Attachment 0007
Integration Schedule Events
WBS
Element Task Evidence Standard Schedule
Duration
1.3.1.1 & 1.3.1.2
Multiplayer and
SWDAR
Modifications Design
Video format 720p HD-SDI or Analog NTSC 17 days
1.3.2.1 Payload Hardware
Integration Design Mechanical drawings Mechanical Interface compatible with
ICD Section 3.1.1 5 days
1.3.2.2 Encoder Modifications Design
Video format 720p HD-SDI or Analog NTSC 10 days
1.3.2.3 Payload INS Design Electrical interface
document GPS Interface per ICD Section 3.3.4 20 days
1.3.2.4 Electrical Harness
Design
Electrical interface drawing
Compatibility with existing wiring harness per ICD Section 3.4 10 days
1.3.2.6 Shock Mount
Design Mechanical Drawings
Compliance with mechanical installation utilizing no shock isolators per ICD Section 3.1.1, or utilizing shock isolators (NSN 5340-33-210- 7059) per ICD Section 3.1.2 if isolation is necessary.
5 days
1.3.2.8 Electromagnetic Environmental Effects (E3) Design
Test report
Documented operation while exposed to electromagnetic environments specified in PBS sections 3.9.5.2 and 3.9.5.3
5 days
1.7.5.4 Electromagnetic Environments Ground Testing
Test report
Documented operation while exposed to electromagnetic environments specified in PBS sections 3.9.5.2 and 3.9.5.3
5 days
1.7.5.7 Public Health
Command Testing
Laser subsystem functional design documentation
Compliance with PBS Sections
3.4.1.3.1 (LTM States), 3.4.1.4.1 (LRF States), 3.4.1.5.1 (LD States)
20 days
1.7.5.8 Hellfire Verification
Testing
Laser subsystem functional design documentation
Compliance with PBS Sections
3.4.1.3.1 (LTM States), 3.4.1.4.1 (LRF States), 3.4.1.5.1 (LD States)
15 days
1.7.5.12 GPS Testing Test report Documentation of integration on an aircraft that uses SAASM GPS 5 days