SF-30 CONTINUATION SHEET
AMENDMENT A0007 Page 2 of 10
Applicability: WMEC 210 A&B Class
1. Q: CLIN’s 0022, 0024, 0025, 0026, 0028, 0030A through 0031A, 0031C, 0031D, 0032B, 0033A through 0034D, 0036A through 0036L, 0038C, 0038E through 0038G, 0038K, 0039A through 0040C, 0043A through 0045, 0055C, 0057, 0079C through 0081, 0094, 0097E, and 0098 all have a “Unit” description of Job, yet the quantities are listed as 2. Shouldn’t these quantities be 1? Please clarify.
A: With few exceptions all QTY’s are being changed to QTY=1 on Rev. 1 Schedule B.
CLIN 000A and CLIN 000C are two examples where QTY is different.
2. Q: Contractor assumes that items 8 and 9 will only be invoked on a task order if propeller shaft removal items are also invoked. Please clarify.
A: Propeller shaft(s) will be removed by other work item(s) and not priced as part of items 8 and 9.
3. Q: Work Item 14 and CLIN 0014 are both titled “Hull and Structural Plating – ¼” to ¾” Steel Plate, Renew, however, paragraph 3.3 lists the thickness parameters as ¼” to ½”. Please clarify.
A: Schedule B will be modified in Rev 1 to reflect different plate sizes.
4. Q: Work Items 16 and 17 require partial preservation of 50 square feet of designated bilge areas. It is impossible to bid this requirement without knowing what interferences are included. Contractor assumes interferences will be addressed as a change order. Please clarify.
A: Interferences listed in Rev 0 specification will be removed in Rev 1 specifications for these work items. Contractor will provide pricing for interferences for these two work items on individual task orders as an additional cost.
5. Q: Work Item 18, paragraph 3.3 requires contractor to dispose of any drained liquids. Contractor assumes that this disposal will be subject to a change order as it is impossible to estimate now the quantity of liquids that may be drained. Please clarify.
A: Generally the volume of liquid in the U/W Appendages listed is minimal and should be considered as part of the pricing for this work item. In the event one of these U/W appendages is filled with preservative or other liquid, the contractor shall submit a CFR documenting the volume of liquid to be removed, and a change request may be authorized and additional costs charged to cover these costs.
6. Q: Contractor assumes that items 21 and 22 will only be invoked on a task order if items 21 and 22.
AMENDMENT A0007 Page 3 of 10
7. Q: Contractor assumes that for items 0029A through 0043C, that the “Remove and Dispose” items will be invoked if the “Clean and Inspect” and “Preserve” items are invoked, and that both the “Remove and Dispose” and ‘Clean and Inspect” items will be invoked if the “Preserve” items are invoked for any tanks or voids on any task order. Please clarify.
A: Tank contentment(s) removal and disposal will be covered under separate work item(s) unless otherwise stated in individual work item specification(s). Unless specifically stated under individual work item(s), cleaning of tank(s) in support of tank preservation is included within the specific work item as “Surface preservation.
The Contractor shall remove and retain the tank manhole cover(s). Prepare and coat the designated tank interior surfaces, using the system specified for "Tanks and Voids (Fuel/JP-5 Tanks, Service, Storage, Overflow, Drain, Option I or Option II)" in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems).
Power tool clean all affected surfaces to “bare metal”, in lieu of using abrasive blasting, and feather edges of existing intact coating to the prepared areas, in order to provide a smooth transition with the new paint.”
8. Q: Work Item 44, paragraph 3.2 requires contractor to dispose of any drained is impossible to estimate the quantity of liquids that may be drained. Please clarify.
A: Generally the volume of liquid in the Voids (Non-Accessible) listed is minimal and should be considered as part of the pricing for this work item. In the event one of these Voids (Non-Accessible) is filled with preservative or other liquid, the contractor shall submit a CFR documenting the volume of liquid to be removed.
9. Q: Work Items 50 and 51, paragraph 1.2 lists quantities of all GFP sleeves as 1. If CLINs 0050C and 0051C are invoked will all sleeves for both port and starboard sides be GFP? Please clarify.
A: Only Propeller (Tail) shaft is renewed. The appropriate QTY of GFP (including sleeves) will be provided as needed for individual Task Orders
10. Q: Contractor assumes that any work items that involve the removal and repairs/replacements of any shaft related items (bearings, sleeves, seals, coatings, intermediate shafts, etc.) that the shaft removal items will also be invoked. Please clarify.
A: Unless shaft related items are specifically list as an interference within individual work item(s) they will be removed and reinstalled as part of another work item as specified on individual Task Orders.
AMENDMENT A0007 Page 4 of 10
11. Q: For work Items 72, 74, and 76, does the Coast Guard have a recommendation for a source/point of contact for a CONUS/domestic LIAAEN CPP System qualified Tech Rep? If so please provide.
A: Suggested: (1) RobCor Enterprises, Inc. – ATTN: Robert Corp, (804) 725-0777.
(2) Rolls-Royce North America.
12. Q: For work items 73, 75, and 77, same question for a qualified KAMEWA Tech Rep.
A: Suggested: (1) RobCor Enterprises, Inc. – ATTN: Robert Corp, (804) 725-0777.
(2) Rolls-Royce North America.
13. Q: Work Item 85 requires replacement of Simplex Sea Strainers. The references listed do not provide proper or sufficient detail for pricing or purchasing these strainers. Please provide all necessary information for pricing the strainers.
A: Bill of Materials (BM NO.9) is being provided. BM NO. 9 provides additional detail sufficient for pricing.
14. Q: Work Item 86, the description of work required for paragraphs 1.1.1 and 1.1.2 appears to be reversed from typical marine standards for valves. Shouldn’t 1.1.1 be valves for renewal, and 1.1.2 valves for overhaul? Please clarify.
A: Rev-1 spec makes correction. Par. 1.1.1 changed “overhaul” to “renewal”. Par.
1.1.2 changed “renewal” to “overhaul”.
15. Q: Work Item 89, the description of work required for paragraphs 1.1.1 and 1.1.2 valves for renewal, and 1.1.2 valves for overhaul? Please clarify.
A: Rev-1 spec makes correction. Par. 1.1.1 changed “overhaul” to “renewal”. Par.
1.1.2 changed “renewal” to “overhaul”.
16. Q: For work items 95 and 96, is it necessary to drydock a vessel within 72 hours of arrival at contractor’s facility in all cases per paragraph 3.4.2.4 of SFLC Std Spec 8634? There are evolutions of work that would be better suited to be accomplished pier side vice in drydock.
A: The Contractor must follow the specifications as written. Any deviation from specification requirements shall be address on a case-by-case basis for Coast Guard approval.
17. Q: Work Item 97 and CLINs 0097A, B, and C require unitized pricing in increments of 1 day, 7 days, and 14 days. It is impractical to have to price all efforts required by SFLC Std Spec 8635 for those short time periods as it makes the pricing look unrealistic. Efforts that can’t be spread out in a daily rate include, but are not limited to, connecting and disconnecting of all services, hazardous waste disposal, and heavy lift equipment. Is it necessary to have these 3 CLINs?
AMENDMENT A0007 Page 5 of 10
A: Changes will be reflected on Rev 1 documents to show pre-defined durations.
Example: 0097A 30-Day Availability Period, 0097B 54-Day Availability Period, 0097C Each Additional Day
18. Q: Work Item 98 – how long of a duration should we use in estimating dock and sea trial efforts?
A: Changes will be reflected on Rev 1 documents to show pre-defined durations for sea trial work item.
19. Q: What length of task order availability should we base our bids on for this proposal? If task order availability durations are changed/shortened upon issuance of any particular task order, will the Cap Pricing be eliminated for that task order?
A: Changes being made to Schedule B, Rev 1 showing pre-defined availability durations (i.e. performance periods).
AMENDMENT A0007 Page 6 of 10
US COAST GUARD RESPONSE TO CONTRACTOR PRE-PROPOSAL QUESTIONS
WMEC 210-270 Drydock IDIQ
Date: 11 December 2012
Applicability: WMEC 270 A&B Class
1. Q: Numerous CLINs have a “Unit” description of Job, yet the quantities are listed as
2. Shouldn’t these quantities be 1? Please clarify.
A: With few exceptions all QTY’s are being changed to QTY=1 on Rev. 1 Schedule B.
CLIN 000A and CLIN 000C are two examples where QTY is different.
2. Q: Contractor assumes that items 6 and 7 will only be invoked on a task order if
A: If stern tube preservation is to be done, the individual work item will be specified on individual Task Order(s). These items will not automatically be used with each propeller shaft removal.
3. Q: Work Items 14 and 15 require partial preservation of 50 square feet of designated bilge areas. It is impossible to bid this requirement without knowing what interferences are included. Contractor assumes interferences will be addressed as a change order. Please clarify.
A: Interferences listed in Rev 0 specification will be removed in Rev 1 specifications for these work items. Contractor will provide pricing for interferences for these two work items on individual task orders as an additional cost.
4. Q: Work Item 16, paragraph 3.3 requires contractor to dispose of any drained is impossible estimate now the quantity of liquids that may be drained. Please clarify.
A: Generally the volume of liquid in the U/W Appendages listed is minimal and should be considered as part of the pricing for this work item. In the event one of these U/W appendages is filled with preservative or other liquid, the contractor shall submit a CFR documenting the volume of liquid to be removed, and a change request may be authorized and additional costs charged to cover these costs.
5. Q: Contractor assumes that items 20 and 21 will only be invoked on a task order if propeller shaft items are also invoked. Please clarify.
items 20 and 21.
AMENDMENT A0007 Page 7 of 10
6. Q: Contractor assumes that if work items 0023 or 0024 are invoked then item 0022 will also be invoked. Please clarify.
A: “Chain Lockers, Clean and Inspect” is used as a stand-alone work item independent of preservation work items. Work items 0023 and 0024 require cleaning within the individual work items to the extent necessary for associated paragraph 3.3 “Surface Preservation.
7. Q: Contractor assumes that for items 0025A thru 0040B, that the “Remove and Dispose” items will be invoked if the “Clean and Inspect” and “Preserve” items are invoked, and that both the “Remove and Dispose” and “Clean and Inspect” items will be invoked if the “Preserve” items are invoked for any tanks on any task order.
Please clarify.
A: Tank contentment(s) removal and disposal will be covered under separate work item(s) unless otherwise stated in individual work item specification(s). Unless specifically stated under individual work item(s), cleaning of tank(s) in support of tank preservation is included within the specific work item as “Surface preservation.
The Contractor shall remove and retain the tank manhole cover(s). Prepare and coat the designated tank interior surfaces, using the system specified for "Tanks and Voids (Fuel/JP-5 Tanks, Service, Storage, Overflow, Drain, Option I or Option II)" in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems).
Power tool clean all affected surfaces to “bare metal”, in lieu of using abrasive blasting, and feather edges of existing intact coating to the prepared areas, in order to provide a smooth transition with the new paint.”
8. Q: Work Items 39 and 40 both list 4 potable water tanks to be dealt with, however, there are only corresponding CLINs for 2 tanks per item. Shouldn’t there be CLINs for tanks 3-78-1-W and 3-78-2-W for both items? Please clarify.
A: Rev 1 spec will reflect changes needed: Deleted Tanks 3-78-1-W and 3-78-2-W from table in par. 1.1 “Intent” and added Potable Water Tank 4-94-1-W to table.
Tanks will be listed as individual sub-CLINS on revised Schedule B.
9. Q: Work Item 40 has tank 3-78-1-W listed twice in paragraph 1.1. Shouldn’t the second tank be 3-78-2-W? Please clarify.
A: Rev 1 spec will reflect changes needed: Deleted Tanks 3-78-1-W and 3-78-2-W from table in par. 1.1 “Intent” and added Potable Water Tank 4-94-1-W to table.
Tanks will be listed as individual sub-CLINs on revised Schedule B.
10. Q: Work Item 41, paragraph 1.1 requires contractor to prepare and coat up to 33% of one or more of the following voids: How many voids should we bid on since there is only one CLIN covering the whole item? Please clarify.
AMENDMENT A0007 Page 8 of 10
A: These voids will be listed as individual sub-CLINs on revised Schedule B.
11. Q: Work Item 42, paragraph 1.1 – same question as #10 for item 41.
A: These voids will be listed as individual sub-CLINs on revised Schedule B.
12. Q: Work Item 42, paragraph 1.1, the third void is listed as 3-B-0-V. Should this void be 4-B-0-V? Please clarify.
A: Rev 1 specification has made the correction; void is 4-B-0-V.
13. Q: Work Item 43, paragraph 3.2 requires contractor to dispose of any drained is impossible to estimate the quantity of liquids that may be drained. Please clarify.
A: Generally the volume of liquid in the Voids (Non-Accessible) listed is minimal and should be considered as part of the pricing for this work item. In the event one of these Voids (Non-Accessible) is filled with preservative or other liquid, the contractor shall submit a CFR documenting the volume of liquid to be removed.
14. Q: Contractor assumes that any work items invoked that involve the removal and repairs/replacements of any shaft related items (bearings, sleeves, seals, coatings, intermediate shafts, etc.) that the shaft removal items will also be invoked. Please clarify.
A: Unless shaft related items are specifically list as an interference within individual work item(s) they will be removed and reinstalled as part of another work item as specified on individual Task Orders.
15. Q: Work Item 55 lists 1 propeller shaft as GFP in paragraph 1.2. If CLIN 0055C is invoked will both shafts be GFP? Please clarify.
A: Yes; both port and starboard propeller shafts will be provided with CLIN 0055C.
16. Q: Work Items 65 and 66 both list the quantity of GFP shafts as 1. If CLINs 0065C and 0066C are invoked respectively, will both shafts be GFP? Isn’t item 66 a duplicate of paragraph 3.8 of item 65? Please clarify.
A: Both required port and starboard shafts will be provided for CLINs 0065C and CLINs 0066C. Par. 3.8 of item 65 does not REQUIRE shaft to be renewed, but USCG reserves the right to do so.
17. Q: Work Item 68, paragraph 3.2.3.2 requires contractor to renew all seals… Seals are listed as GFP in paragraph 1.2. Please clarify.
AMENDMENT A0007 Page 9 of 10
A: This means the contractor shall all stated items in addition to the GFP seals. Rev 1 specification has been revised: Par. 3.2.3.2 modified to include “(including the GFP seals listed in paragraph 1.2 above)”.
18. Q: Work Item 75, paragraph 1.2 lists GFP quantity of 1. If CLIN 0075C is invoked will both thrust bearings be GFP? Please clarify.
A: Yes; both port and starboard thrust bearings will be provided with CLIN 0075C.
19. Q: For work items 76 through 81, does the Coast Guard have a recommendation for a source/point of contact for a CONUS/domestic Escher-Wyss CPP System qualified Tech Rep? If so please provide.
A: Suggested: RobCor Enterprises, Inc. – ATTN: Robert Corp, (804) 725-0777
20. Q: CLIN 0086E is listed as a descriptive pipe size, not a quantity for replacement.
Shouldn’t CLINs 0086E thru 0086M become CLINs 0086E through 0086L, starting with 1 LF section of 2”-3 ½” pipe size and ending with 25 LF section of 4”-6” pipe size? Please clarify.
A: Yes you’re correct; changes will be reflected on Rev 1 Schedule B.
21. Q: Work Item 93 – what are the valve sizes for the 2 manifolds? The drawings are not clear.
A: This information can be found in references/drawings and by performing a ship check prior to submitting proposals. Ship check(s) are ALWAYS encouraged due to possible variations between hulls.
22. Q: Work Item 94, the description of work required for paragraphs 1.1.1 and 1.1.2 valves for renewal, and 1.1.2 valves for overhaul? Please clarify.
A: Rev 1 spec address the necessary changes: Par. 1.1.1 – changed “overhaul” to “renewal”. Par. 1.1.2 – changed “renewal” to “overhaul”
23. Q: Contractor assumes that if work items 99 and 100 are invoked, then work items 101 and 102 will also be invoked in a task order. Please clarify.
A: No; items 99 and 100 are stand-alone items.
24. Q: Work Item 101, paragraph 3.1.2 lists Tech Rep – None, however paragraph
3.3.6.1 requires use of a Thordon Tech Rep. Please clarify.
A: Rev. 1 spec will be revised for this work item to include a Throdon Tech Rep requirement.
AMENDMENT A0007 Page 10 of 10
25. Q: Work Item 102 – same question as #24 for work item 101.
A: Rev. 1 spec will be revised for this work item to include a Throdon Tech Rep requirement.
26. Q: For work items 104 and 105, is it necessary to drydock a vessel within 72 hours of arrival at contractor’s facility in all cases per paragraph 3.4.2.4 of SFLC Std Spec 8634? There are evolutions of work that would be better suited to be accomplished pier side vice in drydock.
A: The Contractor must follow the specifications as written. Any deviation from specification requirements shall be address on a case-by-case basis for Coast Guard approval.
27. Q: Work Item 106 and CLINs 0106A, B, and C require unitized pricing in increments of 1 day, 7 days, and 14 days. It is impractical to have to price all efforts required by SFLC Std Spec 8635 for those short time periods as it makes the pricing look unrealistic. Efforts that can’t be spread out in a daily rate include, but are not limited to, connecting and disconnecting of all services, hazardous waste disposal, and heavy lift equipment. Is it necessary to have these 3 CLINs?
A: Changes will be reflected on Rev 1 documents to show pre-defined durations.
Example: 0097A 30-Day Availability Period, 0097B 54-Day Availability Period, 0097C Each Additional Day
28. Q: Work Item 107 – how long of a duration should we use in estimating dock and sea trial efforts?
A: Changes will be reflected on Rev 1 documents to show pre-defined durations for sea trial work item.
29. Q: What length of task order availability should we base our bids on for this proposal? If task order availability durations are changed/shortened upon issuance of any particular task order, will the Cap Pricing be eliminated for that task order?
A: Changes being made to Schedule B, Rev 1 showing pre-defined availability durations (i.e. performance periods).
NOTE: The due date for receipt of questions is December 19, 2012, 12pm EST.
NOTE: The due date for receipt of proposals is extended to January 16, 2013, 12pm EST.