Pre-Bid Meeting Notes.pdf

PDF 76 KB Posted

Attached to
MT GOAT Site Construction Project
Solicitation number
IFB1 FAAA 2027000006 2
Issued by
Arapahoe County, Denver City, Colorado

About this file

This document consists of pre-bid meeting notes for IFB 2027*006, the MT GOAT Site Construction Project in Colorado. The project involves construction work at three sites: the 80th & Jasmine site, the Birch Street site, and the Eastwood Heights Park site in Pueblo. Key contacts for coordination include Maxwell Grisham and Andrea Thompson at Xcel Energy for the first two sites, Jeff Carney of MEP Engineering, Inc. serving as the subcontracted electrical engineer, and Black Hills Energy for the Pueblo location. The notes indicate that Black Hills Energy will likely require an easement from the landowner, Pueblo D60, for transformer placement at the Eastwood Heights Park site.

Contractors are required to submit costs using a provided template that breaks out expenses by site and includes an allowance line for potential charges from utility companies such as Xcel Energy or Black Hills Energy. Notably, costs included in the allowance will not be factored into the low-cost evaluation for award purposes. The document emphasizes coordination with utility providers and clarifies the cost submission requirements for bidders.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB 2027*006 MT GOAT Site Construction Project

Notes from Pre-Bid Meeting:

Here are the Xcel contacts for the MT GOAT project:

For the 80th & Jasmine site (Reference # SN 16230947):

Maxwell Grisham (Xcel Energy) Email: Maxwell.Grisham@xcelenergy.com Cell: 720-686-4784

For the Birch Street site (Reference # SN 16235582):

Andrea Thompson (Xcel Energy) Email: Andrea.D.Thompson@xcelenergy.com Cell: 303-517-5946

Our subcontracted electrical engineer, who is handling the contact with Xcel:

Jeff Carney (MEP Engineering, Inc.)

Email: jeff@mep-eng.com Direct phone: 720-541-6306

For the Eastwood Heights Park site in Pueblo:

Black Hills Energy

(719)977-3578

We believe that Black Hills Energy will need an easement from the landowner, Pueblo

D60, for the transformer placement.

Attachment 2b.

We are providing contractors a cost template that includes a cost breakout by site as well as an allowance line. Any potential charges from Xcel Energy or Black Hills should be captured there.

The costs included in the allowance will not be included in the low cost evaluation.