This document is a Questions and Answers (Q&A) addendum for the Central Office Additions project by El Paso County School District 49 in Colorado. The addendum covers the bidding process for a general contractor to manage the construction of two pre-engineered metal buildings (PEMBs) at the district's central office complex. The question acceptance deadline is 10/04/2024 at 5:00 PM MDT, with a closing date of 10/18/2024 at 2:00 PM MDT. The project involves constructing two buildings where the metal buildings have already been purchased and are on-site, with the metal building erection also pre-purchased by the district.
Key details from the Q&A include clarifications on various project aspects: pricing requirements (lump sum bid excluding metal buildings), insulation (R19 single layer acceptable for unconditioned space), overhead doors (Cookson Thermiser ESD20 model), and specific responsibilities for different project elements. Notable provisions include that the general contractor will supply insulation and anchor bolts, the metal building contractor will handle framed openings, man doors, and weather barriers, and there will be no liquidated damages for this project. The district has noted that asphalt paving is not part of the initial project and is still under county review, which will be addressed in a later phase.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Appendix C PEMB Covered Parking Quote.pdf | ||
| Barn Shop Drawings.pdf | ||
| D49_Site_Bid-Drawings_250711.pdf | ||
| Overhead Coiling Doors Specs.pdf | ||
| Sample Contract.pdf | ||
| D49_Barn_Bid-Drawings_250711.pdf | ||
| D49_CoveredParking_Bid-Drawings_250711.pdf | ||
| Q_A From 2ndIFB.pdf | ||
| Seeding _ Mulching City of Colorado Springs.pdf | ||
| 2025 Contract Format NEW.pdf | ||
| Appendix C PEMB Barn Quote.pdf | ||
| Covered Parking Shop Drawings.pdf | ||
| Drainage Report.pdf | ||
| RFP_2025_CO_0717.pdf | ||
| Soils Report Kumar.pdf | ||
| D49 Bid Form 2025.docx | DOCX document | |
| GROUNDS EXPANSION BARN AND COVERED PARKING Project Manual-Bid Documents 20250711.pdf | ||
| RFP_Cover_Page _ Signature Sheet (2) (1).pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers
Buyer Organization El Paso County School District 49
Question Acceptance Deadline 10/04/2024 05:00 PM MDT
Closing Date 10/18/2024 02:00 PM MDT
No Vendor Name Question/Answer Question Date
Answer Date
Q1 Bryan Construction Question: Pricing Requirements (by Doug Woody)
The included pricing sheet does not indicate we need to provide a complete number for construction of the two buildings. Are we only to provide numbers for fees and general conditions? Please confirm the required pricing necessary for the submittal.
Public Answer: (by Jim Rohr )
Please do not use the excel fee form. Use the Bid Form in the addendum and provide a lump sum bid for all labor and materials minus PEMBs and erection. You will not be including the cost for the metal buildings or their erection labor as this scope is carried by the Owner.
09/12/2024 02:00 PM
MDT
Draft
Q2 CTL|Thompson, Inc Question: Geotechnical Investigation (by Patrick Foley)
Has a Geotechnical Investigation been prepared for this project? Have you solicited Construction Observation and Materials Testing?
Public Answer: (by Jim Rohr )
Geotech report has been included as an addendum. Materials testing will be carried by the Owner.
09/20/2024 10:50 AM
MDT
Draft
Q3 Buildings By Design, LLC Question: Snow Retention (by Brad Wolf)
Bid Documents show snow retention. This is typically provided and installed by the metal building contractor, but is shown as excluded in the
Bighorn Quotes. Please clarify what is required
Public Answer: (by Jim Rohr )
Owner will add this to the PEMB scope of work so do not include pricing for this.
10/04/2024 09:27 AM
MDT
Draft
Q4 Buildings By Design, LLC Question: Liner Insulation (by Brad Wolf)
Bid Documents show liner insulation system at the roof and wall sections, with the table on the right side of page A1.3 showing this as well. If this building is required to comply with IECC 2021, a full depth liner insulation system; R30 in the roof and R32.5 full depth, or R41 tw-layer wall insulation is typically required. The Bighorn Steel Buildings Barn quote indicates a single layer R19 is to be provided at both roof and walls. Is this adequate to meet code?
Public Answer: (by Jim Rohr )
Per IECC C402.1.1 buildings that do not contain conditioned space are exempt from the building thermal envelope provisions of Section C402.
There are no mechanical heating and cooling systems in either building therefore it is unconditioned space.
10/04/2024 09:27 AM
MDT
Draft
2024-CO-0910 - Central Office Additions Addendum No: 4 (Published)
10/11/2024 10:56 AM MDT Page 1 of 4
No Vendor Name Question/Answer Question Date
Answer Date
Q5 Buildings By Design, LLC Question: Mechanical Openings (by Brad Wolf)
The Bighorn Steel Buildings Barn quote does not note openings for the
Exhaust Fan or Louver framed openings with trim are included. These will be required for the mechanical equipment shown in the bid documents.
Please confirm these will be provided by the metal building contractor.
Public Answer: (by Jim Rohr )
All framed openings will be prepped and trimmed by metal building contractor.
10/04/2024 09:28 AM
MDT
Draft
Q6 Buildings By Design, LLC Question: Steel Building (by Brad Wolf)
Please confirm the 2 psf collateral load noted in the Bighorn Steel Buildings
Barn Quote will be adequate to support the mechanical equipment, lighting and other equipment suspended from the metal building.
Public Answer: (by Jim Rohr )
According to Daniel Corsentino at Bighorn, the 2psf collateral load noted in the Steel Building Barn Quote should be adequate for lighting, HVAC and miscellaneous items
10/04/2024 09:28 AM
MDT
Draft
Q7 Ed Green Construction Co Question: PEMB R/O Prepped (by Rebekah Combs)
1.Has the owner supplied PEMB been R/O prepped for the environmental fans and louvers, or does the GC need to include PEMB framing and trim for install?
Public Answer: (by Jim Rohr )
All framed openings will be prepped and trimmed by metal building contractor.
10/04/2024 12:20 PM
MDT
Draft
Q8 Ed Green Construction Co Question: Walk doors (by Rebekah Combs)
Is the GC to supply and install walk doors? If so, did the PEMB supplier include R/O framing and trim?
Public Answer: (by Jim Rohr )
All framed openings will be prepped and trimmed by metal building contractor. GC to provide and install doors.
10/04/2024 12:21 PM
MDT
Draft
Q9 Ed Green Construction Co Question: Communications and Security Scope (by Rebekah Combs)
Is the GC to supply communications and security scope? If so, does the
District have a requested or preferred vendor?
Public Answer: (by Jim Rohr )
Yes, GC is to provide communications and security scope. We use Arden
Electric and Security extensively but it is not required.
Dustin Petrose
719-304-6507
Dustin@ardenelectricandsecurity.com
10/04/2024 12:22 PM
MDT
Draft
Q10 Ed Green Construction Co Question: Liquidated Damages (by Rebekah Combs)
Will liquidated damages be part of this contract?
Public Answer: (by Jim Rohr )
No. There will be no liquidated damages
10/04/2024 12:23 PM
MDT
Draft
10/11/2024 10:56 AM MDT Page 2 of 4
Q11 Ed Green Construction Co Question: Insulation (by Rebekah Combs)
Is insulation needed and who supplies?
Public Answer: (by Jim Rohr )
Yes, GC will supply the insulation
10/04/2024 12:24 PM
MDT
Draft
Q12 Ed Green Construction Co Question: Builder's Risk (by Rebekah Combs)
Due to the District carry of the building purchase and install, it may not be possible for the GC to provide the Builders Risk Policy. The vertical portion of this project carries the largest exposure and it’s not being provided by the
GC. This is creating major push back from our insurance providers. Would it be possible for the district to carry said Builders Risk coverage?
Public Answer: (by Jim Rohr )
The Owner would rather not carry the Builder's Risk Insurance but if your insurance company will not allow it, please make this exception on your bid.
If the GC cannot provide it, either the Owner or metal building contractor will provide it--just make sure you list this exception on your bid.
10/04/2024 12:25 PM
MDT
Draft
Q13 Wells & West General
Contractors, Inc.
Question: Barn - Overhead Doors (by Tessa Storey)
All plan documents show overhead coiling doors but spec book only includes information on sectional doors. Please clarify what type/brand/model of overhead door is desired.
Public Answer: (by Jim Rohr )
For the overhead doors: Provide overhead coiling door; MFR: Cookson, Model: Thermiser ESD20 with motor operator as recommended by the
MFR. See the attached spec
10/04/2024 12:35 PM
MDT
Draft
Q14 Wells & West General
Contractors, Inc.
Question: Liquidated Damages (by Tessa Storey)
Please clarify the terms of liquidated damages and how they will apply as the end date is TBD.
Public Answer: (by Jim Rohr )
As this project does not involve students and is under no known time constraints, Liquidated Damages will not apply to this project.
10/04/2024 01:00 PM
MDT
Draft
Q15 El Paso County School
District 49 Question: Bond Questions (by Jim Rohr)
Would metal building material and installation labor need to be included in bond cost?
Public Answer: (by Jim Rohr )
This does not need to be included in your bond cost as the Owner has this contract.
10/11/2024 10:06 AM
MDT
Draft
Q16 El Paso County School
District 49 Question: Weather Barrier (by Jim Rohr)
Who is providing the weather barrier per the drawings?
Public Answer: (by Jim Rohr )
The metal building contractor will provide the weather barrier if needed.
10/11/2024 10:11 AM
MDT
Draft
10/11/2024 10:56 AM MDT Page 3 of 4
Q17 El Paso County School
District 49 Question: Door Lites (by Jim Rohr)
Who will be providing door lites?
Public Answer: (by Jim Rohr )
Metal building contractor will be providing solid metal doors without lites as we do not want lites in the doors.
10/11/2024 10:49 AM
MDT
Draft
Q18 El Paso County School
District 49 Question: Anchor Bolts (by Jim Rohr)
Who needs to carry the anchor bolts?
Public Answer: (by Jim Rohr )
GC needs to carry anchor bolts for foundation.
10/11/2024 10:50 AM
MDT
Draft
Q19 El Paso County School
District 49 Question: Metal Building Man Doors (by Jim Rohr)
Who is carrying the man doors?
Public Answer: (by Jim Rohr )
Metal building contractor is carrying man doors.
10/11/2024 10:52 AM
MDT
Draft
Q20 El Paso County School
District 49 Question: Asphalt Paving (by Jim Rohr)
Where is the asphalt going? It looks like it’s the perimeter of the buildings, but doesn’t show up in the Civils.
Public Answer: (by Jim Rohr )
There will not be any asphalt as part of the initial project. We have the civil engineer working on a paving plan but it won't be added until later after we get through county review. We didn't want to delay the building installations waiting on the county approval process as it will take months.
10/11/2024 10:54 AM
MDT
Draft
10/11/2024 10:56 AM MDT Page 4 of 4