This document is a compilation of contract and invoicing materials for the Arizona Department of Transportation's (ADOT) Multimodal Planning Division, specifically a Statewide Climbing and Passing Lane Study. The contract is with Kimley-Horn and Associates, Inc., a professional consulting firm, under the task assignment MPD0437-24 H80. The document includes a billing summary/reimbursement request, vendor hours contribution table, vendor performance report, invoice for professional services, and a progress report covering work through September 30, 2024.
The contract has a total awarded budget of $249,999.23, with the current invoice requesting $34,357.50 for work performed. The project is federally funded through FHWA and involves developing a statewide study on climbing and passing lanes. The contract includes multiple tasks such as project management, data collection, methodology development, and report preparation. The prime contractor (Kimley-Horn) has no DBE (Disadvantaged Business Enterprise) subcontractors for this project, and the work is being managed by Michael Grandy as the project manager. Current progress includes refining data, submitting working papers, updating GIS maps, and developing prioritization methodology, with anticipated further development of Working Paper 2 in the upcoming month.
View the file
Other files
Show 40 more
Latest 50 of 94 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No Partial - In Progress
0.00% 0
No Billing
Start Date 9/1/2024
Billing End Date
9/30/2024
Originally Awarded
Budget Amount
Approved Modifications
Amount
Total Awarded Budget
$ Invoiced Previously
$ Rejected or Disallowed on
Previous Invoices
$ Remaining Project Budget (Total Awarded - $
Invoiced Previously + $ Rejected on Prev.
Invoices)
$ Paid by ADOT Previously
Purchase Order Balance Prior to
This Invoice (Total Awarded -
$ Paid)
$ Invoiced Today
$ Disallowed ($ Invoiced
Exceeds Remaining
Budget)
Net Amount Due for
This Invoice
Balance After This Invoice
447.00$ 447.00$ 447.00$ 447.00$ -$ $ - $ 447.00
20,000.00$ 20,000.00$ 20,000.00$ 20,000.00$ -$ $ - $ 20,000.00
229,552.23$ 229,552.23$ 117,690.49$ 111,861.74$ 117,690.49$ 111,861.74$ 34,357.50$ -$ $ 34,357.50 $ 77,504.24
TOTALS 249,999.23$ -$ 249,999.23$ 117,690.49$ -$ 132,308.74$ 117,690.49$ 132,308.74$ 34,357.50$ -$ 34,357.50$ 97,951.24$
Date Signed / Invoice Date
10/29/2024 Date Signed / Invoice Date
Phone Number Phone
Number
Please leave blank
SUMMARY OF WORK FOR WHICH PAYMENT IS REQUESTED
Task or Deliverable Description from PO Line (Identifies which PO line(s) should be received for this submission) Additional Optional Information
Task 1 Travel
Task 2 Other Direct Cost
Task 3 Statewide Climbing and Passing Study
Michael.Grandy@kimley-horn.com Please Leave Blank
Prime PM Name (Notify if Unaccepted / Rejected / Paid)
Michael Grandy DBE Commitment % How many DBE Subcontractors performed on the Project?
Invoice Number 29486823
Please Leave BlankPrime PM Email
Billing Summary / Reimbursement Request For use by: Vendors / Contractors / Suppliers of MPD
(Version 07/01/2023)
Heidi Yaqub Project Title
(For Research Project add SPR Number)
Statewide Climbing and Passing Lane Study MPD Tracking Number
{Use Format: MPDnnnn-yy};
{RTAP use " MPDRTAP-yy"}
MPD0437-24 H80 ADOT PM Name
Prime Contractor Firm Name Kimley-Horn and Associates, Inc.
Is the Prime an AZ Certified
DBE?
Project Status
(Select from Drop Down) Purchase Order Number PO0000627483
White Field with RED Text =
Urgent Information
Pink with Red Text = Entry/Correction Required Pale Orange = Form Calculated field
Teal = Label Only - Do not Enter Text
Grey = Disregard Field
FMS PROCESSING - SECTION RESERVED FOR FMS PROCESSING
Invoice Received for Processing Please Leave Blank
Date Received by Optional Comment Optional NoteDate Received by
White Field = Entry in Field Permitted
Pink Field = Mandatory Field
Area Reserved Color Key
ADOT PROGRAM/PROJECT MANAGER REVIEW
Invoicing aligns with Progress and Awarded Budget / Pricing
Support Documents align to Invoice and adequately supports costs
Status Reason for Rejection
Progress toward Scope aligns with Awarded Requirements Invoice Approved
Invoice Rejected
Confirmed - Zero DBE SubContractors performed work on the Project
Please Leave Blank
ADOT PM Signature RequiredTravel charges are in accordance with State/ADOT Policy The ADOT Project Manager is required to review for each of these items.
By approving this invoice, you certify these requirements are met
Michael Grandy SignatureSignature
Michael.Grandy@Kimley-Horn.com Email AddressEmail Address
Submitter: I hereby certify / confirm the above statements Optional 2nd Submitter: I hereby certify / confirm the above statements
This section is only applicable to the FINAL reimbursement request submission - Please leave blank.
Pursuant to 2 CFR 200.415: By signing this report, I certify to the best of my knowledge and belief that the report is true, complete, and accurate, and the expenditures, disbursements and cash receipts are for the purposes and objectives set forth in the terms and conditions of the Federal award. I am aware that any false, fictitious, or fraudulent information, or the omission of any material fact, may subject me to criminal, civil or administrative penalties for fraud, false statements, false claims or otherwise. (U.S. Code Title 18, Section 1001 and Title 31, Sections 3729-3730 and 3801-3812).
I Confirm DBE Goal Committment was made for the Project and No AZ DBE Firms Participated.
3) I certify that my typed in signature below is a legally-binding signature.
Enter Brief Reason for Not Meeting the DBE Commitment for this Project
Federal Funding for this Project (Locate in PO Reference/Description text)
FHWA
Submitter Certification (Required with Every Invoice)
Docusign Envelope ID: AEFE1110-9B5F-448A-AB9C-E2FA0ADB97AA
X
Enter Date Received by MPD and Receipt Number
10/29/2024
REC #1546814
AP RECEIVED 10/30/24Accounts Payable DocuSign10/30/2024 mailto:Michael.Grandy@kimley-horn.com mailto:Michael.Grandy@kimley-horn.com mailto:Michael.Grandy@Kimley-Horn.com mailto:Michael.Grandy@kimley-horn.com mailto:Michael.Grandy@Kimley-Horn.com
Prime Firm Name DBE % 0.00%
Task No
Awarded $ Functional Role Plan Actual Plan Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual
Michael Grandy* Technical Expert 53.0 3.5 5.0 16.0 15.0 28.0 20.0 33.5 41.0 12.0 Brent Crowther Technical Expert 8.0 2.0 3.0 2.0 2.0 2.0 3.0 Curtis Rowe Technical Expert 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Deanna Haase Technical Expert 0.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 Raj Christian Principal 2.0 0.0 0.0 0.0 1.0 0.0 1.0 Keith Christian Consultant 8.0 2.0 32.0 0.0 2.0 2.0 32.0 Chris Joannes Consultant 8.0 20.0 3.0 0.0 24.0 2.0 2.0 Siva Sivakumar Consultant 8.0 2.0 2.0 34.0 3.0 51.0 2.0 Anita Johari Technical Expert 0.0 1.0 8.0 0.0 12.0 2.0 1.0 Allen Hathcock Technical Expert 0.0 1.0 2.0 18.0 2.0 60.0 2.0 Taylor Dunkle Engineer 0.0 3.0 9.0 0.0 3.0 2.0 2.0 Karina Trejo Analyst 17.0 8.0 16.0 51.0 23.0 2.0 4.0 Kristen Faltz Planner 0.0 3.0 10.0 2.0 16.0 2.0 2.0 Joseph Cuffari Planner 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Tom Stafford Analyst 0.0 1.0 2.0 2.0 2.0 40.0 3.0 Giovanni Catanzaro Analyst 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Greg Honiotes Analyst 0.0 14.0 37.0 2.0 18.0 2.0 40.0
$ 51,942.00 $ 29,230.00 $ 16,655.00 $ 34,920.00 $ 30,945.00 $ 26,915.00
Staff Name
Task 7 - Final Report and Executive Summary
Task 8 - Modifications
Not Used Not Used Not Used
AZ Certified
DBE?
$ of Contract Award $ 221,752.00
Task 1 - Project Mgmt
Task 2 - Review
Previous Work/Best Practices
$ 31,145.00
Purchase Order Number PO0000627483
Vendor Hours Contribution Table & DBE Compliance Report MPD Tracking Number MPD0437-24 H80
The hours reported on this table are provided to enable visual assessment by the ADOT Project Manager of progress on work tasks. Race Conscious DBE Goal Commitment 0.00%
This information will also be used to verify that the level of team member and/or individual designated for the task is actually performing the work.
This information will also be used if auditing the project for DBE Commercially Useful Function. Vendor's Invoice Number 29486823
Decreases in DBE Firm Participation or Removal MUST be Authorized by the BECO Office in Advance. Total Project Award 249,999.23$
Please update Actual Hours
Task 3 - Collect Data
Task 4 - Conduct
Interviews and Consultations
Task 5 - Update Methodology, Revise Prioritization/
Recommendation s
Task 6 - Field Visits and
Project Sheets
Ajdin Spahic Analyst 0.0 0.5 26.0 29.0 35.5 2.0 30.0 108.5 2.0 20.0 Jason Getz GIS 2.0 0.0 14.0 4.0 1.0 1.0 6.0 10.0 Justin Gilbert Graphic Designer 4.0 1.0 2.0 2.0 1.0 0.0 6.0 Karen Hanas Admin/Financial Support 4.0 1.0 2.0 0.0 0.0 4.0 2.0 Tamie Schofield Admin/Financial Support 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Alexis Hamilton Admin/Financial Support 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Mike Dayton Admin/Financial Support 16.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0
TOTALS 130.0 6.0 90.0 0.0 187.0 50.5 147.0 0.0 160.0 143.0 220.0 0.0 144.0 0.0
SubContractor Firm
DBE % 0.00%
Task No
Awarded $ Functional Role Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual
Tyrone Atkin Technical Expert 20.0 1.0 1.0 1.0 5.0 2.0 1.0 Katrina Trice-Hall Admin/Financial Support 6.0 0.0 0.0 0.0 0.0 0.0 0.0 Stephanie Admin/Financial Support 6.0 0.0 0.0 0.0 0.0 0.0 0.0
TOTALS 32.0 0.0 1.0 0.0 1.0 0.0 1.0 0.0 5.0 0.0 2.0 0.0 1.0 0.0
SubContractor
Firm
DBE % 0.00%
Task No
Awarded $ Functional Role
See Task 6 Other Direct Costs
$ 20,000.00
Not Used Not Used Task 3 - Collect
Data
Task 4 - Conduct
Interviews and Consultations
Task 5 - Update Methodology, Revise Prioritization/
Recommendation s
Task 6 - Field Visits and
Project Sheets
Task 7 - Final Report and Executive Summary
Task 8 - Modifications
Not Used
$ of Contract Award $ 20,000.00
Task 4 - Conduct
Interviews and Consultations
Task 5 - Update Methodology, Revise Prioritization/
Recommendation s
$ 227.99 $ 227.99 $ 1,139.95
RVD SYSTEMS
AZ Certified
DBE?
Task 6 - Field Visits and
Project Sheets
Task 7 - Final Report and Executive Summary
$ 455.98 $ 227.99
Task 8 - Modifications
Not Used Not Used
HORROCKS
AZ Certified
DBE?
$ of Contract Award $ 8,247.23
Task 3 - Collect Data
Not Used Staff Name
Task 1 - Project Mgmt
Task 2 - Review
Previous Work/Best Practices
$ 5,739.34 $ 227.99
Staff Name
Task 1 - Project Mgmt
Task 2 - Review
Previous Work/Best Practices
Contact Division/Unit
Title Location Address
Email Telephone
Supplier Name Supplier Contact
Contract No. Purchase Order #
Date Invoice #
Project Title Interim VPR
Email Date
Describe details of the action taken:
based on, {with MPD revisions to performance section}:
ADOT Vendor Performance Report (11/21)
Describe Compliance with Invoicing Requirements:
Describe Project Delivery Compared with Schedule:
Describe Project Outcomes Compared with Objectives:
Describe Vendor Performance
Services, Goods or Equipment:
Describe the performance issue. Be accurate, complete and factual. Use an attachment if necessary.
MPD Tracking Number MPD0437-24 H80 Statewide Climbing and Passing Lane Study
PROCUREMENT ACTION
Vendor Performance Report Procurement Office 1739 W. Jackson St., Ste. A, MD 100P
Phoenix, AZ 85007
Email: Procurement@azdot.gov
Documenting positive or negative performance and procurement actions, as requested
Reporting Contact Information
Procurement Officer
PO0000627483
29486823
Reporting Contact Information
Kimley-Horn and Associates, Inc. Michael Grandy
DateSignature of Agency Representative
MPD Contracts will submit an electronic copy of the completed form to the ADOT Procurement Office at Procurement@azdot.gov.
Reporting incident, no action requested.
Requesting action:
Docusign Envelope ID: AEFE1110-9B5F-448A-AB9C-E2FA0ADB97AA
MPD /4210
X
HYaqub@azdot.gov
1611 W Jackson St, Phoenix, AZ 85007
Heidi Yaqub
Performance is within expected standards.
Project Objectives have been met.
Project Delivery was within the agreed upon schedule.
Invoicing requirements were met.
602-712-7644
10/29/2024
Scoping document
Regional/Freight Planner
Please remit payment electronically to: If paying by check, please remit to:
Account Name: KIMLEY-HORN AND ASSOCIATES, INC. KIMLEY-HORN AND ASSOCIATES, INC.
Bank Name and Address: WELLS FARGO BANK, N.A., SAN FRANCISCO, CA 94104 P.O. BOX 913221 Account Number:
ABA#:
2073089159554 121000248
DENVER, CO 80291-3221
Please send remittance information to: payments@kimley-horn.com
10pt blank space
ARIZONA DEPARTMENT OF TRANSPORTATION
MULTIMODAL PLANNING DIVISION
ATTN: HEIDI YAQUB
206 SOUTH 17TH AVE, MD310B
PHOENIX, AZ 85007
Federal Tax Id: 56-0885615 For Services Rendered through Sep 30, 2024
Invoice Amount: $34,357.50
Invoice No: 29486823 Invoice Date: Sep 30, 2024
Project No: 291199017.3 Project Name: ADOT CLIMB-PASSLANE STUDY Project Manager: GRANDY, MICHAEL
Client Reference: MPD0437-24
PO0000627483
Description Contract Value Amount Earned to Date Previous Amount
Billed Current Amount
Due
SERVICES RENDERED 249,999.23 152,047.99 117,690.49 34,357.50
291199017.3 Total Invoice: $34,357.50
If you have questions, please contact Mike Dayton at (602) 789-3848, or Mike.Dayton@kimley-horn.com 81MRD
002072291199017.3W10563291199017.3CPM-1DTCPM
Task Category Description/Name Hrs/Qty Rate Current Amount
Due
PROJECT MGMT ADMIN/FINANCIAL SUPPORT DAYTON, MIKE 1.0 125.00 125.00
ANALYST SPAHIC, AJDIN 0.5 135.00 67.50
TECHNICAL EXPERT GRANDY, MICHAEL 3.5 275.00 962.50
HAASE, DEANNA 1.0 275.00 275.00
TOTAL PROJECT MGMT4T 6.0 1,430.00
DATA COLLECTION ANALYST SPAHIC, AJDIN 35.5 135.00 4,792.50
TECHNICAL EXPERT GRANDY, MICHAEL 15.0 275.00 4,125.00
TOTAL DATA COLLECTION2T 50.5 8,917.50
METHODOLOGY & PRIORITY ANALYST SPAHIC, AJDIN 108.5 135.00 14,647.50
GIS GETZ, JASON 1.0 150.00 150.00
TECHNICAL EXPERT GRANDY, MICHAEL 33.5 275.00 9,212.50
TOTAL METHODOLOGY & PRIORITY3T 143.0 24,010.00
TOTAL LABOR AND EXPENSE DETAIL 34,357.50
HOURLY NOT TO EXCEED
10/29/2024 ADOT MPD_0437-24_H80_Update_Progress Report_Sept 2024(Climb & Pass Lane Study).docx 1 of 2
PROGRESS REPORT NO. 9
Arizona Department of Transportation
Task Assignment: MPD0437-24 H80
ADOT Statewide Climbing and Passing Lane Study Contract # CTR060474
Kimley-Horn Project No. 291199017
Reporting Period: Through September 30, 2024
Key Project Staff
Michael Grandy, Project Manager Raj Christian, Principal Brent Crowther, QA/QC
Progress and Accomplishments during the Reporting Period
Task 1 – Project Management Conducted project management activities Updated project schedule Coordinated with Heidi Yaqub
Task 2 – Review Previous Work/Best Practices
No activity during invoice period
Task 3 – Collect Data
Refined data Refined and submitted Working Paper 1 for review
Task 4 – Conduct Interviews and Consultations
Task 5 – Update Methodology, Revise Prioritization/Recommendations
Refined prioritization methodology Updated GIS maps showing prioritization results Updated prioritization tables Developed Working Paper 2
Task 6 – Field Visits and project Sheets
Task 7 – Final Report and Executive Summary
No activity during invoice period
Contacts Made
Coordinated with Heidi Yaqub
Information Generated
ADOT review comments
10/29/2024 ADOT MPD_0437-24_H80_Update_Progress Report_Sept 2024(Climb & Pass Lane Study).docx 2 of 2
Next Month Anticipated Activities
Further development on Working Paper 2
| BillingReport |
| VendorHoursContribution |
| Vendor Performance Report |
| 2024-10-30T09:41:41-0700 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .