Cover
UNCLASSIFIED
Attachment 0015
| ROUTE CLEARANCE & INTERROGATION SYSTEM (RCIS) TYPE I |
| PROGRAM PLAN |
| 23 June 2017 |
| Version 2 |
| Distribution Statement A – Approved for Public Release; distribution unlimited | |
| UNCLASSIFIED |
Revision History
| REVISION DATE | SPREADSHEET | |||
| REFERENCE | CONTRACT MONTH | REVISION - Reference Comments Added to Cells in Column A on Program Plan Tab | ||
| 6/23/17 | Line 1 | N/A | Removed Fiscal Years | |
| 6/23/17 | Line 8 | 1 - 2 | Added delivery of six (6) MPCV Control Vehicles to Contractor | |
| 6/23/17 | Line 8 | 1 - 2 | Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award. | |
| 6/23/17 | Line 10 | 6 | Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days. | |
| 6/23/17 | Line 22 | 46 - 47 | Added Government Technical Manual (TM) Verification to occur during LRIP Option Year 2. | |
| 6/23/17 | Line 23 | 36 | Corrected error with delivery of LRIP asset to White Sands Missile Range to occur 5 business days after TRR during LRIP Option Year 1. |
Program Plan
Novak, Brian CIV USA PEOCS&CSS:
| 1. Removed FISCAL YEARS in Line 1 | Engineering and Manufacturing Development (EMD) Contract | ||||||||||||||||||||||||||||||||||||||||||||||||
| Months | 3 | 2 | 1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | |||||
| Government Milestones | |||||||||||||||||||||||||||||||||||||||||||||||||
| Milestone B | MS B | ||||||||||||||||||||||||||||||||||||||||||||||||
| EMD Contract Award | EMD Award | ||||||||||||||||||||||||||||||||||||||||||||||||
| Start of Work Meeting / System Requirements Review (SOWM/SRR) | SOWM/SRR | ||||||||||||||||||||||||||||||||||||||||||||||||
| GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs |
Novak, Brian CIV USA PEOCS&CSS:
1. Changed Text to add delivery of six (6) MPCV Control Vehicles to Contractor.
From: GFE - Two (2) D-HMEE vehicles (includes RCIS Interrogation Attachments) To: GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs
2. (Reference Cell Q8) Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award.
From: 37 Calendar Days After Contract Award To: 30 Calendar Days After Contract Award
| GFE D-HMEEs and MPCVs delivered to Contractor | ||
| Preliminary Design Review (PDR) | PDR | |
| GFE - Four (4) D-HMEE vehicles (with Interrogation Attachments) |
Novak, Brian CIV USA PEOCS&CSS:
1. (Reference Cell AK10) Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days.
From: 187 Calendar Days After Contract Award
| To: 180 Calendar Days After Contract Award | GFE D-HMEEs delivered to Contractor | |||||||||||
| Critical Design Review (CDR) | CDR | Test Assets @ APG (3) | Test Assets @ WSMR (1) and Yuma (1) | |||||||||
| Deliver RCIS Type I EMD Test Assets APG, WSMR, and Yuma | ||||||||||||
| Test Readiness Review (TRR) | TRR | |||||||||||
| Pre-Production Qualification Test (PPQT) (15 months after CA, 12 months long) | PPQT | |||||||||||
| Operational Test Readiness Review | OTRR | |||||||||||
| Limited User Test (LUT) (24 months after CA, 3 months long) | LUT | |||||||||||
| System Verification Review(SVR)/Functional Configuration Audit (FCA) | SVR/FCA | |||||||||||
| Production Readiness Review (PRR) | PRR | |||||||||||
| Notification of Government's intent to exercise LRIP Option Year 1 | Notification to exercise LRIP 1 | |||||||||||
| Milestone C | MS C | |||||||||||
| LRIP Option Award (1st Year) | LRIP 1 Awd | |||||||||||
| Technical Manuals Option Award |
Novak, Brian CIV USA PEOCS&CSS:
1. (Reference Cells GM22 through GR22) Added Government Technical Manual (TM) Verification to occur during LRIP Option Year 2.
From: N/A
| To: 46 through 47 Months After Contract Award | TM Awd | LRIP Test Assets @ APG (5) | LRIP Test Asset @ WSMR (1) | TM Verification | |
| Deliver RCIS Type I LRIP Test Assets to APG, WSMR, and Yuma |
Novak, Brian CIV USA PEOCS&CSS:
1. (Reference Cell EZ23) Corrected error with delivery of LRIP asset to White Sands Missile Range to occur 5 business days after TRR during LRIP Option Year 1.
From: 36.5 Months After Contract Award To: 36.75 Months After Contract Award Novak, Brian CIV USA PEOCS&CSS:
1. Changed Text to add delivery of six (6) MPCV Control Vehicles to Contractor.
From: GFE - Two (2) D-HMEE vehicles (includes RCIS Interrogation Attachments) To: GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs
2. (Reference Cell Q8) Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award.
From: 37 Calendar Days After Contract Award To: 30 Calendar Days After Contract Award
Novak, Brian CIV USA PEOCS&CSS:
1. (Reference Cell AK10) Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days.
From: 187 Calendar Days After Contract Award
| To: 180 Calendar Days After Contract Award | LRIP Test Assets @ Yuma (2) | |||||||||||||||||||||||
| Test Readiness Review (TRR) | TRR | |||||||||||||||||||||||
| Production Qualification Testing (PQT) (4.75 months after LOA, 6 months long) | PQT | |||||||||||||||||||||||
| Notification of Govt intent to exercise LRIP Option Year 2 | Notification to exercise LRIP 2 | |||||||||||||||||||||||
| LRIP Option Award (2nd Year) | LRIP 2 Awd | |||||||||||||||||||||||
| Logisitics Demonstration (LOGDEMO) (12.75 months after LOA, 2 months long) | LOG DEMO | |||||||||||||||||||||||
| Operational Test Readiness Review | OTRR | |||||||||||||||||||||||
| Operational Test (OT) (16.75 months after LOA, 3.5 months long) | Adversarial Cybersecurity Development Test (ACDT) | OT | ||||||||||||||||||||||
| Government Cybersecurity Test Events | Pre SCA/CVI by ARL/SLAD (WSMR) | Security Control Assessment (SCA) | Cooperative Vulnerability Identification (CVI) | |||||||||||||||||||||
| Authorization To Operate (ATO) | SCA = Security Control Assessment | ATO | ||||||||||||||||||||||
| Physical Configuration Audit (PCA) | CVI = Cooperative Vulnerability Identification | PCA | ||||||||||||||||||||||
| Full Material Release / Type Classification (FMR/TC) | FMR/TC | |||||||||||||||||||||||
| Notification of Govt intent to exercise FRP/TPF/STS/ICS/TDP Options Year 1 | Notification to exercise Options | |||||||||||||||||||||||
| Full-Rate Production Decision Review (FRPDR) | FRPDR | |||||||||||||||||||||||
| FRP Option Award (1st Year) | FRP 1 Awd | |||||||||||||||||||||||
| TPF Option Award (1st Year) | TPF 1 Awd | |||||||||||||||||||||||
| STS Option Award (1st Year) | STS 1 Awd | |||||||||||||||||||||||
| ICS Option Award (1st Year) | ICS 1 Awd | |||||||||||||||||||||||
| TDP Option Award | TDP Awd | |||||||||||||||||||||||
| First Unit Equipped (FUE) | FUE | |||||||||||||||||||||||
| Initial Operational Capability (IOC) | IOC | |||||||||||||||||||||||
| FRP Option Award (2nd Year) | FRP 2 Awd | |||||||||||||||||||||||
| TPF Option Award (2nd Year) | TPF 2 Awd | |||||||||||||||||||||||
| STS Option Award (2nd Year) | STS 2 Awd | |||||||||||||||||||||||
| ICS Option Award (2nd Year) | ICS 2 Awd | |||||||||||||||||||||||
| Production Re-Compete Award | Re-Compete Award |
| Key | Meeting/Event | Activity |
| Government | ||
| Contractor |