PAINT IDIQ LINE ITEMS 1

PAINT IDIQ ITEMS ROBINS AFB

LINE ITEM #DESCRIPTIONEST. QTY.PRICE (NOT TO EXCEED)UNITBASE YEAR SUBTOTALOPTION YEAR 1 PRICE (NOT TO EXCEED)UNITOPTION YEAR 1 SUBTOTALOPTION YEAR 2 PRICE (NOT TO EXCEED)UNITOPTION YEAR 2 SUBTOTALOPTION YEAR 3 PRICE (NOT TO EXCEED)UNITOPTION YEAR 3 SUBTOTALOPTION YEAR 4 PRICE (NOT TO EXCEED)UNITOPTION YEAR 4 SUBTOTAL
INTERIOR PAINTING OF WALLS WITH LATEX PAINT UP TO 10’ HIGH ROLLED
GYPSUM BOARD, PLASTER, CMU, BRICK, CONCRETE:
LIGHT SURFACE PREPARATION
1INCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT25,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
1AINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS25000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
1BINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING AND SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
MEDIUM SURFACE PREPARATION1
2INCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
2AINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
2BINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
HEAVY SURFACE PREPARATION
3INCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT25,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
3AINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
3BINCLUDES DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING AND SPOT PRIM UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS10,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINTING OF INTERIOR WALLS WITH LATEX PAINT OVER 10’ AND UNDER 18' HIGH
GYPSUM BOARD (SHEET ROCK), PLASTER, CMU, BRICK, CONCRETE:
LIGHT SURFACE PREPARATION
4INCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE COAT5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
4AINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
4BINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
MEDIUM SURFACE PREPARATION
5INCLUDES SCAFFOLDING DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE COAT5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
5AINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
5BINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
HEAVY SURFACE PREPARATION
6INCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE COAT5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
6AINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
6BINCLUDES SCAFFOLDING, DROP CLOTH, REMOVE/REPLACE LIGHT SWITCH & RECEPTACLES COVERS, CLEANING, CAULKING, PATCHING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
INTERIOR PAINTING OF CEILINGS UP TO 10’ HIGH FROM FINISHED FLOOR
GYPSUM BOARD (SHEET ROCK), PLASTER, ACOUSTICAL TILE, CELOTEX TILE, CONCRETE:
7INCLUDES DROP CLOTH, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF CEILING SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE COAT10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
7AINCLUDES DROP CLOTH, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF CEILING SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
INTERIOR PAINTING OF CEILINGS BETWEEN 10’ AND 18' HIGH FROM FINISHED FLOOR
GYPSUM BOARD (SHEET ROCK), PLASTER, ACOUSTICAL TILE, CELOTEX TILE, CONCRETE:
8INCLUDES DROP CLOTH, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF CEILING SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE COAT10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
8AINCLUDES DROP CLOTH, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF CEILING SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
EXTERIOR PAINTING OF WALLS WITH LATEX PAINT UP TO 14’ HIGH, ROLLED OR SPRAYED AND BACK ROLLED
METAL, CMU, BRICK, CONCRETE:
LIGHT SURFACE PREPARATION
9INCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
9AINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS35000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
9BINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
MEDIUM SURFACE PREPARATION
10INCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 15% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
10AINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
10BINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
HEAVY SURFACE PREPARATION
11INCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
11AINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
11BINCLUDES PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING PATCHING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
EXTERIOR PAINTING OF WALLS WITH LATEX OVER 14’ HIGH, ROLLED OR SPRAYED AND BACK ROLLED
Metal, CMU, BRICK, CONCRETE:
LIGHT SURFACE PREPARATION
12INCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
12AINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING &SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
12BINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING &SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
MEDIUM SURFACE PREPARATION
13INCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
13AINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
13BINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
HEAVY SURFACE PREPARATION
14INCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
14AINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
14BINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 70%-100%OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS30000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINTING WITH DRY FALL PAINT , SPRAYED
METAL, CMU, BRICK, CONCRETE OVER 14'
LIGHT SURFACE PREPARATION
15INCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
15AINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
15BINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, PATCHING UP TO 10%-30% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
MEDIUM SURFACE PREPARATION
16INCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT10000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
16AINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING & SPOT PRIMING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS20000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
16BINCLUDES MAN LIFT, PRESSURE WASHING / PAINT CHIP CONTAINMENT, CLEANING, CAULKING, PATCHING UP TO 30%-70% OF WALL SURFACE, CAPTURING, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIMER AND TWO FINISH COATS15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINT PERSONNEL DOORS: OIL BASED PAINT BRUSHED, INCLUDING FRAMES AND TRIM, WOOD OR METAL
17INCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT2000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
17AINCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS1000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
17BINCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE PRIME AND TWO FINISH COATS1000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINT WINDOW: LATEX PAINT BRUSHED , INCLUDING FRAMES AND TRIM
18INCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS,ONE FINISH COAT1000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
18AINCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS1000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINT ROLL-UP DOORS: INDUSTRIAL ENAMEL SPRAYED, INCLUDING FRAMES AND TRIM, METAL
19INCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT2500SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
19AINCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
PAINT TRIM: 6" , LATEX OR OIL BRUSHED MISCELLANEOUS METAL OR WOOD
20INCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, ONE FINISH COAT5000LFLFLFLFLF
20AINCLUDES DROP CLOTH, SURFACE PREPARATION, PATCH AND SPOT PRIME, CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS, PAINT BUCKETS, BRUSHES, ROLLER COVERS, TWO FINISH COATS5000LFLFLFLFLF
WALL COVERING REMOVAL
21REMOVE WALL COVERINGS ONE OR TWO LAYERS, PATCH AND REPAIR WALL WITH MEDIUM DAMAGE TO SHEETROCK. INCLUDES CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF WALL COVERING & PAINT CHIPS,25000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
WALL COVERING
22INSTALL KOROSEAL "COLLAGE" 21.0 OZ, 22 MILS.25000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
COVE BASE VINYL
23REMOVE AND INSTALL 4" VINYL COVE BASE12000LF.LF.LF.LF.LF.
23AREMOVE AND INSTALL 6" VINYL COVE BASE5000LF.LF.LF.LF.LF.
23BINSTALL 4" INSIDE OR OUTSIDE CORNER1500EA.EA.EA.EA.EA.
23CINSTALL 6" INSIDE OR OUTSIDE CORNER1500EA.EA.EA.EA.EA.
WOOD TRIM COMPLETE WITH FINISH
24INSTALL 4" STAIN GRADE OAK1000LF.LF.LF.LF.LF.
24AINSTALL 2 1/2" PAINT GRADE TRIM AROUND DOORS AND WINDOWS2000LF.LF.LF.LF.LF.
24BINSTALL 3 1/2" PAINT GRADE TRIM AROUND DOORS AND WINDOWS2000LF.LF.LF.LF.LF.
24CINSTALL 3" STAIN GRADE OAK TRIM AROUND DOORS AND WINDOWS1000LF.LF.LF.LF.LF.
EPOXY FLOORS
25SHOT BLAST CONCRETE FLOORS MINIMUM. INCLUDES CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS,15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
25ASHOT BLAST CONCRETE FLOORS MAXIMUM. INCLUDES CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS,15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
25BHAND GRIND AROUND EDGES AND OBSTRUCTIONS. INCLUDES CONTAINING TESTING AND PROPER APPROVED DISPOSAL OF PAINT CHIPS,5000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
25CINSTALL HIGH SOLID EPOXY INTERMEDIATE COAT 18 MILS WITH ALUMINUM OXIDE AGGREGATE. INCLUDES PROPER APPROVED DISPOSAL OF PAINT BUCKETS, BRUSHES, ROLLER COVERS15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
25DINSTALL URETHANE TOP COAT 8 MILS. INCLUDES PROPER APPROVED DISPOSAL OF PAINT BUCKETS, BRUSHES, ROLLER COVERS15000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
25EPAINT FIRE LANE LINES 6". INCLUDES PROPER APPROVED DISPOSAL OF PAINT BUCKETS, BRUSHES, ROLLER COVERS10000LF. FT.LF. FT.LF. FT.LF. FT.LF. FT.
MISC. OSHA TESTING
26INDUSTRIAL HYGIENIST100HR.HR.HR.HR.HR.
26EAIR SAMPLING FOR LEAD100EA.EA.EA.EA.EA.
26F(R1 4-4-11)LEAD PAINT REMEDIATION PLANS AND METHODS, LEAD PAINT TESTING, X-RAY FLUORESCENCE, AAS ANALYSIS100EA.EA.EA.EA.EA.
LEAD BASED PAINT ABATEMENT/ENCAPSULATION
27(R1 4-4-11)REMOVAL OF LEAD-BASED PAINT, BY CHEMICALS, PER APPLICATION, MISCELLANEOUS, SIDING, DOORS, TRUSSES, BLOCK, BRICK20,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
27A(R1 4-4-11)ENCAPSULATIION OF LEAD-BASED PAINT, INTERIOR, ROLLER,BRUSHWORK, WALLS, DRYWALL, PLASTER, CEILINGS, WOOD, GRILLES, VENTS10,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.
27B(R1 4-4-11)ENCAPSULATIION OF LEAD-BASED PAINT, EXTERIOR, SPRAY, MISCELLANEOUS, BRICK, BLOCK, CONCRETE, STEELL, TRUSSES, SIDING , GUTTERS AND DOWNSPOUTS, COLUMNS20,000SQ. FT.SQ. FT.SQ. FT.SQ. FT.SQ. FT.

BASE YEAR TOTAL EVALUATED PRICE OPTION YEAR 1 TOTAL EVALUATED PRICE OPTION YEAR 2 TOTAL EVALUATED PRICE OPTION YEAR 3 TOTAL EVALUATED PRICE OPTION YEAR 4 TOTAL EVALUATED PRICE $0.00

Sheet2

Sheet3

Other files for this federal contract opportunity

Other files attached to (IDIQ) Contracts for Base Wide Paint Projects at Robins AFB, newest first.
File Type Posted
Questions Answers 04-22-2011.pdf PDF
MEMO FOR CLARIFICATION 14 Apr 2011.pdf PDF
Amendment 0002 —
Questions Answers 04-14-2011.pdf PDF
Amendment 0001.pdf PDF
Pre-proposal Conference Sign-in.pdf PDF
Pre-proposal Conference Questions Answers.pdf PDF
01005 - Statement of Work.doc DOC document
Residential Wage Desicion.docx DOCX document
01503 - Contract Administration.doc DOC document
09900 - Painting.doc DOC document
01580 - Safety Requirements.docx DOCX document
01540 - Green Procurement.docx DOCX document
09960 - High-Performance Coatings.doc DOC document
01560 - Environmental Requirements rev 11-2009.docx DOCX document
09950 - Wallcoverings.doc DOC document
0 - Index of Specifications.pdf PDF
01040 - Site Requirements.doc DOC document
01560 - Environmental Requirements.doc DOC document
07900 - Calking and Sealants.doc DOC document
UHHZ 100240W PAINT IDIQ.pdf PDF
01300 - Submittals Contractor-Furnished Items.doc DOC document
PAINT IDIQ 2010 GOV ESTIMATE —
Solicitation 03-14-2011.pdf PDF
09930 - Painting Concrete Floors.doc DOC document
01572 - Construction and Demolition Waste Management.doc DOC document
Building Wage Desicion.docx DOCX document
02065 - Lead Based Paint Abatement.doc DOC document
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .