About this file
This is an Information for Bidders document issued by the Colorado Office of the State Architect, State Buildings Program, for the MT GOAT Site Construction Project managed by the Colorado Department of Public Health and Environment. The document establishes bidding requirements and procedures for prospective contractors. Bidders must submit bids using the required Bid form, addressing all alternates and specifying completion timelines from Notice to Proceed to Substantial Completion and from Substantial Completion to Final Acceptance. Bidders may request clarification on document inconsistencies at least three business days prior to bid opening. All work must comply with applicable Colorado state and local laws, building codes, and regulations, including apprenticeship and prevailing wage requirements on public projects. Additionally, bidders must report embodied carbon emissions of eligible materials in accordance with Environmental Product Declaration (EPD) requirements established by the Office of the State Architect.
Bid security of not less than five percent of the bid price is required for projects estimated at $50,000 or more, submitted as a surety bond, cash equivalent, or form acceptable to the State. Bids must exclude all applicable federal excise, manufacturers' taxes, and state sales and use taxes. Requests for "or equal" material or equipment substitutions must be submitted in writing at least five business days prior to bid opening and approved by the Architect/Engineer in addendum form at least two business days before bid opening. Owner or architect-initiated addenda will not be issued later than two business days prior to the bid opening date. Award determination follows the lowest responsible bidder method, considering Colorado resident bidder preference provisions, and accounts for either deductible or additive alternates in numerical order to remain within available funds. Bidders should submit proposals through the Rocky Mountain E-Purchasing System (BidNet) at www.bidnetdirect.com/cdphe.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBP-6.12
Rev 7/2025
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
INFORMATION FOR BIDDERS
Institution or Agency:
Project No./Project Name:
1. BID FORM: Bidders are required to use the Bid form attached to the solicitation.
Each bidder is required to bid on all alternates and indicate the time from the date of the Notice to Proceed to Substantial Completion in calendar days. In addition, the bidder is required to indicate the period of time to finally complete the project from Substantial Completion to Final Acceptance, in calendar days.
Bids indicating times for Substantial Completion and Final Acceptance in excess of the number of days indicated in the Advertisement for Bids for completion of the entire Project may be found non-responsive and may be rejected. The bid shall not be modified or conditioned in any manner. Bids and applicable bid security shall be submitted according to the following instructions:
2. INCONSISTENCIES AND OMISSIONS: Bidders may request clarification of any seeming inconsistencies, or matters seeming to require explanation, in the bidding documents at least three (3) business days prior to the time set for the opening of Bids. Decisions of major importance on such matters will be issued in the form of addendum.
3. APPLICABLE LAWS AND REGULATIONS: All work under this Contract shall comply with the provisions of all state and local laws, approved state building codes, ordinances and regulations which might in any manner affect the work to be done or those to be employed in or about the work. Labor for work shall be governed by the provisions of Colorado law which are hereinafter set forth in Articles 27 and 52 of the General Conditions. This includes the requirements for apprenticeship and prevailing wage on Public Projects. The bidder should be aware that reporting of embodied carbon emissions of eligible materials shall be governed by the provisions of Colorado State Law. This includes the requirements for Environmental Product Declarations (EPDs) that meet the maximum acceptable Global Warming Potential (GWP) limits as established by the Office of the State Architect.
4. BID SECURITY: A bid security of not less than 5% of the bid price is required when the price is estimated to be $50,000 or more. The security shall be a bond by a surety company, the equivalent in cash, or otherwise supplied in a form
SBP-6.12
Rev 7/2025 satisfactory for the State. Noncompliance requires the bid to be rejected as nonresponsive.
5. TAXES: The Bid submitted shall exclude all applicable federal excise or manufacturers’ taxes and all state sales and use taxes as hereinafter set forth in Article 9.3 of the GENERAL CONDITIONS.
6. OR EQUAL: The words “OR EQUAL” are applicable to all specifications and drawings relating to materials or equipment specified. Any material or equipment that will fully perform the duties specified, will be considered “equal”, provided the bid submits proof that such material or equipment is of equivalent substance and function and is approved, in writing. Requests for the approval of “or equal” shall be made in writing at least five (5) business days prior to bid opening. During the bidding period, all approvals shall be issued by the Architect/Engineer in the form of addenda at least two (2) business days prior to the bid opening date.
7. ADDENDA: Owner/architect initiated addenda shall not be issued later than two
(2) business days prior to bid opening date. All addenda shall become part of the Contract Documents and receipt must be acknowledged on the Bid form.
8. METHOD OF AWARD - LOWEST RESPONSIBLE BIDDER: If the bidding documents for this project require alternate prices, additive and/or deductible alternates shall be listed on the alternates bid form provided by the Principal Representative.
Bidders should note the Method of Award is applicable to this Bid as stated below.
A. DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
B. ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
C. DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used.
9. NOTICE OF CONTRACTOR’S SETTLEMENT – Agencies/institutions must indicate in the initial Solicitation where settlement will be advertised in electronic media.
| INFORMATION FOR BIDDERS |
| DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder. |
| ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder. |
| DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used. |
| TextInput.136: Colorado Department of Public Health and Environment |
| TextInput.182: 793 - ATOPs SB MT GOAT Site Construction project |
| Submission Instructions: BidNet Instructions - See Exhibit A Submission Instructions |
The Rocky Mountain E-Purchasing System (BidNet) is an online notification system that is utilized by multiple governmental entities. Participating entities post their bids, quotes, proposals, addendums, and awards on this one centralized system. Review bids or register today by visiting this link: www.bidnetdirect.com//cdphe.