This is a draft solicitation for the Threat Systems Management Office Integrated Support II (TSOMIS II) contract opportunity. The Department of the Army Materiel Command Contracting Command Orlando Contracting Center is seeking to award a single-award, indefinite-delivery/indefinite-quantity contract to provide operations, maintenance, sustainment, and event support services for threat systems used in Army testing and training. Key locations of performance will include facilities at Redstone Arsenal, Alabama; Fort Irwin, California; Fort Polk, Louisiana; and White Sands Missile Range, New Mexico. The preponderance of work will be fixed-price, with some cost-plus-fixed-fee contract line items for ancillary services. The period of performance consists of a five-year base ordering period and two one-year option periods, for a potential total of seven years. The draft solicitation and attachments provide additional details on the required services and response requirements, with questions due by December 21, 2018 and final proposal submissions anticipated by March 4, 2019.

Draft Sample Task

View the file

Other files

File Type Posted
W900KK-19-R-0015_TSOMIS_II_5-9-19_Amendment_4_Final.pdf PDF
W900KK-19-R-0015_TSOMIS_II_5-9-19_conform_copy_up_to_Amendment_3.docx DOCX document
W900KK-19-R-0015_TSOMIS_II_5-9-19_conform_copy_up_to_Amendment_3.pdf PDF
W900KK-19-R-0015_Draft_TSOMIS_II_5-1-19_Amendment_1.pdf PDF
Attachment_1_-_PWS_-_Follow-on_TSOMIS_Final_Amendment_3.doc DOC document
W900KK-19-R-0015_TSOMIS_II_5-9-19_Amendment_3_Final.pdf PDF
Attachment_17-Example_CLIN_Workbook_Ammendment_3.xlsx XLSX spreadsheet
Attachment_1_-_PWS_-_Follow-on_Appendix_A_Update_Amendment_3.DOCX DOCX document
Attachment_1_-_PWS_-_Follow-on_TSOMIS_Final_Amendment_2.doc DOC document
Attachment_9_Gfp_Attachment_final_Amendment_2.xlsx XLSX spreadsheet
Consolidated_Question_Set_5-6-19_Amendment_2_Final.xlsx XLSX spreadsheet
GAMB_MOD_B_Spare_Parts_Amendment_2.xlsx XLSX spreadsheet
Attachment_19_-_Maintenance_Hrs_per_system_Amendment_2.xlsx XLSX spreadsheet
Attachment_12-San_Bernardino_CA_15-5629_Rev_9.pdf PDF
Attachment_19_-_Maintenance_Hrs_per_system.xlsx XLSX spreadsheet
Attachment_17_-_Example_CLIN_Workbook.xlsx XLSX spreadsheet
Attachment_14_-_03_-_TSMO_Ops_Overview_Industry_Day.pdf PDF
Attachment_6_SF_1408_Checklist.doc DOC document
Attachment_16_-_Spare_Parts_list.pdf PDF
Attachment_5_-_Data_Item_Transmittal_Form.doc DOC document
Attachment_11_-_Fact_Sheet_67A_-_NQW.pdf PDF
Attachment_8_Proposal_Receipt_Form.docx DOCX document
Attachment_10_-_TSOMIS_Event_Sample_Task_Scenario_V1.docx DOCX document
Attachment_12-DOL_Vernon_LA_15-5197_Rev_10.pdf PDF
Attachment_21_-_TSOMIS_II_CDRL_Report_4_APR19_Final.pdf PDF
Attachment_15_-_NESTSSlickSheet.pdf PDF
Attachment_15_-_WCCJDataSheet.pdf PDF
Attachment_2_Seed_Task_PWS_for_TSOMIS_II_Final.DOCX DOCX document
Attachment_14_-_02_TSMO_Systems_Overview_Industry_Day.pdf PDF
PREAWA~1.PDF PDF
Attachment_15_-_TSIJDataSheet.pdf PDF
Attachment_13_-_SF1444-13c.pdf PDF
Attachment_7_Question_Form.doc DOC document
Attachment_14_-_Final_Comments_of_QnA_Industry_Day.xlsx XLSX spreadsheet
Attachment_1_-_PWS_-_Follow-on_TSOMIS_Updated_3-8-19.doc DOC document
Industry_Day_Questions_and_Answers.zip ZIP file
Attachment 14 - 03 - TSMO_Ops Overview_Industry_Day.pdf PDF
Attachment 14 - 02 TSMO_Systems Overview_Industry_Day.pdf PDF
Attachment_3_PAST_PERFORMANCE_EVALUATION_QUESTIONNAIRE_FORM.docx DOCX document
Attachment_3_Notice_of_questionnaire.doc DOC document
DOL_Wage_Determinations.zip ZIP file
Attachment_16_-_Spare_Parts_list.pdf PDF
Attachment_9_-_GFE_list_TEST_LLC_SMART_FORM_MAJOR_END_ITEMS_LIST(1).pdf PDF
Attachment_18_-_OAWR_Request_form.pdf PDF
Industry_Day_Questions_and_Answers.zip ZIP file
Attachment_1_QASP_-_TSOMIS__5-10-17.doc DOC document
Attachment_6_SF_1408_Checklist.doc DOC document
Industry_Day_Questions_and_Answers.zip ZIP file
Industry_Day_Questions_and_Answers.zip ZIP file
Attachment 12 - DOL Vernon LA 15-5197 PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TSOMIS Event Sample Task Scenario

Assumptions:

• Building 90125 at the White Sands Missile Range in New Mexico is a permanent site location and will be the departure and return point for non-recurring missions unless it is more reasonable and/or cost effective to transport a system from a previous mission site to an alternate location. Building 90125 provides:

• Sufficient office and storage space for personnel and equipment.

• Storage for repair parts, spare parts kits, and equipment.

• Three maintenance bays with lifts able to support all HMMWV tactical vehicles with shelters in the TSMO inventory.

• 10-Ton crane.

• Equipment yard for storing up to 55 vehicles, with a current inventory of:

• 2 x Integrated Threat Force (ITF) – Command Post Vehicles (CPV).

• 2 x ITF – Threat Headquarters Vehicles (THQ)

• 3 x Networked Electronic Support Threat Sensor – High Vehicles

(NESTS-H). This is considered a suite.

• 2 x Networked Electronic Support Threat Sensor – Medium

Vehicles (NESTS-M).

• 2 x Networked Electronic Support Threat Sensor – Low Vehicles

(NESTS-L).

• 1 x Giraffe Agile Multi-Beam (GAMB) radar.

• 1 x Wideband Configurable Controlled Jammer (WCCJ)

• 1 x CICADA Jammer.

• 12 x Enhanced Controlled Signal Transmitter (E-CST) vehicles.

• 9 x Mobile Commercial Network Infrastructure Test Range

(MCNITR) vehicles.

• 1 x Electronic Warfare Open-Air Collector (EWOC) vehicle.

• 3 x 60 KW tactical trailer mounted generators.

• 1 x GSA 4 x 4 (3500 HD dually) with auxiliary 100-gallon fuel tank and pump.

• Fort Irwin, California is a permanent site location supporting recurring missions at the National Training Center.

• Sufficient office space for personnel and storage space for equipment are provided on Post along with a parking area to store 15 tactical vehicles.

• No permanently assigned bays exist; a maintenance bay can be used on a space-available basis to lift vehicles.

• Current equipment inventory includes:

• 1 x GAMB radar,

• 3 x NESTS, 1 x C3 ITF – CPV,

• 1 x CICADA jammer,

• 2 x 60 KW tactical trailer mounted generators,

• 1 x GSA 4 x 4 (3500 HD dually) with auxiliary 100-gallon fuel tank and pump.

• Fort Polk, Louisiana is a permanent site location supporting recurring missions at the Joint Readiness Training Center.

• Sufficient office space for personnel and storage space for equipment are provided on Post along with a parking area to store 15 tactical vehicles.

• No permanently assigned bays exist; a maintenance bay can be used on a space-available basis to lift vehicles.

• Current equipment inventory at this location:

• 1 x Giraffe G-75 radar,

• 1 x WCCJ,

• 2 x 60 KW tactical trailer mounted generators,

• 1 x GSA 4 x 4 (3500 HD dually) with auxiliary 100-gallon fuel tank and pump installed

• The Operational Availability (Ao) goal for all TSMO systems is 90%. All systems have dedicated on-board or towed power generators.

• All required fuel for generators, and ground system prime movers can be obtained on-site but will be the responsibility of the contractor to haul and refuel their vehicles.

Scenario

• Deploy to a US military range vicinity Yuma, AZ to participate in a non-recurring training exercise. The training exercise will last 14 days and require 24/7 coverage after which you will redeploy equipment and personnel to support the next requirement.

• Figure 1 shows target locations and operations center. The customer requests that you perform Electronic Surveillance (ES) and Electronic Attack (EA) on two targets:

• Frequency hopping radio, operating 30-80 MHz, vicinity 12S TA 43027

95014 (MGRS)

• Satellite radio, operating in Ku band, vicinity 12S TB 39809 08542

(MGRS)

• You are limited to 200 watts power from the antenna port during EA.

• Airborne threat platforms will not be used due to cost constraints.

• Perform airborne surveillance up to 50,000 feet and radius out to 60 kilometers from the operations center location show in figure 1.

• Relay ES information over a network to an operations center vicinity

11S QR 80420 95996 (MGRS) shown in figure 1.

• No fiber optic or other land-line network exists in the area.

• The six-month support schedule shown in figure 2 and table 1 provide the execution dates and requirements that will be supported.

Figure 1. Location of Targets and Operations Center for the Scenario.

Figure 2. Six-Month Calendar of Supported Events.

Table 1. List of Supported Events.

Event Execution Dates

Mission Coverage

Equipment Location

NTC-03 11-21 Jan

24 hours per day

1 x GAMB, 3 x NESTS-H, 1 x ITF-CPV.

Fort Irwin, CA

NTC-04 8-18 Feb

NTC-05 8-18 Mar

NTC-06 12-22 Apr 1 x GAMB, 3 x NESTS-H, 1 x ITF-CPV, 1 x CICADA.

NTC-07 10-20 May

NTC-08 7-17 Jun

NTC-03 Live Fire 22-26 Jan

1 x GAMB.

NTC-04 Live Fire 19-23 Feb

NTC-05 Live Fire 19-23 Mar

NTC-06 Live Fire 23-28 Apr

NTC-07 Live Fire 21-26 May

NTC-08 Live Fire 18-23 Jun

JRTC-03 9-19 Jan

1 x G-75, 1 x WCCJ.

Fort Polk, LA

JRTC-04 7-17 Feb

JRTC-05 7-17 Mar

JRTC-06 10-20 Apr

JRTC-07 8-18 May

Training Event 1 15 Feb- 10 Mar

12 hours per day

1 x CICADA Fort Bliss, TX

Training Event 2 15-29 Apr 24 hours per day

Yuma, AZ

Training Event 3 7-22 May 12 hours per day

3 x MCNITR Fort Gordon, GA

Training Event 4 22 May – 10 Jun

12 hours per day

1 x CICADA, 1 x WCCJ.

JPARC, AK

Testing Event 1 8-30 Mar

12 hours per day

1 x CICADA, 2 x ECSTs, 3 x NESTS-H, 1 x EWOC, 1 x ITF-THQ, 2 x ITF-CPV.

29 Palms, CA

Testing Event 2 1-12 May 12 hours per day

1 x GAMB China Lake, CA

Tasks:

The contractor shall:

• List all necessary equipment to perform electronic surveillance on specified targets in the scenario for training event # 2.

• List all necessary equipment to perform electronic attack on specified targets in the scenario for training event # 2.

• List all necessary equipment to relay ES information over a network to an operations center shown in the scenario for training event # 2.

• List all necessary equipment to support the task in the scenario for training event

# 2.

• List the type of assistance that would be required from the Government (TSMO) to support training event # 2?

• Describe how you would transport all equipment to the task location for training event # 2. List equipment, points of embarkation/debarkation, and transport method.

• Describe how the determination was made to emplace the threat systems at the task location for training event # 2. Please list and/or provide a sample of the type of planning tool(s) that was/were used to determine the best employment location(s) for the systems? Plot the general location of all systems and equipment on a map.

• Describe the control measures to manage equipment and personnel during the task exercise for training event # 2. How would you handle normal operations and emergency shutdown of equipment due to thunderstorms and/or cease buzzer operations for training event # 2?

• Describe how you would anticipate, prepare, and address non-mission capable failures of equipment during training event # 2 given that you cannot miss more than 48 hours of support to the customer.

• Describe the measures that you will employ to ensure the safety of personnel while operating on the range in training event # 2.

• Provide an Integrated Master Schedule showing the staging, deployment, setup, execution, reset, and recovery of equipment and personnel for all of the events shown in figure 2 and table 1 from 1 January through 30 June. Provide exact dates and length of time required to execute each of the phases along with particular equipment being used/transported and personnel required.

• Provide a best labor mix to support all test/training event(s) and ongoing operations from 1 January through 30 June for all events shown in figure 2 and table 1. List labor categories, permanent or surge status, event(s) supported, and the location of personnel during each of the phases/events.