Attachment 0015 RCIS PROGRAM PLAN

View the file

Other files

File Type Posted
W56HZV15R0156_Conformed_Copy_thru_Amend_0006.pdf PDF
W56HZV15R0156-0006.pdf PDF
W56HZV15R0156_Conformed_Copy.pdf PDF
W56HZV15R0156-0005.pdf PDF
Attachment_0061_-_Identification_and_Assertion_of_Restrictions.xlsx XLSX spreadsheet
Attachment_0033_-_RCIS_Technical_Data_and_Software_Rights_Evaluation_Spreadsheet.xlsx XLSX spreadsheet
Exhibit_A_-_Contract_Data_Requirements_List_12_Jul_2017.pdf PDF
Attachment_0050_-_Attribute_Selection_Worksheet_-_7_JUL_2017_-_v2.xlsx XLSX spreadsheet
Attachment_0033_-_RCIS_Technical_Data_and_Computer_Software_Rights_Evaluation_Spreadsheet_ver2.xlsx XLSX spreadsheet
W56HZV15R0156-0004.pdf PDF
Attachment_0055_-_Pricing_Attachment_-_12_JUL_17_-_v2.xlsx XLSX spreadsheet
Exhibit_A_-_Contract_Data_Requirements_List_29_Jun_2017.doc DOC document
W56HZV15R0156-0003.pdf PDF
Attachment_0008_-_Government_Furnished_Property_(GFP)_List_6-23-17_v2.pdf PDF
Exhibit_A_-_Contract_Data_Requirements_List__15_Jun_2017.pdf PDF
W56HZV15R0156-_Amendment_0002.pdf PDF
Attachment_0035_-_Past_Performance_Relevancy_Matrix_15_Jun_2017.xls XLS spreadsheet
RCIS_RFP_Q&A_Tracker_(1-10).pdf PDF
Facility_Clearance_(FCL)__Notice.docx DOCX document
FCL_Orientation_Handbook_18FEB15.pdf PDF
W56HZV15R0156_Conformed_Copy.pdf PDF
W56HZV15R0156-0001.pdf PDF
FCL_Sponsorship_Letter_OCT15.pdf PDF
Distribution_A.zip ZIP file
W56HZV-15-R-0156_5-16-17.pdf PDF
Exhibit_A_-_Contract_Data_Requirements_List.doc DOC document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cover

UNCLASSIFIED

Attachment 0015

ROUTE CLEARANCE & INTERROGATION SYSTEM (RCIS) TYPE I
PROGRAM PLAN
23 June 2017
Version 2
Distribution Statement A – Approved for Public Release; distribution unlimited
UNCLASSIFIED

Revision History

REVISION DATESPREADSHEET
REFERENCECONTRACT MONTHREVISION - Reference Comments Added to Cells in Column A on Program Plan Tab
6/23/17Line 1N/ARemoved Fiscal Years
6/23/17Line 81 - 2Added delivery of six (6) MPCV Control Vehicles to Contractor
6/23/17Line 81 - 2Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award.
6/23/17Line 106Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days.
6/23/17Line 2246 - 47Added Government Technical Manual (TM) Verification to occur during LRIP Option Year 2.
6/23/17Line 2336Corrected error with delivery of LRIP asset to White Sands Missile Range to occur 5 business days after TRR during LRIP Option Year 1.

Program Plan

Novak, Brian CIV USA PEOCS&CSS:

1. Removed FISCAL YEARS in Line 1Engineering and Manufacturing Development (EMD) Contract
Months3211234567891011121314151617181920212223242526272829303132333435363738394041
Government Milestones
Milestone BMS B
EMD Contract AwardEMD Award
Start of Work Meeting / System Requirements Review (SOWM/SRR)SOWM/SRR
GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs

Novak, Brian CIV USA PEOCS&CSS:

1. Changed Text to add delivery of six (6) MPCV Control Vehicles to Contractor.

From: GFE - Two (2) D-HMEE vehicles (includes RCIS Interrogation Attachments) To: GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs

2. (Reference Cell Q8) Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award.

From: 37 Calendar Days After Contract Award To: 30 Calendar Days After Contract Award

GFE D-HMEEs and MPCVs delivered to Contractor
Preliminary Design Review (PDR)PDR
GFE - Four (4) D-HMEE vehicles (with Interrogation Attachments)

Novak, Brian CIV USA PEOCS&CSS:

1. (Reference Cell AK10) Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days.

From: 187 Calendar Days After Contract Award

To: 180 Calendar Days After Contract AwardGFE D-HMEEs delivered to Contractor
Critical Design Review (CDR)CDRTest Assets @ APG (3)Test Assets @ WSMR (1) and Yuma (1)
Deliver RCIS Type I EMD Test Assets APG, WSMR, and Yuma
Test Readiness Review (TRR)TRR
Pre-Production Qualification Test (PPQT) (15 months after CA, 12 months long)PPQT
Operational Test Readiness ReviewOTRR
Limited User Test (LUT) (24 months after CA, 3 months long)LUT
System Verification Review(SVR)/Functional Configuration Audit (FCA)SVR/FCA
Production Readiness Review (PRR)PRR
Notification of Government's intent to exercise LRIP Option Year 1Notification to exercise LRIP 1
Milestone CMS C
LRIP Option Award (1st Year)LRIP 1 Awd
Technical Manuals Option Award

Novak, Brian CIV USA PEOCS&CSS:

1. (Reference Cells GM22 through GR22) Added Government Technical Manual (TM) Verification to occur during LRIP Option Year 2.

From: N/A

To: 46 through 47 Months After Contract AwardTM AwdLRIP Test Assets @ APG (5)LRIP Test Asset @ WSMR (1)TM Verification
Deliver RCIS Type I LRIP Test Assets to APG, WSMR, and Yuma

Novak, Brian CIV USA PEOCS&CSS:

1. (Reference Cell EZ23) Corrected error with delivery of LRIP asset to White Sands Missile Range to occur 5 business days after TRR during LRIP Option Year 1.

From: 36.5 Months After Contract Award To: 36.75 Months After Contract Award Novak, Brian CIV USA PEOCS&CSS:

1. Changed Text to add delivery of six (6) MPCV Control Vehicles to Contractor.

From: GFE - Two (2) D-HMEE vehicles (includes RCIS Interrogation Attachments) To: GFE - Two (2) D-HMEEs (with Interrogation Attachments) and six (6) MPCVs

2. (Reference Cell Q8) Moved delivery of two (2) D-HMEEs and six (6) MPCV Control Vehicles to Contractor to occur within 30 calendar days of contract award.

From: 37 Calendar Days After Contract Award To: 30 Calendar Days After Contract Award

Novak, Brian CIV USA PEOCS&CSS:

1. (Reference Cell AK10) Moved delivery of four (4) D-HMEEs to Contractor to occur within 180 calendar days of contract award instead of 187 calendar days.

From: 187 Calendar Days After Contract Award

To: 180 Calendar Days After Contract AwardLRIP Test Assets @ Yuma (2)
Test Readiness Review (TRR)TRR
Production Qualification Testing (PQT) (4.75 months after LOA, 6 months long)PQT
Notification of Govt intent to exercise LRIP Option Year 2Notification to exercise LRIP 2
LRIP Option Award (2nd Year)LRIP 2 Awd
Logisitics Demonstration (LOGDEMO) (12.75 months after LOA, 2 months long)LOG DEMO
Operational Test Readiness ReviewOTRR
Operational Test (OT) (16.75 months after LOA, 3.5 months long)Adversarial Cybersecurity Development Test (ACDT)OT
Government Cybersecurity Test EventsPre SCA/CVI by ARL/SLAD (WSMR)Security Control Assessment (SCA)Cooperative Vulnerability Identification (CVI)
Authorization To Operate (ATO)SCA = Security Control AssessmentATO
Physical Configuration Audit (PCA)CVI = Cooperative Vulnerability IdentificationPCA
Full Material Release / Type Classification (FMR/TC)FMR/TC
Notification of Govt intent to exercise FRP/TPF/STS/ICS/TDP Options Year 1Notification to exercise Options
Full-Rate Production Decision Review (FRPDR)FRPDR
FRP Option Award (1st Year)FRP 1 Awd
TPF Option Award (1st Year)TPF 1 Awd
STS Option Award (1st Year)STS 1 Awd
ICS Option Award (1st Year)ICS 1 Awd
TDP Option AwardTDP Awd
First Unit Equipped (FUE)FUE
Initial Operational Capability (IOC)IOC
FRP Option Award (2nd Year)FRP 2 Awd
TPF Option Award (2nd Year)TPF 2 Awd
STS Option Award (2nd Year)STS 2 Awd
ICS Option Award (2nd Year)ICS 2 Awd
Production Re-Compete AwardRe-Compete Award
KeyMeeting/EventActivity
Government
Contractor