This document outlines a sources sought notice for an optimized remediation contract at Beale Air Force Base in California. The U.S. Army Corps of Engineers seeks information from small and other-than-small businesses to conduct environmental remediation activities at 23 sites, including maintaining remedies, implementing optimizations, and achieving site objectives. Interested firms must have experience in projects of similar scope managing work at multiple locations. The response deadline is July 31, 2019. The anticipated contract will be for 10 years utilizing best-value tradeoff procedures. The contract type will be firm-fixed-price.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Beale AFB ORC Installation Site CLIN/Sub-CLIN Number CLIN/Sub-CLIN Description Projected Award Date (Pending availability of funding and bona fide need) Period of Performance (Proposed Periods of Performance shall not extend beyond 4 Years per SubCLIN. Actual PoPs shall not exceed 5 years per SubCLIN. Proposed and Actual overall contract PoP shall not exceed 10 years from contract award)
| N/A | N/A | 0001 | Complete Project Management Plan (PMP) | ||
| N/A | N/A | 0001AA | Complete PMP | Base Year | Four years from obligation of the Sub-CLIN |
| N/A | N/A | 0001AB | Update PMP | Optional Task | Three years from obligation of the Sub-CLIN |
| N/A | N/A | 0001AC | Update PMP | Optional Task | Three years from obligation of the Sub-CLIN |
| N/A | N/A | 0002 | Complete Quality Assurance Surveillance Plan (QASP) | ||
| N/A | N/A | 0002AA | Complete QASP | Base Year | Four years from obligation of the Sub-CLIN |
| N/A | N/A | 0002AB | Update QASP | Optional Task | Three years from obligation of the Sub-CLIN |
| N/A | N/A | 0002AC | Update QASP | Optional Task | Three years from obligation of the Sub-CLIN |
| N/A | N/A | 0003 | Develop Integrated Master Schedule (IMS)/Milestone Payment Schedule (MPS) and Update Monthly | ||
| N/A | N/A | 0003AA | Develop IMS/MPS and Update Monthly | Base Year | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AB | Update IMS/MPS Monthly - Year 2 | Option Year - FY21 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AC | Update IMS/MPS Monthly - Year 3 | Option Year - FY22 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AD | Update IMS/MPS Monthly - Year 4 | Option Year - FY23 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AE | Update IMS/MPS Monthly - Year 5 | Option Year - FY24 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AF | Update IMS/MPS Monthly - Year 6 | Option Year - FY25 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AG | Update IMS/MPS Monthly - Year 7 | Option Year - FY26 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AH | Update IMS/MPS Monthly - Year 8 | Option Year - FY27 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AJ | Update IMS/MPS Monthly - Year 9 | Option Year - FY28 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0003AK | Update IMS/MPS Monthly - Year 10 | Option Year - FY29 | One year from obligation of the Sub-CLIN |
| N/A | N/A | 0004 | Complete 1,4-Dioxane sampling in accordance with paragraph 8.1.1.f. of the PWS | Optional Task | One year from obligation of the CLIN |
| Beale AFB | N/A | 0005 | Complete Basewide Quality Program Plans (QPPs) | ||
| Beale AFB | N/A | 0005AA | Complete Basewide QPP | Base Year | Four years from obligation of the Sub-CLIN |
| Beale AFB | N/A | 0005AB | Update Basewide QPP | Optional Task | Three years from obligation of the Sub-CLIN |
| Beale AFB | N/A | 0005AC | Update Basewide QPP | Optional Task | Three years from obligation of the Sub-CLIN |
| Beale AFB | N/A | 0006 | Develop a Land Use Control Implementation Plan | Optional Task | One year from obligation of the CLIN |
| Beale AFB | CG041-010 | 0007 | Conduct RA-O | ||
| Beale AFB | CG041-010 | 0007CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-010 | 0007CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-010 | 0007CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-010 | 0007CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-010 | 0007CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-016 | 0008 | Conduct RA-O | ||
| Beale AFB | CG041-016 | 0008CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-016 | 0008CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-016 | 0008CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-016 | 0008CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-016 | 0008CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-017 | 0009 | Achieve Remedy in Place | ||
| Beale AFB | CG041-017 | 0009AA | Achieve Remedy in Place | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-017 | 0009CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-017 | 0009CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-017 | 0009CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-017 | 0009CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-018 | 0010 | Conduct RA-O and Reduce LCCs | ||
| Beale AFB | CG041-018 | 0010CA | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CB | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CC | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CD | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CE | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CF | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CG | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-018 | 0010CH | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-018 | 0010CJ | Maintain compliance with regulatory requirements and binding agreements, Reduce LCCs, and complete the Reduce LCC Summary Report - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-018 | 0010CK | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-018 | 0010CL | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-029 | 0011 | Conduct RA-O | ||
| Beale AFB | CG041-029 | 0011CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-029 | 0011CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-029 | 0011CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-029 | 0011CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-029 | 0011CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-035 | 0012 | Conduct RA-O and Reduce LCCs | ||
| Beale AFB | CG041-035 | 0012CA | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CB | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CC | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CD | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CE | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CF | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CG | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-035 | 0012CH | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-035 | 0012CJ | Maintain compliance with regulatory requirements and binding agreements, Reduce LCCs, and complete the Reduce LCC Summary Report - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-035 | 0012CK | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-035 | 0012CL | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-039 | 0013 | Conduct RA-O | ||
| Beale AFB | CG041-039 | 0013CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-039 | 0013CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-039 | 0013CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-039 | 0013CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-039 | 0013CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-508 | 0014 | Conduct RA-O | ||
| Beale AFB | CG041-508 | 0014CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-508 | 0014CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-508 | 0014CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-508 | 0014CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-508 | 0014CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-509 | 0015 | Achieve Response Complete | ||
| Beale AFB | CG041-509 | 0015AA | Optimize the site in support of Response Complete | Base Year | Five years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015AB | Achieve Response Complete | Option Year - Upon Completion of 0015AA | Five years from obligation of 0015AA |
| Beale AFB | CG041-509 | 0015CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-509 | 0015CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-509 | 0015CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-509 | 0015CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-509 | 0015CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-517 | 0016 | Conduct RA-O | ||
| Beale AFB | CG041-517 | 0016CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG041-517 | 0016CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-517 | 0016CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-517 | 0016CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG041-517 | 0016CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG044 | 0017 | Achieve Remedy in Place | ||
| Beale AFB | CG044 | 0017AA | Achieve ROD | Base Year | Two years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017AB | Achieve Remedial Design | Option Year - Upon Completion of 0017AA | Two years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017AC | Achieve Remedy in Place | Option Year - Upon Completion of 0017AB | Three years from obligation of the Sub-CLIN |
(not to exceed seven years from obligation of 0017AA)
| Beale AFB | CG044 | 0017CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | CG044 | 0017CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG044 | 0017CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG044 | 0017CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | CG044 | 0017CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | DP038 | 0018 | Conduct LTM | ||
| Beale AFB | DP038 | 0018CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | DP038 | 0018CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | DP038 | 0018CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | DP038 | 0018CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | DP038 | 0018CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | DP038 | 0018CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | DP038 | 0018CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | DP038 | 0018CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | DP038 | 0018CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ED631 | 0019 | Achieve Response Complete | ||
| Beale AFB | ED631 | 0019AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | ED631 | 0019AB | Achieve Response Complete | Option Year - Upon Completion of 0019AA | Four years from obligation of 0019AA |
| Beale AFB | ED631 | 0019CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0019AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | ED631 | 0019CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0019CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ED631 | 0019CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0019CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ED631 | 0019CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0019CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ED631 | 0019CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0019CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | FR970 | 0020 | Conduct LTM | ||
| Beale AFB | FR970 | 0020CA | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | FR970 | 0020CB | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | FR970 | 0020CC | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | FR970 | 0020CD | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | FR970 | 0020CE | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | FR970 | 0020CF | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | FR970 | 0020CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF002 | 0021 | Conduct LTM and Reduce LCCs | ||
| Beale AFB | LF002 | 0021CA | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CB | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CC | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CD | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CE | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CF | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CG | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF002 | 0021CH | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF002 | 0021CJ | Maintain compliance with regulatory requirements and binding agreements, Reduce LCCs, and complete the Reduce LCC Summary Report - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF002 | 0021CK | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF002 | 0021CL | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF003 | 0022 | Conduct LTM and Reduce LCCs | ||
| Beale AFB | LF003 | 0022CA | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CB | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CC | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CD | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CE | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CF | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CG | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF003 | 0022CH | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF003 | 0022CJ | Maintain compliance with regulatory requirements and binding agreements, Reduce LCCs, and complete the Reduce LCC Summary Report - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF003 | 0022CK | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF003 | 0022CL | Maintain compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF013 | 0023 | Conduct LTM | ||
| Beale AFB | LF013 | 0023CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | LF013 | 0023CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF013 | 0023CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF013 | 0023CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | LF013 | 0023CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML595 | 0024 | Achieve Response Complete | ||
| Beale AFB | ML595 | 0024AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | ML595 | 0024AB | Achieve Response Complete | Option Year - Upon Completion of 0024AA | Four years from obligation of 0024AA |
| Beale AFB | ML595 | 0024CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0024AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | ML595 | 0024CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0024CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML595 | 0024CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0024CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML595 | 0024CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0024CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML595 | 0024CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0024CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML625 | 0025 | Achieve Response Complete | ||
| Beale AFB | ML625 | 0025AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | ML625 | 0025AB | Achieve Response Complete | Option Year - Upon Completion of 0025AA | Four years from obligation of 0025AA |
| Beale AFB | ML625 | 0025CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0025AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | ML625 | 0025CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0025CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML625 | 0025CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0025CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML625 | 0025CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0025CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | ML625 | 0025CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0025CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT017 | 0026 | Conduct LTM | ||
| Beale AFB | OT017 | 0026CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT017 | 0026CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT017 | 0026CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT017 | 0026CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT017 | 0026CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT584 | 0027 | Conduct RA-O | ||
| Beale AFB | OT584 | 0027CA | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT584 | 0027CB | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT584 | 0027CC | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT584 | 0027CD | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT584 | 0027CE | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | OT584 | 0027CF | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT584 | 0027CG | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT584 | 0027CH | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | OT584 | 0027CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | PL582 | 0028 | Conduct RA-O | ||
| Beale AFB | PL582 | 0028CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | PL582 | 0028CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | PL582 | 0028CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | PL582 | 0028CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | PL582 | 0028CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SD032 | 0029 | Conduct LTM | ||
| Beale AFB | SD032 | 0029CA | Maintain compliance with regulatory requirements and binding agreements - Year 1 | Base Year | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CB | Maintain compliance with regulatory requirements and binding agreements - Year 2 | Option Year - FY21 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CC | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CD | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CE | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CF | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CG | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - FY26 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SD032 | 0029CH | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - FY27 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SD032 | 0029CJ | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - FY28 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SD032 | 0029CK | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - FY29 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SD032 | 0029CL | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - FY30 | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR614 | 0030 | Achieve Response Complete | ||
| Beale AFB | SR614 | 0030AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | SR614 | 0030AB | Achieve Response Complete | Option Year - Upon Completion of 0030AA | Four years from obligation of 0029AA |
| Beale AFB | SR614 | 0030CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0030AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | SR614 | 0030CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0030CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR614 | 0030CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0030CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR614 | 0030CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0030CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR614 | 0030CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0030CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR615 | 0031 | Achieve Response Complete | ||
| Beale AFB | SR615 | 0031AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | SR615 | 0031AB | Achieve Response Complete | Option Year - Upon Completion of 0031AA | Four years from obligation of 0030AA |
| Beale AFB | SR615 | 0031CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0031AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | SR615 | 0031CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0031CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR615 | 0031CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0031CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR615 | 0031CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0031CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR615 | 0031CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0031CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR617 | 0032 | Achieve Response Complete | ||
| Beale AFB | SR617 | 0032AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | SR617 | 0032AB | Achieve Response Complete | Option Year - Upon Completion of 0032AA | Four years from obligation of 0031AA |
| Beale AFB | SR617 | 0032CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0032AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | SR617 | 0032CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0032CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR617 | 0032CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0032CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR617 | 0032CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0032CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR617 | 0032CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0032CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR622 | 0033 | Achieve Response Complete | ||
| Beale AFB | SR622 | 0033AA | Achieve Remedial Design and Remedial Action Work Plan | Option Year - FY21 | Four years from obligation of the Sub-CLIN |
| Beale AFB | SR622 | 0033AB | Achieve Response Complete | Option Year - Upon Completion of 0033AA | Four years from obligation of 0031AA |
| Beale AFB | SR622 | 0033CA | Maintain compliance with regulatory requirements and binding agreements - Year 7 | Option Year - Upon Completion of 0033AB | Three years from obligation of the Sub-CLIN |
| Beale AFB | SR622 | 0033CB | Maintain compliance with regulatory requirements and binding agreements - Year 8 | Option Year - 1 Year after 0033CA | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR622 | 0033CC | Maintain compliance with regulatory requirements and binding agreements - Year 9 | Option Year - 1 Year after 0033CB | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR622 | 0033CD | Maintain compliance with regulatory requirements and binding agreements - Year 10 | Option Year - 1 Year after 0033CC | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SR622 | 0033CE | Maintain compliance with regulatory requirements and binding agreements - Year 11 | Option Year - 1 Year after 0033CD | Obligation of the Sub-CLIN through POP End |
| Beale AFB | SS010 | 0034 | Conduct RA-O | ||
| Beale AFB | SS010 | 0034CA | Maintain compliance with regulatory requirements and binding agreements - Year 3 | Option Year - FY22 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SS010 | 0034CB | Maintain compliance with regulatory requirements and binding agreements - Year 4 | Option Year - FY23 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SS010 | 0034CC | Maintain compliance with regulatory requirements and binding agreements - Year 5 | Option Year - FY24 | Three years from obligation of the Sub-CLIN |
| Beale AFB | SS010 | 0034CD | Maintain compliance with regulatory requirements and binding agreements - Year 6 | Option Year - FY25 | Three years from obligation of the Sub-CLIN |