Execution Milestones
| DDG108 FY20 DSRA | Offerors are not to propose milestones highlighted in Orange. These milestones are calculated. | |||
| Offerors are to propose milestones highlighted in Blue in accordance with "Notes". Entering dates into cells J5, J7 and J23 will allow the milestone spreadsheet to calculated the remaining interim milestones. | ||||
| System | Milestones (Calculated or Proposed) | Work Days Prior to "END OF AVAIL" Milestone | Notes | |
| Avail Start | Tuesday, March 17, 2020 | |||
| DOCK | Tuesday, March 17, 2020 | Offeror to Propose Dock Dates IAW Specification 997-11-001. PHNSY & IMF Dry Dock #4 docking date must occur on a Tuesday or Thursday. | ||
| 20% Open and Inspect | Saturday, April 25, 2020 | Reports due on the date in Column C or, if the date in Column C is on a weekend or Government holiday, due on the next Government business day following the date in Column C | ||
| 25% CONFERENCE | Tuesday, May 05, 2020 | Conference to be held on the next Wednesday following the date in Column C | ||
| 50% CONFERENCE | Wednesday, June 24, 2020 | Conference to be held on the next Wednesday following the date in Column C | ||
| 75% CONFERENCE | Thursday, August 13, 2020 | Conference to be held on the next Wednesday following the date in Column C | ||
| UNDOCK | Offeror to Propose Undock Dates IAW Specification 997-11-001. PHNSY & IMF Dry Dock #4 undock date must occur on a Tuesday or Thursday. | |||
| Hab Complete | Wednesday, September 23, 2020 | 43 | ||
| PCD | Friday, October 02, 2020 | 36 | ||
| Light Off Assessment (LOA) Commence | Tuesday, October 13, 2020 | 29 | ||
| Dock Trials | Thursday, November 12, 2020 | |||
| Fast Cruise | Friday, November 13, 2020 | |||
| Sea Trials Begin | Monday, November 16, 2020 | 5 | ||
| Sea Trials Complete | Friday, November 20, 2020 | 1 | ||
| KTR Contract Complete | Friday, November 20, 2020 | 1 | ||
| END OF AVAIL | Friday, November 20, 2020 | Offeror to Propose "END OF AVAIL" milestone date no later than November 20, 2020. |
Entered date must be a Government Work Day.
| END OF AVAIL (KEY EVENT) No Later than Date | Friday, November 20, 2020 |
| "Days Completed Early" for use in the Value Adjusted Total Evaluated Price Tradeoff (VATEP) Schedule Adjustment and GFP Differential | 0 |
DDG108 MS-KE
| USS WAYNE E MEYER 0C1 Milestone / Key Events | |||
| Description | MS/KE | DATE | A+ DATE |
| START AVAILABILITY | SA00 | 17-Mar-20 | 0 |
| DOCKING | DD00 | 24-Mar-20 | 7 |
| 20% Reports - Critical Work | OI20 | 1-May-20 | 45 |
| 25% CONFERENCE | CN25 | 6-May-20 | 50 |
| 50% CONFERENCE | CN50 | 17-Jun-20 | 92 |
| 75% CONFERENCE | CN75 | 12-Aug-20 | 148 |
| UNDOCKING | UD00 | 17-Sep-20 | 184 |
| HABITABILITY | HB00 | 23-Sep-20 | 190 |
| PRODUCTION COMPLETION DATE | WC00 | 2-Oct-20 | 199 |
| AEGIS LIGHTOFF | AL01 | 13-Oct-20 | 210 |
| LIGHTOFF ASSESSMENT | LA01 | 26-Oct-20 | 223 |
| DOCK TRIALS | DT00 | 12-Nov-20 | 240 |
| FAST CRUISE | FC00 | 13-Nov-20 | 241 |
| 48HR CREW REST | RE01 | 14-Nov-20 | 242 |
| SEA TRIALS START | ST00 | 16-Nov-20 | 244 |
| SEA TRIALS END | ST01 | 20-Nov-20 | 248 |
| CNO AVAILABILITY COMPLETE | CA00 | 20-Nov-20 | 248 |
Work Item Key Event List
| USS WAYNE E MEYER 0C1 Work Item 20% Report / Milestone / Key Event List | |||||
| Work Spec | Title | 20% Report Required | 20% Report Paragraph | MS/KE | MS/KE Date |
| 110-11-001 | Underwater Hull; inspect | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 110-11-002 | Shell Stringer Repair; accomplish | Yes | 3.1.1 | UD00 | 17-Sep-20 |
| 113-11-001 | Auxilary Machinery Room Number One Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-002 | Auxilary Machinery Room Number 2 Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-003 | Engine Room Number One Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-004 | Engine Room Number 2 Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-005 | Gas Turbine Generator Room Number 3 Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-006 | VCHT Room Number One Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-007 | VCHT Room Number 2 Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-008 | Sonar Cooling Equipment Room Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 113-11-009 | VLS Magazine Bilge Drain Well; repair | Yes | 3.4.1.1 | UD00 | 17-Sep-20 |
| 122-00-001 | Auxilary Machinery Room Number One Transverse Bulkhead; inspect and repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-11-001 | Tank and Void Open, Pumping, Clean and Gas Free; accomplish | No | UD00 | 17-Sep-20 | |
| 123-11-008 | Fuel Oil Service Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-009 | Fuel Oil Service Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-010 | Fuel Oil Service Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-011 | Fuel Oil Service Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-012 | Fuel Oil Service Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-013 | Fuel Oil Service Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-014 | Fuel Oil Service Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-015 | Fuel Oil Service Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-019 | Compensated Fuel Tank Group 4; preserve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-11-021 | Compensated Fuel Tank Group 3; preserve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-11-026 | Compensated Fuel Tank Group 5; preserve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-11-027 | Compensated Fuel Tank Group 6; preserve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-11-028 | Compensated Fuel Tank Group 4; preserve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-11-031 | Compensated Fuel Tank Group 3; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-032 | Compensated Fuel Tank Group 4; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-034 | Compensated Fuel Tank Group 2; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-035 | Compensated Fuel Tank Group One; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-036 | Compensated Fuel Tank Group 2; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-037 | Compensated Fuel Tank Group 3; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-038 | Compensated Fuel Tank Group 4; preserve | No | UD00 | 17-Sep-20 | |
| 123-11-049 | Compensated Fuel Tank Group 3; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-052 | Compensated Fuel Tank Group 3; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-054 | Compensated Fuel Tank Group 4; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-055 | Compensated Fuel Tank Group 2; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-056 | Compensated Fuel Tank Group One; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-057 | Compensated Fuel Tank Group 2; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-058 | Compensated Fuel Tank Group 5; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-11-059 | Compensated Fuel Tank Group 4; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-11-060 | Compensated Fuel Tank Group 4; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-11-061 | Compensated Fuel Tank Group 6; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-11-062 | Compensated Fuel Tank Group 4; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-11-063 | Compensated Fuel Tank Group 3; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-12-007 | JP-5 Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-12-008 | JP-5 Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-14-001 | Potable Water Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-14-002 | Potable Water Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-14-003 | Potable Water Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-14-004 | Potable Water tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-14-005 | Potable Water Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-14-006 | Potable Water Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-17-003 | Contaminated Oil; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-17-004 | Contaminated Oil; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-17-005 | Contaminated Oil; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-17-006 | Contaminated Oil; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-17-007 | Contaminated Oil; repair | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 123-17-010 | Contaminated Oil tank; preseve (touch up) | No | UD00 | 17-Sep-20 | |
| 123-17-011 | Contaminated Oil tank; preseve | No | UD00 | 17-Sep-20 | |
| 123-17-013 | Contaminated Oil tank; preseve | No | UD00 | 17-Sep-20 | |
| 123-17-014 | Contaminated Oil tank; preseve | No | UD00 | 17-Sep-20 | |
| 123-17-017 | Contaminated Oil tank; preseve | No | UD00 | 17-Sep-20 | |
| 123-19-001 | Vacuum Collection, Holding and Transfer (VCHT)) Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-19-002 | Vacuum Collection, Holding and Transfer (VCHT)) Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-19-003 | Vacuum Collection, Holding and Transfer (VCHT)) Tank; repair | Yes | 3.4.1 | UD00 | 17-Sep-20 |
| 123-19-004 | Vacuum Collection, Holding and Transfer (VCHT)) Tank; repair | Yes | 3.4.1 | UD00 | 17-Sep-20 |
| 123-19-005 | Waste Water Tank; repair | Yes | 3.2.1.1 | UD00 | 17-Sep-20 |
| 123-19-006 | Waste Water Tank; preserve | No | UD00 | 17-Sep-20 | |
| 123-19-007 | Waste Water Tank; repair | Yes | 3.1.1.1 | UD00 | 17-Sep-20 |
| 123-21-001 | Accessible Void; preserve | No | UD00 | 17-Sep-20 | |
| 123-21-002 | Accessible Void; repair | Yes | 3.3.1 | UD00 | 17-Sep-20 |
| 150-11-003 | Vacuum Collection, Holding and Transfer (VCHT)) Room Number 2 Structural Repair; accomplish | No | UD00 | 17-Sep-20 | |
| 161-11-001 | Strut; repair | No | UD00 | 17-Sep-20 | |
| 163-11-001 | Waster Sleeve; replace | No | UD00 | 17-Sep-20 | |
| 163-11-002 | Sea Chest; inspect and repair | No | UD00 | 17-Sep-20 | |
| 165-11-001 | Lower Sonar Dome Access Scuttle; repair | Yes | 3.1.1 | UD00 | 17-Sep-20 |
| 165-11-002 | Sonar Dome Rubber Window (SDRW); inspect and repair | No | UD00 | 17-Sep-20 | |
| 165-11-003 | Sonar Dome; Pump, Clean, and Gas Free | No | UD00 | 17-Sep-20 | |
| 243-11-002 | Stern Tube Shaft Seal Starboard; overhaul | Yes | 3.2.2.1 | UD00 | 17-Sep-20 |
| 243-11-003 | Propulsion Shafting Starboard; inspect and repair | Yes | 3.1.1.1 | UD00 | 17-Sep-20 |
| 243-11-004 | Waterborne Propulsion Shafting Alignment Starboard; accomplsih | Yes | 3.2.1 and 3.3.1 | UD00 | 17-Sep-20 |
| 243-12-002 | Stern Tube Shaft Seal Port; overhaul | Yes | 3.2.2.1 | UD00 | 17-Sep-20 |
| 243-12-003 | Propulsion Shafting Port; inspect and repair | Yes | 3.1.1.1 | UD00 | 17-Sep-20 |
| 243-12-004 | Waterborne Propulsion Shafting Alignment Port; accomplsih | No | UD00 | 17-Sep-20 | |
| 244-11-001 | Outboard Propulsion Shafting, Bearing Clearance Measurement Starboard; accomplish | No | UD00 | 17-Sep-20 | |
| 244-12-001 | Outboard Propulsion Shafting, Bearing Clearance Measurement Port; accomplish | No | UD00 | 17-Sep-20 | |
| 244-12-002 | Port Main Thrust Bearing Sump Pumping and Cleaning; accomplsih | No | UD00 | 17-Sep-20 | |
| 245-11-002 | Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Starboard; repair | No | UD00 | 17-Sep-20 | |
| 245-11-003 | Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplish | No | UD00 | 17-Sep-20 | |
| 245-11-004 | Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box MER One; replace | No | UD00 | 17-Sep-20 | |
| 245-12-002 | Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Port; repair | No | UD00 | 17-Sep-20 | |
| 245-12-003 | Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplish | No | UD00 | 17-Sep-20 | |
| 245-12-004 | Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box MER 2; replace | No | UD00 | 17-Sep-20 | |
| 256-11-001 | Seawater Service valve; replace | No | UD00 | 17-Sep-20 | |
| 256-71-001 | Centralized Seawater Service Pump; overhaul | No | UD00 | 17-Sep-20 | |
| 262-11-001 | Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspect | No | UD00 | 17-Sep-20 | |
| 438-80-001 | ShipAlt DDG51-76231D, Sonar Dome Stave Cable Connectorization, Stave Cable and Transducer Replacement; accomplish | No | UD00 | 17-Sep-20 | |
| 468-89-001 | DT-513/BQA-8 Hydrophone and Cable Assembly; repalce | No | UD00 | 17-Sep-20 | |
| 520-11-001 | Sea Valve; repair and replace | No | UD00 | 17-Sep-20 | |
| 521-11-001 | Firemain Piping; replace | No | UD00 | 17-Sep-20 | |
| 562-11-001 | Rudder Bearing Seal and Rudderstock Seal; repair | No | UD00 | 17-Sep-20 | |
| 562-12-001 | Rudder Bearing Seal and Rudderstock Seal; repair | No | UD00 | 17-Sep-20 | |
| 593-11-001 | Vacuum, Collection, Holding and Transfer (VCHT) Piping System; chemically clean | No | UD00 | 17-Sep-20 | |
| 631-11-001 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-002 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-003 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-004 | Shell Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-005 | Deck Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-006 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-007 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-008 | Auxilary Machinery Room Number 2 Bilge, preserve | No | UD00 | 17-Sep-20 | |
| 631-00-009 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-11-010 | Auxilary Machinery Room Number One Bulkhead, preserve | No | UD00 | 17-Sep-20 | |
| 631-11-011 | Auxilary Machinery Room Number One Bilge, preserve | No | UD00 | 17-Sep-20 | |
| 631-11-012 | Auxilary Machinery Room Number One Margin Plate, preserve | No | UD00 | 17-Sep-20 | |
| 631-11-013 | Auxilary Machinery Room Number One Deck Plating, preserve | No | UD00 | 17-Sep-20 | |
| 631-11-014 | Tank Top Plating; preserve | No | UD00 | 17-Sep-20 | |
| 631-21-002 | Superstructure; preserve | No | UD00 | 17-Sep-20 | |
| 631-31-001 | Underwater Hull; preserve | No | UD00 | 17-Sep-20 | |
| 631-41-001 | Freeboard; preserve | No | UD00 | 17-Sep-20 | |
| 633-11-001 | Impressed Curent Cathodic Protection (ICCP) System; inspect and repair | No | 3.2.2 | UD00 | 17-Sep-20 |
| 991-11-001 | Temporary Mast and Roller Staging for Ship's Force Use; provide | No | UD00 | 17-Sep-20 | |
| 993-31-001 | Temporary Main Reduction Gear (MRG) Dehumidifier System; provide | Yes | 3.2.1 | UD00 | 17-Sep-20 |
| 512-11-002 | Galley and Laundry Exhaust Ventilation Cleaning; accomplish | No | HB00 | 23-Sep-20 | |
| 512-80-001 | ShipAlt DDG51-64238D, Collective Protection System Supply/Exhaust Hoods; replace | No | HB00 | 23-Sep-20 | |
| 643-80-002 | ShipAlt DDG51-81670D, Officer Berthing Increase Habitability Modification; accomplish | No | HB00 | 23-Sep-20 | |
| 644-11-001 | Crew Shower; preserve | No | HB00 | 23-Sep-20 | |
| 644-11-002 | Crew Shower; preserve | No | HB00 | 23-Sep-20 | |
| 651-80-001 | ShipAlt DDG51-85629D Combination Ovens replace; accomplish | No | HB00 | 23-Sep-20 | |
| 655-80-001 | ShipAlt DDG51-00429D, Self Service Laundry Installation; accomplsih | No | HB00 | 23-Sep-20 | |
| 110-21-001 | Structural Pipe Stanchion; repair | Yes | 3.1.1 | WC00 | 02-Oct-20 |
| 110-21-002 | Structural Pipe Stanchion; repair | Yes | 3.1.1 | WC00 | 02-Oct-20 |
| 123-22-001 | Chain Locker, Starboard; preserve | No | WC00 | 02-Oct-20 | |
| 123-22-002 | Chain Locker, Port; preserve | No | WC00 | 02-Oct-20 | |
| 123-22-003 | Chain Locker Sump; preserve | No | WC00 | 02-Oct-20 | |
| 123-22-004 | Chain Locker, Starboard; repair | Yes | 3.2.1.1 | WC00 | 02-Oct-20 |
| 123-22-005 | Chain Locker, Port; repair | Yes | 3.2.1.1 | WC00 | 02-Oct-20 |
| 123-22-006 | Chain Locker Sump; repair | Yes | 3.2.1.1 | WC00 | 02-Oct-20 |
| 130-11-001 | Aircraft Securing Fitting; replace | No | WC00 | 02-Oct-20 | |
| 150-11-001 | 01 Level Bulkhead; repair | Yes | 3.1.1 | WC00 | 02-Oct-20 |
| 150-11-002 | 01Level Weld; repair | Yes | 3.1.1 | WC00 | 02-Oct-20 |
| 150-11-004 | 01 Level Deck; repair | Yes | 3.2.1 | WC00 | 02-Oct-20 |
| 150-11-007 | 01 Level Deck; repair | Yes | 3.2.1 | WC00 | 02-Oct-20 |
| 150-80-001 | ShipAlt DDG-51-AER86007D (Partial), Increase Deck Plate Thickness Modification; accomplish | Yes | 3.1.1 | WC00 | 02-Oct-20 |
| 167-11-001 | Bolted Equipment Removal Plate (BERP) Repair; accomplish | Yes | 3.2.1 | WC00 | 02-Oct-20 |
| 251-00-001 | Number One Gas Turbine Module (GTM) Clean Air Intake; repair | No | WC00 | 02-Oct-20 | |
| 251-00-002 | Number One Ship Service Gas Turbine Generator Clean Air Intake; Touch up | No | WC00 | 02-Oct-20 | |
| 251-31-002 | Air Intake and Exhaust Louver; clean and preserve | No | WC00 | 02-Oct-20 | |
| 251-32-001 | Gas Turbine Intake Number One; repair | No | WC00 | 02-Oct-20 | |
| 251-32-002 | Gas Turbine Intake Number 2; repair | No | WC00 | 02-Oct-20 | |
| 256-80-001 | ShipAlt DDG-51-64250D, Ship Gas Turbine Generator (SSGTG) Emergency Seawater Cooling System Modification; accomplish | No | WC00 | 02-Oct-20 | |
| 259-10-001 | Number 2 Gas Turbine Mixing Room, Uptakes, and 05 Lvl Stack Top; repair | No | WC00 | 02-Oct-20 | |
| 259-10-002 | Number One Gas Turbine Mixing Room, Uptakes, and 05 Lvl Stack Top; repair | No | WC00 | 02-Oct-20 | |
| 259-11-001 | Gas Turbine (GTRB) Exhaust Duct Collector; repair | No | WC00 | 02-Oct-20 | |
| 320-80-001 | ShipAlt DDG51-64231D, Automatic Bus Transfer (ABT) Relocation; accomplish | No | WC00 | 02-Oct-20 | |
| 512-11-003 | Hanger Number One Vent Duct Cleaning; accomplish | No | WC00 | 02-Oct-20 | |
| 523-11-001 | Countermeasure Washdown (CMWD) Nozzle, Piping and Associated Fitting; clean | No | WC00 | 02-Oct-20 | |
| 528-11-001 | ShipAlt DDG51-64240D, Uptake Drain Piping Overboard Routing Correction; accomplish | No | WC00 | 02-Oct-20 | |
| 551-11-001 | Anti-icing Expansion Joint; replace | No | WC00 | 02-Oct-20 | |
| 571-31-001 | Sliding Padeye, Tilting; overhaul and preserve | No | WC00 | 02-Oct-20 | |
| 571-31-002 | Sliding Padeye, Tilting; overhaul and preserve | No | WC00 | 02-Oct-20 | |
| 582-11-001 | Retractable Chock and Retractable Chock Cover; repalce and preserve | No | WC00 | 02-Oct-20 | |
| 582-11-002 | Retractable Towing Pad; repair and preserve | No | WC00 | 02-Oct-20 | |
| 583-11-001 | Boat handling System; overhaul | Yes | 3.5.3.1 | WC00 | 02-Oct-20 |
| 588-21-001 | Recovery Assist, Securing and Transversing (RAST) System Track and Plate; clean and preserve | No | WC00 | 02-Oct-20 | |
| 593-21-002 | Number 2 Gas Turbine Waste Drain Pump; overhaul | No | WC00 | 02-Oct-20 | |
| 611-80-001 | ShipAlt DDG51-64185D, Anchor Chain Chaffing Plate Installation; accomplish | No | WC00 | 02-Oct-20 | |
| 623-80-001 | DDG51 Class AER 66048, Accomadation Ladder Feathering Bar Securing Pin; accomplish | No | WC00 | 02-Oct-20 | |
| 624-11-001 | Balanced Joiner Door; remove, store and install | Yes | 3.1.2 | WC00 | 02-Oct-20 |
| 631-13-001 | Collective Protection System (CPS) Zone One Fan Room; repair and preserve | No | WC00 | 02-Oct-20 | |
| 631-13-002 | Collective Protection System (CPS) Zone 2 Fan Room; repair and preserve | No | WC00 | 02-Oct-20 | |
| 631-13-003 | Collective Protection System (CPS) Zone 2 Fan Room; repair and preserve | No | WC00 | 02-Oct-20 | |
| 631-13-004 | Collective Protection System (CPS) Zone 3 Fan Room; repair and preserve | No | WC00 | 02-Oct-20 | |
| 631-13-005 | Collective Protection System (CPS) Zone 2 Fan Room; repair and preserve | No | WC00 | 02-Oct-20 | |
| 631-21-004 | Intake/Uptake Deck Preservation; accomplish | No | WC00 | 02-Oct-20 | |
| 634-11-001 | Chemical - Resistant Floor Covering; resurface and repair | No | WC00 | 02-Oct-20 | |
| 634-11-002 | Chemical - Resistant Floor Covering; resurface | No | WC00 | 02-Oct-20 | |
| 634-11-003 | Chemical - Resistant Floor Covering; install | No | WC00 | 02-Oct-20 | |
| 634-11-004 | Chemical - Resistant Floor Covering; replace | No | WC00 | 02-Oct-20 | |
| 634-11-005 | 03 Level peel and Stick Nonskid; replace | No | WC00 | 02-Oct-20 | |
| 634-21-001 | Nonskid; replace | No | WC00 | 02-Oct-20 | |
| 634-21-002 | Nonskid; replace | No | WC00 | 02-Oct-20 | |
| 634-21-003 | 02 Level Refueling Station Nonskid; replace | No | WC00 | 02-Oct-20 | |
| 643-11-001 | Berthing Space Temporary Deck Studs; replace | No | WC00 | 02-Oct-20 | |
| 992-31-003 | Temporary Air Conditioning; provide | No | WC00 | 02-Oct-20 | |
| 993-31-003 | Temporary Deck Covering; provide | No | WC00 | 02-Oct-20 | |
| 472-90-001 | ShipAlt DDG-80156K An/SLQ (V)6 Hardware. ShipAlt DDG51-81382 AN/SLQ-32 (V)6 Data Adaptation Processor (DAP); accomplish | No | AL01 | 13-Oct-20 | |
| 522-80-001 | ShipALt DDG51-82474D, Relocation of CIWS, Torpedo, and DLS Magazine Gauge; accomplsih | No | AL01 | 13-Oct-20 | |
| 721-31-001 | Vertical Launch System (VLS), MK 41 Launcher Top and Uptake Hatch; preserve | No | AL01 | 13-Oct-20 | |
| 844-31-001 | Combat System Discrepancy Correction; accomplish | No | AL01 | 13-Oct-20 | |
| 980-00-001 | Ordalt 83135, Close-in Weapon System (CIWS) Cable Reliability Improvements, Alteration Installation Team (AIT) Support Service; provide | No | AL01 | 13-Oct-20 | |
| 980-11-003 | ShipAlt DDG51-81961K/85114K, Tatical Tomahawk Weapons Control System (TTWCS)V5.4.0.2 Upgrade Alteration Installation Team (AIT) Support; provide | No | AL01 | 13-Oct-20 | |
| 980-11-006 | ShipAlt 86304K, 86222K, 86644K, AN/SQQ89A(V)15 (TI-16/15), AN-UQN Next Gen Fathometer USW: DSS, Alteration Installation Team (AIT) Support Services; provide | No | AL01 | 13-Oct-20 | |
| 980-90-001 | ShipALt DDG51-93762K, Optical Dazzling Interdictor Navy (ODIN), Alteration Installation Team (AIT) Support Services; provide | No | AL01 | 13-Oct-20 | |
| 980-90-002 | OrdAlts DDG51-70111 Empty Case Tray, 70227 Cradle Operating Cylinder, 70751 Gun Port Shield, 70920 Fuze Setter, 70921 Breech Partially, 77862 Snubbers (Electrical Safety Change), and 83489 Servo I/O Obsolesence, Alteration Installation Team (AIT) Support Service; provide | No | AL01 | 13-Oct-20 | |
| 992-11-007 | Pressurized Waveguide and Transmission Line Dry Air Lay-Up; accomplish | No | AL01 | 13-Oct-20 | |
| 993-31-002 | AN/SPY-1D Antenna Protective Cover; install | No | AL01 | 13-Oct-20 | |
| 042-11-001 | Accountability of Manhour and Material Reservation; accomplish | No | CA00 | 20-Nov-20 | |
| 077-01-001 | Hazardous Waste Produced on Naval Vessels; control | No | CA00 | 20-Nov-20 | |
| 980-11-001 | Light-Off Discrepancy Correction Assistance; provide | No | CA00 | 20-Nov-20 | |
| 980-11-002 | ShipAlt Number, ShipAlt Title, Alteration Installation Team (AIT) Support Services; provide | No | CA00 | 20-Nov-20 | |
| 980-11-004 | Maintanance Team Office Space; provide and maintain | No | CA00 | 20-Nov-20 | |
| 980-11-005 | Ship's Force Office Space for Work Authorization Form (WAF) Processing and tag Out Services; provide | No | CA00 | 20-Nov-20 | |
| 992-11-001 | Temporary Dry Provision Stowage; provide | No | CA00 | 20-Nov-20 | |
| 992-11-004 | Temporary Services; provide | No | CA00 | 20-Nov-20 | |
| 992-11-005 | Temporary Refrigerated Storage Facility, 2560 Cubic Feet; provide | No | CA00 | 20-Nov-20 | |
| 992-11-006 | Temporary Flammable Liquid Hazardous Waste and Hazardous Material Storage for Ship's Force Use; provide | No | CA00 | 20-Nov-20 | |
| 992-31-001 | Pumping; accomplish | No | CA00 | 20-Nov-20 | |
| 992-31-002 | Bilge Cleaning and Pumping; accomplish | No | CA00 | 20-Nov-20 | |
| 993-11-001 | Rigging, Crane and Transportation Services; provide | No | CA00 | 20-Nov-20 |
A+ Dates Rev9
| DDG-57 EDSRA 2013 A + DATES | |||||||||||||
| REV9 | 17-Apr-13 | ||||||||||||
| SUN | MON | TUE | WED | THU | FRI | SAT | SUN | MON | TUE | WED | THU | FRI | SAT |
| 3-Feb-13 | 4-Feb-13 | 5-Feb-13 | 6-Feb-13 | 7-Feb-13 | 8-Feb-13 | 9-Feb-13 | 10-Feb-13 | 11-Feb-13 | 12-Feb-13 | 13-Feb-13 | 14-Feb-13 | 15-Feb-13 | 16-Feb-13 |
| XST to BAE | |||||||||||||
| 17-Feb-13 | 18-Feb-13 | 19-Feb-13 | 20-Feb-13 | 21-Feb-13 | 22-Feb-13 | 23-Feb-13 | 24-Feb-13 | 25-Feb-13 | 26-Feb-13 | 27-Feb-13 | 28-Feb-13 | 1-Mar-13 | 2-Mar-13 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| 3-Mar-13 | 4-Mar-13 | 5-Mar-13 | 6-Mar-13 | 7-Mar-13 | 8-Mar-13 | 9-Mar-13 | 10-Mar-13 | 11-Mar-13 | 12-Mar-13 | 13-Mar-13 | 14-Mar-13 | 15-Mar-13 | 16-Mar-13 |
| Dock | |||||||||||||
| 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 |
| 17-Mar-13 | 18-Mar-13 | 19-Mar-13 | 20-Mar-13 | 21-Mar-13 | 22-Mar-13 | 23-Mar-13 | 24-Mar-13 | 25-Mar-13 | 26-Mar-13 | 27-Mar-13 | 28-Mar-13 | 29-Mar-13 | 30-Mar-13 |
| 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
| 31-Mar-13 | 1-Apr-13 | 2-Apr-13 | 3-Apr-13 | 4-Apr-13 | 5-Apr-13 | 6-Apr-13 | 7-Apr-13 | 8-Apr-13 | 9-Apr-13 | 10-Apr-13 | 11-Apr-13 | 12-Apr-13 | 13-Apr-13 |
| 25% Conf | |||||||||||||
| 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 |
| 14-Apr-13 | 15-Apr-13 | 16-Apr-13 | 17-Apr-13 | 18-Apr-13 | 19-Apr-13 | 20-Apr-13 | 21-Apr-13 | 22-Apr-13 | 23-Apr-13 | 24-Apr-13 | 25-Apr-13 | 26-Apr-13 | 27-Apr-13 |
| Turnover 1 | Turnover 2 | ||||||||||||
| 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 |
| 28-Apr-13 | 29-Apr-13 | 30-Apr-13 | 1-May-13 | 2-May-13 | 3-May-13 | 4-May-13 | 5-May-13 | 6-May-13 | 7-May-13 | 8-May-13 | 9-May-13 | 10-May-13 | 11-May-13 |
| Turnover 3 | #1 SWBD | #3 SWBD | #2 SWBD | ||||||||||
| 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 | 80 | 81 | 82 |
| 12-May-13 | 13-May-13 | 14-May-13 | 15-May-13 | 16-May-13 | 17-May-13 | 18-May-13 | 19-May-13 | 20-May-13 | 21-May-13 | 22-May-13 | 23-May-13 | 24-May-13 | 25-May-13 |
| Turnover 4 | Turnover 5 | ||||||||||||
| 83 | 84 | 85 | 86 | 87 | 88 | 89 | 90 | 91 | 92 | 93 | 94 | 95 | 96 |
| 26-May-13 | 27-May-13 | 28-May-13 | 29-May-13 | 30-May-13 | 31-May-13 | 1-Jun-13 | 2-Jun-13 | 3-Jun-13 | 4-Jun-13 | 5-Jun-13 | 6-Jun-13 | 7-Jun-13 | 8-Jun-13 |
| 2 FO Banks | Turnover 6 | ||||||||||||
| 97 | 98 | 99 | 100 | 101 | 102 | 103 | 104 | 105 | 106 | 107 | 108 | 109 | 110 |
| 9-Jun-13 | 10-Jun-13 | 11-Jun-13 | 12-Jun-13 | 13-Jun-13 | 14-Jun-13 | 15-Jun-13 | 16-Jun-13 | 17-Jun-13 | 18-Jun-13 | 19-Jun-13 | 20-Jun-13 | 21-Jun-13 | 22-Jun-13 |
| Turnover 7 | 50% Conf | 2 FO Banks | Undock | VCHT | |||||||||
| 111 | 112 | 113 | 114 | 115 | 116 | 117 | 118 | 119 | 120 | 121 | 122 | 123 | 124 |
| 23-Jun-13 | 24-Jun-13 | 25-Jun-13 | 26-Jun-13 | 27-Jun-13 | 28-Jun-13 | 29-Jun-13 | 30-Jun-13 | 1-Jul-13 | 2-Jul-13 | 3-Jul-13 | 4-Jul-13 | 5-Jul-13 | 6-Jul-13 |
| SW/CCS DK | PW | FM/AFFF/Halon/LP/HP/ENG Vent/MRG LO | LOFSP | 2 FO Banks | PH Dk BA/CHW/AC/Steer | ||||||||
| 125 | 126 | 127 | 128 | 129 | 130 | 131 | 132 | 133 | 134 | 135 | 136 | 137 | 138 |
| 7-Jul-13 | 8-Jul-13 | 9-Jul-13 | 10-Jul-13 | 11-Jul-13 | 12-Jul-13 | 13-Jul-13 | 14-Jul-13 | 15-Jul-13 | 16-Jul-13 | 17-Jul-13 | 18-Jul-13 | 19-Jul-13 | 20-Jul-13 |
| CRP | 400HZ | DIU Cal | AHSS/JP5 | FUELING | |||||||||
| 139 | 140 | 141 | 142 | 143 | 144 | 145 | 146 | 147 | 148 | 149 | 150 | 151 | 152 |
| 21-Jul-13 | 22-Jul-13 | 23-Jul-13 | 24-Jul-13 | 25-Jul-13 | 26-Jul-13 | 27-Jul-13 | 28-Jul-13 | 29-Jul-13 | 30-Jul-13 | 31-Jul-13 | 1-Aug-13 | 2-Aug-13 | 3-Aug-13 |
| Hab Vent | FO Test Comp | COMX HPT | NAVSSI/67/73 | AHSS Vent Test | |||||||||
| 153 | 154 | 155 | 156 | 157 | 158 | 159 | 160 | 161 | 162 | 163 | 164 | 165 | 166 |
| 4-Aug-13 | 5-Aug-13 | 6-Aug-13 | 7-Aug-13 | 8-Aug-13 | 9-Aug-13 | 10-Aug-13 | 11-Aug-13 | 12-Aug-13 | 13-Aug-13 | 14-Aug-13 | 15-Aug-13 | 16-Aug-13 | 17-Aug-13 |
| 75% Conf | AHSS Cal | ALO | |||||||||||
| 167 | 168 | 169 | 170 | 171 | 172 | 173 | 174 | 175 | 176 | 177 | 178 | 179 | 180 |
| 18-Aug-13 | 19-Aug-13 | 20-Aug-13 | 21-Aug-13 | 22-Aug-13 | 23-Aug-13 | 24-Aug-13 | 25-Aug-13 | 26-Aug-13 | 27-Aug-13 | 28-Aug-13 | 29-Aug-13 | 30-Aug-13 | 31-Aug-13 |
| AHSS Cert | Hab T/O | ||||||||||||
| 181 | 182 | 183 | 184 | 185 | 186 | 187 | 188 | 189 | 190 | 191 | 192 | 193 | 194 |
| 1-Sep-13 | 2-Sep-13 | 3-Sep-13 | 4-Sep-13 | 5-Sep-13 | 6-Sep-13 | 7-Sep-13 | 8-Sep-13 | 9-Sep-13 | 10-Sep-13 | 11-Sep-13 | 12-Sep-13 | 13-Sep-13 | 14-Sep-13 |
| HPT COMP | PCD | Move NOB | LOA Prep | ||||||||||
| 195 | 196 | 197 | 198 | 199 | 200 | 201 | 202 | 203 | 204 | 205 | 206 | 207 | 208 |
| 15-Sep-13 | 16-Sep-13 | 17-Sep-13 | 18-Sep-13 | 19-Sep-13 | 20-Sep-13 | 21-Sep-13 | 22-Sep-13 | 23-Sep-13 | 24-Sep-13 | 25-Sep-13 | 26-Sep-13 | 27-Sep-13 | 28-Sep-13 |
| Fueling/JP5 | |||||||||||||
| 209 | 210 | 211 | 212 | 213 | 214 | 215 | 216 | 217 | 218 | 219 | 220 | 221 | 222 |
| 29-Sep-13 | 30-Sep-13 | 1-Oct-13 | 2-Oct-13 | 3-Oct-13 | 4-Oct-13 | 5-Oct-13 | 6-Oct-13 | 7-Oct-13 | 8-Oct-13 | 9-Oct-13 | 10-Oct-13 | 11-Oct-13 | 12-Oct-13 |
| LOA | LOA | LOA | LOA | LOA/DT | FC | Sea Trials | Sea Trials | Sea Trials | EOA |
&D
EquipCable Turnover R9
USS MITSCHER DDG-57
DDGM BF Critical Path Equipment/Cable Turnover, Power-up & Test Requirement Schedule
REV9, 17APR13
| Equipment | A + | Date | Comments |
| Turnover 1 | |||
| SPS-73 ISEA Disconnect SAOP for relocation | 26-Feb-13 | ||
| All Power Sources and Terminal Boxes for Equipment in A+45, A+55 & A+64 to also include new and upgraded sources.* | 44 | 17-Apr-13 | *To include but not limited to: LC11, 12, 13, 21, 23, 24, 25, 31, 32, 33, 34, 35, 41; PP 3-210-2, 2-299-1, 2-299-2, 01-129-2, 1-268-1, 1-288-1, 2-199-2, 3-219-2, 3-173-3, 4-131-1, 2-199-4, 2-219-1, 1-113-1, 3-116-1, 01-130-0, 1-157-2 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources.
| GEDMS Mesh B (BSE B1-B10) | 44 | 17-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 1st Turnover IOUs* | 44 | 17-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A03: J2: 3-210-2-1L-C) (BSE A10: J2: 3-210-2-1L-G) (BSE A04: J2 : LC25-1L-A8) |
robert.gudge: robert.gudge:
have to check power source.
| IOUs: 31, 32, 34, 42, 72, 82 | 44 | 17-Apr-13 | |
| USEs 31A, 31B, 32A, 32B, 34A, 34B, 42A, 72A, 82A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 44 | 17-Apr-13 | |
| C-DR Boxes 12, 13, 14, 14A, 15, 15A, 16, 24, 37 | 44 | 17-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 12, 12A, 13, 13A, 14, 15, 16, 16A, 17, 17A, 25 & 25A. |
| Turnover 2 | |||
| UCCs 1 & 2 | 51 | 24-Apr-13 | |
| RSC DCC, C/O SW & Speaker | 51 | 24-Apr-13 | Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction. |
| RSC Repair 5, C/O SW, Speaker & Access Cut | 51 | 24-Apr-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (CCS) | 51 | 24-Apr-13 | LAN Drop & Power Outlet |
| IOUs: 73, 74, 83, 84, 94 | 51 | 24-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 2nd Turnover IOUs* | 51 | 24-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A09: J2: LC33-1L-H1) (BSE A06: J2: LC25-1L-A12) |
robert.gudge: robert.gudge:
have to check power source.
| C-DR Boxes 7, 8, 8A, 11, 25, 26, 31 | 51 | 24-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 7, 7A, 11, 11A, 26, & 26A. |
| USEs 73A, 74A, 74C, 83A, 83B, 84A, 94A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 51 | 24-Apr-13 | |
| Turnover 3 | |||
| Electric Plant DIU 1 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| Propulsion DIU 4 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| UCC 3 | 60 | 03-May-13 | |
| ECs 1A, 1B (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| FADC 1 | 60 | 03-May-13 | |
| RSC Repair 2, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (MER 1) | 60 | 03-May-13 | LAN Drop & Power Outlet |
| RSC CSMC, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| Fire Detection System ITB Upgrade Electrical Mods & Cabling for IOUs in T/Os 1, 2, and 3. | 60 | 03-May-13 | |
| IOUs: 22, 33, 61, 62 | 60 | 03-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 3rd Turnover IOUs* | 60 | 03-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A02: J2: (3-210-2-1L-D) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources. | C-DR Boxes 19, 21, 22, 23, 23A | 60 | 03-May-13 | Install FDS ITB Modification Kit for the following ITB's; 20, 20A, 22, 23, 23A, 24 & 24A. |
| USEs 22A, 33A, 61A, 62A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 60 | 03-May-13 | ||
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER1 | 60 | 03-May-13 | 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill | |
| #1 SWBD and related Load Centers and 1SF Special Frequency SWBD (2-Days) | 63 | 06-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #3 SWBD and related Load Centers and 2SF Special Frequency SWBD (2-Days) | 65 | 08-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #2 SWBD/1SA and any outstanding work/Final Ringout (2-Days, Ships's 60HZ PWR Secured) | 67 | 10-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| Turnover 4 | ||||
| All Power Sources & Terminal Boxes for Equipment in A+73, A+83 and A+92* | 72 | 15-May-13 | *To include but not limited to: PP 02-167-1, 01-178-2, 2-116-1, 3-173-3, 2-48-1, 2-299-1, 3-258-1, 2-405-2, 1-143-2, 2-282-1, 3-256-2, 3-284-3, 04-154-2, 3-442-2, 3-442-1, 1-157-2, 03-142-2, 03-141-1, 03-154-2, 03-133-1, 03-129-1, 03-132-1, 03-130-1, 3-213-2, 3-255-1 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O.
| Electric Plant DIUs 2 & 3 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| Propulsion DIU 5 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| UCC 4 | 72 | 15-May-13 | |
| RSC Repair 3, C/O SW, Speaker | 72 | 15-May-13 | Hold Keyboard for later installation per SMR direction. |
| ECs 2A, 2B (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| FADCs 2 & 3 | 72 | 15-May-13 | |
| TIWS (MER 2) | 72 | 15-May-13 | LAN Drop & Power Outlet |
| Aft Steering Unit (ASU) | 72 | 15-May-13 | |
| Local Control Steering Units (LCUs 1 - 4) | 72 | 15-May-13 | |
| IOUs: 11, 13, 14, 41, 51, 81 | 72 | 15-May-13 | |
| C-DR Boxes 1, 10, 17, 27, 28, 28A, 30, 33, 34, 35, 36 | 72 | 15-May-13 | Install FDS ITB Modification Kit for the following ITB's; 1, 10, 18, 27, 27A, 28, & 30. |
| USE 11A, 13A, 14A, 41A, 51A, 81A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 72 | 15-May-13 | |
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER2 | 72 | 15-May-13 | 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill |
| Turnover 5 | |||
| Ship Control Console (SCC) | 81 | 24-May-13 | |
| BCCS | 81 | 24-May-13 | |
| HFS | 81 | 24-May-13 | |
| IBNS Racks 1, 2, including HS Firewall, UPS & C/O Switches | 81 | 24-May-13 | |
| IBNS Radar Rack | 81 | 24-May-13 | |
| Trigger/Video Amp/Nulka Processor | 81 | 24-May-13 | |
| IBNS NAV 1 computer (Pilot House) | 81 | 24-May-13 | |
| IBNS NAV 2 computer (Chart Room) | 81 | 24-May-13 | |
| IBNS NAV 3 computer (CIC) | 81 | 24-May-13 | |
| IBNS NAV 4 computer (CO's Laptop) | 81 | 24-May-13 | |
| SPS-73 SAOP, Ethernet SW, C/O SW & UPS | 81 | 24-May-13 | |
| NAVSSI Inputs to IBNS/SAOP | 81 | 24-May-13 | |
| ELS & LAN Drops/Receptacles | 81 | 24-May-13 | |
| RSC CIC & C/O Switch | 81 | 24-May-13 | Hold Keyboard for later installation per SMR direction. |
| Pilot House IBNS Trainer / RSC | 81 | 24-May-13 | Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction. |
| IOUs: 21, 23, 53, 71, 91, 93 | 81 | 24-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 5th Turnover IOUs* | 81 | 24-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A01: J2: (3-210-2-1L-A) (BSE A08: J2: LC33-1L-F) (BSE A07: J2; LC25-1L-A10) (BSE A05: J2: LC25-1L-A11) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O. | C-DR Boxes 4, 6, 5, 5A, 9, 18, 20, 32 | 81 | 24-May-13 | Install FDS ITB Modification Kit for the following ITB's; 2, 4, 5, 6, 8, 8A, 9, 19, 19A, 21, & 21A. |
| Oil Lab PC (SCD 70403K) | 81 | 24-May-13 | Includes all cabling, connections, Oil Lab PC, C-DR 40-43, SCD 70403K, | |
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 89 | 01-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| Turnover 6 | ||||
| Continuous Thermal Monitoring System | 92 | 04-Jun-13 | ADACS unit in MER2, including power and all hook-ups | |
| GEDMS Maintenance Group | 92 | 04-Jun-13 | ||
| GEDMS Mesh A BSE A1-A10 Light Off | 92 | 04-Jun-13 | ||
| Turnover 7 | ||||
| SPS-73 ISEA Connectorize SAOP | 98 | 10-Jun-13 | ||
| DVSS - ALL VIROEs, CJBs, Cables (*) | 98 | 10-Jun-13 | ||
| IOU: 92 & Associated UPS, Relay Enclosure, Junction Boxes, and C/O Switches | 98 | 10-Jun-13 | ||
| C-DR Box 2 & 2A | 98 | 10-Jun-13 | ||
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 106 | 18-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| CCS Deck COMPLETE | 113 | 25-Jun-13 | ||
| Potable Water System, incl Tanks, TBs, MOVs, TLIs & Modified Pump Controllers | 114 | 26-Jun-13 | ||
| Ventilation - Engineering, CPS Zone 4, Exhaust & Supply | 116 | 28-Jun-13 | E=SS01-150-1, SS01-150-3, ES01-146-1, ES01-146-3, SS2-203-1, ES01-191-1, SS3-251-2, ES01-258-2, SS2-262-2, SS2-270-1, ES01-243-1, ES01-255-2 |
CPS=SS01-301-2, SS01-305-2, ES01-308-2, ES01-309-2, ES01-308-4
| LO Filter Separator Purifier (SCD 76253K) | 119 | 01-Jul-13 | |
| Remaining fuel tank groups closed & ready to test - SCD 70403K COMPLETE | 120 | 02-Jul-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) |
| All TLI's not previously turned over, Including Redundant, Radar/TDR and associated TBs, JP-5, all electrical work COMPLETE, SCDs 77829K/77269K COMPLETE | 120 | 02-Jul-13 | SCD 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) |
| Pilot House Deck COMPLETE | 123 | 05-Jul-13 | |
| AHSS Install Complete, Including Vent Mod | 131 | 13-Jul-13 | |
| Digital Indicators SCD 77427 COMPLETE | 138 | 20-Jul-13 | Placeholder |
| (*) Install all DVSS Cameras as directed by PMR |
| 70403 | Digital Fuel Fill Control System |
| 71604 | Machinery Control Station/Damage Control Station Upgrade |
| 71605 | Advanced Galley Mod |
| 71615 | Digital Video Surveillance System |
| 71726 | Full IBNS Upgrade |
| 71734 | Joint Biological Point Detect System |
| 77269 | Redundant TLI in GEN HD TK |
| 73088 | Gigabit Ethernet Data Multiplex System |
| 73622 | H2S Detector System in VCHT Rooms |
| 76034 | Emer JP5 Fill to #3 GEN HD TK |
| 76253 | Lube Oil Filter Separator Purifier |
| 76974 | Moriah WS HW For DDG Mod Plan |
| 77259 | EM Log Rpl AN/WSN-9(V)1 Digital Hybrid Speed Log (DHYSL) |
| 77427 | Digital Indicators |
| 77829 | Radar and TDR TLI's for DFM/JP5/PotWtr |
&P
Shipbd Test Major Milestone R9
| DDG 57 GEDMS/MCS/IBNS/DVSS/DFC INTEGRATED TEST SCHEDULE | |||||
| INTERNAL MAJOR MILESTONES - REV9, 19APR13 | |||||
| System | Scheduled | Revised (4/17/13) | Actual End | A+ Dates | |
| Ship Move to BAE | Thursday, February 07, 2013 | 2/7/13 | |||
| DOCK SHIP (Tentative) | Tuesday, March 05, 2013 | 3/5/13 | 1 | ||
| 1 | TURNOVER 1 | Wednesday, April 17, 2013 | 3/15/13 | 44 | |
| 2 | TURNOVER 2 | Wednesday, April 24, 2013 | 51 | ||
| 3 | GEDMS MESH B POWER UP/INITIAL SW LOAD (ISEA) | Monday, April 29, 2013 | 56 | ||
| 4 | DFC (LM2500) TRAINING (ISEA) | Wednesday, May 01, 2013 | 58 | ||
| 7 | TURNOVER 3 | Friday, May 03, 2013 | 60 | ||
| 6 | #1/3/2 SWBD/LC/1SF/2SF TIE-IN/CTM INSTALL - 6-11 MAY | Monday, May 06, 2013 | 63 | ||
| GEDMS TEMPORARY 3GMG (COMMS AVAILABLE)(ISEA) | Wednesday, May 08, 2013 | 65 | |||
| 8 | START FDS HARNESS CHECKS (T/O 1,2,3) (ISEA) | Wednesday, May 08, 2013 | 65 | ||
| 9 | TURNOVER 4 | Wednesday, May 15, 2013 | 72 | ||
| 10 | START FDS INITIAL POWER UP (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 11 | MCS PWR UP/EC/MCS SW LOAD (INCL TIWS) (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 13 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER1) | Saturday, May 18, 2013 | 75 | ||
| 14 | TURNOVER 5 | Friday, May 24, 2013 | 81 | ||
| 16 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER2) | Saturday, May 25, 2013 | 82 | ||
| 18 | START DC SENSOR TESTING (ISEA) | Monday, May 27, 2013 | 84 | ||
| 19 | IBNS POWER UP (ISEA) | Monday, May 27, 2013 | 84 | ||
| 21 | 2 FO TANK GROUPS TURNED OVER START TLI/FCS TESTING | Saturday, June 01, 2013 | 89 | ||
| 22 | TURNOVER 6 | Monday, June 03, 2013 | 91 | ||
| 24 | IBNS SIGNAL VERIFICATION/SW LOAD (ISEA) | Wednesday, June 05, 2013 | 93 | ||
| GEDMS MESH A POWER UP (ISEA) | Wednesday, June 05, 2013 | 93 | |||
| 23 | TURNOVER 7 | Monday, June 10, 2013 | 98 | ||
| 24 | 2 FO TANK GROUPS TURNED OVER CONT' TLI/FCS TESTING | Tuesday, June 18, 2013 | 106 | ||
| UNDOCK | Monday, June 03, 2013 | Thursday, June 20, 2013 | 108 | ||
| 20 | VCHT (TANKS/PIPING/PUMPS) | Friday, June 14, 2013 | Friday, June 21, 2013 | 109 | |
| 26 | SWS SYSTEM (PIPING/PUMPS/MOVs) | Tuesday, June 18, 2013 | Tuesday, June 25, 2013 | 113 | |
| DECK IN CCS COMPLETE | Tuesday, June 25, 2013 | 113 | |||
| POTWTR SYSTEM (PIPING/TANKS/PUMPS/MOVs) | Wednesday, June 19, 2013 | Wednesday, June 26, 2013 | 114 | ||
| 27 | FM/AFFF/HALON (PIPING/PUMPS/MOVs) | Friday, June 14, 2013 | Friday, June 28, 2013 | 116 | |
| 28 | VENT SYSTEM (FUELING/HPT, ENG/CPS-Z4) | Wednesday, June 19, 2013 | Friday, June 28, 2013 | 116 | |
| 29 | LP/HP AIR (PIPING/VALVES/COMPRESSORS) | Friday, June 21, 2013 | Friday, June 28, 2013 | 116 | |
| 30 | MRG LO SYSTEM (PIPING/MRGs/PUMPS/FILTERS/COOLERS) | Saturday, June 22, 2013 | Saturday, June 29, 2013 | 117 | |
| 31 | LO FILTER SEPARATOR PURIFIER | Saturday, June 22, 2013 | Monday, July 01, 2013 | 119 | |
| REMAINING FO TANKS TURNED OVER TO TEST | Tuesday, June 25, 2013 | Tuesday, July 02, 2013 | 120 | ||
| 32 | DECK IN PILOT HOUSE COMPLETE | Friday, July 05, 2013 | 123 | ||
| BLEED AIR (PIPING/VALVES) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | ||
| 33 | STEERING (RUDDERS/RAMS/HPUs) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | |
| 34 | AC PLANTS / CHILL WATER SYSTEM | Friday, June 28, 2013 | Saturday, July 06, 2013 | 124 | |
| EOSS VALIDATION (ISEA) | Wednesday, July 03, 2013 | Sunday, July 07, 2013 | 125 | ||
| 35 | CPP/CRP (PIPING/SHAFTS/PUMPS/HOPM/OD BOX) | Monday, June 24, 2013 | Sunday, July 07, 2013 | 125 | |
| FCS TRAINING FOR SHIPS FORCE (ISEA/NAG) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | ||
| DVSS OPERATOR TRAINING (ISEA) | Friday, July 05, 2013 | Monday, July 08, 2013 | 126 | ||
| 36 | LUBE OIL FILTER SEPARATOR TRAINING (ISEA) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | |
| 400HZ AVAILABLE | Tuesday, July 02, 2013 | Tuesday, July 09, 2013 | 127 | ||
| DIU CALIBRATIONS COMPLETE | Friday, July 05, 2013 | Friday, July 12, 2013 | 130 | ||
| AHSS SYSTEM COMPLETE (INCL VENT MOD) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| JP5 (TANKS/TLIs/PIPING/PUMPS/FILTERS) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| 37 | RSC TRAINING (ISEA) | Monday, July 01, 2013 | Monday, July 15, 2013 | 133 | |
| 38 | FUEL SHIP | Wednesday, July 03, 2013 | Wednesday, July 17, 2013 | 135 | |
| TIWS TRAINING (ISEA) | Tuesday, July 09, 2013 | Monday, July 22, 2013 | 140 | ||
| VENT SYSTEM (HAB, CPS-Z1-3) | Thursday, July 18, 2013 | Thursday, July 25, 2013 | 143 | ||
| 39 | F/O TESTING COMPLETE | Saturday, July 13, 2013 | Saturday, July 27, 2013 | 145 | |
| 40 | HOT PLANT TESTING COMMENCE | Monday, July 15, 2013 | Monday, July 29, 2013 | 147 | |
| 41 | NAVSSI/IFF/67/73 RADAR AVAILABLE FOR IBNS TESTING | Tuesday, July 23, 2013 | Tuesday, July 30, 2013 | 148 | |
| AHSS VENT VELOCITY TESTING (MSR/BIW) | Monday, July 15, 2013 | Wednesday, July 31, 2013 | 149 | ||
| 42 | AHSS CAL/TESTING/TRAINING (ISEA/OEM) | Thursday, August 01, 2013 | Thursday, August 15, 2013 | 164 | |
| AEGIS LIGHT OFF | Saturday, August 03, 2013 | Saturday, August 17, 2013 | 166 | ||
| 43 | AHSS CERTIFICATION (NHRC) | Monday, August 05, 2013 | Monday, August 19, 2013 | 168 | |
| 44 | HAB TURNOVER / MOVE ABOARD COMMENCE | Thursday, August 08, 2013 | Thursday, August 22, 2013 | 171 | |
| HOT PLANT TESTING COMPLETE | Wednesday, August 21, 2013 | Wednesday, September 04, 2013 | 184 | ||
| 46 | PCD | Thursday, August 22, 2013 | Thursday, September 05, 2013 | 185 | |
| 47 | SHIP MOVES TO NAVSTA | Friday, August 23, 2013 | Friday, September 06, 2013 | 186 | |
| 48 | SHIP LOA PREP | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | |
| MCS OVER THE SHOULDER TRAINING (ISEA ~5 days) | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | ||
| IBNS OPERATOR TRAINING | Tuesday, September 03, 2013 | Monday, September 16, 2013 | 196 | ||
| 49 | FUELING / RECEIVE JP5 | Thursday, September 05, 2013 | Thursday, September 19, 2013 | 199 | |
| IBNS IOS/IBNS OPERATOR TRAINING BUFFER | Monday, September 09, 2013 | Monday, September 23, 2013 | 203 | ||
| LOA | Monday, September 16, 2013 | Monday, September 30, 2013 | 210 | ||
| 51 | DOCK TRIALS | Friday, September 20, 2013 | Friday, October 04, 2013 | 214 | |
| 52 | FAST CRUISE | Saturday, September 21, 2013 | Saturday, October 05, 2013 | 215 | |
| 53 | SEA TRIALS | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | |
| IBNS TRAINING UNDERWAY | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | ||
| 54 | END OF AVAIL | Friday, September 27, 2013 | Friday, October 11, 2013 | 221 | |
| 55 | FINAL SOFTWARE LOAD | Post Sea Trials | |||
| 56 | TLI TESTING (FUELING AT SEA) | Post Sea Trials | |||
| FOLLOW-ON IBNS MAINTENANCE TRAINING (TBD) | Post Sea Trials |
GEDMS Checklist
| DDG61 GEDMS CHECKLIST | |||||||||
| BSE | BSE | IOU | C-DR | NEW | USE-A | USE-B | |||
| A1 | Weight Rm | B1 | Supply Strm 4 | 11 | 30 | ET Shop | 11A | ||
| A2 | DC Locker | B2 | Crew 5 | 13 | 28 | 28A | Load Center 1 | 13A | |
| A3 | PW 1-254-6-L | B3 | Supply Support | 14 | 27 | CO PW 02-154-1-L | 14A | ||
| A4 | PW 1-174-01-L | B4 | Pwr Convers Rm | 21 | 18 | Supply Strm 3 | |||
| A5 | CSMC | B5 | Crew 2 | 22 | 21 | EM Shop | 22A | ||
| A6 | PW 1-78-01-L | B6 | Fwd IC | 23 | 20 | PW 2-338-1-L | |||
| A7 | Sonar | B7 | AUX 1 | 31 | 12 & 13 | MER 2 | 31A | 31B | |
| A8 | Crew 1 | B8 | Supply Strm 1 | 32 | 16 | CCS | 32A | 32B | |
| A9 | MER 1 | B9 | Crew 4 | 33 | 23 | 23A | DC Locker | 33A | |
| A10 | Crew 3 | B10 | Crew 6 | 34 | 37 | MER 2 | 34A | 34B | |
| 41 | 17 | Aft IC | 41A | ||||||
| 42 | 24 | CSER 3 | 42A | ||||||
| 51 | 1 | Fwd IC | 51A | ||||||
| 53 | 5 | 5A | TR 2-116-1-T | ||||||
| 54 | 31 | MER 1 | 54A | ||||||
| 61 | 22 | Rep 3 | 61A | ||||||
| 62 | 19 | Aft Steering | 62A | ||||||
| 71 | 9 | Radio | |||||||
| 72 | 15 | Rep 5 | 72A | ||||||
| 73 | 26 | CSMC | 73A | ||||||
| 74 | 11 | MER 1 | 74A | 74C | |||||
| 81 | 10 | CSER 2 | 81A | ||||||
| 82 | 14 | 14A | OPS Office | 82A | |||||
| 83 | 8 | 8A | Aux 1 | 83A | |||||
| 84 | 25 | Admin | 84A | ||||||
| 91 | 6 | GSE Shop/Gage Cal | |||||||
| 92 | 2 | 2A | Sonar 3 | ||||||
| 93 | 4 | CSER 1 | |||||||
| 94 | 7 | Sec Force Locker | 94A | ||||||
| DELETED: | IOU 12 / C-DR29 IOU 52 / C-DR3 |
Tota # of USE = 26