ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_1.pdf

PDF 4 MB Posted

Attached to
Effluent Sprayfields and Pipeline Route Clearing Grubbing State and local contract opportunity
Solicitation number
ITB-2026-01 A
Issued by
Santa Rosa County, Florida

About this file

This addendum package comprises formal bid solicitation documents for the City of Milton, Florida's Effluent Sprayfields and Pipeline Route Clearing and Grubbing project (ITB-2026-01), including specifications, general conditions, supplementary conditions, and supporting contract documents prepared by Baskerville-Donovan, Inc. The project involves clearing and grubbing approximately 350 wooded acres in preparation for an effluent disposal system for sod farming, including removal of trees, snags, logs, brush, stumps, and rubbish from designated areas with disposal. A mandatory pre-bid meeting is scheduled for January 13, 2026 at 10:00 a.m. CST at City Hall (6738 Dixon Street, Milton, FL 32570). Written questions must be submitted by January 15, 2026 at 2:00 p.m. CST, with answers posted by January 23, 2026. Sealed bids are due February 4, 2026 at 2:00 p.m. CST and will be opened publicly the same day. The contract includes two bid items: general conditions/mobilization (not to exceed 10 percent of total bid) and sitework/clearing and grubbing for approximately 295 acres. The work must be substantially completed within 360 days and fully completed within 390 days of the Notice to Proceed, with liquidated damages assessed at $500 per day for delays beyond these milestones.

Pricing shall be submitted on a lump-sum basis for general conditions and a per-acre unit price basis for clearing and grubbing work. The contractor must provide a 5 percent bid bond and, upon award, furnish 100 percent performance and payment bonds. Contractor's bid must include all materials, equipment, labor, and applicable sales taxes. The City of Milton is exempt from sales tax, but contractors are responsible for all applicable taxes. Mandatory insurance includes commercial general liability ($1,000,000 general aggregate), automobile liability ($1,000,000), workers' compensation (statutory), and builder's risk coverage on a completed value basis. Potential funding sources include the State Revolving Fund Loan Program, RESTORE Act Grant Program, Florida Department of Environmental Protection Resiliency Grant Program, and other state and federal funds. The project is subject to prevailing wage requirements under the Davis-Bacon Act, American Iron and Steel provisions, equal employment opportunity requirements including minority and women business enterprise participation goals, E-Verify employment eligibility verification, and federal compliance with the Build America, Buy America provision. Environmental compliance includes gopher tortoise burrow protection (25-foot radius), eastern indigo snake protection measures with specified notification protocols to U.S. Fish and Wildlife Service, and black bear incident procedures.

View the file

Other files for this state and local contract opportunity

Other files attached to Effluent Sprayfields and Pipeline Route Clearing Grubbing, newest first.
File Type Posted
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_5_Combined.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_4_Contract_Exhibits_B_-_K.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_4_Contract.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3_Site_Clearing.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3_Jan_13_2026_Pre_Bid_Meeting_Minutes.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3_Temp_Storm_Water_Pollution_Control.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_2.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3_Bid_Form.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_3_Special_Conditions.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Construction_Plans.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing_-_Addendum_1.pdf PDF
ITB-2026-01_Effluent_Sprayfields_and_Pipeline_Route_Clearing_Grubbing.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS AND CONTRACT DOCUMENTS

FOR

EFFLUENT SPRAYFIELDS AND PIPELINE ROUTE

CLEARING AND GRUBBING

PREPARED FOR:

CITY OF MILTON

P.O. BOX 909

MILTON, FL 32572

PREPARED BY:

BASKERVILLE-DONOVAN, INC.

449 WEST MAIN STREET

PENSACOLA, FLORIDA 32502

ENGINEERING BUSINESS NO. EB-0000340

BDI PROJECT NO. 25570.06

RELEASE FOR BID

December 2025

THIS PAGE LEFT BLANK INTENTIONALLY

J. Wiesner, P.E.

BDI/PNS

01/05/2026

25570.06 TABLE OF CONTENTS Page 1 of 2

TABLE OF CONTENTS

EFFLUENT SPRAYFIELDS AND PIPELINE ROUTE CLEARING AND GRUBBING

Division Section Title Pages

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

1 - ITB 2026.01 EFFLUENT SPRAYFIELDS AND PIPELINE ROUTE CLEARING AND GRUBBING

INVITATION TO BID

2 – C-451 EJCDC QUALIFICATIONS STATEMENT 12

3 - C-200 EJCDC INSTRUCTIONS TO BIDDERS 12

4 - BID FORM 8

5 - C-430 EJCDC BID BOND 4

6 - C-510 EJCDC NOTICE OF AWARD 2

7 - C-520 EJCDC AGREEMENT 8

8 - C-550 EJCDC NOTICE TO PROCEED 2

9 - C-610 EJCDC PERFORMANCE BOND 4

10 - C-615 EJCDC PAYMENT BOND 4

11 – C-620 EJCDC APPLICATION FOR PAYMENT 4

12 – C-625 EJCDC CERTIFICATE OF SUBSTANTIAL COMPLETION 2

13 – EJCDC C-700 STANDARD GENERAL CONDITIONS 70

14 – EJCDC C-800 SUPPLEMENTARY CONDITIONS 8

15 – CERTIFICATE OF OWNERS ATTORNEY 2

16 – FDEP SUPPLEMENTARY CONDITIONS 28

17 – C-941 EJCDC CHANGE ORDER 2

SPECIFICATIONS GROUP

General Requirements Subgroup

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 SUMMARY 4

01 26 00 CONTRACT MODIFICATION PROCEDURES 2

01 29 00 PAYMENT PROCEDURES 6

01 31 00 PROJECT MANAGEMENT AND COORDINATION 10

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION 8

01 32 16 CONSTRUCTION PROGRESS SCHEDULE 4

01 32 33 PHOTOGRAPHIC DOCUMENTATION 4

01 40 00 QUALITY REQUIREMENTS 10

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL 2

01 73 00 EXECUTION 4

01 77 00 CLOSEOUT PROCEDURES 4

J. Wiesner, P.E.

BDI/PNS

01/05/2026

25570.06 TABLE OF CONTENTS Page 2 of 2

Site and Infrastructure Subgroup

DIVISION 31 - EARTHWORK

31 10 00 SITE CLEARING 4

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 00 SEEDING 2

ATTACHMENT

Attachment 1A STANDARD PROTECTION MEASURE FOR THE EASTERN

INDIGO SNAKE

Attachment 1B EASTERN INDIGO SNAKE BROCHURE

Attachment 1C EASTERN INDIGO SNAKE POSTER

Attachment 1D EASTERN INDIGO SNAKE MONITORING REPORT

Attachment 2 TREASURY RESTORE ACT TERMS AND CONDITIONS

Attachment 3 CSI FORM 13.4A

Attachment 4 CSI FORM 13.6A

END OF TABLE OF CONTENTS

Company Name Page 1 of 20

City of Milton P.O. Box 909, MILTON, FL 32572

Phone: (850) 983-5480

M E M O R A N D U M

TO: Interested Parties

FROM: Michele Williams, Purchasing Officer

RE: 2026.01 ITB Effluent Sprayfield 2 and Pipeline Route Clearing and Grubbing

DATE: January 01, 2026

Notice is hereby given that the City of Milton (City), will receive sealed bids for 2026.01 ITB

Effluent Sprayfields and Pipeline Route Clearing and Grubbing Project. The documents contain the necessary information for preparing and submitting your bid for this effort.

Information is available on the City’s web page at https://MiltonFL.org/322/Purchasing. There you may also register through BidNetDirect.com/florida/city-of-milton (there is no charge to join);

and/or through DemandStar.com (there is no charge to join); and/or through Office of Supplier

Diversity (there is no charge to join).

All must review the Project Description and Terms and Conditions described in this document to ensure their ability to perform as indicated.

The deadline for submitting your sealed bid/proposal is:

Wednesday, February 04, 2026 at 2:00 p.m. (CST) Hand Delivered: 6738 Dixon Street, Milton, Florida 32570

Mailed: 6738 Dixon Street, Milton, Florida 32570

Bids will be opened on Wednesday, February 04, 2026 at 2:00 p.m. (CST), at the City of Milton

Council Chamber located at 6738 Dixon Street, Milton, Florida 32570.

Questions are to be submitted in writing to the Purchasing department via e-mail to mwilliams@miltonfl.org by Thursday, January 15, 2026, at 2:00 p.m. (CST), and the contact number for the Purchasing department is (850) 983-5480. Answers will be posted in an addendum on the City webpage, Bid Net Direct, DemandStar.com, and Office of Supplier Diversity by Friday, January 23, 2026, at 2:00 p.m. (CST).

The Engineer Design Firm is Baskerville-Donovan, Inc., 449 W Main Street, Pensacola, Florida, 32502, phone number:

(850) 438-9661. Sealed bids will be accepted by the City of Milton at 6738 Dixon Street, Milton, FL 32570 for the

Project.

Interpretations, clarification of specifications, and requirements or changes to the documents which have a material effect on the project and bidding process will be documented and communicated only by written addendum posted on the City’s web page, Bidnet Direct, DemandStar, and Office of Supplier Diversity. All are responsible for checking for any addendums that may be issued, and to obtain such addendums.

Michele Williams Michele Williams, Purchasing Officer

Company Name

INSTRUCTIONS

2026.01 ITB Effluent Sprayfields and Pipeline Route Clearing and Grubbing Project

I. Deadlines/Dates:

Invitation to Bid Published: Thursday, January 01, 2026 Mandatory Prebid Tuesday, January 13, 2026 @ 10:00 am (CST)

Questions Deadline: Thursday, January 15, 2026 @ 2:00 p.m. (CST)

Answers Posted by: Thursday, January 23, 2026 @ 2:00 p.m. (CST)

Bids Due: Wednesday, February 04, 2026 p.m. (CST)

II. Contact Information:

Contact: Michele Williams, Purchasing Officer

Phone: (850) 983-5480

Email: mwilliams@miltonfl.org

III. Bids Must be Complete and Include:

1. Bidder’s/Proposer’s Declaration

2. References

3. Public Entity Crime Form F.S. 287.133(3)(A)

4. Drug-Free Workplace Form F.S. 287.087

5. Non-Collusion Affidavit

6. Conflict of Interest Disclosure Form

7. E-Verify Statement of Compliance

8. Certificate Regarding Debarment

IV. Copies:

Please provide one (1) electronic copy, one (1) original, and one (1) copy of your bid/proposal.

V. Faxed or emailed submittals are not accepted.

Submittals can be delivered to: City of Milton

Attn: Purchasing Department

6738 Dixon Street

Milton, Florida 32570

Submittals must be sealed and marked:

To: C i ty of Milton

VENDOR Name:

SEALED BID * DO NOT OPEN

Sealed ITB# 2026.01

Title: 2026.01 ITB Effluent Sprayfields and Pipeline Route Clearing and Grubbing

DUE DATE/TIME: February 04, 2026 / 2:00 p.m. (CST)

BIDDER’S/PROPOSER’S DECLARATION

2026.01 ITB Effluent Sprayfields and Pipeline Route Clearing and Grubbing

The bidder/proposer understands, agrees, and warrants:

1. These items apply to and become a part of the terms and conditions of the bid/proposal submitted. Any exceptions must be in writing.

2. All bids submitted shall be subject to acceptance or rejection. The City of Milton specifically reserves the right to accept or reject any or all bids, to waive any technicalities and formalities in the bid process, and to award the bid in part or in any manner deemed to be in the best interest of the City.

3. All proposals submitted shall be subject to acceptance or rejection. The City of Milton specifically reserves the right to accept or reject any or all proposals, to waive any technicalities and formalities in the proposal process, and to award the proposal in part or in any manner deemed to be in the best interest of the City.

4. The City of Milton is exempt from sales tax.

5. Contractors are responsible for any sales tax on purchases for the project.

6. The City of Milton, Florida will receive sealed bids from interested parties at Milton City

Hall located at 6738 Dixon Street, Milton, FL 32570. Any submittals received after the deadline will not be considered.

7. Bids/proposals will be publicly opened and read at City Hall located at 6738 Dixon Street, Milton, FL 32570, on the submission deadline date.

8. The City of Milton may consider as non-responsive, any bid/proposal in which there is an alteration of, or departure from the bid/proposal form hereto attached.

9. The bid/proposal will be awarded according to criteria stated under Terms and Conditions of this Invitation to Bid.

10. Interested Parties shall submit all required forms and information simultaneously with their sealed bid/proposal. Forms and information become a part of the property of the

City of Milton and will not be returned to the firm unless a written request to withdraw a bid is received prior to opening of bids/proposals.

11. For Bids-Additional Quantities: For a period not exceeding twelve (12) months from the day of the solicitation opening, the right is reserved to purchase any number of additional items at the prices offered in this solicitation. If additional quantities are not acceptable, the bid form shall be noted “offer is for specified quantity only.”

12. For Bids/NOTE: Unless stated on the bid form, the bid submitted will assume all specifications will be met. Please note all exceptions on the bid form.

13. The successful bidder/proposer will be required to submit additional forms, which are available on the City’s website at https://MiltonFL.org/322/Purchasing at the bottom of the page.

Certificate of Non-Discrimination

W-9 Taxpayer Identification Number

Vendor Application

TERMS AND CONDITIONS

Please review these Terms and Conditions carefully.

A. LICENSES/QUALIFICATIONS:

1. All Contractors, together with any Sub-Contractors, must be qualified and licensed under the applicable regulations to perform the work required herein. Contractor’s qualifications including equipment to be used for this project will be subject to review and approval by the City prior to award of bid. Contractor must be prepared to demonstrate, through previous experience and references, the ability to safely and successfully perform the work herein described.

B. INSURANCE:

1. Contractor shall obtain and maintain the minimum insurance coverage set forth below. By requiring such minimum insurance, the City of Milton shall not be deemed or construed to have assessed the risk that may be applicable to the Contractor. Contractor shall assess its own risks and if it deems appropriate and/or prudent, maintain higher limits and/or broader coverage.

Contractor is not relieved of any liability or other obligations assumed or pursuant to the Contract by reason of its failure to obtain or maintain insurance in sufficient amounts, duration, or types.

2. Contractor shall carry the following limits of liability as required below: Dollar amounts may change in accordance with the event or project.

Commercial General Liability - ISO CG 001 Form or equivalent.

General Aggregate $1,000,000

Products/Completed Operations Aggregate $1,000,000

Each Occurrence Limit $1,000,000

Personal/advertising Injury $1,000,000

Fire Damage (Any One Fire) $50,000

Medical Payments (Any One Person) $5,000

Automobile Liability

Bodily Injury/Property Damage $1,000,000 each accident

Personal Injury Protection (PIP) Statutory

Workers' Compensation

Coverage A (Workers' Compensation) Statutory

Coverage B (Employers Liability):

➢ Each Accident $100,000

➢ Disease-Each Employee $500,000

➢ Disease-Policy Limit $100,000

2026.01 ITB Effluent Sprayfields and Pipeline Route Clearing and Grubbing Project

PURPOSE and SCOPE OF WORK

The Work is generally described as follows: EFFLUENT SPRAYFIELDS AND PIPELINE ROUTE CLEARING AND

GRUBBING for the installation of an irrigation system for sod farming in accordance with plans and specifications that are included with this solicitation 2025.12 ITB Effluent Sprayfields and Pipeline Route Clearing and Grubbing

Project. The City of Milton's (City) Effluent Sprayfields and Pipeline Route Clearing and Grubbing (Project) potentially may utilize funding from the State Revolving Fund Loan Program, RESTORE Grant Program, Florida

Department of Environment Protection Resiliency Grant Program, and other State/Federal Funds.

A. PROJECT DESCRIPTION:

The City of Milton is seeking a qualified firm or team to clear and grub approximately 350 wooded acres in preparation for the installation of an effluent disposal system.

The Project consists of the following:

Clearing and grubbing and disposal of trees, snags, logs, brush, stumps, and rubbish from the designated areas.

The CONTRACTOR’S bid shall include the purchase of all materials and equipment, including all applicable sales taxes, required to complete the project in its entirety.

The CITY reserves the right to use Value Engineering which may be negotiated after award of the bid.

The CITY reserves the right to use Owner direct-purchased materials (ODP) which may be negotiated after award of the bid, though it is not expected that the project will require any material purchase.

• The CONTRACTOR shall prepare bills of materials for all materials and equipment required for purchase with the

CONTRACTOR’S normal suppliers in lieu of issuing a purchase order.

• The bills for materials shall be prepared as if the CONTRACTOR was issuing the purchase order himself and in accordance with the plans and specifications.

• The CONTRACTOR’S bills of materials should address the payment conditions, delivery location and all other pertinent information normally included on a CONTRACTOR’S purchase order.

• The CONTRACTOR will be responsible for proper storage in accordance with the manufacturers’ recommendations until they are incorporated into the project.

(The remainder of this page is intentionally left blank)

SUBCONTRACTORS:

3. Contractor may not subcontract work under this Agreement without the express written permission of the City of Milton. If Contractor has received authorization to subcontract work, it is agreed that all subcontractors performing work under the Agreement must comply with its provisions. Further, all agreements between Contractor and its subcontractors must provide that the terms and conditions of this Agreement be incorporated therein.

C. CONTINUATION DURING DISPUTES:

1. Contractor agrees that during any dispute between the parties, Contractor will continue to perform its obligations until the dispute is settled, instructed to cease performance by the City, enjoined or prohibited by judicial action, or otherwise required or obligated to cease performance by other provisions in this Agreement.

D. TERMINATION FOR CONVENIENCE:

1. The City reserves the right to terminate this Agreement in part or in whole upon thirty

(30) calendar days’ written notice.

E. LIQUIDATED DAMAGES:

1. In the event the bidder is awarded the contract and fails to complete the work within the time limit or extended time limit agreed upon, liquated damages will be paid to the City as defined in

Article 4.03 of the Agreement.

F. BID BOND

1. Each bid must be accompanied by a bid bond payable to the City for five percent (5%) of the total amount of the bid. As soon as the bid prices have been checked and compared, the City will return the bonds of all except the three lowest bidders. When the contract is executed, and the payment and performance bonds have been executed and approved, the bid bonds of the remaining bidders will be returned. A certified check may be used in lieu of the bid bond. Each bidder shall guarantee that they will not withdraw his/her bid for a period of 90 days after the bids have been opened.

G. PERFORMANCE AND PAYMENT BOND

1. A performance bond and payment bond each in the amount of 100 percent of the contract price, with a corporate surety approved by the City, will be required for the faithful performance of the contract, when executed. The Contractor whom the contract is being awarded must obtain the performance bond and payment bond on or before ten (10) calendar days following delivery of the Notice of Award. Attorneys-in-fact who sign the payment and performance bonds must file with each bond a current certified copy of their power of attorney.

H. INDEMNIFICATION/LIABILITY:

1. To the fullest extent permitted by law, Contractor agrees to defend, indemnify, and hold the City, its officers, agents, and employees harmless from and against any and all liabilities, demands, claims, suits, losses, damages, causes of action, fines or judgments, including costs, attorneys’, witnesses’, and expert witnesses’ fees, and expenses incident thereto, relating to, arising out of, or resulting from: (i) the services provided by Contractor personnel under this Agreement;

(ii) any negligent acts, errors, mistakes or omissions by Contractor or Contractor personnel; and

(iii) Contractor or Contractor personnel’s failure to comply with or fulfill the obligations established by this Agreement.

2. Contractor will update the City during the course of the litigation to timely notify the City of any issues that may involve the independent negligence of the City that is not covered by this indemnification.

3. The City assumes no liability for actions of Contractor and will not indemnify or hold Contractor or any third party harmless for claims based on this Agreement or use of Contractor-provided supplies or services.

4. Extreme care shall be taken to safeguard all existing facilities, site amenities, irrigation systems, vehicles, etc. on or around the job site. Damage to public and/or private property shall be the responsibility of the Contractor and shall be repaired and/or replaced at no additional cost to the City.

I. SPECIAL CONDITIONS:

1. Extended time may be allowed for the completion of this project due to inclement weather.

2. Decisions to allow days added to the contract due to inclement weather will be based upon weather records as recorded with the Milton WWTF located in Milton, Florida. Calculation for determining lost days is included in the Special Conditions in the Contract Documents.

3. In the event additional days are awarded the contractor must notify City of Milton at the beginning of work stoppage and each succeeding day until work can be safely resumed.

J. FORCE MAJEURE:

1. Failure by either party to perform its duties and obligations will be excused by unforeseeable circumstances beyond its reasonable control, including acts of nature, acts of the public enemy, riots, fire, explosion, legislation, and government regulation. The party whose performance is so affected will within five (5) calendar days of the unforeseeable circumstance notify the other party of all pertinent facts and identify the force majeure event. The party whose performance is so affected must also take all reasonable steps, promptly and diligently, to prevent such causes if it is feasible to do so, or to minimize or eliminate the effect thereof. The delivery or performance date will be extended for a period equal to the time lost by reason of delay, plus such additional time as may be reasonably necessary to overcome the effect of the delay, provided however, under no circumstances will delays caused by a force majeure extend beyond thirty (30) calendar days from the scheduled delivery or completion date of a task unless agreed upon by the parties.

K. CONTRACT:

1. The successful Contractor must execute and return the contract within ten (10) calendar days of issuance of Notice of Award.

L. SCHEDULE:

1. Upon receipt of all required documents a Notice to Proceed will be issued.

2. The successful Contractor must commence work within five (5) calendar days of Notice to

Proceed.

3. Contractor to propose construction schedule as part of the bid response.

M. PAYMENT:

1. Contractor to propose payment schedule as part of bid response.

N. EXPERIENCE/REFERENCES:

1. Bidder must include information on similar projects.

2. Bidders must provide with their proposal material for evaluating the ability of the potential

Bidder to execute a project of this type. Therefore, the Bidder is required to provide a minimum of (3) three references which will be verified. The list of references must be attached with the bid proposal on the form provided within these specifications. All reference materials provided become the property of the City and also become public record.

O. CHANGE ORDERS:

1. Notify the City of Milton of any conditions in the project area that are not addressed within the specifications which may require a change order.

2. Change orders to the scope of work or additional work requested by City of Milton must be in written form and initiated by the Contractor.

3. All changes or additions will be approved by City of Milton prior to work being initiated.

Company Name Page 9 of 20

P. ADDENDUM:

1. It will be the sole responsibility of the bidder to contact City of Milton prior to submitting a bid to determine if any addenda have been issued, to obtain such addenda, and to acknowledge addenda with their bid.

Q. REQUIRED DOCUMENTS:

1. The enclosed documents must be executed and returned with the bid proposal or the proposal may be considered non-responsive. (Public Entity Crime Statement, Drug-Free Workplace

Form, Non-Collusion Affidavit, Conflict of Interest Statement, E-Verify Statement of

Compliance, Certificate Regarding Debarment, References)

R. AWARD OF BID:

1. The City reserves the right to award the bid to one (1) or multiple contractors on a per item basis or to not award the bid to any of the bidders.

2. Four categories of information will be evaluated: responsiveness, responsibility, the technical proposal and price. All proposals must meet the following responsiveness and responsibility criteria:

• Responsiveness. Bids will be evaluated to determine whether the proposal complies with the instructions for submitting proposals including completeness of proposal which encompasses the inclusion of all required attachments and submissions. Any proposals that are submitted late will be rejected. Failure to meet other requirements may result in rejection.

• Responsibility. Bids will be evaluated to determine whether the proposer is one with whom the City can or should do business. Factors that may be evaluated to determine

"responsibility" include, but are not limited to: excessively high or low priced proposals, past performance, references (including those found outside the proposal), compliance with applicable laws, proposer's record of performance and integrity. A proposer must at all times have financial resources sufficient to ensure performance of the contract and must provide proof upon request. FGU and the City reserve the right to inspect and review proposer’s facilities, equipment and personnel and those of any identified subcontractors. Any failure to supply information, or the quality of the information, may result in rejection.

• Technical Proposal. Bids will be evaluated to determine how well proposals meet its requirements in terms of the response to the specifications and how well the offer addresses the needs of the project.

• Price. Each proposal’s pricing will be evaluated.

3. The City’s City Council will have final approval to award the bid.

Company Name Page 10 of 20

S. EMPLOYMENT ELIGIBILITY VERIFICATION (E-VERIFY):

1. In accordance with State of Florida, Office of the Governor, Executive Order 11-116

(superseding Executive Order 11-02; Verification of Employment Status), in the event performance of this Agreement is or will be funded using state or federal funds, the

CONTRACTOR must comply with the Employment Eligibility Verification Program (“E-Verify

Program”) developed by the federal government to verify the eligibility of individuals to work in the United States and 48 CFR 52.222-54 (as amended) is incorporated herein by reference. If applicable, in accordance with Subpart 22.18 of the Federal Acquisition Register, the

CONTRACTOR must (1) enroll in the E-Verify Program, (2) use E-Verify to verify the employment eligibility of all new hires working in the United States, except if the CONTRACTOR is a start or local government, the CONTRACTOR may choose to verify only new hires assigned to the

Agreement; (3) use E-Verify to verify the employment eligibility of all employees assigned to the

Agreement; and (4) include these requirements in certain subcontracts, such as construction.

Information on registration for and use of the E-Verify Program can be obtained via the internet at the Department of Homeland Security Web site:

http://www.dhs.gov/E-Verify.

T. ADDITIONAL INFORMATION:

1. The City of Milton reserves the right to request any additional information needed for clarification from any Bidder for evaluation purposes.

Company Name Page 11 of 20

REFERENCES

List below a minimum of three (3) client/customer references including company name, address, contact person, email address, telephone number and length of time services provided.

(Note: only list references in which a similar scope of work/service was provided)

1. Company Name:

Address:

Business Phone #:

Contact Person:

Email:

Length of time services provided:

Project description:

2. Company Name:

Business Phone #:

Contact Person:

Email:

Length of time services provided: Project description:

3. Company Name:

Business Phone #:

Contact Person:

Email:

Length of time services provided: Project description:

Company Name Page 12 of 20

SWORN STATEMENT PURSUANT TO SECTION 287.133(3)(A).

FLORIDA STATUTES ON PUBLIC ENTITY CRIME

THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE OF A NOTARY PUBLIC OR OTHER OFFICIAL

AUTHORIZED TO ADMINISTER OATHS.

1. This sworn statement is submitted to

By

(print this individual’s name and title) for (print name of entity submitting statements) whose business address is and if applicable whose Federal Employer Identification Number (FEIN) is

If the entity has no FEIN, include the Social Security Number of the individual signing this sworn Statement:

2. I understand that a “public entity crime” as defined in paragraph 287.133(1)(a), Florida Statutes, mean a violation of any state or federal law by a person with respect to and directly related to the transactions of business with any public entity or with an agency or political subdivision of any other state or with the United States including, but not limited to any bid or contract for goods or services to be provided to any public entity or any agency or political subdivision of any other state or of the United States and involving antitrust, fraud, theft, bribery, collusion, racketeering, conspiracy, or material misrepresentation.

3. I understand that “convicted” or “convection” as defined in Paragraph 287.133(1)(b), Florida Statutes means a finding of guilt or a conviction of a public entity crime, with or without adjudication of guilt, in any federal or state trial court of record relating to charges brought by indictment or information after

July 1, 1989, as a result of a Jury verdict, nonjury trial, or entry of a plea of guilty or nolo contendere.

4. I understand that an “affiliate” as defined in paragraph 287.133(1)(a), Florida Statutes, means:

1. A predecessor or successor of a person convicted of public entity crime; or

2. An entity under the control of any natural person who is active in the management of the entity and who has been convicted of a public entity crime. The term “affiliate” includes those officers, directors, executives, partners, shareholders, employees, members, and agents who are active in the management of an affiliate. The ownership by one person of shares constituting a controlling interest in another person, or a pooling of equipment or income among persons when not for fair market value under an arm’s length agreement, shall be a prima facie case that one person controls another person.

A person who knowingly enters into a joint venture with a person who has been convicted of a public entity crime in Florida during the preceding 36 months shall be considered an affiliate.

5. I understand that a “person” as defined in Paragraph 287.133(1)(e), Florida Statutes, means any natural person or entity organized under the laws of any state or of the United States with the legal power to enter into a binding contract and which bids or applies to bid on contracts for the provision of goods or services let by a public entity, or which otherwise transacts or applies to transact business with a public entity. The term “person” includes those officers, executives, partners, shareholders, employees, members, and agents who are active in management of an entity.

6. Based on information and belief, the statement which I have marked below is true in a relation to the entity submitting this sworn statement. (Please indicate which statement applies).

_ Neither the entity submitting this sworn statement, nor any of its officers, directors, executives, partners, shareholders, employees, members, or agents who are active in the management of the entity, or any affiliate of the entity has been charged with and convicted of a public entity crime within the past 36 months.

_ The entity submitting this sworn statement, or one or more of its officers, directors, executives, partners, shareholders, employees, members, or agents who are active in the management of the entity, or an affiliate of the entity has been charged with and convicted of a public entity crime within the past 36 months. AND (Please indicate which additional statement applies).

_ The entity submitting this sworn statement, or one or more of its officers, directors, executives, partners, shareholders, employees, members, or agents who are active in the management of the entity, or agents who are active in the management of the entity, or an affiliate of the entity has been charged with and convicted of a public entity crime within the past 36 months. However, there has been a subsequent proceeding before a Hearing Officers of the State of Florida, Division of

Administrative Hearings and the Final Order by the Hearing Officer determined that it was not in the public interest to place the entity submitting this sworn statement on the convicted vendor list.

(Attached is a copy of the final order).

I UNDERSTAND THAT THE SUBMISSION OF THIS FORM TO THE CONTRACTING OFFICER FOR THE PUBLIC

ENTITY IDENTIFIED IN PARAGRAPH 1 (ONE) ABOVE IS FOR THE PUBLIC ENTITY ONLY AND, THAT THIS

FORM IS VALID THROUGH DECEMBER 31 OF THE CALENDAR YEAR IN WHICH IT IS FILED AND FOR THE

PERIOD OF THE CONTRACT ENTERED INTO, WHICHEVER PERIOD IS LONGER. I ALSO UNDERSTAND THAT

I AM REQUIRED TO INFORM THE PUBLIC ENTITY PRIOR TO ENTERING INTO A CONTRACT IN EXCESS OF

THE THRESHOLD AMOUNT PROVIDED IN SECTION 287.017, FLORIDA STATUTES, FOR CATEGORY TWO

OF ANY CHANGE IN THE INFORMATION CONTAINED IN THIS FORM.

(Signature)

City of

STATE OF FLORIDA

Sworn and subscribed before me this day of , 20 by who is Personally known to me

Or who produced identification -

(Type of Identification)

(Signature) Notary Public—State of Florida

(Printed, typed or stamped commissioned name of notary public)

My commission expires (SEAL)

DRUG-FREE WORKPLACE (F.S. 287.087)

Preference to businesses with drug-free workplace programs.—Whenever two or more bids, proposals, or replies that are equal with respect to price, quality, and service are received by the state or by any political subdivision for the procurement of commodities or contractual services, a bid, proposal, or reply received from a business that certifies that it has implemented a drug-free workplace program shall be given preference in the award process.

In order to have a drug-free workplace program, a business shall:

(1) Publish a statement notifying employees that unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance is prohibited in the workplace and specifying the actions that will be taken against employees for violations of such prohibition.

(2) Inform employees about the dangers of drug abuse in the workplace, the business policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and employee assistance programs, and the penalties that may be imposed upon employees for drug abuse violations.

(3) Give each employee engaged in providing the commodities or contractual services that are under bid a copy of the statement specified in subsection (1).

(4) In the statement specified in subsection (1), notify the employees that, as a condition of working on the commodities or contractual services that are under bid, the employee will abide by the terms of the statement and will notify the employer of any conviction of, or plea of guilty or nolo contendere to, any violation of chapter 893 or of any controlled substance law of the United States or any state, for a violation occurring in the workplace no later than 5 days after such conviction.

(5) Impose a sanction on or require the satisfactory participation in a drug abuse assistance or rehabilitation program if such is available in the employee’s community by, any employee who is so convicted.

(6) Make a good faith effort to continue to maintain a drug-free workplace through implementation of this section.

Vendor Name Date:

We have a drug-free workplace program. □yes; or □no (check one)

Vendor’s Signature

NON-COLLUSION AFFIDAVIT

STATE OF

COUNTY OF

Owner, Partner or Officer of Firm Company

Name, Address, City and State

Being of lawful age, being first duly sworn, on oath says that he/she is the agent authorized by the bidder to submit the attached bid. Affidavit further states as proposer, that they have not been a party to any collusion among bidders in restraint of competition by agreement to bid at a fixed price or to refrain from bidding; or with any officer of the City of Milton or any of their employees as to quantity, quality or price in the prospective contract; or any discussion between bidders and any official of the City of Milton or any of their employees concerning exchange of money or other things of value for special consideration in submitting a sealed bid for:

FIRM NAME:

SIGNATURE:

TITLE:

The foregoing instrument was acknowledged before me this day of

, 20 by the above signed acting on behalf of the organization/company.

He/she is personally known to me or has produced as identification and did (did not) take an oath.

Signature of Notary

SEAL

CONFLICT OF INTEREST DISCLOSURE FORM

For purposes of determining any possible conflict of interest, all bidders/proposers must disclose if any City of Milton, employee(s), elected officials(s), of if any of its agencies is also an owner, corporate officer, agency, employee, etc., of their business.

Indicate either “yes” (a City employee, elected official, or agency is also associated with your business), or “no”. If yes, give person(s) name(s) and position(s) with your business.

YES NO

NAME(S) POSITION(S)

Firm Name By (Printed):

By (Signature): Title

Address Phone No.

E-Mail:

E-VERIFY STATEMENT OF COMPLIANCE

Contractor hereby certifies compliance with the following:

Pursuant to § 448.095(2) Florida Statutes (2020), Contractor shall register with and use the E- Verify system operated by the United States Department of Homeland Security to verify the work authorization status of all new employees hired by Contractor while performing work or providing services for the City of Milton. Contractor shall also include in any related subcontracts a requirement that subcontractors performing work or providing services for the City of Milton on its behalf register with and use the E-Verify system to verify the work authorization status of all new employees hired by the subcontractor while performing work or providing services for the City of

Milton. Additionally, Contractor shall include in any related subcontracts a requirement that subcontractors performing work or providing services for the City of Milton on its behalf provide

Contractor with an affidavit stating that the subcontractor does not employ, contract with, or subcontract with any unauthorized alien as defined in 8 U.S.C. § 1324a(h)(3). Contractor shall maintain a copy of such affidavit for the duration of its contract with the City of Milton.

FIRM NAME

SIGNATURE

TITLE

1. The prospective primary participant certifies to the best of its knowledge and belief that it and its principles:

a. Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

b. Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or Local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;

c. Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, or Local) with commission of any of the offenses enumerated in paragraph (1)(b) of this certification; and

d. Have not within a three-year period preceding this application/proposal had one or more public transactions (Federal, State or Local) terminated for cause or default.

2. Where the prospective primary participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal.

Name Project Name

Title Project Number

Firm Street Address

City, State, Zip

Certification Regarding Debarment, Suspension, And Other Responsibility Matters Primary Covered

Transactions

2026.01 ITB Effluent Sprayfields and Pipeline Route

Clearing and Grubbing Project

BID FORM

ITEM

DESCRIPTION

QTY

UNIT

UNIT PRICE

AMOUNT

General Conditions of contact, bonds, insurance, mobilization (Not more than 10% of total bid)

LS

Sitework

+/-295

AC

TOTAL BASE BID (Numerical) (including all work required by the contract documents and the allowances)

EJCDC® C-451, Qualifications Statement.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

QUALIFICATIONS STATEMENT

THE INFORMATION SUPPLIED IN THIS DOCUMENT IS CONFIDENTIAL TO THE EXTENT

PERMITTED BY LAWS AND REGULATIONS

1. SUBMITTED BY:

Official Name of Firm:

2. SUBMITTED TO: The City of Milton, Florida

3. SUBMITTED FOR: Effluent Sprayfield 2 and Pipeline route Clearing and Grubbing

TYPE OF WORK: This project consists of clearing and grubbing approximately 120 acres +/- in accordance with the contract documents.

4. CONTRACTOR'S CONTACT INFORMATION

Contact Person:

Title:

Phone:

Email:

5. AFFILIATED COMPANIES:

Name:

6. TYPE OF ORGANIZATION:

SOLE PROPRIETORSHIP

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, Name of Owner:

Doing Business As:

Date of Organization:

PARTNERSHIP

Date of Organization:

Type of Partnership:

Name of General Partner(s):

CORPORATION

State of Organization:

Date of Organization:

Executive Officers:

- President:

- Vice President(s):

- Treasurer:

- Secretary:

LIMITED LIABILITY COMPANY

State of Organization:

Date of Organization:

Members:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, JOINT VENTURE

Sate of Organization:

Date of Organization:

Form of Organization:

Joint Venture Managing Partner

- Name:

- Address:

Joint Venture Managing Partner

Joint Venture Managing Partner

7. LICENSING

Jurisdiction:

Type of License:

License Number:

Jurisdiction:

Type of License:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, License Number:

8. CERTIFICATIONS CERTIFIED BY:

Disadvantage Business Enterprise:

Minority Business Enterprise:

Woman Owned Enterprise:

Small Business Enterprise:

Other ( ):

9. BONDING INFORMATION

Bonding Company:

Bonding Agent:

Contact Name:

Aggregate Bonding Capacity:

Available Bonding Capacity as of date of this submittal:

10. FINANCIAL INFORMATION

Financial Institution:

Account Manager:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, INCLUDE AS AN ATTACHMENT AN AUDITED BALANCE SHEET FOR EACH OF THE

LAST 2 YEARS

11. CONSTRUCTION EXPERIENCE:

A minimum of three of the current projects listed as in construction and/or listed as previously completed must be similar to this project in nature and be in excess of

$10,000,000. Contractor shall provide letters of recommendation from a minimum of three (3) previous projects.

Current Experience:

List on Schedule A all uncompleted projects currently under contract (If Joint Venture list each participant's projects separately).

Previous Experience:

List on Schedule B all projects completed within the last 5 Years (If Joint Venture list each participant's projects separately).

Has firm listed in Section 1 ever failed to complete a construction contract awarded to it?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

Has any Corporate Officer, Partner, Joint Venture participant or Proprietor ever failed to complete a construction contract awarded to them in their name or when acting as a principal of another entity?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

Are there any judgments, claims, disputes or litigation pending or outstanding involving the firm listed in Section 1 or any of its officers (or any of its partners if a partnership or any of the individual entities if a joint venture)?

YES NO

If YES, attach as an Attachment details including Project Owner's contact information.

12. SAFETY PROGRAM:

Name of Contractor's Safety Officer:

Include the following as attachment:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, Provide as an Attachment Contractor's (and Contractor's proposed Subcontractors and

Suppliers furnishing or performing Work having a value in excess of 10 percent of the total amount of the Bid) list of all safety citations or violations under any state all received within the last 5 years (indicate disposition as applicable) - IF NONE SO STATE.

13. EQUIPMENT:

MAJOR EQUIPMENT:

List on Schedule C all pieces of major equipment available for use on Owner's Project. This list may be used for determining Owner Purchased Material.

I HEREBY CERTIFY THAT THE INFORMATION SUBMITTED HEREWITH, INCLUDING ANY ATTACHMENTS, IS

TRUE TO THE BEST OF MY KNOWLEDGE AND BELIEF.

NAME OF ORGANIZATION:

BY:

TITLE:

DATED:

NOTARY ATTEST:

SUBSCRIBED AND SWORN TO BEFORE ME

THIS DAY OF , 20___

NOTARY PUBLIC - STATE OF

MY COMMISSION EXPIRES:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, REQUIRED ATTACHMENTS

1. Schedule A (Current Experience).

2. Schedule B (Previous Experience).

3. Evidence of authority for individuals listed in Section 7 to bind organization to an agreement.

4 Resumes of officers and key individuals (including Safety Officer) of firm named in Section 1.

5 Required safety program submittals listed in Section 13.

6. Additional items as pertinent.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE A

CURRENT EXPERIENCE

Project Name Owner's Contact Person Design Engineer Contract Date Type of Work Status Cost of Work

Telephone:

Name:

Company:

Telephone:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE B

PREVIOUS EXPERIENCE (Include ALL Projects Completed within last 5 years)

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE B

PREVIOUS EXPERIENCE (Include ALL Projects Completed within last 5 years)

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Telephone:

Name:

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, SCHEDULE C - LIST OF MAJOR EQUIPMENT AVAILABLE

ITEM PURCHASE DATE CONDITION ACQUIRED VALUE

EJCDC® C-200, Suggested Instructions to Bidders for Construction Contracts.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

Page

ARTICLE 1 – Defined Terms

ARTICLE 2 – Copies of Bidding Documents

ARTICLE 3 – Qualifications of Bidders

ARTICLE 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

ARTICLE 5 – Bidder’s Representations

ARTICLE 6 – Pre-Bid Conference

ARTICLE 7 – Interpretations and Addenda

ARTICLE 8 – Bid Security

ARTICLE 9 – Contract Times

ARTICLE 10 – Liquidated Damages

ARTICLE 11 – Substitute and “Or-Equal” Items

ARTICLE 12 – Subcontractors, Suppliers, and Others

ARTICLE 13 – Preparation of Bid

ARTICLE 14 – Basis of Bid

ARTICLE 15 – Submittal of Bid

ARTICLE 16 – Modification and Withdrawal of Bid

ARTICLE 17 – Opening of Bids

ARTICLE 18 – Bids to Remain Subject to Acceptance

ARTICLE 19 – Evaluation of Bids and Award of Contract

ARTICLE 20 – Bonds and Insurance

ARTICLE 21 – Signing of Agreement

ARTICLE 22 – Sales and Use Taxes, OWNER PURCHASED MATERIAL

ARTICLE 23 – WAGE RATE REQUIREMENTS

ARTICLE 24 – AMERICAN IRON AND STEEL

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General

Conditions and Supplementary Conditions. Additional terms used in these Instructions to

Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the invitation to bid.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor

Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents or bidding documents obtained from sources other than the issuing office.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within five (5) days of Owner’s request, Bidder shall submit, in addition to evidence received with the bid proposal, additional written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any

Bidder on request. These reports and drawings are not part of the Contract

Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

4. Geotechnical Baseline Report: The Bidding Documents contain a Geotechnical Baseline

Report (GBR). The GBR describes certain select subsurface conditions that are anticipated to be encountered by Contractor during construction in specified locations

(“Baseline Conditions”). The GBR is a Contract Document.

The Baseline Conditions in the GBR are intended to reduce uncertainty and the degree of contingency in submitted Bids. However, Bidders cannot rely solely on the Baseline

Conditions. Bids should be based on a comprehensive approach that includes an independent review and analysis of the GBR, all other Contract Documents, Technical

Data, other available information, and observable surface conditions. Not all potential subsurface conditions are baselined.

Nothing in the GBR is intended to relieve Bidders of the responsibility to make their own determinations regarding construction costs, bidding strategies, and Bid prices, nor of the responsibility to select and be responsible for the means, methods,…