Sheet1
| DISN Optical Network Enhancement Link 38 RFP & PWS– Comment Matrix | ||||||
| Question/Comment # | PWS Section | Page | RFP Statement | Recommendation | Government Response | |
| 1 | 6.1.1 | 3 | Initial Project Review (IPR) | |||
| Track and report installation progress to date | Remove "Track and report installation progress to date". | Agree. Installation progress to date will be tracked in the Monthly Progress Report. | ||||
| 2 | 6.4 | 6 | The Contractor will integrate the OLA and SDN sites with the fiber and the network management elements into a complete operating system. The Contractor shall lead in the integration effort with assistance from the Government Network Support Center (GNSC). | Change to "The Contractor shall support the Government Network Support Center (GNSC) as they integrate the installed network elements into a complete operating system." | Agree. PWS will be updated to "The Contractor shall support the Government Network Support Center (GNSC) as they integrate the installed network elements into a complete operating system." | |
| 3 | 6.5.2 | 7 | All access fiber installations shall consist of a minimum of 12 strands in a single fully buried duct dedicated for use solely by the Government with one empty duct alongside. | Remove language "with one empty duct alongside" | If the access fiber exists, then two strands are required with no requirement for an empty duct alongside. If the access fiber does not currently exist, all new access fiber installations shall consist of a minimum of 12 strands in a single fully buried duct dedicated for use solely by the Government with one empty duct alongside. | |
| 4 | 6.5.6.7 | 10 | The Contractor shall provide these underlying data (latitude/longitude) using the Visio diagrams and/or spreadsheets. | Provide clarification of latitude and longitude of what underlying data? Please specify. | The Contractor shall provide amplifier location latitude/longitude using the Visio diagrams and/or spreadsheets. | |
| 5 | 6.8 | 16 | Table 6.8 Response and Repair Time for OLA Equipment Failure | Add the following note under Table 6.8: "Restore time of 8 hours does not include time awaiting parts/spares to be delivered. | Agree to add the following note under Table 6.8: "Restore time of 8 hours does not include time awaiting parts/spares to be delivered. | |
| 6 | 12.4 | 25 | Specifically, for C&A, the Government will conduct a formal Security Test and Evaluation (ST&E) to determine the overall security of the network. | Provide clarification on scope of work regarding C&A and ST&E. | The level of effort will depend on the fiber providers' security posture of the huts and buildings where government equipment is located. If security posture is standard telecom with locks on doors with limited access to government equipment, the level of effort would be escorting of government representative to facilities. | |
| 7 | Attachment 2 | MBOM | Please confirm if the MBOM is finalized. We are concerned with the amperage. | The MBOM is provided as a sample for information purposes. The actual MBOM may vary depending on the proposed solution by the offeror. The number of amplifiers is dependent upon the path proposed by the offeror. |