KC135_AERO_I_Contract_CSDR_Plan.xls
XLS spreadsheet 94 KB Posted
- Attached to
- KC-135 Aero-I SATCOM Replacement Federal contract opportunity
- Solicitation number
- KC-135_Aero-I
About this file
This document contains a cost and software data reporting plan and work breakdown structure for the KC-135 Aero-I SATCOM Replacement program. The program will replace the current INMARSAT Aeronautical Intermediate SATCOM system used in 400 KC-135 aircraft for oceanic air traffic control communications and messaging. The replacement system is planned to utilize Iridium SATCOM service and include a new SATCOM antenna, transceiver, and associated components. The cost and software data reporting plan provides a work breakdown structure detailing reporting requirements for cost, schedule, and software data deliverables. Key reporting dates are identified for initial, interim, and final contract completion reports through 2024. The plan also includes definitions for recurring and non-recurring costs.
An associated federal contract opportunity notice solicits information from potential offerors for the KC-135 Aero-I SATCOM Replacement program. Interested sources are requested to provide capability statements by April 30, 2018 addressing experience, facilities, processes for hardware production, software development, repair, and technical data packages. The Air Force will host an industry day on May 8, 2018 to provide program details and hold one-on-one briefings with interested sources. The replacement is intended to address support issues with the current system and INMARSAT's discontinuation of the Aero-I service by December 2022.
Approved Cost and Software Data Reporting (CSDR) Plan for Aero-I
View the file
Other files for this federal contract opportunity
Show all 38
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD Form 2794, Pg 1
COST AND SOFTWARE DATA REPORTING/EARNED VALUE MANAGEMENT CO-PLAN Form Approved OMB No. 0704-0188 The public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.
| 1. MAJOR PROGRAM | a. NAME: | KC-135 Aero-I SATCOM Replacement | ||||||||||||||||
| b. PHASE/MILESTONE | c. PRIME MISSION PRODUCT | 2. WBS SYSTEM TYPE | 3. SUBMISSION TYPE | 4. CURRENT SUBMISSION DATE (YYYYMMDD) | 5. LAST APPROVED PLAN DATE (YYYYMMDD) | |||||||||||||
| Pre-A | B | C-FRP | AERO-I | Electronic System | X | INITIAL | ||||||||||||
| A | X | C-LRIP | O&S | CHANGE | 20190227 | |||||||||||||
| 6a. POINT OF CONTACT (POC) NAME AND ADDRESS (Include ZIP Code) | 6b. TELEPHONE NUMBER (Include Area Code) | 6c. FAX NUMBER (Include Area Code) | 6d. E-MAIL ADDRESS | |||||||||||||||
| Jacqueline Burns/Bldg 3001 Ste 2AG1/88G, Tinker AFB, OK, 73145 | 405-734-2736 | jacqueline.burns.4.ctr@us.af.mil | ||||||||||||||||
| 7. PLAN TYPE | 8. PREPARING ORGANIZATION | 9a. CONTRACTOR NAME/ADDRESS | 9b. CONTRACT NUMBER | 9c. APPROPRIATION | 10. APPROVED PLAN NUMBER | |||||||||||||
| PROGRAM | X | CONTRACT (PRIME) | i. PERFORMING ORGANIZATION | ii. DIVISION | TBD | RDT&E | AF-19-G1 | |||||||||||
| CONTRACT (SUB) | AFLCMC/WKDM | TBD | X | PROCUREMENT | ||||||||||||||
| O&M | ||||||||||||||||||
| 11. WBS ELEMENT CODE | 12. | |||||||||||||||||
| WBS REPORTING ELEMENTS | 13. REPORTS REQUIRED | |||||||||||||||||
| (X if applicable) | DD 1921-3 (CBDR): | DD 1921-1 / 1921-5 EAC: | EVM Reporting: | |||||||||||||||
| X | ||||||||||||||||||
| a. PROGRAM/ | ||||||||||||||||||
| CONTRACT/ SUBCONTRACT | b. CONTRACT/ | |||||||||||||||||
| SUBCONTRACT | a. CWBS | |||||||||||||||||
| DICTIONARY | CCDR | g. SRDR | ||||||||||||||||
| FORMATS | h. IPMR |
FORMAT 1
| b. DD 1921 | |||||||||||||||
| (CDSR) | c. DD 1921-1 | ||||||||||||||
| (FCHR) | d. DD 1921-2 | ||||||||||||||
| (PCR) | e. DD 1921-5 | ||||||||||||||
| (SFCHR) | f. EAC | ||||||||||||||
| 1.0 | Electronic System | X | X | X | X | ||||||||||
| 1.1 | Prime Mission Product (PMP) | X | X | X | X | X | |||||||||
| 1.1.1 | PMP Integration, Assembly, Test, and Checkout | X | X | X | X | X | |||||||||
| 1.1.2 | PMP Subsystem 1 (A Kit) | X | X | X | |||||||||||
| 1.1.2.1 | Subsystem Integration and Assembly | X | X | X | |||||||||||
| 1.1.2.2 | Subsystem Test and Checkout | X | X | X | X | ||||||||||
| 1.1.2.3 | Subsystem Hardware 1 (A Kit) | X | X | X | |||||||||||
| 1.1.2.3.1 | Wiring Harness | X | X | X | |||||||||||
| 1.1.2.3.2 | Cabling and Associated Components | X | X | X | |||||||||||
| 1.1.3 | PMP Subsystem 2 (B Kit) | X | X | X | X | ||||||||||
| 1.1.3.1 | Subsystem Integration and Assembly | X | X | X | |||||||||||
| 1.1.3.2 | Subsystem Test and Checkout | X | X | X | |||||||||||
| 1.1.3.3 | Subsystem Hardware 2 (B Kit) | X | X | X | |||||||||||
| 1.1.3.3.1 | Iridium Transciever | X | X | X | X | ||||||||||
| 1.1.3.3.2 | Iridium Antenna | X | X | X | X | ||||||||||
| 1.2 | Integration, Assembly, Test, and Checkout | X | X | X | |||||||||||
| 1.2.1 | System Integration Lab (SIL) Integration | X | X | X | X | ||||||||||
| 1.3 | Systems Engineering | X | X | X | X | ||||||||||
| 1.3.1 | SEMP (Annex) | X | X | X | |||||||||||
| 1.3.2 | Requirements Management | X | X | X | |||||||||||
| 1.3.3 | Airworthiness Management | X | X | X | |||||||||||
| 1.3.4 | Other Systems Engineering | X | X | X | |||||||||||
| 1.4 | Program Management | X | X | X | X | ||||||||||
| 1.4.1 | Integrated Logistics Support (ILS) Program Management | N/A | N/A | ||||||||||||
| 1.4.2 | Cybersecurity Management | X | X | X | |||||||||||
| 1.4.3 | Core Program Management | X | X | X | |||||||||||
| 1.4.4 | Other Program Management | X | X | X | |||||||||||
| 1.4.4.1 | LCSP/LCMP (annex) | X | X | X | |||||||||||
| 1.4.4.2 | Integrated Master Plan (IMP) | X | X | X | |||||||||||
| 1.4.4.3 | Integrated Master Schedule (IMS) | X | X | X | |||||||||||
| 1.4.4.4 | Risk Management Plan (Annex) | X | X | X | |||||||||||
| 1.4.4.5 | Product Support Elements | X | X | X | |||||||||||
| 1.5 | System Test and Evaluation | X | X | X | |||||||||||
| 1.5.1 | Development Test and Evaluation | NA | N/A | ||||||||||||
| 1.5.2 | Operational Test and Evaluation | X | X | X | |||||||||||
| 1.5.3 | Cybersecurity Test and Evaluation | X | X | X | |||||||||||
| 1.5.3.1 | Cybersecurity Development Test | X | X | X | |||||||||||
| DD FORM 2794, AUGUST 2015 | PREVIOUS EDITION IS OBSOLETE | ||||||||||||||
| 11. WBS ELEMENT CODE | 12. | ||||||||||||||
| WBS REPORTING ELEMENTS | 13. REPORTS REQUIRED | ||||||||||||||
| (X if applicable) | DD 1921-3 (CBDR): | DD 1921-1 / 1921-5 EAC: | EVM Reporting: | ||||||||||||
| X | |||||||||||||||
| a. PROGRAM/ | |||||||||||||||
| CONTRACT/ SUBCONTRACT | b. CONTRACT/ | ||||||||||||||
| SUBCONTRACT | a. CWBS | ||||||||||||||
| DICTIONARY | CCDR | g. SRDR | |||||||||||||
| FORMATS | h. IPMR |
FORMAT 1
| b. DD 1921 | ||||||||||
| (CDSR) | c. DD 1921-1 | |||||||||
| (FCHR) | d. DD 1921-2 | |||||||||
| (PCR) | e. DD 1921-5 | |||||||||
| (SFCHR) | f. EAC | |||||||||
| 1.5.3.2 | Cybersecurity Operational Test | X | X | X | ||||||
| 1.5.4 | Mock-ups/System Integration Labs (SILs) | X | X | X | X | |||||
| 1.5.5 | Test and Evaluation Support | X | X | X | X | |||||
| 1.5.6 | Test Facilities 1...n (Specify) | X | X | X | X | |||||
| 1.6 | Training | N/A | N/A | |||||||
| 1.7 | Data | X | X | X | X | |||||
| 1.7.1 | Data Deliverables | X | X | X | ||||||
| 1.7.1.1 | Support Data | X | X | X | ||||||
| 1.7.1.1.1 | Ram-C Data | X | X | X | ||||||
| 1.7.1.1.2 | Provisioning Data | X | X | X | ||||||
| 1.7.1.2 | Management Data | X | X | X | ||||||
| 1.7.1.3 | Engineering Data | X | X | X | ||||||
| 1.7.1.3.1 | Drawings | X | X | X | ||||||
| 1.7.1.3.2 | Source Data | X | X | X | ||||||
| 1.7.1.3.3 | Airworthiness Data | X | X | X | ||||||
| 1.7.1.4 | Technical Publications | X | X | X | X | |||||
| 1.7.1.4.1 | Maintenance Manuals/Tech Orders | X | X | X | X | |||||
| 1.7.1.4.2 | Aircrew Manuals | X | X | X | X | |||||
| 1.7.1.4.3 | Commodity Technical Orders | X | X | X | ||||||
| 1.7.1.5 | Time Compliance Tech Order | X | X | X | X | |||||
| 1.7.2 | Data Repository (JEDMICS) | X | X | X | ||||||
| 1.7.3 | Data Rights | N/A | N/A | |||||||
| 1.8 | Peculiar Support Equipment | N/A | N/A | |||||||
| 1.9 | Common Support Equipment | N/A | N/A | |||||||
| 1.10 | Operational/Site Activation | N/A | N/A | |||||||
| 1.11 | Contractor Logistics Support | N/A | N/A | |||||||
| 1.12 | Industrial Facilities | N/A | N/A | |||||||
| 1.13 | Initial Spares and Repair Parts | X | X | |||||||
| Subtotal Cost | X | X | ||||||||
| Reporting Contractor G&A | X | X | ||||||||
| Reporting Contractor Undistributed Budget | X | X | ||||||||
| Reporting Contractor Management Reserve | X | X | ||||||||
| Reporting Contractor FCCM | X | X | ||||||||
| Total Cost | X | X | ||||||||
| Reporting Contractor Profit/Loss or Fee | X | X | ||||||||
| Total Price | X | X | ||||||||
| DD FORM 2794, AUGUST 2015 | PREVIOUS EDITION IS OBSOLETE |
DD Form 2794, Pg 2
| 14. CSDR SUBMISSION DATES | |||||||
| a. | |||||||
| SUBMISSION | b. | ||||||
| FORM(S) | c. | ||||||
| EVENT | d. | ||||||
| REPORT TYPE | e. AS OF DATE | f. DUE DATE | |||||
| (YYYYMMDD) | (YYYYMMDD) | ||||||
| 1 | CWBS Dictionary | Contract Award CWBS Dictionary (plus 12 months) | Initial | 20201231 | 20210302 | ||
| 2 | 1921, 1921-1, 1921-2 | Contract Award CCDR (plus 12 months) | Initial | 20201231 | 20210302 | ||
| 3 | 1921, 1921-1, 1921-2 | Annual CSDR #1 | Interim | 20211231 | 20220302 | ||
| 4 | 1921, 1921-1, 1921-2 | Annual CSDR #2 | Interim | 20221231 | 20230302 | ||
| 5 | 1921, 1921-1, 1921-2 | Annual CSDR #3 | Interim | 20231231 | 20240301 | ||
| 6 | 1921, 1921-1, 1921-2 | Contract Completion - Final CSDR | Final | 20240731 | 20240930 | ||
| 15. REMARKS | |||||||
| NON-RECURRING/RECURRING DEFINITIONS | |||||||
| Recurring cost results from repetitive activities that vary with the quantity being produced. Nonrecurring cost results from non-repetitive activities that do not vary with the quantity being produced. |
Prime Mission Equipment (PME): Recurring hardware costs include fabrication; procurement of raw materials, purchased parts and equipment, and major and minor subcontracts; touch labor; integration and assembly; installation and checkout; engineering support for unit fabrication and quality control/assurance/inspection and certain elements of systems engineering and program management. Examples of software design and development activities include design and development of all software; delivered operational software and software developed to correct deficiencies and add capabilities; Initial integration of COTS and GOTS products into operational configuration; Support for HW-SW integration and test, system level testing; initial integration of COTS and GOTS products into operational configuration; and commercial software licenses for development facilities.
Nonrecurring PME activities include design and development effort such as preliminary, critical prototype and test article design activities, and software design and maintenance, regardless of whether the purpose is to correct deficiencies or add capabilities. In the development phases, hardware component costs are nonrecurring until such times as those components are no longer prototypical but are protoqual, i.e. ready to be delivered on a recurring basis as operational representative. Components, sub-assemblies, assemblies with 100% complete design are considered operational representative. Test articles built to an operational configuration are considered operational representative. The costs of operational representative items are recurring. Subcontractor, vendor, and supplier cost should be obtained and reported in recurring and nonrecurring categories, wherever reasonably possible. (If vendor amortizes their nonrecurring costs across a lot buy resulting in non-visibility of a recurring/nonrecurring split, annotate as such.)
Non-PME System Test and Evaluation (ST&E) activities are typically nonrecurring such as non-production-representative test articles built for testing purposes only such as test stands, bench and coupon test articles; structural development, static, fatigue, software, and ballistics testing; stress analysis; flight or ground testing of system properties; redesign as a result of testing; and retesting efforts. System Engineering, Program Management, and Data activities occur throughout the system life cycle and are supportive in nature; as such, these costs take on the characteristics of the underlying activities being performed.
Nonrecurring cost categories include design and development of Support Equipment and Training devices; Support Equipment and Training activity such as initial equipment design and test efforts, test program sets, initial courseware development, and simulator development are nonrecurring. Training and Support Equipment efforts are recurring when they pertain to repetitive activities that vary with the quantity of training devices or support items being produced. Initial Spares and Repair Parts are recurring as they pertain to repetitively producing hardware. Industrial Facilities are nonrecurring as well as nonrecurring tooling activities such as special test equipment, special tooling, procurement of initial and rate tooling, tool replacement (with exact same tool), and tool modification (to accommodate product configuration changes). For situations not explicitly addressed above, categorize any cost as recurring if it represents repetitive effort that is sensitive to quantity.
| COST ACCOUNTING STANDARDS (CAS) DISCLOSURE STATEMENT DIFFERENCES |
| Describe significant accounting changes from previous accounting period in the Remarks section of the reports, if applicable. |
| 1921-3 CONTRACTOR BUSINESS DATA REPORT |
| a. The Contractor Business Data Report is prepared by and for the business entity (e.g., business unit, segment, or site) responsible for submitting the Forward Pricing Rate Proposal (FPRP) representing the basis for Forward Pricing Rate Agreement (FPRA) negotiations with the government. |
b. Reports are submitted annually at the end of the contractor's fiscal year.
c. Data for Future Years should be reflective of the number of years contained in the most current document, i.e., the FPRP or the FPRA. If the document applies to more than three future years, attach additional future year sheets as required. In the absence of these documents, estimates should be provided for three future years.
d. The existing 1921-3 requires strictly formatted data and necessitates mappings to a government standard, the new DRAFT 1921-3 may be submitted in the contractor’s own format and according to the contractor’s own rate structure, so long as it meets the data requirements in the DRAFT 1921-3 Data Item Description DI-FNCL-81765.
| 1921-2 PROGRESS CURVE REPORT |
| a. Unit or Lot Reporting: Reporting to be provided by UNIT/SUBLOT/LOT. |
b. Product Characteristics: 1921-2 must include the WEIGHT and POWER.
| FAC | |
| The checkmarks for EACs in column 13f at the WBS level shall be reported as "Forecast at Completion" (FAC). The Forecast At Completion (FAC) required here is not subject to the standards established in ANSI/EIA-748 guideline #27 (Estimate at Complete); therefore, the FAC does not need to be, but may be, derived from Industry Earned Value Management (EVM) processes. | |
| Final Cost Report | |
| Final Cost Report to be submitted when final end item has been delivered and accepted by the government (e.g., as evidenced by a completed DD 250) and 95% or more of total contract costs have been incurred. | |
| PoP | |
| If contract Period of Performance is extended, the contractor shall submit an additional cost report for each additional year of extension. The final report will be moved to the revised end of the Period of Performance. | |
| DD FORM 2794 (PAGE 2), AUGUST 2015 | PREVIOUS EDITION IS OBSOLETE |