Attachment 1 FD2020-24-52553 MJU-76B Air Specv4.pdf
PDF 674 KB Posted
- Attached to
- MJU-76/B Flare, Countermeasure Federal contract opportunity
- Solicitation number
- FA821326RB005-Solicitation
About this file
This is a PR/MIPR Air Munitions Specification Coordination Sheet for the production of MJU-76B flares (NSN: 1370016776009, DODIC: LA88, P/N: 201825310). The Purchase Request (PR) is FD2020-24-52553 with a contract cost of $250 million and a coordination start date of 06/06/2024. Government Furnished Material (GFM) is required, consisting of CTG, IMPULSE, BBU-35B cartridges with an NSN of 1377016421574 and P/N 7729436-30, with a quantity of 18,360 units. The item is designated as a Critical Safety Item (CSI), and Section 806 Determination has been completed. The coordination package includes approvals from the Program Manager (Tyson Pesnell, dated 02/23/2026), Equipment Specialist (Bill Cutler, dated 02/24/2026), Engineer (Matt Adams, dated 02/23/2026), Safety (Travis C. Madden, dated 06/06/2024), and other required personnel. The Item Manager is Tanya McCall (801-586-9098, EBHJ branch).
The specification requirements document establishes comprehensive technical and administrative requirements for the flare production contract. Key requirements include: Report of Shipment (REPSHIP) notifications to consignees within specified timeframes; compliance with Department of Defense Identification Code (DODIC) LA88; GFM consumption reporting; ammunition lot numbering per MIL-STD-1168C; Ammunition Data Cards (ADC) with lot acceptance test information; item marking per MIL-STD-130N and CAD/PAD Item Marking Instruction Version 1.6; serialization of items with minimum 4-digit serial numbers; hazard classification as Hazard Class/Division 1.3, Compatibility Group G, UN Number 0093, with Net Explosive Weight of 0.056971 kilograms; Performance Oriented Packaging (POP) compliance; classified data up to Secret level with DD-254 requirement; Configuration Management Plan per EIA-649-1A; Lot Acceptance Test Plans (LATP/ATP) approved 90 days prior to testing; energetic materials not exceeding 24 months from manufacturing date with ITAR compliance; percussion primer recertification and X-ray inspection; First Article Test per AFMC Form 260; Quality Assurance Program Plan per ISO 9001:2015; and Diminishing Manufacturing Sources and Material Shortages (DMSMS) management plans including health assessments and metrics data reporting.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR/MIPR AIR MUNITIONS SPECIFICATION COORDINATION SHEET
Item Manager
OR
Program Manager
FD2020- Package is: PR MIPR Special Instructions
NSN: DODIC: QTY:
NOUN: P/N:
Is this item in the Commodity Council Compliance Database (CCCD)? If Yes:
Reason for PR/MIPR?
Is GFM required?
If Yes, provide: NSN: P/N: QTY:
Hard copy of PR/MIPR Attached Coordination Start Date:
CSI? Contract Cost Completion Date:
Program Manager
Program Manager Name Initials Date Completed
Is Section 806 Determination completed (PRs Only)?
If no, reason:
Equipment Specialist Equipment Specialist Name Initials Date Completed
Engineer
Engineer Name Initials Date Completed
AFMC Form 807 Completed? Remarks:
Market Research Required? Remarks:
DD Form 254 Required? Note: Only Applicable to a PR
Safety Safety Name Initials Date Completed
PQM
Engineering Supervisor
Program Quality Manager Name Initials Date Completed
Engineering Supervisor Name Initials Date Completed
Data Manager Data Manager Name Initials Date Completed
EBE Control #
Item Manager Item Manager Name Phone # Select Branch:
STATEMENTS REQUIRED ON THIS PURCHASE REQUEST/MILITARY INTERDEPARTMENTAL PURCHASE
REQUEST (PR/MIPR)
“AIRMUNITIONS SPECIFICATION” February 6 2024
IM: PR/MIPR# FD2020-
Please initial each item. If you want the statement on the PR/MIPR, initial “YES”! If you do not want the statement on the PR/MIPR, initial “NO”! Please ensure all PRs and MIPRs containing Foreign Military Sales (FMS) requirements are coordinated with the appropriate Case Funded Country Program Manager.
OPR YES NO STATEMENTS (Information for “Airmunitions Specification”) Note: Blocks shown on right of CDRLs are for DM use only – “☐“
TRANS
The contractor shall provide an advanced Report of Shipment (REPSHIP) to the consignee no later than 24 hours prior to the shipment arrival, and for ammunition shipments no later than two hours after shipment departure. A (REPSHIP) shall include all the following data in accordance with ATTACHMENT 1.
CDRL Required CDRL Not Required CDRL (DI-SESS-82098)
IM
Contractor shall contact their nearest Defense Contract Management Agency (DCMA) Office for transportation guidance and assistance for all Foreign Military Sales (FMS) deliveries prior to shipment; and ensure that the DCMA provides one information copy of completed Notice of Availability (NOA) including FMS case and requisition numbers by mail to:
AFLCMC/EBHMB Attn: FMS Transportation 6043 Elm Lane, Hill AFB, UT 84056-5819, or Fax to: (801) 777-1089 or Email to ooalc.gacp.transportation@us.af.mil
IM Department of Defense Identification Code (DODIC)
IM
One copy of all shipping documents shall be furnished to 429 SCMS/GUMAB, by mail to: 6038 Aspen Ave, Hill AFB, Utah 84056-5805 or F requisition number, MIPR number and line item.
(MIPRS ONLY)FAX to: (801)777-5545, or Email: hill.outgoing.mipr@us.af.mil and shall identify requisition number, MIPR number and line item. (MIPRS ONLY)
IM
All SF 1080 billings shall show complete fund citation, MIPR and line item number. (CAT I
OUTGOING MIPRS ONLY)
IM
Government Furnished Material:
Stock Number Part Number Noun Qty
IM
Contractor shall provide a Government Furnished Material (GFM) consumption report as described in CDRL (DI-MGMT-80438B) - this applies to new production. GFM shall be identified by NSN, lot number, and serial number where possible.
Reporting to commence upon receipt of GFM and then every days (reporting frequency)
Item Manager email address: @us.af.mil
CDRL (DI-MISC-80438B)
ES
Ammunition lot numbering shall be accomplished. Reference MIL-STD-1168C for guidance.
Each energetic ingredient and component used in production lot(s) shall be from a single material lot.
ES
Ammunition Data Cards (ADC) shall be filled out; input in accordance with Attachment 2, Statement of Work - Ammunition Data Cards; and state quantity/serial number of lot acceptance test units in the remarks block.
One hard copy of the ADC shall accompany shipments to each shipping location.
CDRL (DI-MISC-80043B)
TM
mailto:ooalc.gacp.transportation@us.af.mil
ES
Items shall be marked using accepted practices for marking (reference MIL-STD- 130N for guidance). Minimum item marking shall include Government / Manufacturer Part Number, Lot Number (reference MIL- STD-1168C), and Serial Number if applicable.
Please Select:
ES
Serial numbers are required for each item, and should be listed individually in the remarks of a LOT Ammunition Data Card, when ADCs are required.
ES
The vendor shall serialize items sequentially for this (each) part number. Do not repeat serial numbers unless approved by the government. Serial numbers shall be a minimum of 4 digits.
ES
Items shall be marked in accordance with CAD/PAD Item Marking Instruction Version 1.6, 6 March 2023, and reference attachment.
ES Shelf-Life Code marking NOT required per MIL-STD-129R (C3).
ES Items are Inert.
ES
Physical Security of Arms, Ammunition & Explosive (AA&E) items shall be safeguarded as sensitive in accordance with DoDM 5100.76, April 17, 2012, 28 February 2014, DFARS 252.223-7007 and the following sensitivity/category code:
If Yes, select one of the following: If GFM is used, select SRC applicable to GFM
ES
Hazard Class/Division:
Compatibility Group:
DOT Marking/EX Number:
DOT Shipping Labels:
UN Number:
Proper Shipping Name:
Net Explosive Weight (NEW):
NEW Unit of Measurement:
NEW for all packaging/shipping documents shall reflect the NEW identified above per JHCS or IHC. If NEW is altered to adjust item performance and is greater than the weight listed, an ECP shall be submitted to the government prior to manufacturing or at least 60 days prior to shipping and shall include the SDS (formerly MSDS) and applicable supporting documentation.
ES
Contractor shall perform testing and shall acquire data necessary to support compliance with the Performance Oriented Packaging (POP) requirements of hazardous materials as defined in Title 49, Code of Federal Regulations (CFR), the International Maritime Organization’s International Maritime Dangerous Goods (IMDG) Code, and the International Civil Aviation Organization (ICAO) Technical Instructions for the Safe Transport of Hazardous Goods. The contractor shall document the results of the testing and data acquisition.
CDRL (DI-PACK-81059C)
ENG
Classified Data up to level is required, generated or both, as a part of this procurement effort (If Yes, a DD-254 Security Classification Specification Package is required) Additional Requirements (Mark if Needed) COMSEC CUI TEMPEST OPSEC
ENG
The contractor shall comply with TB 700-2, DoD Explosive Hazard Classification Procedures and shall submit Explosive Hazard Classification Data sufficient for the USAF to obtain a final DoD Hazard Classification.
(PLEASE NOTE: ANY QUESTIONS WHETHER THIS ITEM IS NEEDED MAY BE
ANSWERED BY COGNIZANT ES or SAFETY, ALCMC/EBHE (801-586-6963).
CDRL (DI-SAFT-81299C)
ENG
All Engineering Change Proposals (ECPs), Notice of Revisions (NORs), and Request For Variances (RFVs, formerly RFD/RFWs) affecting the approved product baseline configuration, acceptance test procedures, or manufacturing process of any item(s) on this contract shall be in accordance with EIA-649-1A. Major ECPs with NORs and Critical/Major RFVs shall be submitted to the responsible Government Engineering Authority for review/disposition by CCB.
Minor/Administrative ECPs with NORs and Minor RFVs shall be processed by the
Government Engineer
ACO
Contractor (Check Applicable CDRLs Below)
ECPs - CDRL (DI-SESS-80639E)
NORs - CDRL (DI-SESS-80642E)
RFVs - CDRL(DI-SESS-80640E)
Distribution Reason:
Statement: (ref. DoDI 5230.24)
CDRL (DI-SESS-80639E)
CDRL (DI-SESS-80642E)
CDRL (DI-SESS-80640E)
ENG
Contractor shall submit a Configuration Management Plan based upon EIA-649-1A and EIA- 649C to ensure product identification and traceability, product/production baselines, change management (tracking, reporting, and implementation accountability), data management systems, interface management, and maintenance of the USAF technical data packages.
Contractor Configuration Management (CM) system (including sub-contractors) that establishes initial baseline for hardware, software, processes, and procedures to meet the requirements as reflected by the Specification and Data List.
CDRL (DI-SESS-80858D)
ENG
(Note : Item(s) requiring ATP submittal with updated Gross Leak Check requirement) Item(s) must pass both gross and fine leak checks. MIL-STD-883L, Method 1014.18 may be used as guidance. The existing leak rate limit established for this item(s) will remain the same.
Contractor shall generate a Lot Acceptance Test Plan (LATP/ATP) with an analysis or test results showing compliance for Hill AFB engineering approval at least 90 days prior to commencement of Lot Acceptance Testing allowing for 30 days approval time after submission.
CDRL (DI-QCIC-80553A)
ENG
(Note: Item(s) requiring ATP submittal but NOT requiring updated Gross Leak Check procedures) The contractor shall provide the Lot Acceptance Test Plan (LATP/ATP) for this item(s) in accordance with the contractual data requirements. No changes to previously approved government Acceptance Test Plans shall be made without prior government approval.
The Lot Acceptance Test Plan provided must be approved by HAFB engineering at least 90 days prior to commencement of Lot Acceptance Testing allowing for 30 days approval time after submission.
CDRL (DI-QCIC-80553A)
Electronic Systems to encompass system, subsystem, pieces parts and assemblies shall not contain any substitutes for Tin-Lead solder and finishes. The use of any Tin-Lead solder substitutes requires approval through PCO and cognizant engineer, REFERENCE:
“Airworthiness Advisory (AA-08-02) Lead- Free Electronics” and GEIA-STD-0005-1 & 2
CDRL Required CDRL Not Required CDRL (DI-MGMT-81772)
Special Munitions Specifications are applicable
Lot Acceptance Test Requirements are:
USAF
Army
Navy
Contractor
ENG
The contractor shall furnish a Lot Acceptance Test/Inspection Report in the following System.
(s):
CDRL (DI-NDTI-80809B)
ENG
LOT ACCEPTANCE TEST: In the event of an end item failure, the contractor shall notify the PCO/ACO and Air Force Engineering Organization within 1 business day Air Force Engineering Organization:
E-mail: @us.af.mil
ENG
In the event of test failure(s), a Failure Summary and Analysis Report with proposed corrective actions/recommendations is required
CDRL (DI-SESS-80255B)
ENG
If Hexanitrostilbene (HNS) explosive material is used in the manufacture of this item, the HNS shall meet the requirements of Government Document WS5003F (or latest revision), Purchase Description of HNS Explosive; and maximum particle size shall not exceed 250 microns.
ENG
The age of the energetic materials and components (i.e., ALL explosives, propellants, pyrotechnics, cartridges, and/or initiators) used in the manufacture of these items or sub-components shall not exceed months based on the original manufacturing date. All energetic materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121 (http://www.pmddtc.state.gov/regulations_laws/itar.html).
ENG
Raw (non-blended) ingredients & materials used in blended/mixed energetic materials such as, but not limited to: fuels, oxidizers, binders, curatives, sensitizers, plasticizers, stabilizers etc., shall not exceed months since date of manufacture and comply with original manufacture’s Specification or MIL-STD. The government may waive the energetic and constituent material requirements listed above or portions thereof, on a case-by-case basis (when acceptable to the government) provided the contractor furnishes all details of the reason for the variance and the age, lot numbers, traceability, and other pertinent information/ test data and Certificate of Analysis/ Conformance (COA/COC) of the subject materials or components. The variance shall be submitted as a RFV and may be subject to, but not limited to, conditions such as sensitivity testing, stabilizer and analysis and/or dehumidification at vendor’s cost; therefore, vendor must plan accordingly. RFV not required provided vendor has approved energetic material and constituent management and recertification plan approved by HAFB technical authority for this specific contract and contract is executed with materials in compliance with said plan.
Recertification test data for materials shall be provided by vendor upon request at no additional charge to the government. All raw ingredients, materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and121.
Percussion primers shall have been certified /recertified by performing sensitivity (all-fire/no fire) and dud testing per applicable specification within the past months unless they are Navy certified and have a 2-year certification. Primers shall be stored in a temperature and humidity-controlled environment and in a sealed container with desiccant from time of primer manufacturing, shipping, storage and through final installation in end item.
All primers shall be X-rayed in top and side views for critical defects prior to use.
This item is designated as a Critical Safety Item (CSI). Documentation for critical characteristics may be found in the contract, TDP, assembly/inspection procedures or QALI.
MRB approval authority shall be retained by government engineer. Other characteristics requiring inspection or special oversight from DCMA:
ENG
The contractor shall comply with MIL-STD-1171B for propellants, explosives and/or chemical materials used in the end item(s) or component(s) on this contract. Acceptance and description sheets shall be submitted in WARP (see Attachment #3).
(Engineer shall provide ATTACHMENT #3, ES7035 to Item Manager)
CDRL (DI-MGMT-81978)
ENG
A detailed end item component listing for Ammo Data Card reporting is required (see Attachment #4).
(Engineer must attach item/component list and provide ATTACHMENT #4, ES6200 to Item Manager)
ENG
The contractor is allowed to pre-select no more than 30% of the required production lot test samples per lot which have external cosmetic defects such as nicks, dings, scratches, paint blemishes, plating blemishes, and small burrs. These units can be used as pre-selected production lot test samples as long as the units do not create an interference with the test fixture. The selection of those samples shall be noted in a discrepancy report that shall identify the item part number, DODIC, contract, lot number, serial numbers of the pre-selected units, and the cosmetic defect of each serial number. DCMA shall be notified in advance by submission of the discrepancy report of the preselected production lot test samples with external cosmetic defects prior to submission of the production lot for random sample selection. LAT units preselected under this premise shall be noted in the Lot Acceptance Test Report.
ENG
Any rework or repair on nonconforming material, beyond approved operation procedures and/or after product has been submitted to the government, shall. be approved by prior to rework and repair of the nonconforming material. (See Attachment #5) (Engineer shall provide ATTACHMENT #5, ES7034 to Item Manager)
ENG
DoD Preferred Methods for Acceptance of Product, MIL-STD-1916, shall be used for this procurement action. All references to MIL-STD-105, MIL-STD-414, MIL-STD-1235, and ANSI Z1.4 appearing in the Technical Data Package (TDP) are replaced by MIL-STD-1916.
Verification Levels (VL) shall replace AQLs and shall be VL IV for major characteristics and VL II for minor characteristics.
ENG
First Article Test/Inspection Report IAW AFMC Form 260 Select FAT below if required:
CDRL (DI-NDTI-80603A)
ENG
First Article Test Plan and Procedures
CDRL (DI-NDTI-81307A)
ENG
The contractor shall provide a Quality Assurance Program Plan (QAPP) which meets the requirements of ISO 9001:2015. The QAPP shall include a corrective action and disposition system for nonconforming material. The contractor QA requirements shall flow down to all tiers of subcontracts and assure subcontractor/vendor supplies conform to the requirements of this contract. The Contractor’s quality program shall focus on the prevention and detection of discrepancies to assure delivered products satisfy the life cycle and performance requirements. This deliverable will be a living document and therefore revisions may be periodically required and resubmitted for approval. Upon request, the contractor shall supply
Quality Manuals, Operating Procedures, or Work Instructions as referenced in the QAPP or as referenced in the contractor's ISO 9001:2015 Quality Management System.
CDRL (DI-QCIC-81794A)
ENG
The Contractor shall prepare and submit an MSE/AIE package to the Government for review and approval.
(Engineer shall provide a tailored ATTACHMENT #9 MSE to Item Manager)
CDRL (DI-QCIC-81960)
ENG
The Contractor shall submit the gauge studies, MSAs for the systems identified in paragraph
(h) in ATTACHMENT #9. This MSA package shall consist of the Assessment plan, associated data and analyses, and requires Government review and approval.
CDRL (DI-QCIC-81960)
ENG
The Contractor shall submit a Critical Characteristics Control Plan , CCCP. (Choose yes only if: 1- The TDP has at least one critical characteristic AND 2- The MSE Attachment is used for procurement.)
(Engineer shall provide ATTACHMENT #10 to Item Manager)
CDRL (DI-MGMT-80004A)
ENG
The Contractor may voluntarily submit Critical Plans of Actions (CPOAs). (Choose yes only if the CCCP option above is activated, otherwise choose no)
CDRL (DI-MGMT-80004A)
ENG
The Contractor shall submit a Critical Item Characteristics List; Notification of Occurrence of a Critical Defect; Root Cause and Corrective Action; Segregated Suspect Material Use;
and Request to Restart Operations. (If the CCCP option above is activated choose yes, otherwise choose no).
CDRL (DI-SAFT-80970A)
ENG
The Contractor shall prepare and submit a Technical Data Package Review Report.
CDRL (DI-MISC-80750)
ENG
The Contractor shall prepare and submit a Quality Assessment Report.
CDRL (DI-QCIC-81187)
ENG
The contractor shall provide all Technical Data Package (TDP) information as required in the Data Item Description (DID).
CDRL (DI-SESS-80776B)
IAW DoDI 4245.15, Section 3, para. f, DMSMS provisions will be placed in contracts and requests for proposals requiring the execution of the DMSMS Management Plan. As a minimum, include a contractor DMSMS Management Plan, Obsolescence Alert Notices, and Health Assessment Report. All other DMSMS deliverables/language will be at the discretion of the Program Team. Refer to SD-22 DMSMS Guidebook and SD-26 DMSMS Contract Guidebook for other contract language options that does not have an associated CDRL.
PM
Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management Plan
CDRL (DI-MGMT-81948)
PM
Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management Implementation Plan.
CDRL (DI-MGMT-81949)
PM
The contractor shall provide a Diminishing Manufacturing Sources and Material Shortages (DMSMS) Parts, Materials, and Processes Management Plan (PM&P) IAW MIL-STD-1191 and shall address all requirements in Sections 4 and 5.
CDRL (DI-STDZ-81993)
PM
Contractor shall submit a Bill of Materials (BOM) for Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management.
CDRL (DI-PSSS-81656B)
PM
Contractor shall provide an Obsolescence Alert Notice that a pending and/or emergent obsolescence issue exists.
CDRL (DI-MGMT-81941)
PM
Contractor shall provide a Diminishing Manufacturing Sources and Material Shortages (DMSMS) Health Assessment Report to support DMSMS management activities as a part of the Department of Defense (DoD) Total System Life Cycle Management responsibilities.
CDRL (DI-MGMT-82273)
PM
Contractor shall provide Diminishing Manufacturing Sources and Material Shortages (DMSMS) Life Cycle Management Data to support DMSMS management activities.
Those activities may require collecting Bill of Materials, DMSMS notifications. DMSMS case data, DMSMS health information, DMSMS cost and budgeting information, and DMSMS case mitigation data as a part of the Department of Defense's (DOD) Total System Life Cycle Management responsibilities.
CDRL (DI-MGMT-82274)
PM
Contractor shall provide Diminishing Manufacturing Sources and Material Shortages (DMSMS) Metrics Data to support reporting on DMSMS management activities as a part of the Governments’ Total System Life Cycle Management responsibilities.
CDRL (DI-MGMT-82275)
PM
Contractor shall provide a Diminishing Manufacturing Sources and Material Shortages (DMSMS) Operations Transfer Plan to assess program risk when transitioning DMSMS operations and management to the Government.
CDRL (DI-MGMT-82276)
PM
Counterfeit Mitigation-DFARS Title 48 252.246-7007 Applies
CDRL (DI-MISC-81832)
PM
Item unique identification (IUID) marking is required.
If required, marking shall be in accordance with MIL-STD-130N and DoD 5000.64.
PM
The contractor shall host a post award meeting at the contractor’s facility no later than days after contract award and provide minutes of the meeting.
PM email: @us.af.mil
CDRL (DI-ADMN-81505)
PM
Contractor shall plan and provide a Conference Agenda for all Program Reviews (PRs)/Technical Reviews (TRs) at their facilities and/or subcontractors facilities.
PM email: @us.af.mil
CDRL (DI-ADMN-81249C)
PM
Contractor shall prepare and deliver conference minutes for all PRs and TRs.
PM email: @us.af.mil
CDRL (DI-ADMN-81505)
PM
Contractor shall prepare and submit monthly progress reports documenting program status of milestones, schedule, cost objectives, and technical performance requirements.
PM email: @us.af.mil
CDRL (DI-MGMT-81928)
PM
Contractor shall prepare and submit monthly production status report documenting production delivery status, production build status, quality testing status, explanation of deviations from the schedule and plans to recover schedule delays. Initial production status report is due with planned schedule to completion of the contract order within 14 days of First Article Test approval or within 14 days of notification of waiving FAT requirement.
CDRL (DI-MGMT-81255)
PM
Contractor shall provide a report of GFP inventory and end-item transactions as described in CDRL (DI-MGMT-80442).
Applies to all inventories that are intended to be returned to the government after repair or use. Excluded are new production and items intended for disposal or expenditure.
CDRL (DI-MGMT-80442)
PM
PLEASE NOTE: THE SECTION ABOVE PERTAINS TO EXPLOSIVE AND HAZARDOUS ITEMS
ONLY. PLEASE INITIAL FOR CONCURRENCE WITH HAZARD CLASSIFICATION DATA LISTED IN
BLOCK. SAFETY TO CONTACT ES IF ANY DISCREPANCIES NOTED.
SE
Contracts involving ammunition and explosives (AE) will contain:
-DFARS Title 48 Part 252.223-7002, Safety Precautions for Ammunition and Explosives -DFARS Title 48 Part 252.223-7003, Change in Place of Performance - Ammunition and Explosives.
Additionally, if the scope of work includes air shipment of explosives, the safety specification should require contractor compliance with:
-AFMAN 24-604 Preparing Hazardous Materials for Military Air Shipments
PQM Program Quality Manager Review SER Supervisory Engineer Review
NOTE TO IM – FOR PRs PLEASE CHECK THE 761/762 SCREENING PACKAGE TO ENSURE IT IS CURRENT AND COMPLETE. IF (FAT) IS REQUIRED, BE SURE THE AFMC FORM 260 IS ACCURATELY AND COMPLETELY FILLED OUT
BY ENGINEER FOR CURRENT REQUIREMENTS.
This document supersedes June 15, 2023, same title.
| Note Blocks shown on right of CDRLs are for DM use only: Off |
| Department of Defense Identification Code DODIC: LA88 |
| Special Munitions Specifications are applicable: IAW PRF201825310 & DTL201825313 |
| Group8: Choice1 |
| FD2020: 24-52553 |
| SP Inst: |
| NOUN: MJU-76/B |
| P/N: 201825310 |
| PR/MIPR: PRODUCTION OF MJU-76/B |
| CCCD: [No] |
| NSN1: 1377016421574 |
| PN1: 7729436-30 |
| PR/MIPR Hard Copy: Off |
| Coord Start Date_af_date: 06/06/2024 |
| GFM: [Yes] |
| Contr Cost: 250M |
| PM Name: Tyson Pesnell |
| Comp Date_af_date: |
| 806: [Yes] |
| 806 Reason: |
| ES Name: Bill Cutler |
| PM Init: TDP |
| ES Init: BC |
| PM Comp Date_af_date: 02/23/2026 |
| ES Comp Date_af_date: 02/24/2026 |
| 807: [Yes] |
| ENG Name: Matt Adams |
| ENG 807: |
| MR Reason: |
| Market Research: [Yes] |
| DD 254: [Yes] |
| ENG Init: MMA |
| ENGComp Date_af_date: 02/23/2026 |
| SAF Name: Travis C. Madden |
| PQM Name: Gerald Pehrson |
| SAFInit: TCM |
| PQM Init: |
| SAFComp Date_af_date: 06/06/2024 |
| PQM Comp Date_af_date: |
| EN SUP Name: Michelle Warmoth |
| EN Sup Init: |
| DM Init: |
| IM Phone: 801-586-9098 |
| EN SUP Comp Date_af_date: |
| DM Comp Date_af_date: |
| Branch: [EBHJ] |
| IM Name: Tanya McCall |
| IM1: TM |
| IM2: |
| CDRL: Choice2 |
| IM3: TM |
| IM4: |
| IM5: |
| IM6: TM |
| IM7: |
| Noun GFM: CTG, IMPULSE, BBU-35/B |
| GFM QTY: 18,360 |
| IM8: TM |
| IM9: TM |
| IM10: |
| IM11: TM |
| IM12: |
| IM14: |
| Part Number: 7729436-30 |
| 82098: Off |
| 80438: Yes |
| IM13: BC |
| ES1: BC |
| ES2: |
| ES3: BC |
| ES4: |
| ES5: |
| ES6: BC |
| ES7: |
| ES8: BC |
| ES9: |
| ES10: BC |
| ES11: BC |
| ES13: BC |
| ES14: |
| MIL-STD-1168: [Government] |
| PSA: [Ammunition and Explosives SRC IV] |
| PSA/GFM: [Ammunition and Explosives SRC IV] |
| ES15: BC |
| Stock Number: 1377016421574 |
| HAZ CLASS/DIV: 1.3 |
| COMP GROUP: G |
| DOT MARKING/EX: EX2024072333 |
| DOT SHIP LABELS: EXPLOSIVE 1.3 G |
| UN NUMBER: 0093 |
| PROPER SHIP NAME: FLARES, AERIAL |
| NET EXP WEIGHT: 0.056971 |
| ES16: |
| ES17: BC |
| ES18: |
| 80043: Yes |
| 81059: Yes |
| CUI: Yes |
| TEMPEST: Off |
| OPSEC: Yes |
| NEW UNIT: [kilograms] |
| ENG1: MA |
| ENG2: |
| ENG4: |
| ENG5: MA |
| 81299: Yes |
| 80639: Yes |
| 80642: Yes |
| COMSEC: Yes |
| GOVT ENG: Yes |
| ACO: Off |
| CONTRACTOR: Off |
| ECP: Off |
| NOR: Off |
| RFV: Off |
| Classification: [Secret] |
| Classification Reason: [Controlled Technical Information] |
| ENG6: |
| ENG7: MA |
| ENG8: |
| ENG9: |
| 80640: Yes |
| 80858: Yes |
| 80553: Off |
| ENG10: MA |
| ENG11: |
| ENG12: MA |
| ENG13: |
| 80533A: Off |
| ENG14: MA |
| ENG15: MA |
| ENG16: |
| ENG17: MA |
| USAF: Yes |
| Army: Off |
| Navy: Off |
| CONT: Off |
| DISTRO: [D] |
| LAT: [WAWF/WARP] |
| ENG18: |
| ENG19: MA |
| ENG20: |
| ENG21: MA |
| 81772: Off |
| 80809: Yes |
| IM Email: tanya.mccall.2.ctr |
| ENG Email: |
| lat requirments: IAW PRF201825310 & DTL201825313 |
| ENG22: |
| ENG23: MA |
| ENG24: |
| ENG25: |
| AGE: 24 |
| RAW: 24 |
| ENG26: MA |
| ENG27: MA |
| ENG28: |
| ENG29: MA |
| DUD: |
| DCMA: |
| ENG30: |
| ENG31: |
| ENG32: MA |
| ENG33: |
| ENG34: MA |
| ENG35: MA |
| ENG36: |
| ENG37: MA |
| 80255: Yes |
| ENG38: |
| ENG39: |
| Rework: [EBH procurement engineering authority) prior to rework and repair of the nonconforming material ] |
| AFMC Form 260: [FAT- Contractor Test (Engineer shall supply ATTACHMENT #8 Clause to Item Manager)] |
| ENG40: MA |
| ENG41: MA |
| ENG42: |
| ENG3: DH |
| ENG44: |
| ENG45: MA |
| ENG46: |
| ENG47: MA |
| 81978: Yes |
| 80603: Yes |
| ENG48: |
| ENG49: MA |
| 81307: Yes |
| 81794: Yes |
| ENG50: |
| ENG51: MA |
| 81960: Yes |
| 819601: Yes |
| 80004: Off |
| ENG52: |
| ENG53: MA |
| ENG54: |
| ENG55: |
| ENG56: MA |
| ENG57: |
| ENG58: MA |
| ENG59: |
| 800041: Off |
| 80970: Off |
| 80750: Off |
| 81187: Off |
| 80776: Off |
| ENG60: MA |
| ENG61: |
| ENG62: MA |
| ENG63: |
| ENG64: MA |
| ENG65: |
| ENG66: MA |
| PM1: TP |
| PM2: |
| PM3: |
| PM4: TP |
| PM5: |
| PM6: TP |
| PM7: |
| PM8: TP |
| PM9: TP |
| 81948: Yes |
| 81949: Off |
| 81748: Off |
| 81656: Off |
| PM10: |
| PM Email: tyson.pesnell |
| PM11: TP |
| PM12: |
| PM13: |
| PM14: TP |
| PM15: |
| PM16: TP |
| PM17: |
| 81941: Yes |
| 82273: Yes |
| 82274: Off |
| 82275: Off |
| 82276: Off |
| 81832: Off |
| 81505: Yes |
| 81249: Off |
| 815051: Yes |
| 81928: Off |
| 81255: Yes |
| 80442: Yes |
| PM18: TP |
| PM19: |
| PM20: TP |
| PM21: |
| PM22: TP |
| PM23: TP |
| PM24: |
| PM25: |
| PM26: TP |
| PM27: TP |
| PM28: |
| PM29: |
| PM30: TP |
| PM31: TP |
| PM32: |
| PM33: TP |
| PQM Text: |
| SER Text: |
| PM34: |
| PM35: TP |
| PM36: |
| SAF1: TCM |
| SAF2: |
| PQM1: |
| PQM2: |
| SER1: |
| SER2: |
| DODIC: LA88 |
| QTY: TBD |
| DM Name: Robert Morgan |
| EBE CONT NUM: |
| Trans1: |
| Trans2: |
| ES12: |
| ES12A: |
| ES13A: BC |
| NSN2: 1370016776009 |
| Number12: 92 |
File details come from the government source that posted it. Updated .