This document package includes a solicitation for the expansion and upgrade of Building 42 for laboratory use at the Marion VA Medical Center. The solicitation seeks construction services to expand the building's lower level and main level, upgrading mechanical, electrical and plumbing systems. Drawings and specifications are provided to guide responses for the base work and listed alternates. The Department of Veterans Affairs Veterans Health Administration VISN 15 is the contracting agency. The response due date is not stated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MENTAL HEALTH
TRAILER '1'
EMERGENCY
GENERATOR
IRM
HUMAN RESOURCES
TELE.
MAIN HOSP.
CANTEEN/
SNRF
BOILER
INCINERATOR
WAREHOUSE
15SHOPS
QUONSET
STRUCTURES
T105 T106 T107 T108 T109
SWITCHGEAR
STATION
COOLING
TOWER
T R A
IL
E R
'2
P A V
IL
IO
N
T R A
IL
E R '3
YARD
D O C
KP
A V
IL
IO
N
MARION
TRAILER '4'
ENGINEERING/SAFETY
CHILLER
BLDG. 49
WATER TOWER
OUTPATIENT
CLINIC
PLANT
CLINICS
EAST TRAILER
SHOP TRAILER
DENTAL/SPD
& CLINICS
NORTH PERIPHERY
ROAD
SOUTH PERIPHERY
ROAD
W E S T
P E R
IP
H E R Y
R O A D
E A
R
IP
H E R Y
R O A D
BOLLARDS
BOLLARDS
x x x x xx
LIQ.
OXYG.
STOR.
STEAM TUNNEL
STEAM
INLET
S
STEAM
TUNNEL
VENT
S
STEAM TUNNEL VENT
STEAM
TUNNEL
STEAM
TUNNEL
SIDEWALK
S
ID
E W A
LK
PATIO
RAMP
SIDEWALK
S
IDEW
ALK
S
ID
E W A
LK
WALK/STAIRS
S
ID
E W A L K
CONCRETE
TRASH
SIDEWALK
CONCRETE
WHEELCHAIR
RAMP
ENTRY
SIDEWALK
W H E
EL
C H A
IR
P A T
IE
N T V
IS
TO
R
P A T
IE
N T V
IS
TO
R
P A
TI
E N T
VI
S
IT
O R
P A
TI
E N T
VI
S
IT
O R
O P E N
P A R K
IN
G
O P E N
P A R K
IN
G
VO
L.
VO
L.
VO
L.
VO
L.
VO
L.
VOL.
VOL.
VOL.
VOL.
VOL.
W H E
EL
C H A
IR
W H E
EL
C H A
IR
W H E
EL
C H A
IR
GOV.CO
NS
UL
T
GOV.
DAV
DAV
DAV
OR
C
LER
GY
CO
NS
UL
T
OR
C
LER
GY
CO
NS
UL
T
OR
C
LER
GY
CO
NS
UL
T
OR
C
LER
GY
CO
NS
UL
T
OR
C
LER
GY
VISITOR
VISITOR
VISITOR
VISITOR
VISITOR
O P E N
P A R K
IN
G
O P E N
P A R K
IN
G
GO
V.
VIS
ITO
R
VIS
ITO
R
W H E
EL
C H A
IR
OPEN PARKING
C O M M
AN
D
ER
D R
IV
E
AS
PH
AL
T
PA
VE
M
EN
T
BLDG. 8 DRIVE
E D U C B
LD
G S E R
VI
C E
D R
P U
LL
O
FF
AP
R O N
STAFF PARKING
NHCU STAFF PARKING LOT
WAREHOUSE/SHOPS PARKING
ENGIN./SAFETY
CONCRETE
ASPHALT
GRAVEL
G R A
VE
L
C O M M
AN
D
ER
D R
IV
E
PARKING
BLDG. 8 DRIVE &
B L D G
S
ER
V
IC
E
D R
IV
E
M O B
IL
E C A
TS
C
AN
P
AR
K
IN
G
S P
AC
E
NHCU
LOADING
DOCK
PARKING
PARKING
ENGIN./SAFETY
FUEL TRUCK APRON
NHCU SERVICE DRIVE
STAFF PARKING
LOADING DOCK APRON
STAFF PARKING
STAFF PARKING
CUSHMAN
PARKING
CUSHMAN
PARKING
PROJECT SITE
LEGEND - SYMBOLS
T.O.
X'-X" A.F.F.
X
X
XXX
X
X
CONTROL POINT
KEYED NOTE
CENTER LINE MARK
REVISION NUMBER
X
ELEVATION DATUM
EXISTING COLUMN LINE
NEW COLUMN LINE
EXTERIOR ELEVATION
MARK
X = ELEVATION NUMBER
Y = SHEET NUMBER
NEW PARTITION
NEW DOOR
W/ DOOR NUMBER
ROOM NAME & NUMBER
WINDOW NUMBER
PARTITION TYPE
DEMOLISHED DOOR
EXISTING DOOR
DETAIL MARK
X = DETAIL
NUMBER
Y = SHEET
NUMBER
NORTH ARROW
SECTION MARK
X = SECTION
NUMBER
Y = SHEET NUMBER
EXISTING PARTITION
DEMOLISHED PARTITION
INTERIOR ELEVATION
MARK
X = ELEVATION NUMBER
Y = SHEET NUMBER
X
YY.Y
X
YY.Y
X
STEEL
CONCRET
E
ALUMINU
M
BRICK
WOOD
(FINISHED)
COMPACTED GRAN.
FILL
BATT
INSULATION
GYPSUM WALL
BOARD
(SMALL SCALE)
CONTINUOUS
WOOD
BLOCKING
HATCH INDICATIONS SHOWN AS GUIDE ONLY; HATCHING SCALES MAY NEED TO BE MODIFIED DEPENDING UPON SCALE USED
MATERIALS INDICATION
NON-
CONTINUOUS
WOOD BLOCKING
EARTH
GYPSUM WALL
BOARD
(LARGE SCALE)
PLYWOO
D
RIGID
INSULATION
SAND
PRECAS
T
ASPHAL
T
XX
X
X
YY.Y
X
YY.Y
Office of Facilities
Management
Project Number
Building Number
Drawing Number
DrawnCheckedDate
Location
Project TitleDrawing Title
ARCHITECT/ENGINEERS:
VA Project #
CONSULTANTS:
Revisions: Date:
VA FORM 08-6231 OCT 1978
on e ei gh th in ch o ne fo ot qu ar te r th re ig ht s on e h al f i nc h f oo t th re qu ar te rs
6" on e i nc h f oo t
6" a nd h al f
6" th re e i nc he s f oo t
6" 6"
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
SHEET INDEX
Approved: Medical Center Director
Approved: Facilities Management Dir.
42-Addition
1 Memorial Dr. STE 1800 Saint Louis, MO 63102
Tel Fax
314.621.4343 314.621.0261
220 N College Ave Indianapolis, IN 46202
Tel Fax
317.464.9090 317.464.9393
McComas Engineers 1717 E 116th Street Carmel, IN 46032
Tel Fax
317.580.0402 317.582.0766
Structural
Asaturian Eaton & Assoc.
1440 Old West Main Carbondale, IL 62901
Tel Fax
618.529.3414 618.529.3423
Civil
John A Jurgiel & Assoc.
123 N. Main Street St. Charles, MO 63301
Tel Fax
636.757.3060 636.757.3064
Industrial Hygenist
Heapy Engineering 1400 W. Dorothy Lane Dyton OH 45409
Tel Fax
618.529.5262
Electrical
VA
Department of Veterans Affairs
Medical Center, VISN 15 Marion, IL
INTEGRATED PROJECT TEAM APPROVAL
SIGNATURES
COR, MARION VAMC
SAFETY, MARION VAMC
VA POLICE, MARION VAMC
INFECTION PROVENTION, MARION VAMC
PATIENT SAFETY, MARION VAMC
MENTAL HEALTH, MARION VAMC
WOMEN VETERANS PROGRAM MANAGER, MARION VAMC
INFORMATION SECURITY OFFICER, MARION VAMC
ENERGY ENGINEER, MARION VAMC
PRIVACY OFFICER, MARION VAMC
STRATEGIC PLANNER, MARION VAMC
ENVIROMENTAL MANAGMENT / INTERIOR DESIGN, MARION VAMC
OFFICE OF INFORMATION AND TECHNOLOGY, MARION VAMC
NURSING SERVICE, MARION VAMC
LOGISTICS, MARION VAMC
CHIEF OF ENGINEERING, MARION VAMC
ASSOCIATE DIRECTOR PATIENT CARE SERVICES, MARION VAMC
CHIEF OF STAFF, MARION VAMC
DIRECTOR, MARION VAMC
ASSOCIATE DIRECTOR, MARION VAMC
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
DATE
11/7/2019 15:39:33
Expand & Upgrade Building 42 for Laboratory 657-502
657-502Expand & Upgrade Building
42 for Laboratory
11-08-2019 RD AJS
G000 Marion, IL
Cover
Bid Documents
Campus Map
NOT TO SCALE
Location Map
NOT TO SCALE
ED100 Partial Lower Level - Demolition Plan
EL100 Lower Level Floor Plan - Lighting
EL101A Partial Lower Level Floor Plan - Lighting
EL101B Partial Main Level Floor Plan - Lighting
EL102 Interstitial Level Floor Plan - Lighting
EL103 Roof Plan
EP100 Lower Level Floor Plan - Power
EP101A Partial Main Level Floor Plan - Power
EP101B Partial Main Level Floor Plan - Power
EP102 Interstitial Level Floor Plan - Power
ES100 Partial Site Plan
ES101 Partial Site Plan - Technology
ES102 Primary Duct Bank Profile
ET100 Lower Level Floor Plan - Technology
ET101A Partial Main Level Floor Plan - Technology
ET101B Partial Lower Level Floor Plan - Technology
ET102 Interstitial Level Floor Plan - Technology
ET200 Building Plans - Bldg 1, Bldg 2, Bldg 27, Bldg
ET300 Tunnel Level Building 42 - Technology
MQ-011 Mechanical Details
DM-101 Tunnel Mechanical Demo
MH-101 Lower Level - HVAC Duct Plan
MH-102 First Floor - HVAC Duct Plan
MH-103 Second Floor Mezzanine - HVAC Duct Plan
MH-104 First Floor - Return & Exhaust Plan
MH-105 Second Floor Mechanical - Return Duct Floor Plan
MH-106 HVAC Isometric
MP-101 Lower Level - HVAC Piping
MP-102 First Floor - HVAC Piping
MP-103 Second Floor Mezzanine -HVAC Piping
MP-201 Mechanical Roof Plan
Plumbing
FP-001 First Floor - Fire Protection Floor Plan
FP-101 Second Floor Mezzanine - Fire Protection Floor Plan
PQ-001 Plumbing Schedules & Abbreviations
PQ-002 Plumbing Details
PQ-003 Plumbing Details
PQ-004 Plumbing Details
PL-101 Lower Level - Sanitary
PL-102 Lower Level Plumbing - Storm Plan
PL-103 First Floor - Sanitary
PL-104 Second Floor - Mezzanine
PL-201 Roof Plan
PL-301 Isometrics
PP-201 Lower Level - Piping Plan
PP-202 First Floor Demstic - Piping Plan
PP-203 Second Floor Mezzanine Domestic - Piping Plan
PP-301 Piping Isometric
Electrical
E001 Legend, Symbols & Index of Drawings
E401 Enlarged TR Room Plan
E501 Details
E502 Details
E503 Details
E601 Schedules
E601A Lighting Schedule
E601B Lighting Schedule
S602 BLDG 42 Distribution Diagram
E603 Primary Single Line Diagram
E604 Site Photographs
E605 Main Level Plan - Electric Room
E606 Panel Schedules
Architectural
AD101 Main Level Demolition Plan
AD102 Existing Roof Demolition Plan
A001 Architectural Site Plan
A100 Overall Lower Level Plan
A101 Overall Ground Floor Plan
A101A Partial First Floor Plan - North
A101B Partial First Floor Plan - South
A102 Overall Interstitial Level Floor Plan
A103 Overall Roof Plan
A120 Enlarged Restroom Plan and Interior Elevations
A200 Exterior Elevations
A201 Exterior Elevations
A300 Building Sections
A301 Building Sections
A350 Vertical Circulation
A351 Vertical Circulation
A400 Overall Lower Level Reflected Ceiling Plan
A401 Overall First Floor Reflected Ceiling Plan
A402 1st Floor Interstitial & 2nd Floor/Roof RCP
A500 Wall Sections
A501 Wall Sections
A510 Enlarged Sections
A520 Plan Details
A521 Plan Details
A550 Details
A551 RCP Details
A552 Sign Schedule & Details
A600 Interior Elevations
A601 Interior Elevations
A650 Casework Details
A700 Opening Schedules & Details
A701 Partition Types
A800 Overall First Floor Room Finish Plan
A850 First Floor Equipment Plan & Schedule
Mechanical
MQ-001 Mechanical Notes & Abbreviations
MQ-002 Mechanical Schedules
MQ-003 Mechanical Schedules
MQ-004 Mechanical Details
MQ-005 Mechanical Details
MQ-006 Mechanical Details
MQ-007 Mechanical Details
MQ-008 Mechanical Details
MQ-009 Mechanical Details
MQ-010 Mechanical Details
General
G000 Cover
G001 Life Safety Plan & Code Analysis
G002 General Info / Accessibility
Civil
V101 Partial Topographical Survey
CD100 Site Demolition Plan and Existing Building Tunnel Plan
CS100 Site Plan and Site Keyed Notes
CS101 Site Dimensioning Plan
CS102 Guildeline Erosion and Sediment Control Plan
CS104 Site Details Cont.
CS103 General Notes and Site Details
CS105 Site Abbreviations and Symbols
CG100 Site Grading Plan
CU100 Site Utility Plan
CU101 Site Utility Details
SL100 Site Lighting
CT100 Traffic Control
Structural
S101A Foundation Plan - North
S101B Foundation Plan - South
S201A Ground Floor Framing Plan - North
S201B Ground Floor Framing Plan - South
S202A Second Floor Framing Plan - North
S202B Second Floor Framing Plan - South
S203A Roof Framing Plan - North
S203B Roof Framing Plan - South
S204 Partial Framing Plans
S301 Building Sections
S302 Building Sections
S303 Building Sections
S401 General Notes Schedules and Abbrev
S402 Schedules
S403 Slab on Grade Details, Foundation & Framing Legends
S404 Schedules
S405 Typical Sections
S406 Typical Sections
S407 Sections & Details
S420 Special Inspections
S501 Framing Elevations
S502 Framing Elevations
S503 Framing Elevations
S504 Framing Elevations
S600 Model Views
In e r s ta te
PROJECT SITE
Sections & DetailsS408
DN
DN
UP
DN
DN
UP
Stair/Elev Vestibule
Corridor
60'-0"130'-0"
76'-0"
110'-0"
149'-0"
DN
100'-0"
Waiting
Break Room
ADA Toilet
Pyxis Storage
PSA
Shared Office
Open OfficeOffice P. Toilet
P. Toilet
HAC
OfficeShared OfficeOffice
Station Station Station Station Station
Conference Room
Main Lab Microbiology
Bio-Safety Level 3
Histology
Corridor
Blood BankAcid/Base Cooler
E018A
Open to below
2-hr spray on fire proofing for all load bearing structure per spec. All deck penetrations to meet 2-hr. The seismic bracing does not require a rating.
Line of floor above
Unfinished Basement
Elevator
Stair/Elev Vestibule
Tunnel Access
Elevator Machine
Room
:2
DN
S lo p e D n
Existing Ramp DownExisting Tunnel
Corridor Temporary
Corridor
2-hr spray on fire proofing for all load bearing structure per spec. All deck penetrations to meet 2-hr. The seismic bracing does not require a rating.
PROJECT DESCRIPTION:
NO. OF STORIES AT OR ABOVE GRADE
NO. OF STORIES BELOW GRADE
BUILDING HEIGHT
BUILDING AREA
LOWER LEVEL
MAIN LEVEL
SECOND LEVEL
THIRD LEVEL
AUTOMATIC SPRINKLER SYSTEM
APPLICABLE CODES:
2009 INTERNATIONAL BUILDING CODE
2009 INTERNATIONAL MECHANICAL CODE
2009 INTERNATIONAL PLUMBING CODE
2015 INTERNATIONAL ENERGY & CONSERVATION CODE
2006 NATIONAL ELECTRICAL CODE
NFPA 101, LIFE SAFETY CODE
AMERICANS with DISABILITY ACT (ADA) - ICC/ANSI 117.1-2009
ILLINOIS ACCESSIBILTY CODE
TYPE OF CONSTRUCTION, BUILDING HEIGHT & AREA:
CONSTRUCTION TYPE (IBC CHAPTER 6)
ALLOWABLE HEIGHT (IBC TABLE 503 AND SECTION 504)
ALLOWABLE AREA (IBC TABLE 503)
26'-2" TO 52'-0"
APPROX 21,127 SF
APPROX 1,516 SF
APPROX 10,841 SF
APPROX 8,802 SF
APPROX 452 SF
FULLY SPRINKLERED
TYPE IIA
5 STORIES/65'-0"
37,500 SF
CODE DATA
GROUND SNOW LOAD= 15 psf
WIND SPEED = 90 MPH
SEISMIC DESIGN CATEGORY = D
OCCUPANCY CATEGORY = I2
FROST LINE DEPTH = 30"
DESIGN PARAMETERS:
OCCUPANCY CLASSIFICATION:
PRIMARY OCCUPANCY CLASSIFICATIONS (IBC CHAPTER 3)
INSTITUTIONAL - I2
OCCUPANCY LOAD CALCULATION:
BUSINESS = 100 GROSS SQFT PER PERSON
ASSEMBLY - UNCONCENTRATED = 15 NET PER PERSON
MECHANICAL = 300 GROSS SQFT PER PERSON
LOWER LEVEL:
MECHANICAL = 100 SQFT /300 = 1 occ BUSINESS = 2000 SQFT /100 = 20 occ
MAIN LEVEL:
ASSEMBLY = 508 SQFT /15net = 34 occ BUSINESS = 9,095 SQFT /100 = 91 occ
SECOND LEVEL:
MECHANICAL = 8678 SQFT /300 = 29 occ
TOTAL OCCUPANTS = 175 OCCUPANTS
EGRESS EXIT CALCULATION:
LOWER LEVEL:
(1) EXIT STAIRS PROVIDED
EGRESS LOAD = 7 occ x 0.3" = 2.1" STAIR WIDTH REQUIRED
EGRESS PROVIDED = MAIN STAIR = 48" (46" CLEAR BETWEEN HANDRAILS)
TOTAL WIDTH PROVIDED = 46"
MAIN LEVEL:
ASSEMBLY = 35 occ / 0.2" = 7" BUSINESS = 82 occ / 0.2" = 18.4"
EGRESS PROVIDED = 127B = 72" WIDE DOORS (68" CLEAR)
130B = 36" WIDE DOOR (33" CLEAR)
TOTAL WIDTH PROVIDED = 101"
Exit Enclosure
Wall Rating Legend
Smoke Partition
100/person
Capacity of Space
Occupancy Formula Used
Allowable Capacity of Exit (Door size minus 4"/.2)
Egress Number
Smoke Barrier
Purpose
2 hour
1 hour
Rating
2 layers/ both sides
1 layer / one side
1 layer/ both sides
Gyp.
Yes
No
Yes
Dampers
Stair and Elevator Shaft
Location
Separation btwn Lab and Phelbot/Admin
Main corridor separation
Waiting @ 15 sf/occupant
Non Occupied Space
I2 Occupancy @ 100 sf/occupant
Legend
Fire Extinguisher Cabinet
D N
Roof Below
92'-0"
98'-0"
Mechanical Equipment - See MEP drawings
Open to Below
2-hr spray on fire proofing for all load bearing structure per spec. All deck penetrations to meet 2-hr. The seismic bracing does not require a rating.
Underside of metal decking to receive 1-hr spray on fire proofing per spec.
2-hr spray on fire proofing for all load bearing structure per spec.
A200 Open to below
D N
Underside of metal decking to receive 1-hr spray on fire proofing per spec.
2-hr spray on fire proofing for all load bearing structure per spec.
Roof
Drawing Title Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
42-AdditionApproved: Associate Director
Approved: Chief of Staff
Approved: Chief Engineer
Approved: Infection Control
Approved: Safety Officer
Approved: Chief, Police & Security o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
1 Memorial Dr. STE 1800 Saint Louis, MO 63102
Tel Fax
314.621.4343 314.621.0261
220 N College Ave Indianapolis, IN 46202
Tel Fax
317.464.9090 317.464.9393
Office of Facilities
ManagementMcComas Engineers 1717 E 116th Street Carmel, IN 46032
Tel Fax
317.580.0402 317.582.0766
Structural
Asaturian Eaton & Assoc.
1440 Old West Main Carbondale, IL 62901
Tel Fax
618.529.3414 618.529.3423
Civil
John A Jurgiel & Assoc.
123 N. Main Street St. Charles, MO 63301
Tel 636.757.3060 636.757.3064
Industrial Hygenist
Heapy Engineering 1400 W. Dorothy Lane Dyton OH 45409
Tel 618.529.5262
Electrical
11/7/2019 15:39:40
Life Safety Plan & Code Analysis Expand & Upgrade Building 42 for Laboratory
G001
657-502
Marion, IL
11-08-2019
Bid Documents
RD AJS
N
3/32" = 1'-0"1 Ground Floor Life Safety N
3/32" = 1'-0"2 Basement Life Safety
N
3/32" = 1'-0"3 1st Floor Interstitial Level Life Safety 3/32" = 1'-0"4 Partial 2nd Floor (Roof) Life Safety Plan
NOTE:
PROJECT-STANDARD PLACEMENT
SWITCH, THERMOSTAT,
HORN/STROBE
FLOOR
CEILING
OPTIONAL LOCATION, F.A.
HORN/STROBE (WHEN OCCURS)
EDGE OF DOOR FRAME
CL
NOTE:
F.A. HORN/STROBE PREFERRED
INSTALLATION IS AT CEILING
LIGHT SWITCH
THERMOSTAT
CL
CL
8" MIN. - 12" MAX
3'
CL
CL
POWER/COMM RECEPTACLE
1'
8" MIN.
6" MAX.
M
IN
M
IN
4'-0"
CLEAR FLOOR SPACE
AT LOWER UNIT
M A
X
CLEARANCES FOR DOORS IN SERIES
4'-0" 4'-0"
1'-6"
1'-0"
W/ LATCH
& CLOSER
4'-6" MIN.
M
IN
W/ LATCH
& CLOSER
M
IN
(I F
A
3'-0" MIN. (THEN, A)
M
IN
(I F
B
3'-6" MIN. (THEN, B)
MIN.
2'-0"
W
C L
O S
E R
M
IN
MIN.
2'-0"
W /C
L O
S E
R
PULL SIDE PUSH SIDE
NO MAX.
M
A X
4" MAX.
M
IN
M
IN
1'-9"
M A
X . H
E
IG
H
F
O R
A C
C E
S S
IB
LE
O
R A
G
A
C E
S
M
IN
M A
X
1'-9"
MAX.
10" MIN.
MAX.
OF SHELVES
WHEN WHEEL CHAIR DISTANCE IS >10", ABOVE HEIGHTS APPLY
TOILET PAPER
DISPENSER
WATER CLOSET URINAL GRAB BAR
(BACK)
PAPER TOWEL
DISPENSER & TRASH
RECEPTACLE
TRASH
RECEPTACLE
SEAT COVER
DISPENSER
NAPKIN
DISPENSER
NAPKIN
DISPOSAL
LAVATORY
M
A X
M
IN
M
IN
H
.C
HIGHEST POINT
OF OPERATION
M
IN
. K N
E E
C
LE
A R
A N
C E
T O
P O
F R
IM
TOP OF
REFLECTIVE
SURFACE
BOTTOM OF
REFLECTIVE
SURFACE
FLUSH CONTROL
44" MAX.
TOP OF
RIM
3'-0" MIN
Top of Bar
GRAB BAR
(SIDE)
42" MIN 12" MAX
M
IN
39"-41"
F I R E
E X T I N G U I S H E R
FULLY RECESSED FIRE
EXTINGUISHER CABINET BY
LARSON OR SIM. - RE: PLAN
FLOOR PLAN FOR LOCATIONS
/2
M A
X
X
(2) METAL STUDS ON
EACH SIDE OF CABINET
DASHED LINE INDICATES
GYPSUM BOARD WHERE
OCCURS - RE: FLOOR PLAN
AND PARTITION TYPES FOR
ADDITIONAL INFO.
METAL STUD PARTITION -
RE: FLOOR PLAN AND
PARTITION TYPES FOR
ADDITION INFO.
GWB - PAINTED
SOUND INSULATION
WHERE OCCURS -
RE: FLOOR PLAN
AND PARTITION
TYPE FOR
LOCATION
PLAN VIEW
ELEVATION
SEMI RECESSED FIRE
EXTINGUISHER CABINET
BY LARSON OR SIM. - RE:
PLAN FLOOR PLAN FOR
LOCATIONS
CLEAR ACRYLIC DOOR
GLAZING - TYP
DIE CUT LETTERING - TYP
DOOR HARDWARE BY
CABINET MANUF.
A
F F
NOTE:
FIRE EXTINGUISHER
CABINET TO MEET ALL
ADA REQUIREMENT.
CONTRACTOR TO
REFER TO LIFE SAFETY
PLANS FOR LOCATION
OF CABINETS. REFER
TO SPECIFICATION FOR
ADDITIONAL INFO.
P-TYPE;
RE: PLAN
/4
1-hr rated partition; provide an interior layer of 1/2" Type X GWB with 3M Fire Barrier Moldable Putty Pads top and bottom of cabinet or provide a rated cabinet equal to wall rating
Drawing Title Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
42-AdditionApproved: Associate Director
Approved: Chief of Staff
Approved: Chief Engineer
Approved: Infection Control
Approved: Safety Officer
Approved: Chief, Police & Security o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
1 Memorial Dr. STE 1800 Saint Louis, MO 63102
Tel Fax
314.621.4343 314.621.0261
220 N College Ave Indianapolis, IN 46202
Tel Fax
317.464.9090 317.464.9393
Office of Facilities
ManagementMcComas Engineers 1717 E 116th Street Carmel, IN 46032
Tel Fax
317.580.0402 317.582.0766
Structural
Asaturian Eaton & Assoc.
1440 Old West Main Carbondale, IL 62901
Tel Fax
618.529.3414 618.529.3423
Civil
John A Jurgiel & Assoc.
123 N. Main Street St. Charles, MO 63301
Tel 636.757.3060 636.757.3064
Industrial Hygenist
Heapy Engineering 1400 W. Dorothy Lane Dyton OH 45409
Tel 618.529.5262
Electrical
11/7/2019 15:39:43
General Info / Accessibility Expand & Upgrade Building 42 for Laboratory
G002
657-502
Marion, IL
11-08-2019
Bid Documents
RD AJS
1/2" = 1'-0"2 DETAIL - TYP. MOUNTING LOCATIONS
1/4" = 1'-0"4
FLOOR CLEARANCE @ DRINKING
FOUNTAINS
1/8" = 1'-0"1 MANEUVERING CLEARANCES
1/4" = 1'-0"5 PROTRUDING HAZARDS
1/4" = 1'-0"6 SHELVES / CLOTHES ROD ADA
1/4" = 1'-0"3 STANDARD MOUNTING HEIGHTS
1 1/2" = 1'-0"7 DETAIL - FIRE EXTINGUISHER CABINET
Project General Notes
BE ALL NEW VERTICAL AND HORIZONTAL DUCTS, PIPES, CONDUITS, ETC., IN FINISHED ROOMS
OR AREAS THROUGHOUT BUILDING, NOT ENCASED IN MASONRY OR CONCRETE
CONSTRUCTION, SHALL BE ENCLOSED IN METAL STUDS AND DRYWALL CHASE WALLS AS
DETAILED IN THE DRAWINGS AND FINISHED TO MATCH THE ROOM FINISH.
BF WORK THAT MUST OCCUR IN OCCUPIED AREAS OF THE MEDICAL CENTER OR DISRUPT A
MEDICAL CENTER FUNCTION, WILL BE DONE AT TIMES OTHER THAN NORMAL WORKING
HOURS AT NO ADDITIONAL COST TO THE GOVERNMENT. WORK MUST BE SCHEDULED
WITH THE VA PROJECT ENGINEER.
BG CONTRACTOR SHALL NOT INSTALL CONDUIT, PIPING, LIGHTING, OR OTHER OBSTRUCTIONS
UNDER ADJACENT HVAC EQUIPMENT THAT WILL ELIMINATE OR OBSTRUCT ACCESS TO
COILS, MOTORS, VALVES, SWITCHES, PANELS, ETC.
BH BEFORE THE CONTRACTOR BEGINS WORK CONTRACTOR SHALL RECORD ANY EXISTING
SYSTEM INFORMATION SUCH AS TEMPERATURE, FLOW RATE, PRESSURE, CURRENT,
VOLTAGE, OR ANY OTHER INFORMATION NECESSARY FOR HIM TO RETURN THE AFFECTED
SYSTEM TO ORIGINAL OPERATING CONDITION. UNLESS NOTED OTHERWISE IT IS ASSUMED
THAT ALL SYSTEMS (HVAC, ELECTRICAL, PLUMBING, ETC.) ARE WORKING PROPERLY IN
EVERY MANNER AT THE BEGINNING OF THE PROJECT. THE CONTRACTOR'S RECORDED
MEASUREMENTS MUST BE SUBMITTED TO THE PROJECT ENGINEER FOR REVIEW AND
ACCEPTANCE BEFORE ANY DEMOLITION OR OTHER RELATED WORK CAN PROCEED.
BI THE CONTRACTOR WILL BE RESPONSIBLE FOR MAINTAINING ALL EXISTING ACCESS DOORS
TO CONSTRUCTION AREAS, EXISTING MECHANICAL AND ELECTRICAL AREAS, ASSIGNED
STORAGE AREAS, EQUIPMENT ACCESS AREAS, ETC. DOORS MUST BE RESTORED TO THE
CONDITION ENCOUNTERED AT BEGINNING OF PROJECT. THIS INCLUDES DOOR
REPLACEMENT, HARDWARE REPLACEMENT, HARDWARE REPAIR, DOOR REPAIR, ETC.
BJ CONTRACTOR MUST PROVIDE HIS OWN EQUIPMENT FOR MOVING OF MATERIALS,
EQUIPMENT AND TRASH. THIS INCLUDES CARTS FOR REMOVAL OF DEMOLITION
MATERIALS, PALLET JACKS FOR EQUIPMENT MOVING, TWO OR FOUR WHEEL CARTS FOR
EQUIPMENT TRANSFER, ETC. CONTRACTOR MAY NOT BORROW VA OWNED EQUIPMENT
FOR THIS PURPOSE.
BK SEVERE NOISE PRODUCING WORK WILL NOT BE ALLOWED DURING NORMAL WORKING
HOURS AND MUST BE SCHEDULED WITH THE VA PROJECT ENGINEER FOR OTHER TIMES.
THIS INCLUDES JACK-HAMMERING CONCRETE, SAW-CUTTING CONCRETE, REPETITIVE
HAMMER DRILLING OF CONCRETE, ETC.
BL THE VA DOES NOT PROVIDE PHONES FOR THE CONTRACTOR’S USE. IT IS THE
CONTRACTOR’S RESPONSIBILITY TO COVER THE COSTS OF THE INSTALLATION OF A
TEMPORARY LAND LINE PHONE. THE CONTRACTOR SHALL CONTACT THE PHONE
COMPANY TO HAVE THIS PHONE INSTALLED.
BM ALL ELECTRICAL CIRCUITRY TO BE CONCEALED UNLESS OTHERWISE SPECIFIED.
CIRCUITING FOR ELECTRIC DOOR HOLD OPENS IN MASONRY WALLS SHALL BE SURFACE
RACEWAY.
BN DRAWINGS ARE DIAGRAMMATIC AND SHOW ONLY THE GENERAL ARRANGEMENT OF EACH
SYSTEM. BECAUSE OF SMALL SCALE OF DRAWINGS IT IS NOT POSSIBLE TO SHOW OR
INDICATE ALL BRANCHES, OFFSETS, FITTINGS, BOXES, AND ACCESSORIES WHICH MAY BE
REQUIRED. CONTRACTOR MUST CAREFULLY INVESTIGATE STRUCTURAL AND FINISH
CONDITIONS AFFECTING ALL WORK, FURNISHING SUCH FITTINGS, TRAPS, VALVES, BOXES,
ACCESSORIES, ETC., AS MAY BE REQUIRED.
BO LOCATIONS OF NEW EQUIPMENT, PIPING, AND ASSOCIATED ITEMS SHOWN ON THE
DRAWINGS ARE SCHEMATIC ONLY. THE CONTRACTOR SHALL FIELD VERIFY EXACT
LOCATION AND ELEVATION FOR ALL WORK, INCLUDING CONNECTIONS TO EXISTING WORK.
ALL OFFSETS, FITTINGS, TRANSITIONS, EXTENSIONS, ETC., REQUIRED FOR A COMPLETE
AND FUNCTIONAL SYSTEM SHALL BE PROVIDED AT NO ADDITIONAL COST.
BP ALL EXISTING DUCTWORK, ELECTRICAL OR MECHANICAL PIPING, CABLE TRAYS, ETC., IS
NOT NECESSARILY SHOWN ON THE DRAWINGS. PRIOR TO ANY DEMOLITION AND
CONSTRUCTION WORK, THE CONTRACTOR SHALL FIELD VERIFY THE EXACT LOCATION OF
ALL EXISTING EQUIPMENT, DUCTWORK, PIPING, ETC. AND REPORT ANY DISCREPANCIES TO
THE COR.
BQ IF THERE IS ANY WORK TO BE DONE ON EXISTING ROOFS, SUCH AS ROOF PENETRATIONS
OR STANDS, OR ANYTHING THAT DAMAGES THE INTEGRITY OF THE ROOF, THIS WORK
MUST BE DONE BY A CONTRACTOR LICENSED BY THE ROOFING MEMBRANE
MANUFACTURER. HE/SHE MUST BE APPROVED BY THE MEMBRANE MANUFACTURER SO AS
TO NOT VOID OR INTERRUPT EXISTING SINGLE PLY MEMBRANE ROOF WARRANTIES.
BR IF ASBESTOS INSULATION IS REMOVED ON THIS PROJECT ALL PIPING AND OTHER
MECHANICAL ITEMS THAT HAD THE ASBESTOS INSULATION REMOVED MUST BE
RE-INSULATED WITH MATERIALS ACCORDING TO THE SPECIFICATIONS.
BS WHEN WORKING IN OCCUPIED AREAS OF THE MEDICAL CENTER THE CONTRACTOR
CANNOT LEAVE TOOLS, EQUIPMENT, LADDERS, ETC., UNATTENDED WHERE THEY ARE
ACCESSIBLE TO PATIENTS, STAFF, VISITORS, ETC. CEILING TILES AND CEILING ACCESS
PANELS MUST ALSO BE REPLACED WHEN UNATTENDED, FOR SAFETY REASONS.
BT WATER OR LIQUIDS MUST NOT BE ALLOWED TO COME INTO CONTACT WITH NEW OR
EXISTING DRYWALL FROM CONSTRUCTION RELATED ACTIVITIES. REMOVE AND REPLACE
ANY DRYWALL THAT HAS COME INTO CONTACT WITH WATER OR OTHER LIQUIDS.
BU LIVE ELECTRICAL CIRCUITS ARE BURIED WITHIN THE CONCRETE FLOOR SLABS AND THERE
IS NO RECORD OF THE EXACT LOCATIONS. THE CONTRACTOR SHALL X-RAY THE FLOOR
WHEREVER THE CONTRACTOR PLANS ON DRILLING THROUGH THE CONCRETE FLOOR
SLABS. IT WILL BE THE CONTRACTOR'S RESPONSIBILITY TO IMMEDIATELY REPAIR ANY
CIRCUIT THAT HAS BEEN CUT OR DAMAGED.
BV WHEN AN EXIT IS CLOSED BECAUSE OF THIS PROJECT THE CONTRACTOR MUST INSTALL
BARRICADES AND SIGNAGE AT THE EXIT DOOR. THE CONTRACTOR MUST ALSO COVER OR
REMOVE THE LIGHTED EXIT SIGN.
BW CONTRACTOR SHALL PROVIDE BOXES, CONDUIT, WIRE, AND RECONNECTIONS AS
REQUIRED TO RECONNECT ANY AND ALL EXISTING LIGHT FIXTURES, RECEPTACLES, OR
DEVICES REMAINING IN USE. REMOVAL OF ANY ELECTRICAL EQUIPMENT SHALL NOT
AFFECT THE OPERATION OF EQUIPMENT REMAINING IN USE.
BX CONTINUITY OF ALL SERVICES TO AND FROM THE FACILITIES IN THE EXISTING BUILDING
SHALL BE MAINTAINED WITHOUT INTERRUPTION, EXCEPT FOR SUCH PERIODS OF TIME
WHICH THE V.A. MAY DESIGNATE. IF TEMPORARY CONNECTIONS, ETC. ARE NECESSARY TO
ASSURE THE CONTINUITY OF SERVICE, THEY SHALL BE FURNISHED WITHOUT ADDITIONAL
CHARGE TO THE V.A. AND SHALL BE REMOVED WHEN NO LONGER NECESSARY.
BY ALL EXISTING CONDUIT AND WIRING MADE ABANDONED BY THIS PROJECT OR FOUND TO
BE ABANDONED DURING DEMOLITION SHALL BE REMOVED.
BZ COORDINATE THE PROVISION AND INSTALLATION OF ALL CONTROL WIRING FOR
MECHANICAL EQUIPMENT WITH THE GENERAL CONTRACTOR AND MECHANICAL
CONTRACTOR.
CA FOR SAFETY PURPOSES THE CONTRACTOR WILL NOT WORK ON ANY ELECTRICAL
EQUIPMENT HOT. ALL SHUTDOWNS WILL BE SCHEDULED IN ADVANCED WITH THE VA.
CB CONTRACTOR SHALL BE RESPONSIBLE FOR ALL OPENINGS REQUIRED IN WALLS. ALL
OPENINGS SHALL BE REPAIRED TO MATCH EXISTING BY A QUALIFIED CONTRACTOR AT THE
EXPENSE OF THIS CONTRACTOR. ALL CONDUITS IN WALLS SHALL BE GROUTED OR
SEALED INTO OPENINGS.
CC CONTRACTOR SHALL COORDINATE ‘IN-WALL’ & ‘OVERHEAD CEILING’ INSPECTIONS WITH VA
PROJECT ENGINEER PRIOR TO THE INSTALLATION OF FINISHES. IN-WALL INSPECTIONS
REQUIRE 24 HOUR NOTIFICATION. OVERHEAD CEILING INSPECTIONS REQUIRE 48 HOUR
NOTIFICATION. CONTRACTOR TO SUPPLY A CART WITH A LOG SHEET AND FULL SET OF
HARD COPY DRAWINGS FOR ALL INSPECTIONS. LOG SHEET SHALL BE ITEMIZED BY TYPE
OF INSPECTION AND BY ROOM. NO SUCH FINISHES SHALL BE INSTALLED WITHOUT
INSPECTION APPROVAL FROM PROJECT ENGINEER.
CD FOR ANTICIPATED CONSTRUCTION SEQUENCE SEE DRAWING 1 / 1-1A-100 FOR MORE
INFORMATION.
CE FOR ALTERNATE DEDUCTION BID LIST ITEMS SEE SHEETS 1-1A-100, 1-1A-101, 1-1A-102
Project General Notes
AA PHASE ALL DEMOLITION & CONSTRUCTION TO BE SEQUENCED & COORDINATED TO INSURE
THAT THE BUILDING OWNER'S OPERATIONS ARE CONTINUOUSLY MAINTAINED.
AB THESE PLANS REFLECT INFORMATION GATHERED FROM EXISTING CONDITIONS DRAWINGS
& ARCHITECT'S FIELD VERIFICATION. CONTRACTOR SHALL VERIFY ACCURACY OF
INFORMATION PRIOR TO COMMENCEMENT OF ANY DEMOLITION AND /OR CONSTRUCTION
ACTIVITIES AND REPORT ANY DISCREPANCIES TO COR.
AC ITEMS TO BE DEMOLISHED, REMOVED, OR RELOCATED ARE SHOWN DASHED. EXISTING
ITEMS TO REMAIN SHALL BE PROTECTED DURING CONSTRUCTION BY CONTRACTOR.
PATCH & REPAIR ALL RESULTING SURFACES TO REMAIN.
AD COORDINATED ALL WORK BETWEEN TRADES AS REQUIRED TO INSURE TIMELY & PROPER
INSTALLATION OF ALL BUILDING SYSTEMS.
AE ACCESS TO EMPLOYEE ENTRY AND EXIT DOORS MUST BE MAINTAINED THROUGHOUT
CONSTRUCTION. PROVIDE ALL VA REQUIRED BARRIERS AND SIGNAGE AT THE LIMITS OF
THE CONSTRUCTION SITE
AF PROVIDE FULLY SEALED DUST PARTITIONS AS REQUIRED AT ALL LOCATIONS WHERE
CONSTRUCTION MEETS THE EXISTING BUILDING IN ORDER TO MAINTAIN A CLEAN
DUST-FREE ENVIRONMENT INSIDE THE BUILDING.
AG ALL GYPSUM BOARD USED IN THIS PROJECT SHALL BE TYPE "X"
AH CONTRACTORS SHALL VISIT THE SITE TO FAMILARIZE THEMSELVES WITH THE EXISTING
CONDITIONS AND INCLUDE THE WORK NECESSARY TO COMPLY WITH THE SCOPE OF THE
WORK. ADDITIONAL COMPENSATION WILL NOT BE CONSIDERED FOR EXTRA WORK WHEN
SUCH WORK COULD HAVE BEEN REASONABLY ASCERTAINED FROM THE PRE BID SITE
VISIT REVIEW OF THE EXISTING CONDITIONS AND THE WORK SCOPE DESCRIBED IN THE
DOCUMENTS.
AI COORDINATION OF ALL WORK AS DESCRIBED ON THE DOCUMENTS IS THE GENERAL
CONTRACTOR'S RESPONSIBILITY.
AJ PERFORM WORK IN ACCORDANCE WITH ALL APPLICABLE CODES, REGULATIONS, AND
ORDINANCES HAVING JURISDICTION
AK IMMEDIATELY REPORT DISCREPANCIES BETWEEN CONTRACT DOCUMENTS AND FIELD
CONDITIONS, CONFIRM THE WORK IS BUILDABLE AS SHOWN.
AL ALL DIMENSIONS ARE FROM COLUMN CENTER LINE TO FACE OF PARTITION U.O.N. UNDER
NO CIRCUMSTANCES SHALL ANY MEASUREMENT BE SCALED FROM THE DRAWINGS. ANY
MEASUREMENTS NOT GIVEN AN ACTUAL NUMBER DIMENSION SHOULD BE BROUGHT TO
THE ATTENTION OF THE ARCHITECTS BEFORE PROCEEDING
AM ALL WOOD USED IN THIS PROJECT SHALL BE FIRE-RETARDANT TREATED
AN ALL NEW PARTITIONS, UNLESS OTHERWISE SHOWN, SHALL BE 20 GA. MTL STUDS
AO COORDINATE & PROVIDE BLOCKING AS REQUIRED FOR MILLWORK & ITEMS ATTACHED OR
MOUNTED TO WALLS & CEILINGS
AP ALL INSULATING MATERIALS WITHIN WALLS & IN UNCONCEALED SPACES SHALL HAVE A
FLAME SPREAD INDEX OF NOT MORE THAN 25 AND A SMOKE-DEVELOPED INDEX OF NOT
MORE THAN 450
AQ ALL MATERIALS EXPOSED WITHIN PLENUMS ARE REQUIRED TO BE NON-COMBUSTIBLE OR
SHALL HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 25 AND A SMOKE DEVELOPED
INDEX OF NOT MORE THAN 50 AS DETERMINED IN ACCORDANCE WITH ASTM E-84
AR PROJECT LIMIT LINES INDICATES THE AREA OF A MAJORITY OF THE PROJECT WORK. BUT
SOME WORK WILL BE REQUIRED OUTSIDE OF THE PROJECT LIMITS. REFER TO DRAWINGS
AND SPECIFICATIONS FOR INFORMATION.
AS CONSTRUCTION MATERIALS AND INSTALLATION METHODS PROVIDED AND PERFORMED BY
ALL CONTRACTORS SHALL BE IN COMPLIANCE WITH VAMC FACILITY OPERATIONS, NFPA,
ICRA, ILSM, VA SPECIFICATIONS, AND AS FURTHER DESCRIBED IN THIS SCOPE.
AT PAINT ALL EXPOSED NEW AND EXISTING PIPING, CONDUIT, WIRE MOLD, ELECTRICAL
PANELS, ACCESS PANELS, ETC., TO MATCH WALL FINISH UNLESS OTHERWISE NOTED.
AU THE CONTRACTING OFFICER’S REPRESENTATIVE (COR) WILL PERFORM FIELD
VERIFICATION AS REQUIRED FOR THE DURATION OF THE PROJECT TO MONITOR PROJECT
PROGRESS.
AV UTILITY SHUT DOWNS WILL BE COORDINATED BY IPT (INTEGRATED PROJECT TEAM)
INCLUDING: COR, VA FACILITY OPERATIONS, AND GENERAL CONTRACTOR.
AW ANY INTEGRATED PROJECT TEAM MEMBER (IPT) INCLUDING BUT NOT LIMITED TO:
CONTRACTORS / SUB-CONTRACTORS, ARCHITECTS AND/OR ENGINEERS WHO ENTER THE
PROJECT BOUNDARY SHALL WEAR ALL PROPER PERSONAL PROTECTIVE EQUIPMENT
(PPE’S: CERTIFIED BY OSHA) AT ALL TIMES. SUCH PPE’S INCLUDE: HARD HATS, SAFETY
GLASSES, PROPER SHOES, HIGH VISIBILITY SHIRTS, ETC.
AX IF THE PROJECT AREA AND AREAS AFFECTED BY THE PROJECT INCLUDE EXISTING
EQUIPMENT, SURFACES, FINISHES, MATERIALS, ETC., NOT TO BE REMOVED, THE
CONTRACTOR MUST PROTECT THIS EQUIPMENT FROM DUST, DEBRIS, DAMAGE, ETC. THE
CONTRACTOR MUST ALSO CLEAN THESE ITEMS/SURFACES TO THE ORIGINAL CONDITION
FOUND AT THE START OF THE PROJECT PRIOR TO FINAL INSPECTION.
AY PATCH ALL FINISHES WHERE DISTURBED BY THE WORK AND WHERE UNFINISHED
SURFACES HAVE BEEN EXPOSED BY DEMOLITION. PATCHING MUST MATCH ADJACENT
MATERIALS, COLORS, AND FINISHES. WALL SURFACES THAT ARE PATCHED SHALL HAVE
THE FINISHES (PAINT, VINYL WALL COVERING, ETC.) REPLACED FROM CORNER TO CORNER
AND FLOOR TO CEILING.
AZ UNLESS OTHERWISE INDICATED, FINISH ALL NEW FRAMES AND PARTITIONS TO MATCH
SURROUNDING. NEW HOLLOW METAL DOORS SHALL BE PAINTED SAME COLOR AS
FRAMES. EXISTING PARTITIONS RECEIVING NEW DOOR FRAMES THAT HAVE VINYL WALL
COVERING (VWC) SHALL HAVE THE VWC COMPLETELY REMOVED AND REPLACED WITH
NEW VWC OF MATCHING TEXTURE AND COLOR.
BA CORRIDOR WALLS AND PLUMBING PARTITIONS SHALL BE CONSIDERED 1 HOUR FIRE /
SMOKE RATED WALLS AND NEW OR EXISTING PENETRATIONS MUST BE SEALED
ACCORDINGLY WITH UL APPROVED FIRE STOPPING MATERIAL THE SAME DAY THE
PENETRATION IS MADE OR DISCOVERED. ALL FLOOR SLABS, VERTICAL SHAFTS AND
STAIRWELLS SHALL BE CONSIDERED 2 HOUR FIRE / SMOKE RATED SEPARATIONS AND
SHALL BE SEALED ACCORDINGLY IN THE MANNER LISTED HEREIN. PENETRATIONS
THROUGH THE EXTERIOR WALLS SHALL BE SEALED WATERTIGHT.
BB IF EXISTING WALLS ARE TO BE USED AS DUST OR SMOKE BARRIERS SEPARATING THE
CONSTRUCTION AREA FROM THE MEDICAL CENTER, THE CONTRACTOR IS RESPONSIBLE
FOR SEALING ALL EXISTING PENETRATIONS IN THIS WALL, EXTENDING WALL TO CEILING
SLAB AND ANY OTHER WORK TO ENSURE THE WALL MEETS THE REQUIREMENTS IN THE
GENERAL REQUIREMENTS SPECIFICATIONS FOR CONSTRUCTION BARRIERS.
BC WHENEVER EXISTING EQUIPMENT, PIPING, DUCTS, ETC., ARE REQUIRED TO BE REMOVED,
SUCH REMOVAL SHALL INCLUDE ALL ANCHORS, HANGERS, FOUNDATIONS, ETC., UNLESS
NOTED OTHERWISE. AFTER REMOVAL; FLOORS, WALLS, AND CEILINGS SHALL BE FINISHED
TO MATCH ADJOINING SURFACES.
BD UTILITY WORK THAT WILL REQUIRE A SHUTDOWN OF EXISTING SERVICE WILL BE DONE AT
TIMES OTHER THAN NORMAL WORKING HOURS AT NO ADDITIONAL COST TO THE
GOVERNMENT. WORK MUST BE SCHEDULED WITH THE COR.
LAVATORY
LINEAR FEET
LINTEL
KNEE BRACE
LAV
LF
LNTL
KB
BD
BL
BLDG
BLKG
BOD
BR
BTWN
ACT
ADJ
ADJC
AFF
ALT
ALUM
ARCH
AVG
REFER TO THE MATERIAL LEGEND FOR ABBREVIATIONS RELATED TO FINISHES NOT HERE LISTED
BOARD
BLINDS
BUILDING
BLOCKING
BOTTOM OF DECK
BRICK
BETWEEN
ACOUSTIC CEILING TILE
ADJUSTABLE
ADJACENT
ABOVE FINISHED FLOOR
ALTERNATE
ALUMINUM
ARCHITECTURAL
AVERAGE
ON CENTER
OUTSIDE FACE
OPENING
OPPOSITE
OC
OF
OPNG
OPP
NIC
NOM
NTS
NOT IN CONTRACT
NOMINAL
NOT TO SCALE
R
RB
RD
REF
REINF
REQD
REV
RLG
RM
RO
RISER OR RADIUS
RUBBER BASE
ROOF DRAIN
REFERENCE
REINFORCED
REQUIRED
REVISION
RAILING
ROOM
ROUGH OPENING
P
PBD
PLAM, PL
PLBG
PLS
PR
PREF
PROP
PT
PTD
PTN
PWD
PAINT
PARTICLE BOARD
PLASTIC LAMINATE
PLUMBING
PLASTIC
PAIR
PREFINISHED
PROPERTY
PRESSURE TREATED
PAINTED
PARTITION
PLYWOOD
C
CAB
CB
CC
CG
CJ
CL
CLNG
CMU
COL
CONC
CONST
CONT
CP
CRT
CS
CSJ
CST
CT
CARPET
CABINET
CATCH BASIN
CONCRETE, COLORED
CORNER GUARD
CONTROL JOINT
CENTERLINE
CEILING
CONCRETE MASONRY UNIT
COLUMN
CONCRETE
CONSTRUCTION
CONTINUOUS
COMMUNICATIONS PANEL
CATHODE RAY TUBE
CONSTRUCTION JOINT
CONCRETE, SEALED
CONCRETE, STAINED
CERAMIC TILE
EA
EJ
ELECT
ELEV
EP
EQ
EQUIP
EWC
EXT
EXTG
EACH
EXPANSION JOINT
ELECTRICAL
ELEVATION
ELECTRICAL PANEL
EQUAL
EQUIPMENT
ELECTRIC WATER
COOLER
EXTERIOR
EXISTING
DEMOLITION
DIAMETER
DIMENSION
DOWN
DOOR
DOWNSPOU
T
DETAIL
DRAWING
DEMO
DIA
DIM
DN
DR
DS
DTL
DWG
MAS
MAT
MAX
MDF
MECH
MFR
MH
MIN
MIR
MISC
MO
MTD
MTL
MASONRY
MATERIAL
MAXIMUM
MEDIUM DENSITY FIBERBOARD
MECHANICAL
MANUFACTURER
MANHOLE
MINIMUM
MIRROR
MISCELLANEOUS
MASONRY OPENING
MOUNTED
METAL
T
TC
TEL
TGL
TJ
TS
TW
TYP
TREAD
TOP OF CONCRETE
TELEPHONE
TEMPERED GLASS LITE
TOP OF JOIST
TOP OF STEEL
TOP OF WALL
TYPICAL
VB
VCT
VERT
VIF
YARDYD
W
W/
WCL
WD
WDW
WF
WO
WPG
WIDTH
WITH
WATER CLOSET
WOOD
WINDOW
WIDE FLANGE
WITHOUT
WATERPROOFING
VINYL BASE
VINYL COMPOSITION TILE
VERTICAL
VERIFY IN FIELD
UF
UON
UR
UNFINISHED
UNLESS OTHERWISE NOTED
URINAL
JOINT
IF
INSUL
JT
HC
HD
HDBD
HDW
HDWD
HM
HOR
HR
HT
HWH
INSIDE FACE
INSULATION
HOLLOW CORE
HEAD
HARDBOARD
HARDWARE
HARDWOOD
HOLLOW METAL
HORIZONTAL
HANDRAIL
HEIGHT
HOT WATER HEATER
GRANITE
GAUGE
GLASS
GRADE
GROUT
GYPSUM WALLBOARD
G
GA
GL
GR
GT
GWB
FABRICATED
FAN COIL UNIT
FLOOR DRAIN
FOUNDATION
FIRE EXTINGUISHER CABINET
FINISH FLOOR
FINISH GRADE
FIRE HOSE CABINET
FINISH
FLOOR
FLASHING
FLOOR TILE
FIREPROOFING
FIRE RATING
FIBERGLASS REINFORCED PANEL
FLOOR SINK
FEET
FOOTING
FIRE TREATED WOOD
FABRIC WRAPPED PANEL
SC
SCH
SECT
SHTH
SIM
SK
SM
SOF
SPEC
SQ
SSM
SST
STD
STL
STR
SUSP
SW
SYS
SOLID CORE
SCHEDULE
SECTION
SHEATHING
SIMILAR
SINK
SHEET METAL
SOFFIT
SPECIFICATIONS
SQUARE
SOLID SURFACING MATERIAL
STAINLESS STEEL
STANDARD
STEEL
STRUCTURE
SUSPENDED
SLAT WALL
SYSTEM
FAB
FCU
FD
FDN
FEC
FF
FG
FHC
FIN
FLR
FLG
FLT
FPG
FR
FRP
FSK
FT
FTG
FTWD
FWP
ABBREVIATIONS LIST
File details come from the government source that posted it. Updated .