Q&A 3.pdf

PDF 288 KB Posted

Attached to
Central Florida Rail Corridor (CFRC) Track Improvements - Multiple Locations
Solicitation number
RFP-10060
Issued by
Volusia County, Florida

About this file

The document is a Question and Answer document (#3) related to a Request for Proposal (RFP) issued by the Florida Department of Transportation (FDOT) for Central Florida Rail Corridor (CFRC) Track Improvements at multiple locations. The RFP includes four separate projects: Project 1 - Universal Crossovers, Project 2 - Rail Renewal, Project 3 - Switches, and Project 4 - MOW Siding. The RFP has an advertisement number of DOT-RFP-25-5002-TIML and a due date of October 2, 2024 at 10:00am. A mandatory pre-proposal meeting was held on September 4, 2024. The document provides clarifications on the scope of work, materials, and other details for the various projects included in the RFP.

The RFP is subject to MFMP transaction fees and compliance with Title VI of the Civil Rights Act of 1964 and related nondiscrimination statutes. The contract will be awarded to the responsive and responsible bidder that provides the best value to the state. Funding for the projects will come from state and federal sources, but specific amounts are not provided.

View the file

Other files

File Type Posted
Exhibit A - Scope of Services.pdf PDF
Exhibit C - FTA Provisions.pdf PDF
Exhibit F - Fence Policy.pdf PDF
Exhibit J - GCOR.pdf PDF
Addendum 2.pdf PDF
DOT-RFP-25-5002-TIML RFP.pdf PDF
Exhibit I - CWR.pdf PDF
Exhibit J - GCOR.pdf PDF
Exhibit M - CFRC Track Chart APRIL 2023.pdf PDF
Exhibit O - CFRC MWIs.pdf PDF
Addendum 1.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Addendum 1.pdf PDF
Agreement between Dept and Contractor.pdf PDF
Exhibit H - CFRC GENERAL ORDER NO. 6 TTSI 2.pdf PDF
Exhibit M - CFRC Track Chart APRIL 2023.pdf PDF
Q&A 2 Complete.pdf PDF
Q&A 3.pdf PDF
Addendum 5 Complete - Part 2.pdf PDF
Exhibit C - FTA Provisions.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit I - CWR.pdf PDF
Exhibit J - GCOR.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Q&A 1.pdf PDF
Q&A 4 TIML Final.pdf PDF
Addendum 5 Complete - Part 1.pdf PDF
Addendum 6.pdf PDF
DOT-RFP-25-5002-TIML RFP.pdf PDF
Exhibit D.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit F - Fence Policy.pdf PDF
DOT-RFP-25-5002-TIML RFP.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit I - CWR.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Exhibit L - CFRC TRACK AND SIGNAL CHART.pdf PDF
Exhibit O - CFRC MWIs.pdf PDF
Addendum 1.pdf PDF
Exhibit A - Scope of Services.pdf PDF
Exhibit C - FTA Provisions.pdf PDF
Exhibit D.pdf PDF
Exhibit F - Fence Policy.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Q&A 1.pdf PDF
Addendum 2.pdf PDF
Addendum 3.pdf PDF
Exhibit A - Scope of Services.pdf PDF
Exhibit B - Method of Compensation.pdf PDF
Exhibit F - Fence Policy.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Transportation

RON DESANTIS

GOVERNOR

605 Suwannee Street

Tallahassee, FL 32399-0450

JARED W. PERDUE, P.E.

SECRETARY

Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov

Questions and Answers # 3

ADVERTISEMENT NUMBER: DOT-RFP-25-5002-TIML SunRail DESCRIPTION: Central Florida Rail Corridor (CFRC) Track Improvements - Multiple Locations

DATE: 9/11/2024

1. Project 1 (Universal Crossovers) – Please clarify if the special trackwork material stored at 523 N.

Garland Avenue is panelized or loose.

Answer: Crossovers panelized except the crossover “common ties”, 15 - 23 ft long ties.

2. Project 1 (Universal Crossover) – Section 3.1.1 of the Scope of Services document notes that

Contractor shall supply “OTM”. It is assumed that this is limited to track spikes and rail anchors only. Please confirm.

Answer: correct

3. Project 2 (Rail Renewal) includes the replacement of rail through several grade crossings.

Please clarify the scope of work at these locations.

Answer: At grade crossing cut existing rail at the grade crossing welded joints and match new rail to existing grade crossing rail. Assume no transition rails are required. All rail cuts shall be staggered in accordance with the CFRC MWI 801-06 CFRC Welding Manual.

4. Project 4 (MOW Siding) shows a 700’ underdrain on the plan & profile drawing which is not mentioned in the Scope of Services document. Please clarify.

Answer: The civil work including the underdrain is complete. The Project 4 scope of work is only for the construction of the MOW Storage track – ties, rail, fasteners, ballast, etc. See

Addendum 4 for revised MP806.3 Storage Track Plan.

File details come from the government source that posted it. Updated .