2018.02.15.CAS_TACT_AirworthinessBrief.pdf

PDF 2 MB Posted

Attached to
Terminal Attack Controller Trainer Federal contract opportunity
Solicitation number
N00421-17-R-0018
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

This document provides an overview of the Navy's aircraft airworthiness certification process and requirements for the Terminal Attack Controller Trainer services solicitation. Key details include:

The Navy will conduct a pre-solicitation conference on February 21, 2018 to brief interested parties on the updated requirements for contracted Terminal Attack Controller Trainer services under solicitation N00421-17-R-0018. The conference will include presentations on Navy airworthiness and weapons danger zone approval processes. The final RFP for the services is expected to be released in March 2018, with multiple award IDIQ contracts to be awarded in the first quarter of fiscal year 2019. The services will include providing aircraft, pilots, and maintenance to support terminal attack controller training. Offerors must comply with registration and security requirements to attend the pre-solicitation conference.

The document outlines the Navy's aircraft airworthiness certification steps, including the public aircraft operations assessment, physical configuration audit, interim flight clearance process, continuing airworthiness oversight, and weapons danger zone approval requirements. It provides references and sources for additional airworthiness guidance.

Industry Day Brief 2

View the file

Other files for this federal contract opportunity

Other files attached to Terminal Attack Controller Trainer, newest first.
File Type Posted
N0042117R0018_RFP_Q&As_FINAL.pdf PDF
N0042117R0018-0001.pdf PDF
N0042117R0018_-_Exhibit_A_CDRLs_A001-A007-signed_12.20.18.pdf PDF
Attachment_P3_CPAQ.pdf PDF
N0042117R0018_TACT_FINAL_RFP.docx DOCX document
Attachment_P1_Solicitation_Question_Form.xlsx XLSX spreadsheet
Attachment_1_DD_Form_254.pdf PDF
Attachment_2_QASP.pdf PDF
N0042117R0018_-_Exhibit_A_CDRLs_A001-A007-signed.pdf PDF
Attachment_P2_Past_Performance_Information_Form.pdf PDF
Attachment_P4_Minimum_Performance_Requirements_(Threshold).pdf PDF
Attachment_2-QASP.PDF PDF
CDRL-A005_GFP_v2.pdf PDF
Attachment_P3-CPAQ.pdf PDF
Attachment_P1-Solicitation_Question_Form.xlsx XLSX spreadsheet
CDRL-A003_Fuel_Chit_Report_v2.pdf PDF
CDRL-A004_Prog_Stat_Mgm_v2.pdf PDF
CDRL-A001_Airworthiness_v2.pdf PDF
CDRL-A006_OPSEC_v2.pdf PDF
CDRL-A007_Mgmt_v2.pdf PDF
CDRL-A002_Mgmt_v2.pdf PDF
N0042117R0018_TACT_DRAFT_RFP_11.12.18.pdf PDF
N0042117R0018_GOVT_RESPONSES_TO_QUESTIONS_IN_RESPONSE_TO_RFI.pdf PDF
Attachment_1-DD254.pdf PDF
Attachment_P2-Past_Performance_Information_Form.pdf PDF
N0042117R0018_DRAFT_RFP_Section_B.pdf PDF
Attachment_1,_DD254.pdf PDF
Attachment_6,_Contractor_Performance_Assessment_Questionnaire.pdf PDF
N0042117R0018_DRAFT_RFP_Section_L&M.pdf PDF
N0042117R0018_DRAFT_RFP_Section_F.pdf PDF
Attachment_5,_Past_Performance_Information_Form.pdf PDF
Attachment_2,_-Solicitation_Question_Form.xlsx XLSX spreadsheet
N0042117R0018_DRAFT_RFP_Section_C.pdf PDF
N0042117R0018_DRAFT_RFP_Section_H.pdf PDF
Attachment_4,_Task_Order_Pricing_Spreadsheet.XLS XLS spreadsheet
N0042117R0018_DRAFT_RFP_Section_J.pdf PDF
Attachment_3,_QASP.PDF PDF
N0042117R0018_DRAFT_RFP_Section_A.pdf PDF
Industry_Day_Q&As_N0042117R0018_TACT_PreSolicitation_Conference.pdf PDF
2018.02.15.TACT_PRESOLCON.pdf PDF
Attachment_Question_Form.xlsx XLSX spreadsheet
2018.2.1_TACT_N00421-17-R-0018_PWS.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Presented to:

Presented by:

CAS Aircraft Airworthiness

Industry

Specialized and Proven Aircraft Program Office

21 February 2018

PMA-226

DISTRIBUTION A. Approved for public release: distribution unlimited.

Ground Rules

DISTRIBUTION A. Approved for public release: distribution unlimited.

• No electronic recording of presentation or discussion

• Please silence your cell phones

• Classification: UNCLASSIFIED

• This pre-solicitation conference constitutes an informal exchange of information

• Provides insight into Government Airworthiness Requirements

• The information shared today represents the Government’s current intentions with regard to the subject acquisition; however, the

Government’s intentions may change based on today’s discussions and any follow-up comments / questions

• The remarks made by Government officials during this exchange should in no way be construed as a guarantee of the

Government’s final course of action

• The formal solicitation, when issued, is the ONLY document that should be relied upon as defining the Government’s requirement

• Briefing will be posted on FedBizOpps Solicitation N00421-17-R-0018

What is a NAVAIR IFC?

DISTRIBUTION A. Approved for public release: distribution unlimited. 3

• A formal document that provides assurance of airworthiness & safety of flight and ensures risk has been identified, mitigated and/or accepted at the appropriate level, within acceptable bounds for the intended mission

• Flight clearances provide flight / operating limitations and/or restrictions for specific configurations and store loadings

– Does not account for every applicable limit or restriction

– Does not replace good headwork or common sense by the pilot / aircrew

Flight Plan

• How do I get a Navy Flight Clearance?

– Contract

– PAO Assessment / Determination

– Physical Configuration Audit

– Interim Flight Clearance

• Flight Clearance Data Requirements

• Wiring Assessment

• EMC SOFT and RADHAZ testing

• Continuing Airworthiness

• Weapon Danger Zone (WDZ) Approval

• References

• Questions

DISTRIBUTION A. Approved for public release: distribution unlimited. 4

How do I get a NAVY Flight Clearance?

NOTE: Components of Terminal Attack Controller Trainer

(TACT) flight activities are considered Public operations as they are outside of the purview of the FAA.

• Five primary elements of the USN Flight Clearance

Process:

– Contract

– Public Aircraft Operations (PAO) Assessment/Determination and

Declaration

– Physical Configuration Audit (PCA)

– Interim Flight Clearance (IFC)

– Continuing Airworthiness (AW)

5DISTRIBUTION A. Approved for public release: distribution unlimited.

Contract

• Contains but not limited to the following:

– Service being provided

– Who is in the binding agreement with the government

– How Continuing Airworthiness oversight is being provided

– Liability/Indemnity

– Government Furnished Equipment (GFE) list

6DISTRIBUTION A. Approved for public release: distribution unlimited.

PAO Assessment / Determination (1 of 2)

• PMA-226, Airworthiness and CYBERSAFE (AIR 4.0P), Test and Evaluation (AIR 5.0)

– Responsible for PAO Assessment and Determination

• PAO Assessment

– Used to determine if the contracted operation with its mission specific equipment is civil or public

– Uses U.S. Armed Forces PAO decision tool

– Input includes but not limited to the following:

• Detailed Mission Description

• Contract

• Contract Data Requirements List (CDRL)

• FAA Airworthiness Certificates and Operating Limits

• FAA Major Repair and Alteration, Form 337s

• FAA Statement of Compliance with AW Standards, Form 8110-3s

• Documentation for Unapproved Installations (Installations that do not have FAA approval documents or are not approved by the FAA)

• Carry-on Equipment

• Persons on board

• Program Letter for Special Experimental or Restricted Certificates

• Insurance Documentation

• PAO Declaration Letter provided by PMA-226 to Owner/Operator

• Owner/Operator provides declaration to FAA, as required by FAA

7DISTRIBUTION A. Approved for public release: distribution unlimited.

PAO Assessment / Determination (2 of 2)

• Examples of PAO missions:

– Mission is outside of FAA approved Operating Limits

(e.g. Adversary Fighter)

– Mission is in support of an inherently military requirement (e.g. Dropping of Ordinance, Launching

Targets, Electronic Attack(EA)/Electronic Warfare

(EW) etc.)

8DISTRIBUTION A. Approved for public release: distribution unlimited.

Physical Configuration Audit (PCA)

• PMA-226

• To establish existing aircraft pedigree

• Conducted on-site

• Formal Examination of the as-built configuration (e.g

PAO Airworthiness Checklist) to identify non-conformances, if any

• Examination of aircraft as configured for PAO

• Various types of audits: Engineering drawings, specifications, technical data and tests, Quality

Assurance, processes and procedures and others as necessary, to determine existing aircraft pedigree for the intended mission

9DISTRIBUTION A. Approved for public release: distribution unlimited.

Continuous Maintenance Record Coverage Critical to Support Pedigree / Airworthiness

Interim Flight Clearance (1 of 3)

• PMA-226 Class Desk, supported by AIR 4.0P and NAVAIR Technical

Competencies

– Responsible for all CAS Flight Clearances

• Technical Area Expert (TAE) Data requirements

– A list comprised of engineering technical data required to certify aircraft airworthiness for a flight clearance release

– Include but not limited to: Test plans, test reports, analyses, Failure Modes

Effects Criticality Analyses (FMECA), drawings, model specifications and other source data applicable to hardware and software (Primarily those NOT approved by the FAA)

• TAE Data review

NOTE: Throughout the process TAEs may request additional information/data needed to substantiate airworthiness for the Flight Clearance approval process.

• Identify Limitations, Warnings and Cautions

• IFC Released (AIR 4.0P signs IFC)

10DISTRIBUTION A. Approved for public release: distribution unlimited.

Interim Flight Clearance (2 of 3)

• FAA Airworthiness Documentation:

– Type Certificate (TC): Approved aircraft design

– Supplemental Type Certificate (STC): Required for modifications to aircraft design

– Current FAA Type Cert Data Sheet (TCDS)

– Flight Manuals and Flight Manual Supplements

– FAA Approved Maintenance Plan

– FAA Form 8110-3s: Statement of Compliance with the Federal Aviation Regulations

– FAA Form 337s: Major Repair and Alteration

– Approved Minimum Equipment List (MEL) if applicable

– Restricted Certificate has similar limitations to Experimental. Key difference is government personnel could be carried on aircraft with Restricted Certificate

– Experimental Certificate: Modifications performed on aircraft with Experimental

Certificate are NOT validated by the FAA. This certificate requires further review of aircraft pedigree/design

• Program Letter submitted to FAA for application of Experimental

Certificate

– Identifies aircraft configuration

– States intended purpose

• Operating Limitations provided by FAA in conjunction with Experimental Certificate

11DISTRIBUTION A. Approved for public release: distribution unlimited.

NAVAIR leverages FAA to establish DoN Airworthiness (IFC)

Interim Flight Clearance (3 of 3)

• AIR 4.0P can accept Airworthiness documentation from others as a basis for their AW certification

– FAA

– Other military branches

– Foreign Military - If reciprocity exists between United States Government and the foreign nation

– Recognized foreign nation Civil Airworthiness Authority (AA)

• AIR 4.0P will work with TAEs and the CAS Class Desk to determine if an AW basis can be established based on artifacts provided

Note: If a Safety of Flight hazard is identified, a Systems Safety Risk Acceptance (SSRA) is developed to document the hazard for formal acceptance.

• TAEs will assess areas for which an AW basis can’t be established

– Lack of data

– No AW basis exists

Note: CAS Class Desk must be notified of any IFC content changes for reassessment and IFC revision as needed.

12DISTRIBUTION A. Approved for public release: distribution unlimited.

Flight Clearance Data Focus (1 of 2)

• FAA approved data: Data specifically approved by the FAA or FAA-delegated representatives. These data may include:

– Aircraft Manuals, Procedures

– FAA Registration Certificate

– Program Letter

– Operating Limitations

– FAA Airworthiness Certificate. If a Special Certification, include Operating Limitations

– Copy of FAA Letter authorizing current aircraft inspection program

– Copy of FAA Letter authorizing aircraft to operate under provisions of the approved Minimum

Equipment List (MEL)

– Type Certificate data and Specification sheets

– FAA Form 337s and 8110-3s

– Supplemental Type Certificates (STC)

– Airworthiness Directives (ADs)

– Copy of Current Maintenance Program

– FAA Designated Engineering Representative (DER) data

– FAA Designated Alteration Station (DAS) data

– Configuration Summary: A spreadsheet that lists all the FAA approved modifications with detail on specific aircraft

13DISTRIBUTION A. Approved for public release: distribution unlimited.

Flight Clearance Data Focus (2 of 2)

DISTRIBUTION A. Approved for public release: distribution unlimited. 14

• OEM documents

– Aircraft Manuals, Procedures, etc.

– Model specifications

• Military Documentation

– Manuals

– Airworthiness Certification

– Technical Directives (Time Compliance Technical Order (TCTOs), Air Frame Changes

(AFCs), Bulletins, etc.)

• Test plans

• Test reports

• Engineering analyses

• Models and Simulations

• FMECA

• Engineering Drawings

• Any other source data applicable to hardware and software modifications

Testing & Assessment Requirements Prior to IFC

Release (1 of 2)

• Evaluation for operation of mission specific electronic equipment

– Determination of Safe Distances for:

• Hazards of Electronic Radiation to Personnel (HERP)

• Hazards of Electronic Radiation to Ordnance (HERO)

• Hazards of Electronic Radiation to Fuel (HERF)

– Electromagnetic Interference/ Electromagnetic Compatibility

Safety of Flight Test (EMC SOFT)

• Equipment operating in all modes and at all frequencies that will be used in flight

DISTRIBUTION A. Approved for public release: distribution unlimited. 15

Testing & Assessment Requirements Prior to IFC

Release (2 of 2)

• Aircraft Validation and Verification (Val/Ver) Electrical

Wiring Interconnect System (EWIS) assessments

– Conducted on wiring associated with aircraft modifications not approved by FAA

– May be required at four different stages within the modification process

• 30%, 60%, 90%, and 100% of completion

• Dependent on availability of engineering documentation

• Assessments for CAS aircraft are typically conducted at 100% completion

– All terminations are made

– Wire bundles and cables are completely installed and secured

– All of the equipment has been installed

– Quality Assurance (QA) function has accepted the installation

DISTRIBUTION A. Approved for public release: distribution unlimited. 16

IFC Process and Sequence of Events (1 of 2)

• Conduct a Planning Meeting (Class Desk, Contractor)

– To occur immediately post contract award

– Develop an Engineering Data Requirements Agreement Plan (EDRAP)

• Identify TAEs based on aircraft modification requiring review and approval

– Plan for Data Requirements

• Physical Configuration Audit (PCA) (Class Desk, Contractor)

– Initial PCA to determine aircraft pedigree

– Final PCA post modification completion

– Schedule and conduct

• To occur post contract award

• Aircraft must be available for inspection

• Communicate early and often (All)

– Class Desk: actively coordinate and communicate with TAEs, AIR-4.0P, Contractor

– Program/Contractor: Provide ALL required data early enough to allow for sufficient review

DISTRIBUTION A. Approved for public release: distribution unlimited. 17

IFC Process and Sequence of Events (2 of 2)

• Testing/Assessments

– Determine requirement (Class Desk, TAEs)

– Schedule tests (PMA, Class Desk, Contractor, TAE)

• Typically occur post completion of required aircraft modification (or as required by TAEs)

• Electronic equipment must be available and approved for carriage prior to EMC SOFT testing

• Class Desk submits complete IFC request to the AIR 4.0P Airworthiness Office

– A complete request means adequate planning & coordination with Stakeholders (Program, Airworthiness, Customer, Operator, Support Personnel, TAEs/Competencies) is in place and all data is ready and available

– Data includes all flight clearance references and any additional data required per EDRAP for review and release of an IFC by TAEs and Airworthiness authority

– Met all known TAE requirements

• IFC Review (TAEs, Class Desk)

– Provide concurrence

• May require additional discussions and documentation

• IFC Release (AIR 4.0P)

DISTRIBUTION A. Approved for public release: distribution unlimited. 18

Continuing Airworthiness Oversight

• Ensures contractor “maintains” airworthiness through approved air and maintenance operations over the life of contract. Required by:

– Contract (PWS paras. 1.3.5.1 and 1.3.5.7 through 21)

– DCMA INST 8210.1C w/ CH1 (NAVAIRINST 3710.1G CH 1)

• Government Flight Representative (GFR) conducts initial and semiannual audits to:

– Approve Contractor Ground, Flight Operational Procedures (GOPS / FOPS) and Safety Program

– Review Pilot and Maintenance Records to assure continued compliance with approved Procedures

• NAVAIR Aircraft Maintenance Management Team will conduct

Aircraft Maintenance Inspections (AMI) to provide an outside evaluation of the contractors maintenance and assess the overall risks associated with the contract

– Before flight operations

– Every two years thereafter

19DISTRIBUTION A. Approved for public release: distribution unlimited.

Live Close Air Support

• All vendor selected platforms shall have an approved, valid existing straight path dive Weapons Danger Zone (WDZ) footprint for one of the Threshold munitions or sufficient weapons release data to support approval process by the

DoN that, at least a straight path dive for one of the

Threshold munitions will be required before the award of a

Task Order to conduct live CAS

Note: Range Operating Authority will prohibit weapons employment unless an applicable WDZ footprint or test footprint has been applied to the target for the specific delivery platform, weapon and employment parameters.

DISTRIBUTION A. Approved for public release: distribution unlimited. 20

Weapon Danger Zone (1 of 2)

DISTRIBUTION A. Approved for public release: distribution unlimited. 21

Weapon Danger Zone (2 of 2)

• A Range Planning and Operations Waiver

Request can be submitted for certain situations to meet training/exercise needs

• WDZ is normally developed using computer modeling such as Range Managers Toolkit which enables the installation range control officer to reduce risks to personnel and facilities involved with aviation operations

• PMA-226 is working with USFF and TECOM to utilize single trajectory WDZ for approved CAS aircraft on DoN and USMC ranges

DISTRIBUTION A. Approved for public release: distribution unlimited. 22

Reference List

a) Advisory Circular 43-201A: Standardized Procedures for

Obtaining Approval of Data Used in the Performance of Major

Repairs and Major Alterations.

b) Advisory Circular 00-1.1A: Public Aircraft Operations.

c) Advisory Circular 91-91 Maintaining Public Aircraft.

d) FAA Order 8300.16.

e) Title 14, Code of Federal Regulations.

f) DCMA INST 8210.1C (NAVAIRINST 3710.1G) w/ CH1

Contractor’s Flight and Ground Operations, 5 April 2017.

g) NAVAIRINST 13034.1F – Flight Clearance Policy for Air

Vehicles and Aircraft Systems.

h) Department of Defense (DoD) Directive 5030.61 DoD

Airworthiness Policy.

i) Department of the Army Pamphlet 385-63 - Range Safety.

23DISTRIBUTION A. Approved for public release: distribution unlimited.

QUESTIONS?

DISTRIBUTION A. Approved for public release: distribution unlimited.