Moose_Water_System_Specs_Volume_I.pdf

PDF 9 MB Posted

Attached to
GRTE 149677 Moose Waste Water/Water Plant Federal contract opportunity
Solicitation number
P16PS01023
Issued by
Department of the Interior National Park Service National Office

About this file

Moose Water System_Vol I Specifications

View the file

Other files for this federal contract opportunity

Other files attached to GRTE 149677 Moose Waste Water/Water Plant, newest first.
File Type Posted
07_13_26_FL_-_SELF-ADHERING_SHEET_WATERPROOFING_WATER.PDF PDF
07_16_16_-_CRYSTALLINE_WATERPROOFING_WWTP.PDF PDF
Amendment_0007_P16PS01023.pdf PDF
07_13_26_-_SELF-ADHERING_SHEET_WATERPROOFING_WWTP.PDF PDF
Amendment_0006_to_P16PS01023.pdf PDF
07_53_16_-_Chlorosulfonate-Polyethylene_(cspe)_Roofing.pdf PDF
Amendment_0005_to_P16PS01023.pdf PDF
Final_Amendment_0004_to_P16PS01023.pdf PDF
Q_and_A_Amend_004.pdf PDF
Amendment_003_Q_and_A.pdf PDF
Amendment_0003_to_P16PS01023_GRTE_149677.pdf PDF
Section_31_23_18_-_Rock_Excavation_GRTE_149677_WATER.pdf PDF
Amendment_0003_Contract_Price_Schedule.pdf PDF
Amendment_0003_Wage_Rates_Buildings.pdf PDF
Section_01_27_00_-_Contract_Line_Items_GRTE_149677_WATER.pdf PDF
Taggart_Supply_and_Storage_1982.pdf PDF
Ground_Protection_Mats_b.JPG JPG image
Amendment_0002_to_P16PS01023_GRTE_149677.pdf PDF
Moose_Lift_Station_partial_set.pdf PDF
Transmission_ _Windy_Point_Tank_1956.pdf PDF
Moose-Kelly_Pit_map.pdf PDF
Q_and_A_Amendment_002.pdf PDF
Moose_WWTP_partial_set.pdf PDF
Ground_Protection_Mats_a.JPG JPG image
Pre-Bid_Attendance_List_05.17.2016.pdf PDF
GRTE_149677_PreProposal_Presentation5-17-16.pdf PDF
Amendment_0001_Q_and_A_spreadsheet.pdf PDF
Amendment_0001_to_P16PS01023_GRTE_149677.pdf PDF
Amendment_0001_Vol_I_Submission_Package_P16PS01023.pdf PDF
Amendment_0001_Spec_01_27_00_Volume_I_WWTP.pdf PDF
MooseWater_DrawingSetv3.pdf PDF
USACE_022916_NP12_Authorization_Original.PDF PDF
Attachment_3_Wage_Rates.pdf PDF
MooseWater_DrawingSetv2.pdf PDF
Vol_I_Submission_Package_P16PS01023.pdf PDF
Moose_Waste_Water_-_Volume_III_Specs.pdf PDF
Moose_WWTP_Permit_to_Const._No_15-585.pdf PDF
Moose_WWTP_Drawing_setv3.pdf PDF
Permit_to_Construct_Moose_Water.pdf PDF
Moose_Water_System_Specs_Volume_II.pdf PDF
Vol_II_Submission_Package_P16PS01023.pdf PDF
GRTE_149677_Moose_WWTP_Wetlands_Report_09-29-14.pdf PDF
MooseWater_DrawingSetv1.pdf PDF
Final_Solicitation_P16PS01023_GRTE_149677.pdf PDF
GRTE_149677_Moose_Water_Wetlands_Report.pdf PDF
Moose_WWTP_Drawing_setv2.pdf PDF
Attachment_5_Contractor_Tour_Request_Form.pdf PDF
Moose_Waste_Water_-_Volume_I_Specs.pdf PDF
Moose_WWTP_Drawing_setv1.pdf PDF
Moose_Waste_Water_-_Volume_II_Specs.pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRTE – 149677-WATER 01 00 00 - 1

SPECIFICATIONS TABLE OF CONTENTS

GRAND TETON NATIONAL PARK

TETON COUNTY, WYOMING

ADDRESS CRITICAL MOOSE WATER SYSTEM

DEFICIENCIES

PARK (GRTE)

PMIS NO. 149677

PROJECT SPECIFICATIONS

(VOLUME I)

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

July, 2015

GRTE – 149677-WATER 01 00 00 - 2

TABLE OF CONTENTS

VOLUME I

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 CONTRACT MODIFICATION PROCEDURES

01 11 00 SUMMARY OF WORK

TAGGART WATER TANK GEOTECHNICAL INVESTIGATION

MOOSE WATER TRANSMISSION LINE GEOTECHNICAL INVESTIGATION .

FONSI MITIGATION MEASURES

HAZARDOUS MATERIALS INSPECTION REPORT

RADIO PATH STUDY

01 12 00 NATURAL FEATURES PROTECTION

01 27 00 DEFINITION OF CONTRACT LINE ITEMS

01 31 00 PROJECT MANAGEMENT & COORDINATION

01 32 16 CONSTRUCTION SCHEDULE

01 32 33 PHOTOGRAPHIC AND VIDEO DOCUMENTATION

01 33 23 SUBMITTAL PROCEDURES

01 35 13.22 ARCHEOLOGICAL PROTECTION

01 35 23 SAFETY REQUIREMENTS

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 55 26 TRAFFIC CONTROL

01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION

SWPPP – NOTICE OF TRANSFER AND ACCEPTANCE

01 67 00 PRODUCT REQUIREMENTS

01 73 40 EXECUTION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PROJECT WASTE MANAGEMENT PLAN WORKSHEET

STANDARD SOLID WASTE CONVERSIONS

01 77 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 79 00 DEMONSTRATION AND TRAINING

01 81 13 SUSTAINABLE DEVELOPMENT FOR NON-LEED PROJECTS

DIVISION 02 – EXISTING CONDITIONS

02 41 16 STRUCTURE DEMOLITION

DIVISION 03 – CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 37 00 CONCRETE CURING

03 41 00 PRECAST STRUCTURAL CONCRETE

03 60 00 GROUTING

GRTE – 149677-WATER 01 00 00 - 3

DIVISION 04 – MASONRY

04 22 00 CONCRETE UNIT MASONRY

DIVISION 05 – METALS

05 50 00 METAL FABRICATIONS

05 50 10 ANCHOR BOLTS AND EXPANSION ANCHORS

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 53 MISCELLANEOUS ROUGH CARPENTRY

06 16 00 SHEATHING

06 17 53 SHOP-FABRICATED WOOD TRUSSES

06 64 00 PLASTIC PANELING

06 82 00 GLASS-FIBER-REINFORCED PLASTIC FABRICATIONS

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 13 26 SELF-ADHERING SHEET WATERPROOFING

07 21 00 THERMAL INSULATION

07 25 00 WEATHER BARRIERS

07 41 13.16 STANDING-SEAM METAL ROOF PANELS

07 46 19 STEEL SIDING

07 46 46 FIBER-CEMENT SIDING

07 53 16 CHLOROSULFONATED-POLYETHYLENE (CSPE) ROOFING

07 62 00 SHEAT METAL FLASHING AND TRIM

07 72 00 ROOF ACCESSORIES

07 92 00 JOINT SEALANTS

VOLUME II (SEPARATE BINDER)

DIVISION 08 – OPENINGS

08 11 13 HOLLOW METAL DOORS AND FRAMES

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 80 00 GLAZING

08 91 19 FIXED LOUVERS

VOLUME II (SEPARATE BINDER)

DIVISION 09 – FINISHES

09 91 13 EXTERIOR PAINTING

09 91 23 INTERIOR PAINTING

GRTE – 149677-WATER 01 00 00 - 4

DIVISION 10 – SPECIALTIES

(NOT USED)

DIVISION 11 – EQUIPMENT

(NOT USED)

DIVISION 12 – FURNISHINGS

(NOT USED)

DIVISION 13 – SPECIAL CONSTRUCTION

(NOT USED)

DIVISION 14 – CONVEYING EQUIPMENT

(NOT USED)

DIVISION 21 – FIRE SUPPRESSION

(NOT USED)

DIVISION 22 – PLUMBING

22 05 23.12 BALL VALVES FOR PLUMBING PIPING

22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 11 16 DOMESTIC WATER PIPING

22 11 19 DOMESTIC WATER PIPING SPECIALTIES

22 13 16 SANITARY WASTE AND VENT PIPING

22 13 19 SANITARY WASTE PIPING SPECIALTIES

22 45 00 EMERGENCY PLUMBING FIXTURES

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC

23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING OF HVAC

23 07 13 DUCT INSULATION

23 09 23.12 CONTROL DAMPERS

23 09 23.19 MOISTURE INSTRUMENTS

23 31 13 METAL DUCTS

23 33 00 AIR DUCT ACCESSORIES

23 34 23 HVAC FANS

23 82 39 UNIT HEATERS

GRTE – 149677-WATER 01 00 00 - 5

DIVISION 25 – INTEGRATED AUTOMATION

25 51 00 INTEGRATED AUTOMATION CONTROL OF FACILITY EQUIPMENT

DIVISION 26 – ELECTRICAL

26 00 00 BASIC ELECTRICAL REQUIREMENTS

26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 23 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33.10 RACEWAYS

26 05 43 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

26 05 44 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 05 48 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

25 05 53 ELECTRICAL SYSTEMS IDENTIFICATION

26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

26 05 83 EQUIPMENT WIRING SYSTEMS

26 05 93 ELECTRICAL SYSTEMS FIRESTOPPING

26 09 35 TELEPHONE AUTOMATIC DIALER SYSTEM

26 22 00 LOW-VOLTAGE TRANSFORMERS

26 24 16 PANELBOARDS

26 27 26 WIRING DEVICES

26 28 13 FUSES

26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26 29 23 VARIABLE-FREQUENCY MOTOR CONTROLLERS

26 41 13 LIGHTNING PROTECTION

26 43 00 TRANSIENT VOLTAGE SUPPRESSION

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

26 90 30 PROGRAMMABLE LOGIC CONTROLLERS

DIVISION 27 – COMMUNICATIONS

27 05 28 PATHWAYS FOR COMMUNICATIONS SYSTEMS…………………………… . ……

27 05 27 TELEMETRY SYSTEMS .................................................................................. ……………

27 10 00 COMMUNICATIONS AND SECURITY GENERAL REQUIREMENTS………… .. …

DIVISION 28 – ELECTRONICS SAFETY AND SECURITY

(NOT USED)

DIVISION 31 – EARTHWORK

31 05 13 SOILS FOR EARTHWORK

31 05 16 AGGREGATES FOR EARTHWORK

31 10 00 SITE CLEARING

31 23 16 EXCAVATION

GRTE – 149677-WATER 01 00 00 - 6

31 23 17 TRENCHING

31 23 18 ROCK REMOVAL

31 23 19 DEWATERING

31 23 23 FILL

31 23 23.43 GEOFOAM

31 23 24 FLOWABLE FILL

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 ASPHALT PAVING

32 17 23 PAVEMENT MARKINGS

32 91 19.13 TOPSOIL PLACEMENT AND GRADING

DIVISION 33 – UTILITIES

33 05 17 PRECAST CONCRETE VALVE VAULTS

33 05 23 TRENCHLESS UTILITY INSTALLATION

33 11 13 PUBLIC WATER UTILITY DISTRIBUTION PIPING

33 12 16 WATER UTILITY DISTRIBUTION VALVES

33 12 19 WATER UTILITY DISTRIBUTION FIRE HYDRANTS

33 13 00 DISINFECTING OF WATER UTILITIES

33 14 00 WATER UTILITY DISTRIBUTION EQUIPMENT

33 14 05 WATER UTILITY EQUIPMENT IDENTIFICATION

33 21 13 PUBLIC WATER SUPPLY WELLS

33 29 00 WELL ABANDONMENT

33 36 14 WASH WATER HOLDING TANKS

33 42 13.13 PUBLIC PIPE CULVERTS

33 46 00 SUBDRAINAGE

DIVISION 34 – TRANSPORATION

(NOT USED)

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

(NOT USED)

DIVISION 40 – PROCESS INTEGRATION

(NOT USED)

DIVISION 41 – MATERIALS PROCESSING AND HANDLING EQUIPMENT

(NOT USED)

DIVISION 42 – PROCESS HEATING, COOLING, AND DRYING EQUIPMENT

GRTE – 149677-WATER 01 00 00 - 7

(NOT USED)

DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND

STORAGE EQUIPMENT

(NOT USED)

DIVISION 44 – POLLUTION CONTROL EQUIPMENT

(NOT USED)

DIVISION 45 – INDUSTRY – SPECIFIC MANUFACTURING EQUIPMENT

(NOT USED)

DIVISION 46 – WATER AND WASTEWATER EQUIPMENT

46 33 46 PROGRESSIVE CAVITY METERING PUMPS

46 41 10 MIXERS

46 41 17 INLINE STATIC MIXERS

DIVISION 48 – ELECTRICAL POWER GENERATION

(NOT USED)

END OF INDEX

01 10 00 - 1 GRTE – 149677-WATER

CONTRACT MODIFICATION PROCEDURES

060613

SECTION 01 10 00 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

01 10 00 - 2 GRTE – 149677-WATER

060613

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

01 10 00 - 3 GRTE – 149677-WATER

060613

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

01 10 00 - 4 GRTE – 149677-WATER

060613

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

01 10 00 - 5 GRTE – 149677-WATER

060613

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:

Overhead………………10% Profit………………6.75%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

01 10 00 - 6 GRTE – 149677-WATER

060613

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 10 00

GRTE – 149677-WATER 01 11 00 - 1

050611 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Locating Utilities

9. Work Restrictions.

10. Special Construction Requirements.

11. Protection of Parks and Public Lands.

12. Soils Investigation Report.

13. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Grand Teton National Park, Moose, Wyoming.

B. The Work consists of the following:

1. The Work includes construction of new water system infrastructure including two 150 gpm wells, a 520 square foot Well House building with electrical and chemical treatment rooms, 300,000 gallon buried concrete water storage tank, installation of approximately 17,100 and 5,525 lineal feet of 12 inch and 8 inch diameter HDPE water transmission main, electrical and fiber conduits, and telemetry based SCADA control system.

2. The Work includes demolition of existing water system infrastructure including Taggart Well No. 1, the Taggart Well House, a 50,000 gallon insulated above ground steel water storage tank (Taggart Tank), 100,000 gallon buried concrete water storage tank (Windy Point Tank) and existing utility vaults as indicated in the construction drawings.

3. Completion of each item includes all materials, labor, reclamation, transportation, material processing plants, equipment, royalties, warranties, O&M manuals, and incidentals necessary to complete the Work as described in the construction drawings and these specifications.

4. Contractor is responsible to obtain and pay for all permits and fees from the state and local authorities, including utility and construction permits, fees, and inspections, GRTE – 149677-WATER 01 11 00 - 2 whether temporary or permanent. Contractor is responsible to include in the bid amount any costs associated with work by Utility Companies.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. Phasing will not be required for this project, however, the Contractor is required to schedule Work in accordance with Section 01 32 16 – Construction Schedule, comply with Paragraph 1.10, “Work Restrictions” and the following requirements:

1. Mark construction boundaries and obtain approval of the boundary locations by the

Contracting Officer (CO) prior to commencing with any construction.

2. Contractor shall maintain operation of a minimum of two (2) wells (including disinfection systems) and 150,000 gallons of storage during construction. For the purpose of maintaining fire protection to Moose, Windy Point tank shall remain in operation until the new water storage tank and transmission line has been completed, accepted an on-line. Contractor shall make all temporary utility connections and control modifications to maintain required storage and supply capacities. Submit a plan for approval of temporary shutdowns and changeovers to the CO. Do not proceed with service interruptions, or water facility shutdowns, without prior written consent from the

CO.

3. When practical, complete mowing and mulching of waterline construction corridors.

Work shall be completed the fall prior to construction to prevent birds from nesting within the construction corridor the following spring.

4. Replace the culvert at Beaver Creek prior to new water tank and transmission line construction.

5. Do not demolish or abandon existing facilities until new facilities are fully operational and approved by the CO. Water supply to Moose is required during all new construction.

Abandonment of facilities shall be approved by the CO.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. Well House Telephone Service: A separate contract will be awarded to CenturyLink Communications for installation of a telephone line extending from Teton Park Road to the new Well House. Work under this contract is described on Sheet C1.4 in the construction drawings.

C. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

GRTE – 149677-WATER 01 11 00 - 3

1. Moose Water Seeding and Reclamation: A separate contract will be awarded for completing final site revegetation, including soil prep, seeding, mulching, planting and weed control of disturbed areas within the project area of this Contract.

1.5 GOVERNMENT-FURNISHED MATERIALS

A. Government will furnish products indicated.

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.

4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

5. Contractor is responsible for protecting Government-furnished items from damage during storage, handling and use, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.

B. Government-Furnished Products:

1. Ground Protection Mats: The Government will furnish, for Contractor use, ground protection mats. Mats will be used in locations to minimize compaction and disturbance of Park Resources. Requirements for use are provided in Section 01 50 00 - Temporary Facilities and Controls.

1.6 SUBMITTALS

A. Section 01 33 23 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit data on spare stock pipe and fittings.

1.7 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the construction limits indicated on the drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated. Construction limits are defined by the “Limit of Disturbance” boundary shown in the Construction Drawings.

B. Coordinate with CO and Park Staff to minimize disruption of normal Park activities. Inform construction workers and supervisors about the special sensitivity of Park values, regulations, and appropriate housekeeping.

GRTE – 149677-WATER 01 11 00 - 4

C. Maximize the use of previously disturbed areas for staging and stockpile areas to minimize ground disturbance.

D. Storage of Materials: Confine storage of materials to Contractor Staging Areas and designated Stockpile Areas as shown on the drawings. Acceptable use of each staging area is defined in the drawings.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings located outside construction limits. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with the CO and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

6. Comply with requirements of Section 01 12 00 - Natural Features Protection.

F. Driveways and Entrances: Keep driveways, parking lots, and roadways serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials unless otherwise indicated or approval is given.

1. Schedule deliveries to minimize use of driveways, entrances and accesses.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp: Establishment of a camp within the park will not be permitted.

H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.8 PUBLIC USE OF SITE

A. Contractor, shall at all times, conduct his operations to ensure the least inconvenience to the public. All traffic on Park Roads must be permitted to pass. If excavation, backfill, or paving operations require a temporary closure of a street, the Contractor shall route traffic on a clearly signed and marked detour. The Contractor will be required to place and maintain signs for all detours.

B. Comply with requirements specified in Section 01 55 26 - Traffic Control.

C. Implement measures to reduce adverse effects of construction on visitor health and safety.

GRTE – 149677-WATER 01 11 00 - 5

1.9 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Facilities

1. Government will occupy and/or maintain existing facilities adjacent to the construction including the Taggart Well House, Taggart and Windy Point Tanks until structures have been approved for demolition.

2. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.

3. Perform the Work so as not to interfere with Government's day-to-day operations.

Maintain existing accesses and exits, unless otherwise indicated.

4. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

B. New Facilities

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of facilities, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational and required tests, inspections and training of Government personnel shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of facility.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for accepted portions of the facility.

1.10 LOCATING UTILITIES

A. Comply with Section 01 73 40 – Execution, for location and verification of existing utilities.

1.11 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be performed from 8 a.m. to 6 p.m., Monday through Friday.

Work outside these hours or days shall be approved by the CO. It is expected that certain work activities including cut-over from existing to new water facilities will involve work at night to minimize water service disruptions.

B. Operation of Existing Facilities: The Contractor is not authorized, except under emergency conditions, to operate any Park-owned water valves or equipment.

C. Construction Limits: “Limit of Disturbance” lines are provided on the drawings to describe construction boundaries. Do not operate equipment outside the construction boundaries. Install orange or green plastic fencing at boundaries to confine construction operations. Any

GRTE – 149677-WATER 01 11 00 - 6

unauthorized disturbance may result in Grand Teton National Park issuing the appropriate level of law enforcement to the responsible person, or Contractor.

D. GRTE Mitigation Restrictions

1. Wildlife

a. Birds (General): Work within waterline corridors is limited to August 1st due to nesting birds. If Contractor desires to work between May 10th and August 1st, Contractor shall notify the CO 60 days in advance. Subsequent to notification, the waterline construction corridor will be surveyed for nesting birds by Park biologists. The survey will be conducted within a week of anticipated waterline construction. If nests are found, the Contractor will be required to maintain working distances from nests established by Park staff.

b. Contractor shall inform construction personnel and supervisors that under the Migratory Bird Treaty Act, no migratory bird, nest, or egg can be disturbed, removed, or destroyed. Provide instructions for notification of NPS staff if the potential for disturbance is discovered.

c. A bird survey completed in 2011 did not find nesting birds including sage grouse, bald eagles, osprey, trumpeter swan, peregrine falcon and great blue heron within the project vicinity, however, if said birds are found within or adjacent to the project area, the Contractor shall comply with the following:

1) Plan work in the Park so that it does not occur within 100 yards of any osprey, trumpeter swan, peregrine falcon, or great blue heron nests from April 1 to September 1.

2) Bald Eagles: Protect bald eagle nests from human disturbance between February 15 and August 15. Plan work to ensure that it does not occur within a half-mile of any active bald eagle nest from February 1 through August 15.

3) Trumpeter Swans: Avoid working at the Snake River Bridge at Moose if trumpeter swans are in the area. Typically, swans do not nest at either location but they are known to use both areas for loafing and foraging the winter months. No construction shall take place before September 1 near active nesting sites.

4) Sage Grouse and Other Sage Dependent Species: Prohibit all habitat removal between March 15 and June 30 to protect breeding, nesting, and brood rearing, as stipulated in the Wyoming Governor’s Executive Order.

Do not remove any habitat within 1 mile of any sage grouse leks between April 1 and June 30.

5) Bats: Notify NPS staff if bats are located in any project facilities. To minimize adverse effects to any bats present, survey buildings before they are removed. If bats are found using the site as a roost, delay removal activities until after an NPS survey determines that individuals and/or young have left the buildings.

6) Other Candidate, Threatened and Endangered Species: If known candidate, threatened or endangered species are discovered, Contractor is required to stop construction until NPS staff can evaluate the situation. NPS will implement protection measures as appropriate to protect the discovery.

2. Soil: Schedule construction during dry periods and when surface and ground water levels are low to minimize soil compaction outside of trenches.

GRTE – 149677-WATER 01 11 00 - 7

E. Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify CO not less than one week in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without CO’s written permission.

3. Do not conduct planned utility interruptions outside the days of Monday through

Wednesday.

4. Comply with Section 33 11 13 – Public Water Utility Distribution Piping, for planned service interruptions relating to the existing water system.

F. Permitting: Contractor shall obtain all permits required for construction of facilities described in this Contract. Comply with permitting requirements listed in Section 01 31 00, PART 1.9 “Project Management and Coordination”.

1.12 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: The Governments NPS SharePoint website will be used for purposes of managing communication and documents during the construction stage of this project.

Coordinate access to the site with CO.

1. See Section 01 31 00 - Project Management and Coordination, for requirements on using the Project Website.

B. There are no seasonal restrictions for this project. Normal Park closure dates are from Nov. 4th through April 6th. A gate on Teton Park Road is located just north of the Taggart Lake Trailhead and southeast of the Well House site to prevent public entry during Park closure. Contractor shall notify CO if access is required to the Well House facility during Park closure. Costs associated with plowing snow to gain access to the Well House or Taggart Tank sites shall be borne by the Contractor.

C. Pre-construction Video: Prior to execution of Work, Contractor shall submit a video recording of the work site in accordance with Section 01 32 33 - Photographic and Video Documentation.

D. Repair Stock: Contractor shall maintain a stock of spare parts and materials at the job site including couplers and pipe for emergency repair of utilities located adjacent to new construction. Spare parts shall be approved for the intended application and comply with Division 33 of these specifications. Spare parts and materials shall include, but is not limited to:

a. Pipe:

1) 4-inch dia. CIP (20 lineal feet)

2) 4-inch dia. DIP (20 lineal feet)

3) 4-inch dia. PVC (20 lineal feet)

4) 6-inch dia. CIP (20 lineal feet)

5) 6-inch dia. DIP (20 lineal feet)

6) 6-inch dia. PVC (20 lineal feet)

7) 10-inch dia. CIP (20 lineal feet)

b. Couplers: Supply with gaskets and end rings to accommodate repair of PVC pipe, DIP, and CIP).

1) 4 inch repair couplers (2 ea.)

2) 6 inch repair couplers (2 ea.)

GRTE – 149677-WATER 01 11 00 - 8

3) 10 inch repair couplers (2 ea.)

1.13 PROTECTION OF PARKS AND PUBLIC LANDS

A. Equipment and Vehicle Cleaning: All vehicles and equipment including office trailers and residential trailers that enter the Park and are staged in association with this project, will be inspected by the CO prior to the entry into the Park for mud, weeds and other unwanted substances. Pressure wash all vehicles, including earth-moving and mulching equipment for mud and seed. Comply with the following:

1. The spread of exotic invasive plant species in the Park is a serious concern, and no equipment will be allowed to offload, nor remain within the Park, if dirt or other contaminants with the potential to harbor seeds are apparent. Any equipment which departs the project site (excluding hauling vehicles) must repeat an identical cleaning and inspection process, including formal acceptance by the CO prior to being remobilized and offloaded at the project site.

2. Notify the CO a minimum of 48 hours prior to the entry of vehicles and equipment. The CO will make arrangements for the inspections.

3. Prior to offloading of any equipment, obtain verbal approval from the CO.

4. Clean hauling vehicles before their initial entrance into the Park; subsequent entries will not require cleaning or inspection unless equipment is used at another job site or as requested by CO.

5. Any equipment that is unacceptable to the CO shall be immediately removed from the Park.

B. Construction Limits: Do not operate or park any equipment off the paved or established roadways except in approved areas. Do not operate or store vehicles and equipment leaking oil, gas, or anti-freeze within the Park boundaries. Do not drain oil, hydraulic fluids, anti-freeze, or other chemicals onto the ground within Park boundaries. Completely contain diesel fuel at the work site. Notify CO of any spill and clean up spill immediately. Contractor is required to have a Hazardous Spill Plan in accordance with Section 01 50 00 - Temporary Facilities and Controls.

C. Overnight Camping: Sleeping vehicles or camping within the Park Boundaries will not be allowed.

D. Explosives: Do not use explosive materials within the Park boundaries.

E. Wildlife Protection: Do not feed or disturb wildlife within the Park Boundaries. Store and handle food, fuel, food containers, dishes or other attractants, including toiletries, pet food/bowls, and any odorous item in a manner that does not attract bears, i.e., no food, pet food, garbage, drinks, trash including food and drink containers except during actual use.

Construction workers shall maintain required distances from all wildlife at all times.

1. All on-site construction personnel will be required to attend and complete Wildlife and

Bear briefing sessions provided by Park personnel, entitled “Working Bear Country”, reference 36 CFR., The Human-Bear Management Plan for GRTE; and the JDR (1989), Interagency Grizzly Bear Committee; 1986 Interagency Grizzly Bear Guidelines, Missoula, Montana. Construction personnel will receive training with regards to the NPS Bear Management Plan safety protocols, sanitation standards, and food storage regulations. Notify CO two(2) weeks before starting Work so the briefing session can be coordinated.

GRTE – 149677-WATER 01 11 00 - 9

2. Construction personnel are required to report all bear sightings in the work area to the Teton Interagency Dispatch Center (TIDC) and the CO immediately. Contractor shall temporarily suspend Work when a grizzly bear is near an active construction area and creates a potential animal/human conflict.

3. When it is determined by the CO that there is a potential animal/human conflict, stop work at the construction site until the CO determines that it is safe for work to continue.

If required by Park staff, Contractor, Subcontractors, and employees may be required to purchase and carry bear pepper spray. The Government will not supply bear pepper spray.

4. Contractor supplied garbage bins placed at the construction site must be bear proof and meet Park requirements. Remove all garbage and food trash from the project site daily.

5. Any mishandling of garbage, trash, food, and other potential bear attractants described above will result in Grand Teton National Park issuing the appropriate level of law enforcement to the responsible person, or Contractor. If mishandling occurs and a specific individual is not determined, the Contractor will be held responsible.

6. In camping, picnic, trailhead, and day-use front country areas, all food items must be attended at all times or stored inside bear resistant food storage lockers and/or inside hard sided vehicles with doors locked and windows closed.

F. Protection natural features including vegetation, soils, streams and wetlands in accordance with Section 01 12 00 - Natural Features Protection.

1.14 SOILS INVESTIGATION REPORT

A. A soils investigation report entitled “Geotechnical Investigation Taggart Water Tank, Grand Teton National Park, Wyoming”, January 2012 has been prepared by Nelson Engineering.

B. A soils investigation report entitled “Geotechnical Investigation Moose Water Transmission Line, Grand Teton National Park, Wyoming”, March, 2014 has been prepared by Nelson Engineering. Test pits were excavated and logged along the water transmission line alignment between Taggart Tank and Moose. Logs of the test pits are provided on the drawings.

C. A copy of these reports are attached following this Section and provided to all plan holders with this package.

D. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

1.15 ADDITIONAL REPORTS

A. The following reports and project information are provided as supplemental information following this specification:

1. The FONSI report entitled “Mitigation Measures Included as Part of the Selected

Action,” has been prepared by National Park Service, U.S. Department of Interior, Grand Teton National Park.

2. Hazardous Materials: A hazardous materials inspection for limited asbestos, lead-based paint and universal waste was completed in 2014 at the existing Taggart Well House and Tank sites.

GRTE – 149677-WATER 01 11 00 - 10

3. Radio Path Study: A Radio Path Study Report was completed to verify radio signal strength at each proposed radio site.

B. The following reports and project information can be provided to the Contractor upon request to the CO:

1. A report entitled “Wetland Delineation Report, Grand Teton National Park Waterline

Improvements” dated September 2014 was completed on areas within and in the immediate vicinity of the Project area.

2. A report entitled “Environmental Assessment Replace Moose Wastewater System and Address Critical Water System Deficiencies Grand Teton National Park Teton County, Wyoming,” March 2012 has been prepared by the National Park Service, U.S.

Department of Interior, Grand Teton National Park.

C. If conflicts occur between these reports and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

TABLE OF CONTENTS

GENERAL AND PROJECT DESCRIPTION

SCOPE OF SERVICES

SITE CONDITIONS

DESCRIPTION

GEOLOGY

SEISMIC HAZARD

SEISMIC DESIGN PARAMETERS

SITE INVESTIGATIONS

FIELD INVESTIGATIONS

LABORATORY TESTING

SUBSURFACE CONDITIONS

GROUNDWATER

ENGINEERING ANALYSIS AND RECOMMENDATIONS

GENERAL

EXCAVATIONS AND DEWATERING

TANK BEARING CAPACITY AND SUBGRADE MODULUS

LATERAL EARTH PRESSURE

EARTHWORK AND SITE GRADING

GENERAL COMMENTS

WARRANTY AND LIMITING CONDITIONS

- 1 -

S:\Proj2010\148-03 (Moose Geotech & Surveying)\Geotech\Tank Geo\DD Phase\2014 Taggart Tank Geo Report.doc

GENERAL AND PROJECT DESCRIPTION

A feasibility study of the Moose Water system was performed for Grand Teton National Park (GTNP) (PMIS 149677) by Nelson Engineering in July of 2011. Study recommendations included the construction of a new water tank to replace the existing Taggart Tank. This is a report of a geotechnical investigation at the proposed site of the replacement tank and is formulated as part of design efforts for water system improvements for Grand Teton National Park (GTNP). The proposed water tank site is in close proximity to the existing tank as shown on the Design Development Plans.

The purpose of the investigation was to provide geotechnical recommendations for the design and construction of a concrete cylindrical water tank of the size, elevation, and at the site as denoted in the Moose Water System Improvements Design Development Plans.

Scope of Services

The scope of services for this investigation was to provide geotechnical recommendations for the design and construction of a water tank based on a subsurface investigation and soils laboratory testing. A tank site, dimensions, and elevations were identified in the Schematic Design Phase and a subsurface investigation was performed to determine subsurface soil, rock, and groundwater characteristics for the proposed tank. The results of the subsurface investigation and subsequent laboratory testing were utilized in an engineering analysis assessing possible dewatering, excavation, construction, fills, and structural design requirements.

SITE CONDITIONS

Description

The existing and replacement tank sites are located west of the Taggart Lake trailhead on glacial moraine deposits. The proposed replacement tank site is located upslope and northwest of the existing tank on a moraine occupied by forest and brush. To the north of the site is the channel of Taggart Creek, flowing from east to west in a steep incised channel. Typical terminal moraine geomorphology predominates in the vicinity; features include potholes and multiple low ridges and swales. Potholes south and south east of the tank site are seasonally inundated during the spring snowmelt period. Granitic boulders typical of Teton moraines are visible at the ground surface throughout the area. Most boulders are less than 5 feet in diameter.

Geology

The site is mapped on the USGS "Geologic Map of the Grand Teton National Park, 1992". Mapped deposits are moraine drift deposits related to the 4th glaciation.

Seismic Hazard

Grand Teton National Park is located in a seismically active area known as the Intermountain Seismic Belt. Numerous active faults are mapped throughout Grand Teton National Park and the surrounding

- 2 -

S:\Proj2010\148-03 (Moose Geotech & Surveying)\Geotech\Tank Geo\DD Phase\2014 Taggart Tank Geo Report.doc area. Of particular note is the southern section of the Teton Fault located about ½ mile to the west of the tank site. The Teton fault is thought to capable of producing major earthquakes of magnitude seven or greater. Multiple minor earthquakes have occurred in the vicinity in recent years as recorded by the U.S. Geological Survey. Per the U.S. Geological Survey’s National Seismic Hazard Mapping Project, peak ground acceleration at the project site has a 10% probability of exceeding

0.246 times that of gravity (g) in 50 years and a 2% probability of exceeding 0.685g in 50 years.

Seismic Design Parameters

The International Building Code, 2012 Table 1613.5.2, designates site class by determining soil properties in the top 100 feet. Data obtained in this investigation and local geologic mapping indicates medium dense soils form the upper 100 feet of the subsurface, therefore, site Class D is appropriate. Ground acceleration parameters for seismic structure design per the IBC and related ACI seismic design method for tanks should be determined for N 43.697°, W 110.739°, Site Class D.

SITE INVESTIGATIONS

Field Investigations

On November 18 and 19, 2011 three geotechnical borings, (TT-1, 2, and 3) were advanced at the proposed site as shown on the Boring Location Map in the Appendix. Axis Drilling of Belgrade, Montana advanced the borings with a track mounted Davey-Kent air rotary drill rig. Borings were advanced with an Odex type bit and casing was advanced continuously to the depth of all of the borings.

Philip Gyr, a Professional Engineer at Nelson Engineering, directed the field investigation. Field logs were prepared that recorded the observations of the field geologist. Each sample was carefully observed as it was recovered.