This document is a specification section outlining requirements for clearing and grubbing work on a construction project at Joint Base Andrews in Camp Springs, Maryland. It details preparation requirements including protecting roads, walks, trees, shrubs and existing facilities. It also specifies that trees, stumps, roots, brush and other vegetation are to be cut off flush with or below the original ground surface in clearing areas. Grubbing requirements include removing stumps, roots and matted roots to a depth of at least 18 inches below the original surface level. Disposal of excess materials must be in accordance with the approved solid waste management permit. All wood and wood-like materials from clearing and grubbing, except salable timber, will become the property of the contractor to dispose of as specified.
The related federal contract opportunity is a multiple award construction contract for large projects with the Naval Facilities Engineering Command. Offerors should refer to SAM.gov for the full solicitation, attachments and amendments under solicitation number N40080-23-R-0020.
View the file
Other files for this federal contract opportunity
Show all 50
N4008023R0020 LARGE PROJECTS MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-3002 Relocated HCP & EOD Proficiency Range eProjects # 1396650 Joint Base Andrews, Camp Springs, MD IFC, September 26, 2022
SECTION 31 11 00
CLEARING AND GRUBBING
11/18
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES.
1.2 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.
PART 2 PRODUCTS
2.1 MATERIALS
NOT USED
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Protection
3.1.1.1 Roads and Walks
Keep roads and walks free of dirt and debris at all times.
3.1.1.2 Trees, Shrubs, and Existing Facilities
Protect trees and vegetation to be left standing from damage incident to clearing, grubbing, and construction operations by the erection of barriers or by such other means as the circumstances require.
3.1.1.3 Utility Lines
Protect existing utility lines that are indicated to remain from damage.
Notify the Contracting Officer immediately of damage to or an encounter with an unknown existing utility line. The Contractor is responsible for the repair of damage to existing utility lines that are indicated or made known to the Contractor prior to start of clearing and grubbing operations. When utility lines which are to be removed are encountered within the area of operations, notify the Contracting Officer in ample time to minimize interruption of the service. Refer to Section 01 30 00 ADMINISTRATIVE REQUIREMENTS and Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for additional utility protection.
SECTION 31 11 00 Page 1
3.2 CLEARING
Clearing consists of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Clearing also includes the removal and disposal of structures that obtrude, encroach upon, or otherwise obstruct the work. Cut off flush with or below the original ground surface trees, stumps, roots, brush, and other vegetation in areas to be cleared, except such trees and vegetation as may be indicated or directed to be left standing. Trim dead branches 1-1/2 inches or more in diameter on trees designated to be left standing within the cleared areas and trim all branches to the heights indicated or directed. Neatly cut close to the bole of the tree or main branches, limbs and branches to be trimmed.
3.2.1 Tree Removal
Where indicated or directed, trees and stumps that are designated as trees shall be removed from areas outside those areas designated for clearing and grubbing. This work includes the felling of such trees and the removal of their stumps and roots as specified in paragraph GRUBBING.
Dispose of trees as specified in paragraph DISPOSAL OF MATERIALS.
3.2.2 Grubbing
Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas. Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 18 inches below the original surface level of the ground in areas indicated to be grubbed and in areas indicated as construction areas under this contract, such as areas for buildings, and areas to be paved. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.
3.3 DISPOSAL OF MATERIALS
Dispose of excess materials in accordance with the approved solid waste management permit and include those materials in the solid waste management report.
All wood or wood like materials, except for salable timber, remaining from clearing, prunning or grubbing such as limbs, tree tops, roots, stumps, logs, rotten wood, and other similiar materials shall become the property of the Contractor and disposed of as specified. All non-saleable timber and wood or wood like materials remaining from timber harvesting such as limbs, tree tops, roots, stumps, logs, rotten wood, and other similiar materials shall become the property of the Contractor and disposed as specified.
3.3.1 Saleable Timber
All timber removed from the project site shall become the property of the Contractor. A valuation survey for the timber within project limits was determined to have no commerical value.
SECTION 31 11 00 Page 2 bbullock Cloud bbullock Text Box
-- End of Section --
SECTION 31 11 00 Page 3
| 31 11 00 - CLEARING AND GRUBBING |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 DELIVERY, STORAGE, AND HANDLING |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| PART 3 EXECUTION |
| 3.1 PREPARATION |
| 3.1.1 Protection |
| 3.1.1.1 Roads and Walks |
| 3.1.1.2 Trees, Shrubs, and Existing Facilities |
| 3.1.1.3 Utility Lines |
| 3.2 CLEARING |
| 3.2.1 Tree Removal |
| 3.2.2 Grubbing |
| 3.3 DISPOSAL OF MATERIALS |
| 3.3.1 Saleable Timber |