Request for Information (RFI) document_01.pdf

PDF 117 KB Posted

Attached to
Camp Perry Logistics Complex Federal contract opportunity
Solicitation number
W50S8R-22-B-0001
Issued by
Department of the Army Ohio Army National Guard

About this file

This document contains a Request for Information (RFI) related to a solicitation for the Camp Perry Logistics Complex project. The RFI includes nine questions from potential offerors regarding environmental reports, materials retention, an ARMAG weapons vault, existing foundations, work hours, a geotechnical report, dampproofing specifications, laydown areas, and temporary fencing. The responses provide details on the attached environmental report, the Army National Guard's lack of interest in retaining materials on site, specifications regarding the empty ARMAG vault, the contractor's lack of responsibility for existing foundations, standard work hours, the attached geotechnical report, the need for dampproofing on foundation walls, and the location of staging areas and need for fencing as indicated on drawing C101.

The related federal contract opportunity is a solicitation notice issued by the 179th Airlift Wing Ohio Air National Guard Contracting Office for project number EUBC 009109, the new construction of the Camp Perry Logistics Complex. The project has a magnitude between $5-10 million and is set aside 100% for small businesses. The NAICS code is 236220 with a $39.5 million size standard. The bid opening is scheduled for October 31, 2022. The solicitation and plans are available on SAM.gov. The project site is located at Camp Perry, Ohio and questions should be directed to the listed contracting officer.

View the file

Other files for this federal contract opportunity

Other files attached to Camp Perry Logistics Complex, newest first.
File Type Posted
Abstract REV01_Complex.pdf PDF
Abstract_Complex.pdf PDF
Sign in sheet_Complex.pdf PDF
W50S8R-22-B-0001 0008.pdf PDF
Request for Information (RFI) document_06.pdf PDF
Request for Information (RFI) document_05.pdf PDF
W50S8R-22-B-0001 0007.pdf PDF
W50S8R-22-B-0001 0006.pdf PDF
Request for Information (RFI) document_04.pdf PDF
Request for Information (RFI) document_03.pdf PDF
W50S8R-22-B-0001 0005.pdf PDF
W50S8R-22-B-0001 0004.pdf PDF
Request for Information (RFI) document_02.pdf PDF
W50S8R-22-B-0001 0003.pdf PDF
RFI 01_Red Horse Site Plan.pdf PDF
RFI 01_Geotechnical Report.pdf PDF
RFI 01_Environmental Report.pdf PDF
W50S8R-22-B-0001 0002.pdf PDF
sign in sheet.pdf PDF
Pre-Bid Conference minutes_Complex.pdf PDF
Pre-Bid Conference-slides.pptx PPTX presentation
W50S8R-22-B-0001 0001.pdf PDF
Attachment 01-G_Drawings.pdf PDF
Exhibit A_Sealed Bid Checklist Reminders.pdf PDF
Attachment 01-I_Drawings.pdf PDF
Attachment 01-H_Drawings.pdf PDF
Attachment 01-D_Drawings.pdf PDF
Attachment 01-B_Drawings.pdf PDF
Attachment 03_Specifications Vol 02.pdf PDF
Attachment 02_Specifications Vol 01.pdf PDF
Attachment 01-F_Drawings.pdf PDF
Attachment 01-E_Drawings.pdf PDF
Attachment 01-C_Drawings.pdf PDF
Attachment 01-A_Drawings.pdf PDF
Exhibit B_Checklist for Bid Bonds.pdf PDF
W50S8R-22-B-0001.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUESTS FOR INFORMATION (RFI’s) AND RESPONSES – CAMP PERRY LOGISTICS COMPLEX

QUESTION 01:

Are there environmental reports for the buildings to be demolished? (Buildings in the base bid and building 4 alternate) Is there any known abatement? Can you provide those environmental reports?

RESPONSE:

Environmental Report is attached.

QUESTION 02:

The project goal is 100% recycled material as specified. Does Camp Perry Ohio Air National Guard base want to retain any materials on site? (asphalt, concrete, soil spoils, metals, any other materials) If so, what materials and how much? If so please provide a location information so we can appropriately allocate proper equipment and cycle cost.

RESPONSE:

Camp Perry Base does not want to retain any materials on site. See specification 015240 Construction Waste Management and 015719 Temporary Environmental Controls and 017320 Selective Demolition for Recycled Materials.

QUESTION 03:

During the walk through it was said that ARMAG weapons vault would be mobilized 2 times and wouldn't be used during the construction period. Can you provide confirmation that the ARMAG weapons vault will not be utilized and therefore not need utilities during the construction period? Can a staging area be identified to understand the cost associated with each pick? Can a weight of the vault be provided?

RESPONSE:

ARMAG shipping weight is 54,000 pounds. The ARMAG will be empty and will not be utilized by government for the period of performance of the contract. Contractor shall secure and store the ARMAG within Project Location.

QUESTION 04:

During the walk an existing foundation was noted where the storm retention area is to be located. Can you provide information regarding the foundation? (location, depth, construction type)

RESPONSE:

Contractor shall not be responsible for the noted foundations. Foundations will be removed, backfilled by Government.

QUESTION 05:

Can you confirm the work hours for this base?

RESPONSE:

Base hours are listed in specification 011000, paragraph 1.8. Hours are 7:00 a.m. to 3:30 p.m.

QUESTION 06:

Specification Section 31 23 19 - 1.6 Project Conditions - B. A geotechnical report has been prepared for this project. B- 2. Geotechnical report is included elsewhere in the project manual. Can you please provide the prepared geotechnical report?

RESPONSE:

Geotechnical report is attached.

QUESTION 07:

Specification section 07 11 13 Bituminous Dampproofing is called out. I didn't see any reference to the specification on the architectural nor structural drawings. What is the intent of the dampproofing specification?

RESPONSE:

Bituminous Dampproofing shall be applied to the exterior face of all foundation walls (footing included).

QUESTION 08:

I didn't see specific lay-down or staging areas. For planning purposes, can you identify the contractor lay-down and staging areas for this project? Will the staging area need temporary fence?

RESPONSE:

See Drawing sheet C101 for staging/lay-down area.

QUESTION 09:

Will the construction areas require temporary fencing?

RESPONSE:

See Drawing sheet C101 for fencing.

File details come from the government source that posted it. Updated .