Electro-Optic/Infrared/Laser Designator Payload Production and System Support Contract
ELECTRO-OPTIC / INFRARED / LASER DESIGNATOR (EO/IR/LD) PAYLOAD
PRODUCTION AND SYSTEM SUPPORT BASE CONTRACT
Appendix C Deliverables
C-1.0 Data Deliverables
The Government shall develop Contract Data Requirements List (CDRLs) (DD Form 1423) requirements for base contract and each individual Task Order/Delivery Order (TO/DO) as required.
The Contractor shall then deliver CDRLs per DD Form 1423 and Data Item Deliverable (DID) requirements, as specified in their corresponding TOs/DOs. The CDRLs associated with this effort are listed in Table C-1 and included in Section J of the contract. This list does not preclude the Government from adding CDRLs to subsequent TOs/DOs based upon specific TO/DO requirements;
any additional CDRLs shall be included and addressed through TO/DO negotiations.
CDRL No. CDRL Title Date Item
Description (DID)Title
DID #
PWS Reference
Paragraph
B001
Contractor’s Progress, Status, and Management Report (CPSMR)
Contractor’s Progress, Status and Management Report
DI-MGMT-
80227
3.1
B002 Integrated Master Schedule (IMS)
Integrated Master Schedule
DI-MGMT-
81650
3.1.1, 3.3.1.1, 3.3.1.2
B003 Conference Agenda Conference Agenda
DI-ADMN-
81249B
3.1.2, 3.1.3, 3.1.4, 3.3.1, 3.5.2, 3.6.7.2.9
B004 Presentation Material
Presentation Material
DI-ADMN-
81373
3.1.2, 3.1.3, 3.1.4, 3.3.1, 3.5.2, 3.6.7.2.9
B005 Report, Record of Meeting/Minutes
Report, Record of Meeting/Minutes
DI-ADMN-
81505
3.1.2, 3.1.3, 3.1.4, 3.1.5, 3.3.1, 3.5.2, 3.6.7.2.9
B006 Trip Report Trip / Travel Report
DI-MISC-
81943
3.1.5, 3.4.2, 3.6.7.1.1.4, 3.6.7.2.4, 6.
B007
Government Furnished Property (GFP) and Contractor Acquired Property (CAP) Master Report
Government Furnished Property and Contractor Acquired Property Master Report
DI-MGMT-
80441B
3.1.6, 3.2.3
B008 Contract Work Breakdown Structure (CWBS)
Contract Work Breakdown Structure
DI-MGMT-
81334D
3.1.7.1
B009 Cost Data Summary Report (DD Form 1921)
Cost Data Summary Report (DD Form 1921)
DI-FNCL-
81565C
3.1.7.2
B010 Functional Cost- Hour Report (DD Form 1921-1)
Functional Cost-Hour Report (DD Form 1921-1)
DI-FNCL-
81566C
3.1.7.2
B011 Contractor Business Data Report (Form
DD 1921-3)
Contractor Business Data Report (Form DD 1921-3)
DI-FNCL-
81765B
3.1.7.2
A001
Scientific and Technical Report / Retrofits of Fielded Systems
Scientific and Technical Reports
DI-MISC-
80711A
3.2.2, 3.2.3
A002 Engineering Change Proposal-Class I, Major
Engineering Change Proposal
DI-SESS-
80639D
3.3.4.1, 3.2.4.3
A003 Engineering Change Proposal- Class II, Minor
Engineering Change Proposal
DI-SESS-
80639D
3.3.4.2
A004 Request for Variance
Request for Variance
(RFV)
DI-SESS-
80640D
3.3.4.4
A005 Notice of Revision Notice of Revision
(NOR)
DI-SESS-
80642D
3.3.4.4
A006 Environmental Stress Screening Report (ESS)
Environmental Stress Screening Report
DI-ENVR-
81663
3.2.5
A007 Acceptance Test Procedure
Test Procedure
DI-NDTI-
80603A
3.2.5
A008 Quality Assurance Plan (QAP)
Quality Assurance Program Plan
DI-QCIC-
81794 NOT 1
3.2.6
A009
Specification Requirement Verification Matrix (SRVM) (Pre—PBR)
Specification Requirement Verification Matrix
DI-MISC-
81283
3.3, 3.3.1.1
A010
Systems Engineering Management Plan (SEMP) (Pre-PBR)
Systems Engineering Management Plan
(SEMP)
DI-SESS-
81785
3.3, 3.3.1.1
A011 Risk Analysis (Pre-
PBR)
Contractor’s Risk Management Plan
DI-MGMT-
81808
3.3.1.1
A012 First Article Test Plans – Pre-PBR
Test Plan
DI-NDTI-
80566A
3.3.1.1, 3.5.3
A013 Reliability Test Plan
- Pre-PBR
Test Plan
DI-NDTI-
80566A
3.3.1.1, 3.5.4
A014 Risk Analysis (Update) (Post-
PBR)
Contractor’s Risk Management Plan - Update
DI-MGMT-
81808
3.3.1.2
A015
Systems Engineering Management Plan (SEMP) Update (Post PBR)
Systems Engineering Management Plan
(SEMP)
DI-SESS-
81785
3.3. 3.3.1.2
A016 First Article Test Plans – Post-PBR
Test Plan
DI-NDTI-
80566A
3.3.1.2, 3.5.3
A017 Reliability Test Plan
- Post-PBR
Test Plan
DI-NDTI-
80566A
3.3.1.2, 3.5.4
A018
Specification Requirement Verification Matrix (SRVM) Update (Post –PBR)
Specification Requirement Verification Matrix
DI-MISC-
81283
3.3.1.2, 3.5.3
A019 Configuration Management Plan
Configuration Management Plan
(MIL-STD-3046)
DI-SESS-
81875
3.3.3
A020
Configuration Status Accounting (CSA) Information-As Built Data
Configuration Status Accounting Information
DI-SESS-
81253C
3.3.3
A021 EO/IR/LD Payload Product Specification
Baseline Description Document
DI-SESS-
81121A
3.3.3
A022 Interface Control Document (ICD)
Interface Control Document
DI-SESS-
81248B
3.3.3
A023 Software Requirements Specification (SRS)
Software Requirements Specification
DI-IPSC-
81433A NOT
3.3.4
A024 Software Version Description (SVD)
Software Version Description)
DI-IPSC-
81442A NOT
3.3.4
A025 Reliability and Maintainability Predictions Report
Reliability and Maintainability Predictions Report
DI-SESS-
81497A
3.3.5
A026 Reliability Centered Maintenance (RCM) Analysis
Reliability-Centered Maintenance (RM) Analysis Report
DI-PSSS-
82114
3.3.5
A027
Failure Reporting Analysis and Corrective Action Report
Failure Summary and Analysis Report
DI-SESS-
80255A
3.6.6
A028 Technology Insertion
Scientific and Technical Reports
DI-MISC-
80711A
3.4.1
A029 Payload Cybersecurity Posture
Scientific and Technical Reports
DI-MISC-
80711A
3.4.3
A030 Certificate of Volatility
Technical Report- Study/Services, DI-MISC-
80508
3.4.4
A031 First Article Test Procedures
Test Procedure
DI-NDTI-
80603A
3.5.3
A032 First Article Test Reports
Test / Inspection Report
DI-NDTI-
80809B NOT
3.5.3
A033 Reliability Test Procedures
Test Procedure
DI-NDTI-
80603A
3.5.4
A034 Reliability Test Report
Test / Inspection Report
DI-NDTI-
80809B NOT
3.5.4
A035 Failure Item Analysis Report
Failure Summary and Analysis Report
DI-SESS-
80255A
3.5.5
A036 Software Product Specification
DI-IPSC-
81441A
3.3.4
C001 Field Service Representative Spares Parts List
Field Services Representative Consumables/Repairs, and Spares Parts List
OT-18-10002 3.6.7.1.1
D001 Level of Repair Analysis (LORA) Input Data
Level of Repair Analysis (LORA) Report
DI-PSSS-
81873A
3.6.1.1
D002 Depot Maintenance Study
Depot Maintenance Study
DI-ILSS-
80739
3.6.1.2
D003 Bill of Materials
(BOM)
Bill of Materials (BOM) for Logistics and Supply Chain Risk Management
DI-PSSS-
81656B
3.6.2.1
D004 Inventory Reports
Consumable Parts Bond Room / Inventory and Parts Usage Report
DI-ILSS-
80834
3.6.2.2
D005 Provisioning Parts Data
Engineering Data for Provisioning (EDFP)
DI-SESS-
81874
3.6.2.3
D006 Maintenance Allocation Chart
(MAC)
LSA-004,
Maintenance Allocation Chart
DI-ILSS-
81140A
3.6.2.4
D007
Diminishing Manufacturing Sources and Material Shortages
(DMSMS)
Management Plan
Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management Plan
DI-MGMT-
81948
3.6.2.5
D008
DMSMS
Implementation Plan
Diminishing Manufacturing Sources and Material Shortages (DMSMS) Implementation Plan
DI-MGMT-
81949
3.6.2.5
D009 Obsolescence Alert Notice
Obsolescence Alert Notice
DI-MGMT-
81941
3.6.2.5
D010 Integrated Logistics Support Plan
Integrated Logistics Support Plan
DI-ILSS-
80095
3.6.4
D011 Software Transition Plan
Software Transition Plan (STRP)
DI-IPSC-
81429A
3.6.5
D012 Item Unique Identification (IUID) Marking Plan
Item Unique Identification (IUID) Marking Plan
DI-MGMT-
81803
3.6.6.1
D013
Item Unique Identification (IUID) Marking and Verification Report
Item Unique Identification (IUID) Marking and Verification Report
DI-MGMT-
81858
3.6.6.1
D014 Maintenance Plan Logistics Product Data Summaries
DI-SESS-
81759A
3.6.7
D015 Depot Repair Inspection Report
Repairable Item Inspection Report
DI-PSSS-
80386A
3.6.7.1.1.2
D016 Repair Data Report Technical Report- Study/Services
DI-MISC-
80508B
3.6.7.1.1.3
D017 Reach Back Call Log
Technical Report- Study/Services
DI-MISC-
80508B
3.6.7.1.1.5
D018 Training Plan Training Program Development and Management Plan
DI-ILSS-
81070
3.6.7.1.2
D019 Technical Manuals
Preparation of Digital Technical Information for Page-Based Technical Manuals (TMs) & Department of Defense Handbook:
Guide to the General Style and Format of U.S. Army Work Package Technical Manuals
MIL-STD-
40051-2C &
MIL-HDBK-
1222F
3.6.7.1.2.1
D020 Repair Parts and Special Tools List
Parts List
DI-SESS-
81359B
3.6.7.2.3
D021 Training Materials Training Materials
DI-ILSS-
80872
3.6.7.2.5
D022 Logistics Product Data Summaries
Logistics Product Data
DI-SESS-
81758A
3.6.7.2.7
D023 Data Accession List
(DAL)
Data Accession List
(DAL)
DI-MGMT-
81453B
D024 Operations Security (OPSEC) Plan
Operations Security (OPSEC) Plan
DI-MGMT-
80934C
D025 Program Protection Implementation Plan
Program Protection Implementation Plan
DI-ADMN-
81306
D026 Safety Assessment Report (SAR)
Safety Assessment Report
DI-SAFT-
80102C
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administration / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
B001 Contractor's Progress, Status and Management Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MGMT-80227 PWS Section 3.1, 6.0 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
MTHLY 30 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
N/A
SEE BLOCK 16 ^
Reg
Repro
16. REMARKS:
Block 4: Files shall be in the Microsoft Office Suite of products. Contractor format is acceptable.
The report shall include the following, at a minimum: Progress of testing events; components and materials deliveries; reach back support and travel;
depot repair status data; and beyond economical repair data.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government will have ten (10) business days to review and respond back to Contractor with comments/updates. The Contractor shall have ten (10) business days to reply with updates to Government.
Block 14: Report emailed to the Contracting Officer and the Contracting Officer Representative
SFAE-IEW-TE
CCAP-CCV-A
15. TOTAL 2 2
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Joseph Maheady PM EO/IR, Shadow PL
11 Dec 2017
Jerord E. Wilson Deputy PdM EO/IR Payloads
DD Form 1423-1, Feb 2001
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administration / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B002 Integrated Master Schedule
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MGMT-81650 PWS Sections 3.1.1, 3.3.1.1, 3.3.1.2 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
MTHLY 30 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
See Block 16 ^
Block 4: Files shall be in the Microsoft Office Project. Contractor format is acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administration / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B003 Conference Agenda
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ADMN-81249B PWS Sections 3.1.2, 3.1.3, 3.1.4, 3.3.1, 3.5.3, 3.6.7.2.9
SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in the Microsoft Office Suite of products. Contractor format is acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12 and 13: Draft to be provided at a minimum of eight (8) business days prior to the meeting event. The Government requires three (3) business days to review and provide comments.
Block 13: Five (5) business days after receipt of comments
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administration / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B004 Presentation Material
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ADMN-81373 PWS Sections 3.1.2, 3.1.3 3.1.4, 3.3.1, 3.5.3, 3.6.7.2.9
SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
SEE BLOCK
SEE BLOCK 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SEE BLOCK 16 ^
Block 4: Files shall be in the Microsoft Office Suite of products. Contractor format is acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 10 and 12: Draft to be provided at a minimum of eight (8) business days prior to the meeting event. The Government requires three (3) business days to review and provide comments.
Block 13: Five (5) business days after receipt of comments
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administration / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B005 Report, Record of Meeting/Minutes
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ADMN-81505 PWS Sections 3.1.2, 3.1.3, 3.1.4, 3.3.1, 3.5.3, 3.6.7.2.4, 3.6.7.2.9
SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in the Microsoft Office Suite of products. Contractor format is acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: To be provided three (3) business days after the meeting event.
Government requires three (3) business days to review and provide comments.
Block 13: Three (3) business days after receipt of comments.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B006 Trip / Travel Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MISC-81943 PWS Sections 3.1.5, 3.4.2, 3.6.7.1.1.6, 3.6.7.2.4
SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in the Microsoft Office Suite of products. Contractor format is acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: To be provided three (3) business days after travel completed.
Government requires three (3) business days to review and provide comments.
Block 13: Three (3) business days after receipt of comments
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
B007 Government Furnished Property and Contractor Acquired Property Master Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MGMT-80441 PWS Section 3.1.6 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
MTHLY 30 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in the Microsoft Office Excel. Contractor format is acceptable.
Separate tabs within the excel spreadsheet shall be utilized; one tab will be used to report GFP and one tab will be used to report CAP.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B008 Contract Work Breakdown Structure (CWBS)
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MGMT-81334D
PWS Section 3.1.7.1 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
AS REQ 100 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
N/A 60 DADO See Block 16 ^
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor is required to be in compliance with the structure defined in the
PWS.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: Government requires ten (10) business days to review and provide comments. The Contractor is required to submit updated report to the DCARC Portal as defined in DOD 5000.4-M-1 NLT 120 DADO.
04 Jan 2018
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B009 Cost Data Summary Report (DD Form 1921)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-FNCL-81565C PWS Section 3.1.7.2 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
Annual
100 DADO
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor is required to be in compliance with the structure defined in Appendix A of the PWS.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: Government requires ten (10) business days to review and provide comments. The Contractor is required to submit updated report to the DCARC Portal as defined in DOD 5000.4-M-1 NLT 120 DADO.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
B010 Functional Cost-Hour Report (DD Form 1921-1)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-FNCL-81566C PWS Section 3.1.7.2 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
Annual 100 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor is required to be in compliance with the structure defined in Appendix A of the PWS.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: Government requires ten (10) business days to review and provide comments. The Contractor is required to submit updated report to the DCARC Portal as defined in DOD 5000.4-M-1 NLT 120 DADO.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Administrative / Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
B011 Contractor Business Data Report (Form DD 1921-3)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-FNCL-81765B PWS Section 3.1.7.2 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
Annual 100 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor is required to be in compliance with the structure defined in Appendix A of the PWS.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: Government requires ten (10) business days to review and provide comments. The Contractor is required to submit updated report to the DCARC Portal as defined in DOD 5000.4-M-1 NLT 120 DADO.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
A001 Scientific and Technical Reports Retrofits of Fielded Systems
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MISC-80711A PWS Section 3.2.3 SFAE-IEW-TE
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ 30 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products.
The report shall document, at a minimum, the purpose, scope, technical interdependencies, performance impacts, sustainment impacts, cost, and schedule of the modification.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A002 Engineering Change Proposal (ECP) Engineering Change Proposal (ECP) Class I, Major
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-80639D PWS Sections 3.3.4.1, 3.3.4.3 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products
ECP Class I are for system changes that affect form, fit, function, performance, reliability, logistic baseline, logistics infrastructure to include depot capability and delivered Logistics Management Information (LMI) data, and any system certifications such as but not limited to airworthiness, Information Assurance (IA), and anti-tamper. Class I vs. Class II - In instances where the Contractor cannot determine the classification of the change, the change must be designated Class I and must be reviewed /approved by the Government prior to implementation.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: Ten (10) days after the change is known
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A003 Engineering Change Proposal (ECP) Engineering Change Proposal (ECP) Class II, Minor
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-80639D PWS Section 3.3.4.2 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ASREQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products
ECPs not classified as Class I are Class II. Class II changes may be processed by the Contractor-No Government approval required.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: Ten (10) days after the change is known
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
A004 Request for Variance (RFV) Major Request for Variance (RFV)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-80640D PWS Section 3.3.4.4 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
AS REQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor format acceptable. Variation or exception to any Government approved test procedure (ex., acceptance test procedure or environmental test screening) shall necessitate a Major Request for Variance.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: Ten (10) days after the change is known
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
A005 Notice of Revision (NOR)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-80642D PWS Section 3.3.4.4 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
AS REQ See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products.
Contractor format acceptable. Contractor shall submit for each instance of change initiated by the Contractor.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 12: Ten (10) days after the change is known
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Logistics Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
A006 Environmental Stress Screening Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ENVR-81663
PWS Section 3.2.5 SFAE-IEW-TE
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ANNUAL/REVISI
ON AS
REQUIRED
60 DADO
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
N/A 90 DADO See Block 16 ^
Block 4: Files shall be in Microsoft Office Suite of products. Contractor format acceptable.
Environmental stress screening (ESS) is a cost effective means of improving quality and reliability of electrical, electronic, electro-optical, electro-mechanical and electrochemical assemblies and systems at a time when defect removal is relatively inexpensive. CDRL shall detail procedures related to MIL-
STD-810G.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: Government requires ten (10) business days to review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Management Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
A007 Test Procedure Acceptance Test Procedure
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-NDTI-80603A PWS Section 3.2.5 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ONE See Block 16
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products. Contractor format acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
A008 Quality Assurance Program Plan Quality Control Plan (QCP)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-QCIC-81794 PWS Section 3.2.6 SFAE-IEW-TE
INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ONE 30 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
Block 4: Files shall be in Microsoft Office Suite of products. Contractor format acceptable.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government requires ten (10) business days for review and approval of the draft submission. The Contractor shall have ten (10) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A009 Specification Requirement Verification Matrix Specification Requirement Verification Matrix (Pre PBR Submission)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MISC-81283 PWS Sections 3.3, 3.3.1.1 SFAE-IEW-TE
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD
D
ONE 20 DADO
b. COPIES
SECT B
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT
The Requirements Verification Test Matrix (RVTM) shall detail traceability between all PBS requirements and Contractor documentation that the system meets (or will meet) the requirements.
Block 9: DISTRIBUTION STATEMENT D. "Distribution authorized to DoD and U.S. DoD Contractors only.”
Block 13: The Government requires five (5) business days for review and approval of the draft submission. The Contractor shall have five (5) business days to reply with updates to Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
CLIN TBD A Engineering Data
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Electro-Optic/Infrared/Laser Designator Payload
TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A010 Systems Engineering Management Plan Systems Engineering Management Plan (Pre PBR Submission)