McCOOK GROUT II CURTAIN AMENDMENT 0002
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6690139627
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SUBJECT: REQUEST FOR PROPOSAL NUMBER W912P6-09-R-0006, CONTRACT FOR CONSTRUCTION SERVICES IN SUPPORT OF THE GROUT CURTAIN II CUP McCOOK RESERVOIR PROJECT
The government is issuing this Amendment Number 0002 to its previously issued Solicitation W912P6-09-R-0006 for the purpose of amending various areas of the Solicitation Package as delineated on the follow ing pages of this Amendment.
Wage Rate Change from IL080009 06/12/2009 To IL080009 07/17/2009
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Aug-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-09-R-0006
X 9B. DATED (SEE ITEM 11)
06-Jul-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Aug-2009
CODE
U. S. ARMY ENGINEER DISTRICT, CHICAGO
111 NORTH CANAL STREET SUITE 600
CHICAGO IL 60606-7206
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P6-09-R-0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
A. AMENDED SPECIFICATION SECTIONS:
Replace 28 23 29.00 03_ Existing Webcam, 29 Pages and the Location Plan, 1 Page With 28 23 29.00 03_ Existing Webcam System, 715 Pages.
Amendment to Spec 00 31 19.01 03
Part 1.3 has been amended to include the following statement: “Blasting occurs at the discretion of the quarry operator. In General, blasting occurs in the afternoon with shut downs lasting no longer than 30 minutes. All personnel in the blast zone must vacate the area. The blast zone is identified as lagoons 1-10 inclusive. Incurred stand-by due to blasting totaling a whole day will be granted a contract extension.”
Part 1.3 has been amended to include: “Access through the Option 1 area to the Base Bid area will be possible prior to the execution of the Options; however access may be limited by the operations of other contractors during that time, and coordination with the COR will be required throughout the contract duration for this access.”
Amendment to Spec 31 83 00.00 03 Par. 3.4.5 has been amended to remove the requirement for use of dispersing agent.
Par 2.2.1 has been amended to reflect the allowance for the use of Schedule 40 or Schedule 80 PVC pipe, provided the criteria for hole deviation are met and the watertight seal between the casing and rock is maintained.
Paragraph 3.4.5 has been amended to state that the nozzle pressure shall be no greater than ½ psi per vertical foot of overburden cover for this zone. This is different than the gage pressure, and will require determination of the nozzle pressure by calculation based upon the gage pressure, grout hole inclination, depth of nozzle, and the thickness of overburden cover.
B. AMENDED DRAWING SHEETS:
1. Amendment Sheet C-12, Erosion Control Area Modified
2. Sheet G-03 Added
3. Replace G-02 with new revised G-02
C. QUESTIONS AND RESPONSES:
QUESTION 1. Paragraph 3.4.5 of Section 31 83 00 requires Contractor to use dispersing agent during the pressure washing operation “if directed to do so by the COR”. Will the government consider providing a separate pay item for Dispersing Agent. If not, request that a usage rate for the dispersing agent be provided to contractors, in order to properly estimate quantities and costs.
RESPONSE: Paragraph 3.4.5 of Section 31 83 00.00 03 has been amended to remove the requirement for use of dispersing agent.
QUESTION 2. Will flush joint threaded PVC schedule 40 casing be allowed for the entire depth of overburden?
RESPONSE: Paragraph 2.2.1 of Section 331.83.00.00 03 has been amended to reflect the allowance for the use of Schedule 40 or Schedule 80 PVC pipe, provided the criteria for hole deviation are met and the watertight seal between the casing and rock is maintained.
QUESTION 3. Section 31 83 3.2.3.3, page 20 states that a washing additive should be utilized in hole washing operations, at what concentration should the washing additive be used?
RESPONSE: Section 31 83 00.00.03 page 20 states that a washing additive should be utilized in hole washing operations, at what concentrations should the washing agent be used?
QUESTION 4. Interface washing is to be conducted at 10psi (but it is approximately 60 ft depth so just water column is about 30psi), please clarify.
RESPONSE: Paragraph 3.4.5 of Section 31 83 00.00 03 has been amended to state that the nozzle pressure shall be no greater than ½ psi per vertical foot of overburden cover for this zone. This is different than the gage pressure, and will require determination of the nozzle pressure by calculation based upon the gage pressure, grout hole inclination, depth of nozzle, and the thickness of overburden cover.
QUESTION 5. Will the contractor be required to shut down during the blasting operations within the quarry? If so, please provide a schedule of blast outages with which we can base our proposal.
RESPONSE: Paragraph 1.3 of Section 00 31 19.01 03 has been amended to include:
“Blasting occurs at the discretion of the quarry operator. In general, blasting occurs in the afternoon with shutdowns lasting no longer than 30 minutes. All personnel in the blast zone must vacate the area. The blast zone is identified as Lagoons 1 through 10 inclusive. Incurred stand-by due to blasting totaling a whole day will be granted a contract extension.”
QUESTION 6. Can grouting work areas for grout equipment be built inside of the lagoons?
RESPONSE: The logistical constraints in Paragraph 1.3 of Section 00 31 19.01 03 state that “It may be possible to obtain very limited access to the berm from the northeast end of Lagoon 1; however, there will be no other access permitted, and the Contractor's access will be restricted to the confines of the work areas defined in the Drawings.” No other work areas are defined within the reservoir footprint, and lagoons other than 21 will not be available as work areas.
QUESTION 7. Will the contractor be allowed to use the Option 1 work area as an access road to the base bid work area?
RESPONSE: Paragraph 1.3 of Section 00 31 19.01 03 has been amended to include:
“Access through the Option 1 area to the Base Bid area will be possible prior to the execution of the Options; however access may be limited by the operations of other contractors during that time, and coordination with the COR will be required throughout the contract duration for this access.”
QUESTION 8. Please clarify the ongoing blasting operations. What is the amount of standby time associated with each blast? What operations will have to be stopped during each blast? During which months of the year will blasting be performed on a daily basis?
RESPONSE: Amended Paragraph 1.3 of Section 00 31 19.01 03 provides the extent to which USACE is able to predict the duration of standby time associated with blasting, and the limitations implied by this constraint: “Blasting occurs at the discretion of the quarry operator. In general, blasting occurs in the afternoon with shutdowns lasting no longer than 30 minutes. All personnel in the blast zone must vacate the area. The blast zone is identified as Lagoons 1 through 10 inclusive. Incurred stand-by due to blasting totaling a whole day will be granted a contract extension.”
QUESTION 9. Does the quantity of standby time provided in the bid schedule need to be shown on the project schedule submitted with the proposal? Is this amount of standby time included in the contract performance time of 730 calendar days?
RESPONSE: No. Specification Section 00 31 19.01 03 EXISTING CONDITIONS, Part
1.3 LOGISTICAL CONSTRAINTS, paragraph 3 has been amended to include the following statement:
“Incurred stand-by time due to blasting totaling a whole day will be granted a contract time extension.”
QUESTION 10. …it is requested that the district provide the survey data mentioned in Section 31 00 00 - Page 11 (3.2.3 Work Platform).
RESPONSE: Please refer to Sheets C-02 through C-04 for cross-sectional survey data.
QUESTION 11. …it is requested that the date for submission of proposals be moved at least one month in order to allow sufficient time to estimate and assemble the proposal package.
RESPONSE: As per Amendment 0001, a one week extension was provided. Proposals are to be submitted by August 13, 2009. No further extension is provided at this time.
QUESTION 12. What is the frequency, duration, and time of day that blasting will occur during the project?
RESPONSE: Specification Section 00 31 19.01 03 EXISTING CONDITIONS, Part 1.3 LOGISTICAL CONSTRAINTS, paragraph 3 has been amended to include the following statement:
“Blasting occurs at the discretion of the quarry operator. In general, blasting occurs in the afternoon with shut downs lasting no longer than 30 minutes.”
QUESTION 13. Please provide as built data showing the location of the slurry cut-off wall.
RESPONSE: Please refer to Reference document “e. Stage I Cut-off Wall As-Builts”, “c. Stage II Cut-off Wall Contract Plans”, and “f. Stage I Cut-off Wall Foundation Report”. References can be accessed through ftp site:
ftp://ftp.usace.army.mil/pub/lrc/McCookStage2%20Grout%20References/
QUESTION 14. Please provide as built data showing the location of existing underground utilities. … Electric and Sanitary manholes were observed along the MWRD Sludge Transportation rail line.
RESPONSE: Please refer to Reference documents including “e. Stage I Cut-off Wall As-Builts” and “c. Stage II Cut-off Wall Contract Plans” for known underground utility. Contractor shall verify underground utility locations prior to construction activities.
QUESTION 15. Please provide detailed plans of the tunnel system below the grout line and quarry.
RESPONSE: There is a Record Drawing provided in the Contract Plan Set. Please refer to Sheet C-11.
QUESTION 16. What is the frequency, duration, and time of day that MWRD Sludge Transportation rail line is in operation?
RESPONSE: Generally the train makes two round trips per day, once in the morning and once in the afternoon. The train passes through the work area with out stopping with a transit time through the work area of a few minutes.
QUESTION 17. At locations along MWRD Sludge Transportation line, where sheet pile wall exists, is the sheet pile wall capable of handling additional loads of work platform and heavy equipment?
RESPONSE: Yes.
QUESTION 18. What is the depth of the sheet pile toe?
RESPONSE: Please refer to attached record drawings at the end of this Question and Answer Section.
QUESTION 19: Specification Section 01.57 20.01 03 Pg 15 3.5.5 Waste Water; On the Stage I Contract, was drill water and clean up water treated in accordance with this section, ie was it treated and taken off site?
RESPONSE: Part of the Stage 1 contract was performed while there was access to an MWRD drop shaft for water disposal, and that was utilized. Once the connection between the shaft and the mainstream tunnel system was plugged as part of the Stage 1 contract work, the water was treated on site and much of it re-used by the contractor.
QUESTION 20: Section B/C07 shows a concrete work platform with formed concrete gutter. The Stage I contractor used a concrete work platform with an excavated trench lined with filter fabric. Will the fabric lined trench be allowed on this project?
RESPONSE: The conditions and ongoing operations and work adjacent to the Stage 2 area are such that the design of the Contractor’s work platform will require a concrete gutter.
QUESTION 21: Blasting Schedule…How close can drilling and grouting operations be to the blast before they have to go on standby?
RESPONSE: The contractor will be required to cease drilling and grouting activities within the blasting zone. Specification Section 00 31 19.01 03 EXISTING CONDITIONS, Part 1.3 LOGISTICAL CONSTRAINTS, paragraph 3 has been amended to include the following statement:
“In general, blasting occurs in the afternoon with shutdowns lasting no longer than 30 minutes. All personnel in the blast zone must vacate the area. The blast zone is identified as Lagoons 1 through 10 inclusive.”
QUESTION 22: It appears that the actual elevations are not what is represented on the cross sections on sheets C-02, C-03 and C-04. Will these drawings be revised to reflect the actual conditions?
RESPONSE: No. Solicitation Set drawings shall be the basis of bids.
QUESTION 23: Based on actual slope conditions it appears a considerable amount of fill and/or some sort of structural support will be needed to gain access to the "A" line. Does the slope have to be restored to its original condition at the conclusion of this contract?
RESPONSE: Yes. Specification 31 00 00 EARTHWORK Part 3.2.3 paragraph 2 states “The work platform shall be removed upon completion of the contract and work area restored to existing conditions prior to work platform construction.” However, if Option 2 is exercised, slope locations that are included in Option 2 shall be constructed to meet Option 2 Plans and Specifications.
QUESTION 24: At the East end of the site, will the excavation contractor for overburden removal leave sufficient bench to allow construction of the work platform so that the stage II contractor does not have to provide fill to construct the work platform?
RESPONSE: Paragraph 1.3 of Section 00 31 19.01 03 is amended to state that: "The grades will be essentially restored by others along the east side of the project prior to execution of Option 1, to the elevations shown in the drawings."