Attachment_6a_-_RDIF_Sample_Task_PWS.docx
DOCX document 38 KB Posted
- Attached to
- Rapid Development Integration Facility (RDIF) Support Federal contract opportunity
- Solicitation number
- FA8629-14-R-2408
About this file
Attachment 6a - RDIF Sample Task PWS. This Document Replaces the Original Attachment 6a - RDIF Sample Task PWS posted on 11 Aug 14.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
***THIS IS A SAMPLE TASK. THE GOVERNMENT WILL NOT AWARD A PROJECT BASED UPON THIS TASK ORDER.*** Attachment 6(a) – RDIF Sample Task PWS
Performance Work Statement (PWS) Rapid Development Integration Facility (RDIF) HC/MC-130 Hose Reel Limit Switch
1.0 Description of Services: The Contractor shall provide the manpower and materials to fabricate 30 ACC HC/MC-130 Hose Reel Limit Switches. These individuals will perform to the standards and specifications contained in the Performance Work Statement referenced in section C of this request for proposal.
2.0 Background: The RDIF has been tasked by AFLCMC/WISN/E to build-to-print, thirty (30) ACC HC/MC-130 Hose Reel Limit Switches.
3.0 Scope:
3.1 The Contractor shall provide the manpower and the required materials to fabricate thirty (30) ACC HC/MC-130 Hose Reel Limit Switches as detailed in the government provided drawings.
4.0 Program Management: The Contractor shall plan, organize, coordinate, and control all task order activities to ensure compliance with contract requirements, and the timely delivery of the required services. The Contractor shall designate a Program Manager who will be the primary point of contact for interface with the Government for all issues regarding this task order.
5.0 Specific Tasks/Objectives:
The contractor shall:
1) Provide the manpower expertise and the required materials to fabricate and perform the QA function on 30 HC/MC-130 Hose Reel Response Limit Switches. The QA function will provide a certificate of conformance stating it was manufactured IAW the attached drawings (CDRL A020).
2) Accomplish the fabrication according to the attached drawings. There is one change required by the customer and reflected in red within the drawings:
a. The text on the box will be etched versus using decals.
6.0 Principal Place of Performance / Hours of Operation: Work in support of this task order will be performed at Building 148, WPAFB, OH and the contractor facility as required. Normal work days are Monday through Friday, except United States (U.S.) Federal holidays. Workers normally work eight (8) hours per day, 40 hours per week, or as otherwise specified in the PWS.
| 7.0 | Overtime: N/A |
| 8.0 | Security Requirements: No security requirements. |
| 9.0 | Travel Requirements: N/A |
10.0 Government Furnished Facilities, Information, Supplies, and Services: The Contractor will have access to and shall use the Government supplied facilities, supplies, and equipment required to accomplish the efforts described above (i.e., work space, test equipment, tools, machinery, office supplies, etc). The Government shall provide the HC/MC-130 Hose Reel Response Limit Switches drawings (as attachment to the PWS).
11.0 Required reports: Certificate of Conformance (CDRL A020)
12.0 Period of Performance: N/A (Sample Task not to be awarded)
13.0 Constraints: N/A
14.0 Performance Standards: The following Performance Objectives, Thresholds, and Surveillance Methods specified in the Quality Assurance Surveillance Plan (QASP) apply to this task order.
Performance Objective
PWS
Paragraph
Performance Threshold
Surveillance Method
Program Management
5.4.12 Keep customer informed.
Timely and accurate reporting.
100% Inspection
Sheet Metal Components and Assembly
5.2.5 Capability to perform these tasks IAW industry standards
100% Inspection
| Purchasing material support |
| 5.4.1 |
| > Orders placed on time. |
> On time deliveries of ordered products.
100% Inspection
Integration (Mechanical and Electrical subsystems
5.4.2 Able to perform electrical subsystem integration
Quality Assurance
5.4.5 > 100% detection of poor workmanship
15.0 Mission Essential Service: Contractor personnel are not considered mission essential.
16.0 Schedule: N/A (Sample Task not to be awarded)
| 17.0 | Attachments: |
| 17.1 Hose Reel Limit Switch Drawing Package (6 Drawings) |
**These Drawings will be disseminated to Qualified U.S. Contractors in accordance with DoD Directive 5230.25. Please see www.fbo.gov for instructions on how to obtain a Qualified U.S. Contractor certificate.