Amendment_W912WJ-17-R-0003-0002.pdf

PDF 65 KB Posted

Attached to
Mechanical Remediation Dredging in the Lower Harbor
Solicitation number
W912WJ-17-R-0003
Issued by

About this file

Amendment 0002

View the file

Other files

File Type Posted
LHCC_PILES.XLSX XLSX spreadsheet
Amendment_W912WJ-17-R-0003-0005.pdf PDF
Core_Photos_a.pdf PDF
Dredge_Area_33B.DWG DWG drawing
Dredge_Area_35G.DWG DWG drawing
Dredge_Area_37B.DWG DWG drawing
Dredge_Area_35C.DWG DWG drawing
Dredge_Area_33C.DWG DWG drawing
Phase_2_CAD_Cell_20170206_20FT_SMOOTH_SHEET-actual.pdf PDF
Dredge_Area_34B.DWG DWG drawing
Dredge_Area_35F.DWG DWG drawing
Dredge_Area_37A.DWG DWG drawing
20170206_3ft_MIN_MLLW_Depth.xyz XYZ file
Dredge_Area_35E.DWG DWG drawing
Amendment_W912WJ-17-R-0003-0004.pdf PDF
Amendment_W912WJ-17-R-0003-0003.pdf PDF
33B_Target Elevations_XYZ.txt TXT text file
33C_Target Elevations_XYZ.txt TXT text file
Lower_Harbor_Pre_Dredge_Bathy_2014-2015_XYZ.txt TXT text file
34B_Target Elevations_XYZ.txt TXT text file
37B_Target Elevations_XYZ.txt TXT text file
34B_Boundary.dwg DWG drawing
33B_Boundary.dwg DWG drawing
35G_Target Elevations_XYZ.txt TXT text file
35C_Target Elevations_XYZ.txt TXT text file
35F_Target Elevations_XYZ.txt TXT text file
37B_Boundary.dwg DWG drawing
33C_Boundary.dwg DWG drawing
37A_Boundary.dwg DWG drawing
35E_Boundary.dwg DWG drawing
35E_Target Elevations_XYZ.txt TXT text file
Amendment_W912WJ-17-R-0003-0001.pdf PDF
35G_Boundary.dwg DWG drawing
35C_Boundary.dwg DWG drawing
35F_Boundary.dwg DWG drawing
37A_Target Elevations_XYZ.txt TXT text file
SPECS.pdf PDF
PLANS_.pdf PDF
Solicitation_W912WJ-17-R-0003.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment necessary to publish submitted Requests for Information and the Government Responses.

All other aspects remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Feb-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ-17-R-0003

X 9B. DATED (SEE ITEM 11)

20-Jan-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Feb-2017

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ-17-R-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

BASIS OF AWARD CHANGE SUMMARY:

The following highlighted languages reflects changes made to the first paragraph of the Basis of award section.

The award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, based on the following evaluation factors listed in descending order of importance: Company/Project Team Experience; Past Performance; Technical Approach; Key Personnel;

Small Business Participation and Price. All evaluation factors other than Price, when combined, are significantly more important than Price. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for all non-price factors (Factors 1, 3, 4 and 5) and at least “neutral confidence” for Factor 2. Offerors will be cautioned that the award may not necessarily be made to the lowest price proposal offered.

REQUESTS FOR INFORMATION AND GOVERNMENT RESPONSES

1. For Factor 1 – Company/Project Team Experience, the RFP requests that we submit excerpts from the project specifications as well as PDFs of plans and cross-sections.

Are these items included in the 130 page limitation?

RESPONSE: Yes.

2. Volume II – Factor 5 Small business Participation Plan, it is our understanding that a Small Business Subcontracting Plan is not required as part of the proposal submittal.

Please verify that this is correct.

RESPONSE: Contractors are not required to submit subcontracting plans with their proposal. If the potential awardee is a large business, s subcontracting plan will be required prior to award.

3. As a self-perform contractor, we have a limited need for subcontracted services on this project, and, therefore, a limited opportunity for SB participation. We own the vast majority of equipment required and the amount of materials required for the project is limited. Therefore, we respectfully request that you consider lowering the Total Small Business Participation Goal of 20% of total contract value or realign the goal to be a percentage of subcontracted dollars.

RESPONSE: The Government will not lower the participation goal. The Small Business Participation Goal of 20% is based on the Total Contract Value of the offeror’s proposal. Market research was conducted by means of past history on similar dredging projects to determine a challenging, yet attainable Small Business Participation Goal for this solicitation. The dollar values that are proposed in the Small Business Participation Plan shall be reflected in the Subcontracting Plan.

4. For Factor 6 – Price, the RFP proposal requirement states, “This volume shall consist of all information, required to support proposed prices.” Can you please provide more specifics on what the Government’s expectations are for this requirement i.e. what we should submit as support documentation?

RESPONSE: Offerors are not required to submit any supporting information for their proposed prices. If the offeror does chose to provide supporting information, the information shall be placed in Volume II. Volume I shall not contain price information.

5. Paragraph A, Basis of Award. Please confirm that the offeror must receive an Acceptable rating for all non-price factors (Factors 1, 3, 4, and 5 versus Factors 1, 2, 3, and 4).

RESPONSE: Please see Basis of Award Change Summary.

6. We did not see a due date for clarifying questions on the RFP, can you please provide one?

RESPONSE: We request that all Requests for Information be submitted within 10 days for the date that proposals are due.

7. In the Note Block on Sheet C-101 of the plans it states that the “Contractor shall use the electronic data supplied by GOV (target elevations, bathymetric survey, and dredge area AutoCAD files) for its dredge plan preparation.” Those files are not provided in the Solicitation #1. Can you please provide those files?

RESPONSE: All electronic data was posted on FBO as part of Amendment 0001.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .