This is a Request for Proposal (RFP) issued by District 49 (D49), located east of Colorado Springs, seeking a General Contractor to manage the construction of two pre-engineered metal buildings and site improvements at their central office complex at 10850 E. Woodmen Road. The metal buildings have already been purchased and are on-site, with the erection of Pre-Engineered Metal Buildings (PEMBs) by Bighorn Steel Buildings already purchased. The project is based on construction drawings provided by DLR Group Architects. The solicitation was published on 7/18/25, with a mandatory pre-bid meeting scheduled for 7/24/25, and proposals due by 8/1/25. The anticipated contract term is set to begin on 9/1/25, with a total duration not expected to exceed one year.
The evaluation methodology will use a comprehensive scoring approach, with 35% allocated to cost proposal, 25% to organizational experience and capacity, 20% to project approach and schedule, 15% to key personnel qualifications, and 5% to references and past performance. Offerors must demonstrate a minimum of three commercial or public sector renovation projects within the past five years, each valued at least $1 million, and provide proof of bonding capacity of $2 million. The contract will be awarded to the offeror providing the best value to the district, with the district reserving the right to award to multiple offerors, adjust scope if funding is insufficient, or reject all proposals.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Appendix C PEMB Covered Parking Quote.pdf | ||
| Barn Shop Drawings.pdf | ||
| D49_Site_Bid-Drawings_250711.pdf | ||
| Overhead Coiling Doors Specs.pdf | ||
| Sample Contract.pdf | ||
| 2025 Contract Format NEW.pdf | ||
| Appendix C PEMB Barn Quote.pdf | ||
| Covered Parking Shop Drawings.pdf | ||
| Drainage Report.pdf | ||
| Soils Report Kumar.pdf | ||
| D49_Barn_Bid-Drawings_250711.pdf | ||
| D49_CoveredParking_Bid-Drawings_250711.pdf | ||
| Final Q_A from Previous IFB.pdf | ||
| Q_A From 2ndIFB.pdf | ||
| Seeding _ Mulching City of Colorado Springs.pdf | ||
| D49 Bid Form 2025.docx | DOCX document | |
| GROUNDS EXPANSION BARN AND COVERED PARKING Project Manual-Bid Documents 20250711.pdf | ||
| RFP_Cover_Page _ Signature Sheet (2) (1).pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTENTS
SECTION 1.0 INTRODUCTION
1.1. GENERAL INFORMATION
1.2. BACKGROUND
1.3. OVERVIEW AND GOALS
1.4. ANTICIPATED CONTRACT TERM
SECTION 2.0 OFFEROR’S EXPERIENCE AND PERSONNEL
2.1. ORGANIZATIONAL EXPERIENCE
2.2. ORGANIZATIONAL PERSONNEL
SECTION 3.0 REQUIREMENTS AND SCOPE OF WORK
3.1. ACCESSIBILITY REQUIREMENTS
3.2. MANDATORY REQUIREMENTS
3.3. SCOPE OF WORK
SECTION 4.0 REQUESTED BID FORMAT
SECTION 5.0 EVALUATION METHODOLOGY
5.1. EVALUATION PROCESS
5.2. EVALUATION COMMITTEE
5.3. BID EVALUATION CRITERIA
5.4. DEMONSTRATIONS AND DISCUSSIONS
5.5. SINGLE BID
5.6. AWARD
SECTION 6.0 OTHER TERMS&CONDITIONS
6.1. OFFEROR INQUIRIES
6.2. CONFLICTS OF INTEREST/ETHICS/SUSPENSION AND DISBARMENT
6.3. PROTESTED SOLICITATIONS AND AWARDS
6.4. PERFORMANCE OUTSIDE OF COLORADO
6.5. MISTAKES AND MINOR INFORMALITIES IN OFFERORS PROPOSALS
6.6. MODIFICATIONS OR WITHDRAWAL OF PROPOSALS
6.7. SUBMISSION OF CONFIDENTIAL OR PROPRIETARY INFORMATION
6.8. PROPOSAL RESPONSE MATERIAL OWNERSHIP
6.9. CERTIFICATION OF INDEPENDENT PRICE DETERMINATION
6.10. OFFEROR ACCEPTANCE OF SOLICITATION TERMS
6.11. TIMELINES OF PROPOSAL SUBMISSION
6.12. MODIFICATIONS AND/OR SUPPLEMENTAL INFORMATION
APPENDICES
APPENDIX A – BID FORM
APPENDIX B – 2025 DRAFT CONTRACT
APPENDIX C- CONSTRUCTION DRAWINGS/SITE IMPROVEMENTS
SECTION 1.0 INTRODUCTION
1.1. GENERAL INFORMATION
District 49 is located east of Colorado Springs and serves twenty public schools, 3 administration buildings, and nine charter schools along the eastern boundaries of Colorado Springs and in Peyton.
1.2. OVERVIEW
D49 is looking for a General Contractor to manage the construction of two pre-engineered metal buildings and site improvements at their central office complex at 10850 E. Woodmen Road. The metal buildings have already been purchased and are on site. Additionally, the erection of the PEMBs by the metal building supplier (Bighorn Steel Buildings) has already been purchased by D49 but will need to be managed by the GC. Construction drawings are provided by DLR Group Architects.
1.3. ANTICIPATED CONTRACT TERM
1.3.1. The initial term of the awarded Contract is anticipated to begin on 9/1/25 and end on TBD. The total duration of the Contract, including all options, is not anticipated to exceed ONE year.
1.3.2. The District may extend the Contract beyond the anticipated term in accordance with the Colorado Procurement Code, and in the event that the District determines an extension is necessary.
1.4. SCHEDULE OF ACTIVITIES
This Schedule of Activities is for information and planning purposes only. Schedules for Activities listed as “Estimated” may be subject to change depending on the needs of the District. All times are considered in Mountain Time (MT), as adjusted for daylight savings.
1-Solicitation Published via Bidnetdirect.com - 7/18/25
2-Pre-Bid Meeting (MANDATORY) - 7/24/25 10am
3-Written Inquiries Deadline Send Inquiries to Bidnetdirect.com - 7/24/25 4pm
4-Response to written inquiries; will be posted to Bidnetdirect.com. - 7/28/25 4pm
5-Proposal Submission Deadline - 8/1/25 For this solicitation, proposals will be accepted using an online submission application (Bidnetdirect.com). Hard copy submissions will not be accepted. To use the online submission application, please register for free at Bidnetdirect.com. Please note the following:Offerors should submit one PDF file that contains all required proposal submission documents. The PDF file name should include the following title: RFP Number, RFP Title and also include the Offeror’s name.
6-Notice of Intent to Award Published on Bidnetdirect.com (Estimated) - 8/15/25 http://bidnetdirect.com
8-Contract Execution (Desired) - 9/1/25
SECTION 2.0 GENERAL CONTRACTOR MINIMUM QUALIFICATIONS
2.1. ORGANIZATIONAL EXPERIENCE AND CAPACITY
2.1.1.Contractor must have successfully completed a minimum of three (3) commercial or public sector renovation projects within the past five (5) years, each with a construction value of at least $1 million.
2.1.2. Proven track record of managing and completing projects similar in scope and scale. Provide 3 references with project address, project budget, POC phone and Email.
2.1.3. Proficiency in project management software and tools. Provide summary of tools Used
2.1.4. Capacity to provide performance and payment bonds in the amount of $2 million, and liability insurance per the requirements in this RFP. Provide a letter from a bonding agency and certificate of insurance from the insurance company.
2.1.5. Capacity to begin project in September of 2025
2.2. ORGANIZATIONAL PERSONNEL
2.2.1. Provide resumes of project manager and site superintendent that will be working on this project. The PM and Superintendent must have done similar work for a minimum of 5 years.
SECTION 3.0 REQUIREMENTS AND SCOPE OF WORK
3.1. ACCESSIBILITY REQUIREMENTS
3.1.1. All work performed as a result of this solicitation must comply with all applicable provisions of §§24-85-101, et seq., C.R.S., and the Accessibility Standards for Individuals with a Disability, as established by the Office Of Information Technology pursuant to Section §24-85-103 (2.5), C.R.S. and 3) all District technology standards related to technology accessibility and with Level AA of the most current version of the Web Content Accessibility Guidelines (WCAG), incorporated in the District of Colorado technology standards.
3.2. MANDATORY REQUIREMENTS
Proposals must meet all mandatory requirements to be considered responsive. This includes timely submission in the required format, proof of valid contractor licensing in Colorado and the local jurisdiction, and the ability to provide 100% performance and payment bonds. Offerors must submit a certificate of insurance meeting the minimum coverage levels, demonstrate experience with similar renovation projects, and include resumes for key personnel such as the Project Manager and Superintendent. All required forms must be completed and signed, including acknowledgment of any issued addenda. Failure to meet any of these requirements may result in disqualification.
3.3. SCOPE OF WORK
3.3.1. Work includes installing two metal buildings (Owner provided) and site improvements in accordance with DLR Group’s Construction Drawings (provided as Original Documents to this RFP).
3.3.2. Update D49 team at weekly OAC meeting.
3.3.3. Provide all closeout documents in digital format
3.3.4. Provide 6-month and 11-month walkthrough with D49 staff and complete punch lists prior to 12 month warranty expiration.
SECTION 4.0 DOCUMENTS TO INCLUDE WITH THE RESPONSE
4.1. COVER SHEET AND SIGNATURE PAGE
4.2. BID FORM. FILL OUT BID FORM
4.3. DEMONSTRATED ORGANIZATIONAL EXPERIENCE AND CAPACITY
4.3.1.Offeror’s Response- Describe how the Offeror’s experience and capabilities make it the ideal candidate to perform the work. Describe experience with similar projects. Reference Section 2.1 of this solicitation regarding the desired organizational experience.
4.3.2.Offeror’s Response- Indicate key personnel who will be assigned to the project and describe their experience. Reference Section 2.2 of this solicitation regarding the desired organizational personnel.
4.3.3.Offeror’s Response- Please include schedule from Notice to Proceed (Purchase Order) through Certificate of Occupancy. If the schedule does not allow for a September 2025 start date, please note that in your response.
4.4. BID BOND IF BID IS OVER $50,000
4.5. EXCEPTIONS TO SAMPLE CONTRACT. Bullet list is acceptable
4.6. LETTER FROM BONDING AGENCY CONFIRMING BONDING CAPACITY FOR
PERFORMANCE AND PAYMENT BONDS.
SECTION 5.0 EVALUATION METHODOLOGY
5.1. EVALUATION PROCESS
Proposals will be evaluated using a comprehensive and qualitative scoring method designed to determine the proposal that offers the best value to the District.
Cost Proposal – 35% Total proposed price, clarity of cost breakdown, and overall value. Lower cost proposals will be scored more favorably, assuming they meet all other requirements.
Organizational Experience and Capacity – 25% Relevant experience with public sector renovations of similar size and complexity, especially in occupied facilities.
Project Approach and Schedule – 20% Realistic timeline, phasing, and strategies for minimizing disruption during construction.
Key Personnel Qualifications – 15% Credentials and experience of assigned Project Manager and Superintendent.
References and Past Performance – 5% Verification of past performance on similar projects.
The evaluation process shall be conducted in accordance with C.R.S. §24-103-203 and §24-103-301, and will consider both technical merit and cost, as outlined in this Request for Proposal (RFP). The Agency reserves the right to award a contract based solely on the written proposals received, without engaging in further discussions or interviews. However, at its sole discretion, the Agency may choose to:
- Request additional information or clarifications from proposers,
- Invite selected proposers to participate in interviews, presentations, or product demonstrations, and/or
- Engage in negotiations with one or more proposers to clarify or improve the proposal.
The Agency also reserves the right to:
- Reject any or all proposals,
- Waive informalities or minor irregularities,
- Cancel or reissue this RFP at any time without obligation,
- Select the proposal that, in the Agency’s judgment, is most advantageous and in the best interest of the Agency, based on the evaluation criteria stated in this RFP.
5.2. EVALUATION COMMITTEE
5.2.1. An evaluation committee composed of District staff and subject matter experts will independently review and score each proposal.
5.2.1.1. Selecting committee members who do not have a conflict of interest regarding this solicitation.
5.2.1.2. Facilitating the independent review of bids.
5.2.1.3. Requiring the evaluation of the bids to be based strictly on the content of the bids.
5.2.1.4. Ensuring the fair and impartial treatment of all Offerors.
5.2.2. The objective of the Evaluation Committee is to conduct reviews of the bids that have been submitted, to hold frank and detailed discussions among themselves, and to recommend an Offeror for award.
5.3. RFP EVALUATION CRITERIA
5.3.1. The District will evaluate bids to determine if each Offeror meets all minimum qualification requirements; provided, however, that the District has the authority to waive non-material requirements in certain circumstances. Reference Procurement Rule R-24-103-301-03. The minimum qualification requirements are scored on a Met/Not Met basis and only those bids found to meet all minimum requirements, other than non-material requirements waived by the District, can be considered for a Contract resulting from this solicitation.
5.3.2. Bids will be evaluated by the Evaluation Committee using the evaluation criteria listed below. The evaluators will consider whether the Scope of Work requirements in the solicitation have been addressed, and they will review the capabilities of the Offeror, as well as the quality of the approach proposed, the price, and any other aspect determined relevant to the evaluation criteria.
5.3.3 Each criterion will be scored on a defined scale (e.g., 0–100), and weighted according to its importance. Scores will be totaled to arrive at a composite score for each Offeror. Proposals will then be ranked from highest to lowest total score.
5.5. SINGLE BID
If only one proposal is received, the District may evaluate it for responsiveness, responsibility, and fair pricing. The District reserves the right to proceed with award, negotiate terms, re-solicit, or cancel the RFP in accordance with C.R.S. §24-103-301.
5.6. AWARD
5.6.1. A Notice of Intent to Award will be published on Bidnetdirect.com.
5.6.2. The award determination is ultimately a business decision that will reflect an integrated assessment of the relative merits of the bids received, using the factors set forth in Section 5.3.3. The contract will be awarded to the Offeror whose proposal is determined to be the most advantageous to the District, based on the evaluation criteria stated in this RFP. Award is subject to successful contract negotiation and approval.
5.6.3. An Award does not guarantee the amount of the contract. If the District does not have sufficient funds to complete the contract at the Offeror’s price, scope will be removed/adjusted to a final price agreed to by both parties.
5.6.4. The District reserves the right to award to multiple offerors if it is determined to be in the best interest of the District.
SECTION 6.0 OTHER TERMS AND CONDITIONS
6.1. OFFEROR INQUIRIES
6.1.1. Offerors may submit written inquiries via bidnetdirect.com concerning this solicitation to obtain clarifications. The District may not accept inquiries after the date and time indicated in the Schedule of Activities. Where appropriate, inquiries should include references to any relevant Section/paragraph of the solicitation.
6.1.2. Responses to Offeror’s inquiries will be published collectively, as a modification on Bidnetdirect.com. Offerors shall not rely on any verbal statements that alter any specification or other term or condition of the solicitation. Such changes are valid only if provided in writing by the Procurement Contact.
6.2 CONFLICTS OF INTEREST/ETHICS/SUSPENSION AND DEBARMENT
6.2.1. The Offeror must disclose in its proposal any potential or actual conflict of interest in connection with a response to this solicitation. A conflict of interest may include, but is not limited to, access to any non-public information by the Offeror regarding the solicitation or its subject matter.
6.2.2. The Offeror acknowledges that even the appearance of a conflict of interest may be harmful to the District’s interests. The Offeror shall disclose in its proposal whether there currently is, or potentially could be, the appearance of a conflict of interest regarding this solicitation, its staff, any proposed subcontractors or partners, or any related business with the District.
6.2.3. The Offeror acknowledges that they are not suspended or debarred from bidding on state or federal contracts in accordance with the list of excluded individuals and firms on the SAM.gov website:
(https://sam.gov/data-services/Exclusions/Public%20V2?privacy=Public)
6.2.4. Requirements set forth in this Section are continuing requirements throughout the solicitation process and, for the awarded Offeror, the Contract term, including any extensions. Reference §24-18-201, C.R.S., et seq. (Proscribed Acts Related to Contracts and Claims); §24-50-507, C.R.S.(Conflict of Interest); §18- 8-301, C.R.S., et seq. (Bribery and Corrupt Influence); §18-8-401, C.R.S., et seq. (Abuse of Public Office);
§6-4-101, C.R.S., et seq., (Colorado Antitrust Act of 1992); §24-109-105, C.R.S (Debarment and Suspension); and Procurement Rule R-24-101-107-01 (Ethics).
6.3. PROTESTED SOLICITATIONS AND AWARDS
An aggrieved party may file a protest concerning a material issue(s), at any phase of solicitation, including but not limited to, specifications, award or a disclosure of information marked confidential in the proposal. The protest shall be submitted to the District 49 Procurement Official within ten (10) business days after such aggrieved person knows, or should have known, of the facts giving rise thereto.
Reference §24-109-102, C.R.S., as amended, and Procurement Rule R-24-109-102-01, et seq. Protests should be submitted in writing to the following: dana.reichers@d49.org
6.4. PERFORMANCE OUTSIDE OF COLORADO
Awarded Offeror, per Section 24-102-206, C.R.S., prior to contracting shall disclose in a written statement whether it anticipates performing or subcontracting any services under the contract, where such subcontracted services will be performed under the contract, including any subcontracts, and whether any subcontracted services under the contract or any subcontracts are anticipated to be performed outside the United States or the state. If the prospective vendor anticipates services under the contract or any subcontracts will be performed outside the United States or the state, the vendor shall provide in its written statement a provision setting forth why it is necessary or advantageous to go outside the United States or the state to perform the contract or any subcontracts.
https://sam.gov/data-services/Exclusions/Public%20V2?privacy=Public mailto:dana.reichers@d49.org
6.5. MISTAKES AND MINOR INFORMALITIES IN OFFEROR PROPOSALS
In certain circumstances, an Offeror may correct a mistake(s) in its proposal and/or the District may waive minor informalities. Reference Procurement Rule R-24-103-201-08.
6.6. MODIFICATIONS OR WITHDRAWAL OF PROPOSALS
An Offeror may modify or withdraw its proposal by written notice to the Procurement Contact prior to the established proposal submission deadline. Withdrawal of an Offeror’s proposal following the proposal submission deadline and prior to award, may be allowed, at the District’s discretion. Withdrawal of an Offeror’s proposal after award is not allowed. Reference Procurement Rules R-24-103-201-08 and R-24-103-201-09.
6.7. SUBMISSION OF CONFIDENTIAL OR PROPRIETARY INFORMATION
6.7.1. District 49 is subject to the requirements of §24-72-200.1, C.R.S., et seq., Colorado Open Records Act.
6.7.2. An Offeror may submit, as a part of its proposal, a written request for classification of certain portions of the proposal as a trade secret or other confidential or proprietary information. Material for which the Offeror is requesting confidentiality shall be readily identifiable and separated from other portions of the proposal to facilitate public inspection of the non-confidential portion of the proposal.
Commingling of confidential and non-confidential information is not acceptable. Neither price information nor any information that will be included in a resulting Contract will be considered confidential.
6.7.3. The Offeror must include the rationale for any request to classify portions as a trade secret or confidential or proprietary, including references to the authority that allows for such treatment.
6.7.4. In no event shall an entire proposal be classified as confidential. The Procurement Official or his or her designee shall determine if the information identified in the Offeror’s request is exempt from disclosure in accordance with §24-72-204, C.R.S., and shall inform the Offeror in writing of his or her determination.
If the Offeror does not agree with the determination, the Offeror may protest the determination in accordance with article 109 of the Colorado Procurement Code and the terms of this solicitation. Reference Procurement Rule R-24-101-401-03.
6.7.5. Any additional Offeror information, which may be part of the evaluation/negotiation process and for which an Offeror claims confidentiality, is subject to the same requirements and processes identified above.
6.8. PROPOSAL RESPONSE MATERIAL OWNERSHIP
All material submitted in response to this solicitation becomes the property of the District.
6.9. CERTIFICATION OF INDEPENDENT PRICE DETERMINATION
By its signature on the cover page, the Offeror certifies that the prices and other terms in the proposal have been arrived at independently without any consultation, communication, agreement with, or knowledge of the contents of the proposal by any other competing Offerors. For purposes of this paragraph, "consultation, communication, agreement with, or knowledge" does not include knowledge of prices or terms gained through availability of established price lists or catalogues made available to the public by the competing Offerors. No attempt has been made or will be made by the Offeror to induce any other person or firm to submit or not to submit a proposal for restricting competition. Reference §6-4-101, C.R.S., et seq., (Colorado Antitrust Act of 1992) as amended.
6.10. OFFEROR ACCEPTANCE OF SOLICITATION TERMS/OFFEROR PROPOSAL CONTENT
6.10.1.An Offeror’s proposal submitted in response to this solicitation shall constitute a binding offer. The signature of the Offeror shall indicate acknowledgment of this condition. Signature shall be that of a person legally
6.10.2. authorized to execute contractual obligations. The proposal, including pricing, shall allow for a minimum of 90 calendar days for acceptance by the District, unless otherwise specified in this solicitation.
The contents of the proposal of the awarded Offeror will become contractual obligations under the awarded Contract.
6.10.3. Once an offeror is awarded a contract under Colorado procurement law, they are legally obligated to fulfill the terms of their offer unless there are exceptional circumstances. Declining the work after the award can have significant consequences, including:
6.10.3.1. Forfeiture of Bid Security: If the solicitation required bid security (e.g., a bid bond), declining the work after the award will result in forfeiture of that security.
6.10.3.2. Breach of Contract: An awarded contract is a legally binding agreement. Refusing to perform can be considered a breach, potentially exposing the offeror to legal liability for damages.
6.10.3.3. Disqualification from Future Bidding: Many procurement laws and regulations, including those in Colorado, allow for an offeror to be disqualified or debarred from future opportunities if they fail to honor an awarded contract.
6.11. TIMELINESS OF PROPOSAL SUBMISSION
6.11.1. Proposals received after the submission deadline shall not be opened and shall be rejected as a late proposal, unless otherwise permitted by the Procurement Official in accordance with Procurement Rule R-24-103-201-10.
6.11.2. Responsibility for ensuring that an Offeror’s proposal is received on time rests with the Offeror.
Reasonably foreseeable problems inherent in the delivery of proposals are not extraordinary circumstances permitting acceptance of late Proposals.
6.12. MODIFICATIONS AND/OR SUPPLEMENTAL INFORMATION TO THE SOLICITATION
6.12.1. Any modifications, amendments or supplemental information to the solicitation will be published on Bidnetdirect.com.
6.12.2. It is the Offeror’s sole responsibility to check Bidnetdirect.com on a regular basis, prior to the proposal submission deadline, as this is the primary means for communicating any clarifications or changes to solicitation content, timeline and/or requirements.