

Access to the project site will be discussed at the Preconstruction Conference. The Contractor shall be responsible to secure any wharf facilities required for this project. The government shall have access to any upland facilities used by the contractor.

1.6 COORDINATION

Numerous businesses and government agencies have water-dependent activities within or near the project dredge area which could potentially be affected by the dredging operations. The Contractor is required to coordinate its activities with the appropriate authorities and affected parties within New Bedford Harbor.

1.6.1 Warnings to Shippers and Other Users of the Harbor

a. Notice to Mariners. Before beginning dredging operations, the Contractor shall coordinate with the U.S. Coast Guard (USCG) to issue a "Notice to Mariners" regarding the work to be performed and the Contractor's proposed operations. The Coast Guard requires a minimum of three weeks lead time, in writing, for publication of all notices.

The U.S. Army Corps of Engineers and the USCG have agreed to phraseology when issuing navigational bulletins and notices. The information furnished shall be consistent with "USCG Broadcast Notice to Mariners" and "Local Notice to Mariners". When requesting local USCG offices to issue navigational information for U.S. Army Corps of Engineers work involving marine construction, the following terminology shall be used, as applicable:

For cautionary areas: "Mariners are urged to use extreme caution in the area".

For dredging and work operations: "Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made".

b. Radio Monitoring. The contractor's floating plant or other craft working in the harbor shall at all times monitor and transmit radio calls on VHF marine channels 13 and 16.

1.6.2 Points-of-Contact

a. Coast Guard: Ms. Mary Swanson, mary.f.swanson@uscg.mil. 508-991-6812

b. City of New Bedford Port Director: Ed Anthes-Washburn hdc@newbedford-ma.gov Telephone 508-961-3000.

c. New Bedford Harbor Master: David Condon Telephone - 508-965-8019

d. Fairhaven Harbor Master: Tim Cox 508-962-1416.

e. Debris and PPE Pickup: Mark Gouviea (Jacobs Engineering) 508-966-5462

Additional Points-of-Contact for property owners are included in Attachment

SECTION 01 11 00 Page 9

B. Points-of-Contact for utility owners are listed in Section 35 20 23

DREDGING.

1.6.3 Archaelogy

1.6.3.1 Archaelogical and Paleontological Salvage

A. The Contractor's attention is directed to the United States Department of Transportation, Federal Highway Administration, Federal Aid Highway Program Manual, Volume 7, Chapter 7, Section 4, subject "Archaeological and Paleontological Salvage", incorporating Policy and Procedure Memorandum 20-7, dated March 31, 1979, and to the Commonwealth of Massachusetts, Acts of 1973, Chapter 1155.

B. In compliance with these procedures and legislation, the Contractor shall exercise special care during his operations to avoid injury to underground prehistoric and historic archaeological remains or paleontological remains. Should any archaeological or paleontological remains be encountered during any phase of construction, the Contractor shall immediately suspend all work in the area and shall notify the Contracting Officer. The Contracting Officer shall immediately notify the State Archaeologist and the Massachusetts Historical Commission. All construction work in that area will be temporarily delayed while the State Archaeologist and representatives of Massachusetts Historical Commission inspect the site to determine the importance of the discovery. Areas of prehistorical, historical, or paleontological significance shall be carefully protected in accordance with the above referenced manual and shall not be disturbed by the Contractor until so directed by the Contracting Officer. The Government has conducted prior archeological surveys in the harbor to clear the area prior to dredging, however the potential always exists to encounter artifacts

C. Contractor shall receive no extra compensation for such special care, unless said compensation is authorized in writing by the Contracting Officer as provided for in Article 7.04. Material from such areas shall be carefully protected, and if necessary to remove specimens, the Contractor shall do so only at the Engineer's direction, and after an authorized agent has witness or otherwise referenced their locations.

1.6.3.2 Salvaged Item

All items removed in order to perform the work, which are not considered archaeologically or paleontologically significant and not required to be replaced, shall, unless otherwise specified, be disposed in the CAD Cell or in a TSCA landfill as described in Section 00 80 00.

1.6.4 Aids to Navigation

Aids to navigation (beacons, buoys, markers, etc.) have been placed by the USCG in the vicinity of the project area. The Contractor shall not interfere with these aids to navigation. If the work of this project requires the temporary movement or relocation of any aid to navigation, the Contractor shall notify the USCG and the Contracting Officer of the requirement 30 days in advance. USCG personnel will then move or relocate the aid to navigation as appropriate for the progress of the work. Under no circumstances shall the Contractor move or relocate an aid to navigation under his own authority with his own personnel. The Contractor shall also contact the USCG at the completion of all work and the removal of all

SECTION 01 11 00 Page 10 marine plant.

1.7 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent and Quality Control Representative shall attend this conference. All submittals which are ready for submission prior to the start of the work may be brought to the conference for distribution to the participating reviewers.

1.8 Meetings

The Contractor will be required to prepare for and attend weekly on-site project meetings to discuss planning, project status, schedules, and general project issues as needed. These meetings are to be included in the cost of dredging under Line item 0002 in Section 00 41 00.

Additionally, the contractor will also be required to prepare for, attend, and participate in public meetings as needed by the Government.

For Government requests that the Contractor be present at public meetings, include costs for meeting preparation, attendance, participation, and supplies/handouts. Public meetings will occur in the evening. The Contractor will be required to summarize ongoing dredging operations and discuss key issues. The Contractor shall assume attendance at five public meetings; the total effort per meeting is on average at 30-hours each.

These meetings are also to be included in the cost of dredging under Line item 0002 in Section 00 41 00.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 11 00 Page 11

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

11/12

PART 1 GENERAL

1.1 SUBMITTALS

1.2 Job PAYMENT ITEMS

1.3 UNIT PRICE PAYMENT ITEMS

1.4 BIDDING SCHEDULE - PAYMENT ITEMS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

11/12

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

Quantity Surveys

Submit originals of all field notes and all other records relating to the quantity surveys.

1.2 Job PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. Submit originals of all field notes and all other records relating to Quantity Surveys.

1.4 BIDDING SCHEDULE - PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed job item most closely associated with the work involved.

BASE BID ITEMS

SECTION 01 22 00 Page 2

a. Item No. 0001, "Mobilization and Demobilization for Dredging Operations".

All costs for labor, equipment, and materials for installation and maintenance of the turbidity curtain as defined in Section 01 57 20 ENVIRONMENTAL PROTECTION, and for mobilization and demobilization for dredging operations, as defined in the Special Contract Requirements Clause "PAYMENT FOR MOBILIZATION AND DEMOBILIZATION".

Unit of measure: Job.

b. Item Nos. 0002 , "Mechanical Dredging and Disposal; Material from Dredge Areas 33-37".

All costs for labor, equipment and materials for Item No. 0002 "Mechanical Dredging and Disposal; Material from Dredge Areas 33,34,35, and 37"(see table in Section 01 11 00, 1.1.1), shall include all cost for removal and disposal of dredged sediment, including suitable debris, from the designated dredge areas, as shown on the contract drawings and as specified in Section 35 20 23 DREDGING and other appropriate sections of the specifications. This item shall include all cost for inspection, minor adjustments and minor repairs of the turbidity curtain and oil boom as defined in Section 01 57 20

ENVIRONMENTAL PROTECTION.

The amount of material removed under the contract for this item, will be measured as cubic yards in place. The volume will be determined by calculating the difference between the pre-dredge and post-dredge bathymetric survey, not to exceed the target depths represented on the plans.

The contract price for dredging for this item shall include the cost of removal and disposal of all materials as specified herein or indicated on the contract drawings, except ledge rock, large boulders, and other unclassified materials, which cannot be removed by the plant specified in the accepted bid. Should ledge rock or other material which cannot be removed by the plant specified in the accepted bid, or its equivalent be encountered the Contractor shall remove therefrom all overlying material which in the judgment of the Contracting Officer can be removed by the use of plant so specified or its equivalent. Removal and containerization of floating debris and treatment of decanted water from the scows, as discussed in later sections, shall be included in this price.

The contract drawings referenced in the Special Contract Requirements (Section 00 80 00), Paragraph "Contract Drawings, Maps and Specifications" are believed to accurately represent conditions existing on the date of the last bathymetric survey shown on the drawings, but the depths and the specific areas to be dredged shown thereon will be verified and corrected by a new survey taken by the Government within 6 months before dredging. Existing conditions of material to be dredged are presented in Section 00 32 00.

The cost for installing a Type II turbidity curtain shall be included in the cost of dredging.

A post-dredge bathymetric survey will be conducted within 10 days of being notified by the contractor that an area will be completed and ready for the final survey. The post dredge survey will be performed

SECTION 01 22 00 Page 3 by an independent Government contractor under a separate contract at no cost to the Contractor. Determination of quantities removed after having once been made by the Contracting Officer, will not be reopened, except on evidence of collusion, fraud, or obvious error.

The cost of preparing for and attending meetings shall be included in the cost of dredging. See Section 01 11 00, 1.8 for scope of meeting prparticipation.

Unit of measure: CY.

Optional Bid Items

d. Item No. 0003AA and 0003AB "Replacement of Turbidity Curtain"

The contract price for the replacement of sections of the turbidity curtain will include acquisition, installation, and maintenance of a new sections as needed and as specified in Attachment H.

Unit of measure: LF.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 Information Only

1.5 PREPARATION

1.5.1 Transmittal Form

1.6 QUANTITY OF SUBMITTALS

1.6.1 Government Approved

1.6.2 Information Only

1.7 INFORMATION ONLY SUBMITTALS

1.8 VARIATIONS

1.8.1 Considering Variations

1.8.2 Proposing Variations

1.8.3 Warranting That Variations Are Compatible

1.8.4 Review Schedule Is Modified

1.9 SUBMITTAL REGISTER

1.9.1 Use of Submittal Register

1.9.2 Contractor Use of Submittal Register

1.9.3 Approving Authority Use of Submittal Register

1.9.4 Copies Delivered to the Government

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Safe Practice Manual

Certificates of Insurance

Surety Bonds

SECTION 01 33 00 Page 2

List of Proposed Subcontractors

List of Proposed Products

Construction Progress Schedule

Submittal Register

Schedule of Prices

Health and Safety Plan

Work Plan

Offsite Disposal Plan

Quality Control(QC) Plan

Environmental Protection Plan

Pre-Diving Submittals

Diving Plan

Activity Hazard Analysis

Emergency Management Plan

Dive Personnel Qualifications

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

SECTION 01 33 00 Page 3

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

SECTION 01 33 00 Page 4

Submittal Register; G, RO

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.4.1.1 Approval Codes

a. Construction/Operations Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction/Operations Division. Send all such submittals to the project Resident or Area Engineer, as applicable.

b. Engineering/Planning Division {"DO" (District Office) Reviewer): A "DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering/Planning Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.

c. Architect-Engineer Firm {"AE" reviewer): An "AE" on the attached submittal register, column "f" indicates that the submittal review action is by the Architect-Engineer firm associated with the project.

d. Government acceptance is required for submittals with a "G, A" designation.

1.4.2 Information Only

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.5 PREPARATION

1.5.1 Transmittal Form

Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor and are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

SECTION 01 33 00 Page 5

1.6 QUANTITY OF SUBMITTALS

Submit an electronic PDF copy and seven paper copies of each submittal item with an attached ENG FORM 4025 Transmittal Form. The Contractor will be informed at the pre-construction conference to send all submittals to either the project Resident Office or to the project Area Engineer Office, or other office, as applicable.

1.6.1 Government Approved

Submit an electronic copy in acceptable format (PDF or word) of each submittal requiring review and approval by the Contracting Officer. Upon approval, the Contractor shall submit two hard copies.

1.6.2 Information Only

Submit an electronic copy in acceptable format (PDF or word) of each submittal designated "For Information Only". Upon acceptance, the Contractor shall submit two hard copies.

1.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.8 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.8.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval.