PROJECT TITLE: GROUT CURTAIN CUP McCOOK RESERVOIR
Solicitation number
W912P6-09-R-0006
Issued by

About this file

GROUT II Amd 0002 PLANS

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

_C-07.dgn 8/5/2009 2:30:19 PM

D E

S

IG

N E

B Y

D A

T

A

B C D

E F G H

SHEET

REFERENCE

NUMBER:

D A

T E

D E

S C

R

IP

T

IO

N D

A T

E A

P P

R O

V E

D A

P P

R O

V E

D S

Y M

B O

L S

Y M

B O

L

US Army Corps of Engineers

Chicago District

U .S

A R

M

N

G

IN

E

R

IS

T R

IC

T

C O

R P

S

O F

G

IN

E E

R S

C H

IC

A G

O

IL

L

IN

O

IS

P L

T

T E

F

IL

E N

A M

E

C

D o c u m e n t s a n d

S e t t in g s h t e c d r s y o c u m e n t s

W r k in g ir e c t o r y d m s

C .d g n

S C

A L

E

C H

E C

K

D R

A

SHEET OF

A B C D E F G H

A M

E N

D M

E

S C

R

IP

T

IO

N D

A T

E

S U

B M

IT

T

H

O W

N

W

P

R

D R

S

C H

IC

A G

O L

A

U

D E

R F

L

L

A N

C

U c

C O

K

S E

R V

O

IR

S T

A G

G

O

C

R T

A

IN

J

U

J O

O B

O S

K I, P .E

R D

H

D R

S

R D

H J

C W

S O

L

IC

IT

A T

IO

M B

E R

C-07

G R

O

R T

IN

T A

IL

S A

M E

N D

M E

R G

P

D R

S

A M

E N

D M

E

P Q T Q S Q T Q Q T

P Q T Q S Q T Q Q T

P(I)

P(I)

20’

T Q S Q T Q Q

Q S Q T Q Q T

Q S Q T Q P Q

Q S Q T Q P Q T

TQ S Q T Q Q

Q S Q T Q Q T

T Q S Q T Q Q T

Q S Q T Q Q T

Q S Q T Q P Q

Q S Q T Q P Q T

TT Q Q

T Q Q T

T Q S Q T T

Q S Q T Q T

Q S Q T Q P Q

Q S Q T Q P Q T

TQ S Q T Q Q

Q S Q T Q Q T

T Q S Q T Q Q T

Q S Q T Q Q T

Q S Q T Q P Q

Q S Q T Q P Q T

TT Q S Q T Q Q

Q S Q T Q Q T

T Q Q T Q

Q Q T Q Q T

Q Q Q S Q

Q P Q S Q T

P(I)

P(I)

P P(I)

P(I)

P

P

P(I)

P(I)

P

P

P(I) P

P P(I)

P(I) T T

Q T

T Q Q T Q Q T

Q Q T

Q Q Q S Q

Q P Q S Q T

PS Q

S

P

P

Q Q T Q

Q Q T Q

S

Q S Q T P(I)

S

S

V

V

VV

P S

10’

5’

SCALE: 1"=5’

5’ 5’ 10’2.5’

GROUT HOLE ORIENTATION

(SEE NOTE 2)

GROUT HOLE ORIENTATION

(SEE NOTE 2)

(SEE NOTE 4)

CENTERLINE,

’C-LINE’ (AS-

REQUIRED)

C-07

B

A-LINE

B-LINE 6

.0

.5

.5

S E

E

S P

E C

NOTE:

WORK PLATFORM CURRENT SITE CONDITIONS TO BE

VERIFIED PRIOR TO COMMENCEMENT OR WORK.

C-07

B

SLOPE

A-LINEB-LINE

SECTION

N.T.S.

GROUT CURTAIN >

C-LINE (AS REQUIRED)

CONCRETE WORK

PLATFORM

DRAINAGE

GUTTER

OVERBURDEN CUTOFF WALL

WIDTH VARIES (3 FT MIN)

WORK PLATFORM

RAILROAD

STABLE WITH CONSTRUCTION LOAD

NOT TO SCALE

W

SLOPE BREAK

VARIES

VARIES FROM

EL. 5’ TO EL. 1O’

6’-0"

O V

E R

B U

R D

V

R

IE

S

MIN 3’

CLSM CUTOFF WALL CAP

VARIES FROM EL. +12 TO

EL.+17

TOP OF CUTOFF WALL

TYPICAL CUTOFF WALL DETAIL AT CANAL SIDE, STA. 74+25 TO STA. 104+003

C-07

25’¨

13’ MIN

CENTERLINE OF CUTOFF WALL

AND GROUT CURTAIN

TO BE INSTALLED

LEGEND

NOT TO SCALE

73RD TO 57TH ST. (EXTD.) TUNNEL CROSSING DETAIL 2

C-04 C-07

P T S T P T S T PQTQSQTQPQTQSQ

NOTES;

PQTQSQTQPQTQSQTQPQTQSQTQPQTQSQ P T S T P T S T PTQTQ

TOP OF ROCK (SEE NOTE 1)

SECTION A

SCALE: 1"=40’

DETAIL

SCALE: 1"=20’

BOTTOM OF GROUT HOLES

(SEE NOTE 4)

BRAINARD FORMATION MEMBER

WILHELMI FORMATION

ELWOOD FORMATION

KANKAKEE FORMATION

JOLIET FORMATION

SUGAR RUN FORMATION

RACINE FORMATION

SCALE: 1"=40’

40’ 40’ 80’20’

PRIMARY HOLE

SECONDARY HOLE

TERTIARY HOLE

DISTANCE IN FEET FROM STATION 19+00

CENTERLINE

SCALE: 1"=20’

20’ 20’ 40’10’

120’40’

500’

480’

(SEE NOTE 7)

(SEE NOTE 6) (SEE NOTE 5)

A-LINE

B-LINE

C-03 C-07

C-07C-03

GROUNDSURFACE (SEE NOTE 3)

E L

E V

A T

IO

IN

E T

E

L E

V

.2

D

(ELEV. - 579.5 = CCD)

249.5

BOTTOM OF FUTURE RESERVOIR

(EL. 295)

73RD TO 57TH ST. TUNNEL

(INVERT APPROX. 437.5’)

DRILL AND GROUT THROUGH

CONCRETE TUNNEL PLUG

INCLUDED IN THIS CONTRACT

TOP OF ROCK (APPROX. 555)

GROUNDSURFACE (APPROX. 595)

1. ELEVATIONS OF FORMATION CONTACTS LISTED ARE ESTIMATED

AVERAGES; HOWEVER, THEY DO VARY IN CONTRACT AREA.

2. HOLES SHALL BE DRILLED PARALLEL TO THE GROUT CURTAIN

ALIGNMENT AT AN INCLINATION OF 15 DEGREES FROM VERTICAL.

3. SURFACE TOPOGRAPHY VARIES ALONG THE GROUT CURTAIN

ALIGNMENT.

4. GROUT HOLES SHALL BE DRILLED TO DEPTHS DIRECTED BY

CONTRACTING OFFICER’S REPRESENTATIVE.

5. INITIAL PRIMARY HOLES SHALL BE DRILLED 120 FEET APART. REFER

TO SECTION 31 83 00.00 03 IN THE SPECIFICATIONS.

6. INITIAL VERIFICATION HOLES SHALL BE CORED AS THE INITIAL

PRIMARY HOLES. THERE WILL BE TWO INITIAL VERIFICATION HOLES

FOR EVERY 1,000 FEET. LOCATIONS ARE BASED ON THE ASSUMPTION

THAT THE B-LINE WILL BE DRILLED FIRST.

7. FINAL VERIFICATION HOLES WILL BE SPACED 500 FEET APART ALONG

THE CENTERLINE.

8. TUNNEL CROSSING DETAILS ARE TYPICAL FOR EACH OF THE 2 ROWS

OF THE GROUT CURTAIN.

9. OVERBURDEN CUT-OFF WALL AND ASSOCIATED EMBANKMENT

AND WORK PLATFORM SHOWN ARE BASED ON DATA PROVIDED

IN THE OVERBURDEN GROUNDWATER CUT-OFF WALL CONTRACT

DOCUMENT: DACW27-00-C-0008 AND W912P6-06-C-0001.

10.ADDITIONAL GROUT HOLES MAY BE ADDED BETWEEN THE TWO LINES

OF THE GROUT CURTAIN TO PROVIDE CLOSURE.

’C-LINE’ (AS REQUIRED)

_C-12.dgn 8/5/2009 3:15:03 PM

C-12

MWRD RAILROADGROUT CENTERLINE

’B’LINE

’A’ LINE

S L

O

A B

IL

IZ

A T

E A

S

FILTER FABRIC

BASE SOIL

12" RIPRAP

SLOPE STABILIZATION DETAIL

TOP OF SLOPE

2.5:1 SLOPEBEGIN - STATION 72+00

END - STATION 36+00

NOTE:

SEE SPECIFICATIONS 31 05 19.13 03, 31 22 50, 31 37 16.00 03

FOR MATERIAL DESCRIPTIONS.

SCALE IN FEET

0100 100 200

EXISTING GABION WALL

(STA 49+00-42+00)

SLOPE STABILIZATION AREA

EXISTING TOE OF SLOPE

BASE ALIGNMENT

FORMER LAGOONS

NOTES:

1. CONTRACTOR SHALL PROVIDE SURFACE

GRADING ALONG EXISTING SLOPE TO

ACHIEVE A 2.5:1 SLOPE.

2. EXISTING CONDITIONS ARE SHOWN.

GRADING CONDITIONS AT TIME OF

EROSION PROTECTION INSTALLATION MAY

BE MODIFIED.

A M

E N

D M

E

G P

D R

S

2APPROXIMATE LOCATION

OF ELECTRICAL DUCT BANK

R G

P

D R

S A

M E

N D

M E

L E

T

IL

M P

B13 B16 B14

B9

B8

A

B C

D

E

F G H

K

J

L

I

NO M

PQ

0 2 0 2

+0

37+00

38+00

39+00

40+00

41+00

GROUT >

’B’LINE

BASE ALLIGNMENT

’A’LINE

P

P

P

P

P

P

P P

P P

P P

P P

P

P

P

P

P

P

P

S

S

S

S

S

S

S S

S S

S S

S S

S

S

S

S

S

S

P S P S P

S

P

S

P S

P S

P S

P S

P

S P

S

P S

P S

P S

P S

P S

P S

P

S

P

P

S

S

B10

B11

B12

B15

D

I

A

L,’A’ LINE =739

.6255f t

L,’B’ LINE =802

.9400f t

B E

G I

N

A

B E

G I

N

A

B E

G I

N

A

B E

G I

N

A

D

A

0CHICAGO SANITARY SHIP CANAL

INTERSTATE 55

D E

S

IG

N

D A

T

B C D

E F G H

SHEET

REFERENCE

NUMBER:

D A

T E

D E

S C

R

IP

T

IO

N D

A T

E A

P P

R O

V E

D A

P P

R O

V E

D S

Y M

B O

L S

Y M

B O

L

US Army Corps of Engineers

Chicago District

U .S

A R

G

IN

E

IS

T R

IC

T

C O

R

G

IN

E E

R S

C H

IC

A G

O

IL

L

IN

O

IS

P L

T E

F

IL

E N

A M

E

C

D o c u m e n t s a n d

S e t t in g s h t e c d r s y c u m e n t s r k in g ir e c t o r y d m s

C .d g n

S C

A L

E

C H

E C

K

D R

A

SHEET OF

A B C D E F G H

A M

E N

D M

E

S C

R

IP

T

IO

N D

A T

E

S U

B M

IT

T

O W

N

W

P

R

D R

S

C H

IC

A G

O L

A

D E

R F

L

A N

C

U c

C O

K

S E

R V

O

IR

S T

A G

O

R T

A

IN

J

U

J O

O B

O S

K I, P .E

R D

H

D R

S

R D

H J

C W

S O

L

IC

IT

A T

M B

E R

0 2 0 2

+0

37+00

38+00

39+00

40+00

41+00

P

P

P

P

P

P

P P

P P

P P

P P

P

P

P

P

P

P

P

S

S

S

S

S

S

S S

S S

S S

S S

S

S

S

S

S

S

P S P S P

S

P

S

P S

P S

P S

P S

P

S P

S

P S

P S

P S

P S

P S

P S

P

S

P

P