Updated MMIII Acquisition DRAFT PWS v1.12.pdf

PDF 522 KB Posted

Attached to
Integration Support Contract (ISC) 2. 0 Federal contract opportunity
Solicitation number
FA8207-20-ISC-2
Issued by
Department of the Air Force Materiel Command Nuclear Weapons Center

About this file

This performance work statement outlines requirements for an acquisition task order under the Integration Support Contract 2.0 to provide programmatic and engineering support services to the Air Force Nuclear Weapons Center's ICBM Systems Directorate for various Minuteman III acquisition programs. Key programs addressed include the Arm/Disarm Switch Replacement, Automatic Switching Unit Replacement, Battlespace Awareness upgrades, Control Monitor Procedures Trainer replacement, Fast Rising B-Plug Service Life Extension, Flight Test Telemetry and Termination replacement, ICBM Cryptography Upgrade II, Launch Control Center Block Upgrade, Payload Transporter Replacement, Strategic Automated Command Control System Replacement, T-41 trainer relocation, and Transportation Erector Replacement. The contractor shall perform tasks such as program management, engineering analysis, risk management, logistics planning, documentation development and review, meeting support, and configuration management across all acquisition phases in accordance with DoD directives and regulations. Twelve program-specific appendixes outline additional requirements for individual acquisition efforts.

View the file

Other files for this federal contract opportunity

Other files attached to Integration Support Contract (ISC) 2. 0, newest first.
File Type Posted
Updated H001 OCI Clause.docx DOCX document
Attachment 18 - ISC2.0 PWS TO1 MMIII DIRSUP.pdf PDF
Attachment 24 - Section M.pdf PDF
Attachment 3 - Labor Quantity Workbook.xlsx XLSX spreadsheet
Attachment 19 - ISC2.0 PWS TO2 MMIII SUST.pdf PDF
Attachment 6 - ISC 2.0 Draft CDRL Package.docx.pdf PDF
Attachment 11 - DD254.pdf PDF
Attachment 23 - Section L.pdf PDF
Attachment 16 - Draft CLIN Structure for Task Order 4 MMIII Integration.pdf PDF
Attachment 15 - Draft CLIN Structure for Task Order 3 MMIII Acquisition.pdf PDF
Draft RFP FA820721R0001.pdf PDF
Attachment 10 - Appendix C Safety Plan.pdf PDF
Attachment 17 - Draft CLIN Structure for Task Order 5 GBSD Enterprise.pdf PDF
ISC 2.0 Strategy Updates 9-Sept-20.pptx PPTX presentation
ISC 2.0 Draft TO 3 MMIII Acquisition.docx DOCX document
ISC 2.0 Draft Small Business H Clause.docx DOCX document
ISC 2.0 Draft TO 1 MMIII Directorate Support.docx DOCX document
ISC 2.0 Draft Labor Rate Adjustment H Clause.docx DOCX document
ISC 2.0 Draft TO 2 MMIII Sustainment.docx DOCX document
ISC 2.0 Draft Award Fee Plan.docx DOCX document
Draft RFP Package - TO 3 MMIII Acquitision Support PWS.docx DOCX document
Draft RFP Package - Basic PWS.docx DOCX document
Draft RFP Package - Attachment 1 - GRIDS.docx DOCX document
Draft Special H Clause - Joint Cyber Information Tracking System.docx DOCX document
Draft RFP Package - Attachment 9 - CDRL (list).docx DOCX document
Draft RFP Package - TO 1 Directorate Support PWS.docx DOCX document
Draft RFP Package - Attachment 6 - GFP list.xlsx XLSX spreadsheet
Draft RFP Package - Attachment 2 - Suggested Labor Matrix Workbook.xlsx XLSX spreadsheet
Draft RFP Package - Attachment 4 - Labor Category Mapping.xlsx XLSX spreadsheet
Draft RFP Package - Attachment 7 - Appendix C Safety Plan.docx DOCX document
ISC_2_M_comp v1.2.docx DOCX document
ISC_2_L_comp v1.2.docx DOCX document
Industry Day 3 Updated Slides.pptx PPTX presentation
ICBM Governance Model.pptx PPTX presentation
ISC_2_M_Intro and Factor 1 - v2.0.docx DOCX document
ISC 2.0 Draft OCI Clause.pdf PDF
ISC 2.0 Industry Day 2 Additional Timeslots.docx DOCX document
ISC 2.0 Industry Day 2 Map.pdf PDF
MMIII INTEG DRAFT v1.16.pdf PDF
Updated MMIII Sust DRAFT v2.1.pdf PDF
ISC 2.0 Industry Day 2 Timeslots.docx DOCX document
ISC 2.0 PWS Comment Resolution Matrix_CONTRACTOR NAME.xlsx XLSX spreadsheet
Updated DIR Support DRAFT PWS v1.19.pdf PDF
ISC_2_L_Factor 1 v2.8.docx DOCX document
ISC_2_M_Factor 1 v2.2.docx DOCX document
ISC_2_M_intro v2.2.docx DOCX document
General Session Attendance.pdf PDF
ISC 2.0 Draft Award Fee Plan.docx DOCX document
19 November Industry Day Slides - Final.pptx PPTX presentation
INDUSTRY Q&A RESPONSE 1.0.docx DOCX document
Show all 50

Integration Support Contract (ISC) 2. 0 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8207-XX-X-XXX

MMIII ACQUISITION TASK ORDER PWS- ISC 2.0

INTERCONTINENTAL BALLISTIC MISSILE (ICBM)

INTEGRATION SUPPORT CONTRACT (ISC) 2.0

MMIII ACQUISITION TASK ORDER

PERFORMANCE WORK STATEMENT (PWS)

FOR

AIR FORCE NUCLEAR WEAPONS CENTER (AFNWC)

ICBM SYSTEMS DIRECTORATE (ICBMSD)

dd MMM 2019

CONTENTS

1.0 ISC – MMIII ACQUISITION

1.1 Scope

1.2 Purpose ............................................................................... Error! Bookmark not defined.

2.0 Appendices ............................................................................... Error! Bookmark not defined.

APPENDIX A: ACRONYMS AND ABBREVIATIONS ............ Error! Bookmark not defined.

APPENDIX B: WORK BREAKDOWN STRUCTURE .............. Error! Bookmark not defined.

APPENDIX C: SAFETY, FIRE PROTECTION AND HEALTH SPECIFICATION ......... Error!

Bookmark not defined.

APPENDIX D: GOVERNMENT FURNISHED PROPERTY/SERVICES/EQUIPMENT

(GFP/GFS/GFE) Error! Bookmark not defined.

APPENDIX E: CONTRACT DATA REQUIREMENTS LIST (CDRL) ... Error! Bookmark not defined.

APPENDIX F: PROGRAM SPECIFIC REQUIREMENTS

1.0 ACQUISITION PROGRAM (NAME).............................. Error! Bookmark not defined.

2.0 ACQUISITION PROGRAM (NAME).............................. Error! Bookmark not defined.

1. MMIII ACQUISITION TASK ORDER (TO) PWS

ISC – MMIII ACQUISITION SCOPE

MMIII Acquisition Branch Description

The Acquisition Branch consists of 3 Sections: ACAT I & II, ACAT III, and Services. The branch is responsible for…

Acquisition Programs

Per DoDI 5000.02, “All defense acquisition programs are designated by an ACAT (i.e., ACAT I through III)”. ACAT level is based on the program’s estimated dollar value and type of funding.

Thresholds are listed in Enclosure 1, Table 1, of DoDI 5000.02. The ICBM Systems Directorate currently has programs of all ACAT levels.

This body of this Task Order PWS defines overarching requirements for all ICBMSD acquisition programs. Appendices to this TO PWS define requirements specific to individual programs.

Due to Organizational Conflict of Interest (OCI) laws, the Services Section will not use ISC support, and is therefore not included in this or any TO on the contract.

Organization Structure

2. GENERAL REQUIREMENTS

2.1. All requirements in the Basic PWS of this contract apply to this Task Order

2.2. The contractor shall accomplish any and all of the requirements in this Task Order that are applicable to their assigned programs

2.3. The contractor shall accomplish any program-specific requirements detailed in the applicable program appendix to this Task Order PWS

2.4. All work shall be performed in coordination and cooperation with pertinent overseeing goverment personnel. (The Gov Program Manager and Engineer are responsible for meeting the program’s cost, schedule, technical and performance objectives. As the system integrator, the Government is the decision authority.)

2.5. All work shall be performed IAW applicable laws and regulations. The contractor shall

NOT perform any Inherently Government Functions as defined in XXX

2.6. The contractor shall collaborate with appropriate internal and external stakeholders as needed to accomplish requirements and tasks

2.7. The contractor shall provide support to the Gov Program Manager and Engineer in meeting program cost, schedule, technical, and performance objectives throughout the acquisition phases of the program.

2.8. The contractor shall support acquisition planning and execution of acquisition phase activities consistent with DoD 5000 series directives, applicable AFIs, and any other laws and regulations relevant to ACAT acquisition and sustainment programs. This support generally includes:

Program management

Engineering analysis

Risk management

Logistics planning

Document verification

Determining requirements to meet acquisition milestones (e.g. Workloads, technical requirements, adequacy of technical submissions, schedules, test equipment, facilities, skills, training, etc.)

Cost estimation and budget submissions

Responding to deficiencies

Analysis, planning, and reporting capability gaps or mission enhancements that may be mitigated/enhanced through materiel solutions

Other requirements and tasks as circumstances dictate specific needs

3. PROGRAMMATIC REQUIREMENTS

3.1. The contractor may be required to serve as Deputy Program Manager, depending on specific program requirements.

3.1.1. While serving as Deputy PM, the contractor shall ensure all Inherently Government

Functions are accomplish only by Government personnel.

3.2. The contractor shall provide programmatic support for assigned programs during all phases of the acquisition lifecycle.

3.3. The contractor shall participate in activities of program managers, contracting officers, engineers, program control specialists, configuration managers, testing specialists and logisticians

3.4. The contractor shall assist the government program manager in day to day management and execution of the program

3.5. The contractor shall assist the Program Manager in developing and completing acquisition program planning and execution activities, sustainment planning, and other program management related requirements as needed.

3.6. The contractor shall represent the program and perform management activities during instances when the Government is not available.

3.7. The contractor shall perform analyses, assessments, trade studies, and forecasts (81284)

3.7.1. The contractor shall provide information to facilitate program decisions (81759)

3.7.2. The contractor shall monitor and analyze program performance and cost, and recommend efficiencies/opportunities

3.7.3. The contractor shall analyze, plan, and estimate financial forecasts, current year obligation and expenditure plans, and unfunded requirements

3.8. The contractor shall perform risk management for the assigned program (e.g. plan and conduct risk assessments, provide mitigation recommendations, implement approved mitigations, track program risks, etc.)

3.9. The contractor shall accomplish Tech Refresh activities and documentation for the assigned program (81429)

3.10. The contractor shall have knowledge of life-cycle sustainment requirements.

3.11. The contractor shall participate in planning for transition of future capabilities from acquisition to sustainment

3.12. The contractor shall have knowledge of the LRDP process.

3.13. The contractor shall support and participate in the provisioning process as applicable

3.14. The contractor shall support acquisition program contract preparation/requirements and other procurement activities

3.14.1. The contractor shall prepare information/documents for RFPs (81606)

3.14.2. The contractor shall act as advisor in the source selection process to review proposals and provide recommendations, IAW current DoD source selection regulations

3.14.3. The contractor shall perform contract closeout activities as appropriate

3.14.4. The contractor shall initiate, attend, and provide other needed support for Data Calls

3.14.5. The contractor shall assist with Market Research

3.15. Program Schedule

3.15.1. The contractor shall develop and maintain program schedules (81623)

3.15.2. The contractor shall recommend and implement (after government approval) timely resolutions for schedule conflicts to minimize program impacts

3.16. The contractor shall perform acquisition program logistics activities.

3.16.1. The contractor shall participate in planning for system sustainment and life cycle issues

3.16.2. The contractor shall perform assessments, analyses, studies, etc. to inform logistics planning

3.16.3. The contractor shall provide Supply Chain Management support

3.16.4. The contractor shall perform suitable substitutes analysis and documentation

3.16.5. The contractor shall perform spares analysis

3.16.6. The contractor shall coordinate Tech Refresh installation activities and any other installation needs

3.16.7. The contractor shall support inventory management of equipment with pertinent contractor(s)

3.16.8. The contractor shall perform deployment planning and scheduling activities

4. ENGINEERING/TECHNICAL REQUIREMENTS

4.1. The contractor shall provide engineering support as prescribed by each specific acquisition program appendix to this Task Order PWS. Each acquisition program will require a different mix of contractor engineering support in areas such as Aerospace, Electrical, Mechanical, Software, Systems, Sustainment, Test, etc.

4.2. The contractor shall provide engineering support for assigned programs throughout all phases of the acquisition lifecycle.

4.3. The contractor shall provide technical expertise to the Program Manager for acquisition program planning and execution activities

4.4. The contractor shall serve as support to and assist the Government engineer in managing the full scope of day-to-day engineering demands of the program

4.5. The contractor shall assist the government program engineer with engineering/technical tasks and activities, and developing and completing technical planning and execution activities

4.6. The Contractor shall assist the Program Engineer to write, review, and update technical acquisition and program documents

4.7. The Contractor shall assist the Program Engineer to review deliverables from other contractors as appropriate.

4.8. The contractor shall serve as a program technical focal point

4.9. The contractor shall perform analyses, assessments, trade studies, evaluations, etc.

4.9.1. The contractor shall perform technical and engineering analyses (e.g. FRACAS analysis, RAM analysis, Failure Mode Effects Analysis (FMEA), etc.)

4.9.2. The contractor shall perform engineering assessments

4.9.3. The contractor shall perform weapon system assessments (e.g. Deficiency

Reporting, ETAR, 202, 107 Support, etc.)

4.9.4. The contractor shall perform environmental health and safety assessments

4.9.5. The contractor shall investigate and evaluate deficiencies

4.9.6. The contractor shall evaluate network topology and architecture development

4.9.7. The contractor shall perform feasibility studies of proposed modifications

4.9.8. The contractor shall model and/or simulate current and projected system functionality

4.9.9. The contractor shall perform, develop, and/or evaluate Trade-off Studies &

Analysis

4.9.10. The contractor shall perform other analyses, assessments, studies, and evaluations in support of the acquisition program

4.10. The contractor shall provide technical expertise and participate in planning and execution of engineering-related activities

4.11. The contractor shall develop, review, analyze, and provide recommendations on System

Level Requirements (82007)

4.12. The contractor shall develop/refine program requirements and associated documentation

(80004)

4.13. The contractor shall review and provide feedback on Technical Data Packages (31000)

4.14. The contractor shall develop and recommend sustainment strategies (881)

4.15. The contractor shall analyze supportability strategies

4.16. The contractor shall identify technical risks, and develop and recommend mitigation strategies (81399)

4.17. The contractor shall provide third party quality assurance oversight to hardware installation, hardware and software testing, and closure reporting

4.18. The contractor shall manage development, testing, production, and delivery of replacement hardware/software, including facilitating fielding, system training, spares, technical orders, etc.

4.19. The contractor shall oversee the Radios Frequency Authorization (RFA) process, if necessary for the individual program.

4.20. The contractor shall support parts substitution, modifications, modification installations, etc.

4.21. The contractor shall accomplish Requests for Nomenclature (DD Form 61)

4.22. The contractor shall provide technical expertise and participate in planning and execution of System Engineering Technical Review (SETR) events (SRR, PCA, FCA, etc.)

4.23. The contractor shall participate in planning and accomplishing site surveys

4.24. The contractor shall review and support configuration management activities (e.g.

Engineering Change Proposals (ECPs), drawing reviews/redlines, etc.)

4.25. The contractor shall participate in planning and accomplishing Tech Refresh activities and documentation

4.26. The contractor shall accomplish Value Engineering.

“Value Engineering” is a systematic method to improve the "value" of goods or products and services by using an examination of function, or the formal technique by which contractors may voluntarily suggest methods for performing more economically. Value engineering also attempts to eliminate, without impairing essential functions or characteristics, anything that increases acquisition, operation, or support cost.

4.26.1. The contractor shall continuously look for solutions in which the Government may receive best value or save cost without imposing unnecessary or burdensome technical, cost, or schedule risk.

4.27. The contractor shall collaborate and coordinate with government Cybersecurity personnel to accomplish Cybersecurity requirements for the programs, including research, answering questions, developing/gathering/reviewing/providing information and documentation, etc.

(82143)

4.28. The contractor shall provide software support and documentation review/updates (81756)

4.29. Test Support

4.29.1. The contractor shall assist with developmental and operational tests

4.29.2. The contractor shall support First Article Acceptance Testing (FAAT)

4.29.3. The contractor shall support Initial Operational Test and Evaluation (IOT&E), Operational Utility Evaluation (OUE) and other testing as needed

4.29.4. The contractor shall design tests, develop test procedures, write/review test plans, identify test facility requirements, schedule tests, and execute tests (81284)

4.29.5. The contractor shall review and provide recommendations on System Test Plans

(e.g. Test & Evaluation Program Plan, Master Test Plan, Detailed Test Plan, Test

Procedure, Test/ Inspection Report, etc.) (81284)

4.29.6. The contractor shall review and analyze Prime contractor test plans for completeness, thoroughness, and correlation to applicable engineering specifications

4.29.7. The contractor shall manage verification logic networks

4.29.8. The contractor shall make test statistically viable recommendations

4.29.9. The contractor shall participate in and provide support for the program Integrated

Test Team (ITT), including maintaining the charter, generate and distribute minutes, capture and track action items, answer action items, etc.

5. Documentation Support

5.1. The appropriate functional contractor personnel shall create, develop, draft, review, update, maintain, provide input to, coordinate, etc. the program acquisition/milestone information requirements and documents required throughout the acquisition process IAW DoDI

5000.02, AFI 63-101, and other applicable regulation. These documents include: (CDRL)

Affordability Analysis

Acquisition Decision Memorandums (ADMs)

Acquisition Program Baseline (APB)

Acquisition Strategy

Corrosion Control Plan

Cybersecurity Strategy (CSS)

Exit Criteria

Frequency Allocation Application

Intellectual Property Strategy

Item Unique Identification (IUID) Plan

Life Cycle Sustainment Plan (LCSP)

PESHE and NEPA Compliance Schedule

Program Office Estimates (POE)

Program Protection Plan (PPP)

Radios Frequency Awareness (RFAs)

Risk Management Plan

Specifications

Spectrum Supportability Risk Assessment (SSRA)

System Engineering Plan (SEP)

Test and Evaluation Master Plan (TEMP)

Etc.

5.2. The contractor shall establish and maintain schedules to develop the documentation and ensure documentation is ready for program Milestones (CDRL)

5.3. The appropriate functional contractor personnel shall review and assess

CDRLs/deliverables from program Prime contractors, and provide acceptance/non-acceptance recommendations

5.3.1. Review shall include assessment of format and content expectations.

5.4. The appropriate functional contractor personnel shall create, develop, draft, review, update, maintain, provide information for, coordinate, etc. program management documents, such as: (CDRL)

CLIN Status Reports

Contract Funds Status Report

Demilitarization & Disposal

Horse Blanket

LCMP

Level II

Monthly Activity Reports

Performance & Cost Report

Quality Assurance Program Plan

Schedules (e.g. Integrated Master Schedule, executive schedule, project schedules, deployment schedules, etc.)

Sustainment forecasts

Team Charters

Transition Plans

Work Breakdown Structures

Etc.

5.5. The appropriate functional contractor personnel shall create, develop, draft, review, update, maintain, provide information for, coordinate, etc. procurement documentation such as:

(CDRL)

Contract Modifications

Letters of Clarification/Concern

Market Research Reports

Purchase Requests

PWSs

RFP Documentation

Statements of Objectives (SOOs)

Statements of Work (SOWs)

Etc.

5.6. The appropriate functional contractor personnel shall create, develop, draft, review, update, maintain, provide information for, coordinate, etc. engineering documents, such as:

(CDRL)

Detail Specification Documents

Engineering Change Proposals

Interface Control Documents

Master Engineering Document Lists

Performance Specification Documents

Request for Nomenclature (DD Form 61)

Specification Change Notices

System/Subsystem Specifications

Technical Orders

TERB documentation

Other engineering and technical documents as needed

6. MEETING SUPPORT

6.1. Appropriate functional contractor personnel shall participate in, contribute to, and provide technical and programmatic expertise for meetings, reviews, and boards involving the program, IAW the basic PWS paragraph #-#.

SPECIFIC PROGRAM APPENDICIES

APPENDIX 1: ARM/DISARM SWITCH REPLACEMENT (ADSR)

A1.1. ADSR Description

The Arm Disarm Switch Replacement (ADSR) Program will replace the Arm/Disarm (A/D)

Switch with a new design. The A/D Switch is an electromechanical switch that physically locks out several ordnance circuits on the MMIII. The switch will safe (disrupte the electrical pathway needed for the missle to arm), arm (facilitate the electrical pathway needed for the missle to arm), and facilitate execution of a number of critical weapon functions prior to and throughout the duration of missile flight, and is mandatory in both the missile operational and test configurations. There is one A/D switch in each interstage, one on the 2nd stage motor, and two on the PSRE for a total of five switches per missile.

ADSR will primarily utilize the DCA engineers from the program for primary engineering support.

A1.2. Security Requirement

A1.3. Program-Specific Requirements

The ADSR acquisition strategy will have up to three contractor’s complete designs and qualify the same. Once this has been completed any/all of the contractos which have successfully completed the qualification process will be allowed to bid on a larger competitive production order.

APPENDIX 2: AUTOMATIC SWITCHING UNIT (ASU) REPLACEMENT PROGRAM

A2.1. ASU Description

The ASU Replacement Program addresses obsolescence in the ICBM power distribution system and replaces the aging power switchgear with a modern Commercial-Off-The-Shelf

(COTS) solution.

A2.2. Security Requirement

A2.3. Program-Specific Requirements

APPENDIX 3: BATTLESPACE AWARENESS

A3.1. Battlespace Awareness Description

WaRTAK provides a tactical, common operating picture via a secure, high-bandwidth, wireless radio network utilizing the Android Tactical Assault Kit (ATAK). ATAK enables sharing/presentation for text chat, video, pictures, and an interactive, layered, shared, moving map, plus many other niche data types for the tactical user within a closed network. ATAK runs within a small, personal tablet (smartphone) in the Dismount Kits or larger tablets in vehicles and buildings. The user also has a headset for audio that connects to the radio. The rest of WaRTAK exists to support and route data between each persons’ ATAK application.

RVA CLS monitors top side activity at the Air Force MMIII Launch Facilities (LF) and provides CCTV capabilities back to the Missile Alert Facilities (MAF) thereby allowing security forces to facilitate site security from the MAF and the ability to perform tailored responses to sites within the missile fields dependent on the severity of the identified activties.

RVA II consists of a series of modifications/upgrades built on foundation of existing RVA system. The upgraded modifications to the system are: Improved video to Ground Security

Forces (SF), Outer Zone/Inner Zone (OZ/IZ) Activation Alarm, Extended 1-Hour Power Backup, Video to Airborne SF, Extended 7-Day Video Archive, Enhanced Cybersecurity

A3.2. Security Requirement

A3.3. Program-Specific Requirements

A3.3.1. The contractor Logistician shall coordinate P&D installation activities with RVA

CLS activities.

A3.3.2. The contractor Logistician shall coordinate of transferring GFP from P&D contractor to CLS contractor.

A3.3.3. The contractor Logistician shall inventory RVA II equipment with the P&D contractor.

APPENDIX 4: CONTROL MONITOR PROCEDURES TRAINER (CMPT)

A4.1. CMPT Program Description

The CMPT Program will replace obsolete hardware and software on all CMPT systems across the ICBM Enterprise to increase supportability. This program is required to maintain required training levels on the CMPT to ensure compliance with current certification standards.

A4.2. Security Requirement

Contractor resources supporting the CMPT Program shall maintain a Secret security clearance.

A4.3. Program-Specific Requirements

APPENDIX 5: FAST RISING B-PLUG (FRBP) PROGRAM

A5.1. FRBP Program Description

The Fast Rising B-Plug (FRBP) Service Life Extension Program (SLEP) was initiated in order to meet an Air Force Global Strike Command (AFGSC) requirement for B-Plug technology insertion to address system obsolescence, safety and reliability.

This program will replace the Actuator Locking Bar (ALB), Secondary Door Linear Actuator

(SDLA), add a position sensor to the Electro-Mechanical Actuator (EMA), replace the Energy

Storage System (ESS), integrate a M1 Motor Drive alternative solution, software development for the Secondary Door Control Assembly (SDCA), and add a slow raise mode to the Site

Activation Remote Controller (SARC).

A5.2. Security Requirement

A5.3. Program-Specific Requirements

APPENDIX 6: FLIGHT TEST, TELEMETRY, AND TERMINATION (FT3) PROGRAM

A6.1. FT3 Description

The purpose of the Flight Test, Telemetry, and Termination (FT3) Program is to replace aging

MMIII ICBM flight test unique equipment (FTUE). The replacement systems/subsystems must meet 30th Space Wing (SW) Range Safety requirements to ensure the future reliability of MMIII

ICBM Operational Test Launches (OTL) and developmental flight test programs.

A6.2. Security Requirement

Contractor resources supporting the FT3 program shall possess and maintain a Secret security clearance.

A6.3. Program-Specific Requirements

A6.3.1. The contractor shall develop and maintain the FT3 Integrated Master Schedule

(IMS)

A6.3.1.1. The schedule shall combine the Guidance SSC IMS with government activities, ISC activities, and other activities as identified by the

Government Program Manager.

A6.3.1.2. The contractor shall provide reports, analyses, and summaries of the

IMS as required. (CDRL)

A6.3.2. Associated Contractor Agreements - The contractor shall enter into agreements with the Guidance SSC and their subcontractors.

A6.3.3. Reference Models

A6.3.3.1. The contractor shall perform assessments comparing the FT3 configuration changes to baseline Reference Models.

A6.3.3.2. The contractor shall update the baseline models where necessary.

A6.3.3.3. The contractor shall provide updated Reference Models in support of

ICBM operational software changes, using FT3 data provided by the

Guidance SSC. (CDRL)

A6.3.4. Information Technology (IT) and Cybersecurity - Portions of FT3 systems will be considered IT according to DoDI 5000.02. Many IT requirements identified in

Enclosure 11 of DoDI 5000.02 will apply.

A6.3.4.1. The contractor shall support the Government in achieving these requirements/attaining waivers

A6.3.4.2. The contractor shall coordinate IT and Cybersecurity efforts with

Guidance SSC.

A6.3.4.3. The contractor shall work with 30th Space Communications Squadron

(30 SCS) to coordinate usage and security requirements for using

Minuteman Telemetry Transportation Network (MTTN) for LSS communications between LFs/Missile Alert Facilities (MAF) and base facilities.

A6.3.4.4. The contractor shall provide Cybersecurity support and documentation for the Authorization and Accreditation (A&A) process to achieve/obtain an Authority to Operate (ATO) or Interim Authority to

Operate (IATO) for FT3 systems. (CDRL)

APPENDIX 7: ICBM CRYPTOGRAPHY UPGRADE II (ICU II) PROGRAM

A7.1. ICU II Description

The ICU II Program will modify the MM III Weapon System to use the KS-60’s Irreversible

Transformation (IT) functionality to mitigate risks associated with current Enable and Launch command authentication. The ICU II Program will also mitigate risks associated with the current manual code change approach by implementing a Remote Code Change (RCC) capability, which will allow Launch Control Centers (LCCs) to securely encrypt code updates to the Launch

Facilities (LFs), allowing the LFs to remain physically secured during code change. The ICU II

Program also implements a more robust and cost effective response with The ICU II Program replaces WSP TDS with a more robust Continuous Signal Lock Out (CSLO) capability

A7.2. Security Requirement

Contractor resources supporting the ICU II Program shall possess and maintain a Top Secret

(SSBI) security clearance.

A7.3. Program-Specific Requirements

A7.3.1. The contractor shall provide support for engineering efforts related to Depot

Support Equipment and Guided Missile Launch Electric Circuit (GMLEC) Test

Set.

A7.3.2. The contractor shall provide logistics services to plan and coordinate A4 Drawer

Hardware Operational Certification (OPCERT) and Decertification (DECERT) processes.

A7.3.3. In the EMD Phase, the contractor shall:

Assess readiness for production.

Support development of a detailed production design.

Support design and evaluation of design producibility.

Analyze manufacturing processes and equipment.

Evaluate producibility engineering and production planning.

A7.3.4. In the P&D Phase, the contractor shall:

Maintain production surveillance.

Support quality assessment determinations.

Perform engineering analysis in support of depot maintenance, product support, or sustainment engineering.

Accomplish second sourcing/component breakout.

Complete industrial preparedness planning.

Assist in planning for the accomplishment system transition from acquisition to sustainment.

APPENDIX 8: LAUNCH CONTROL CENTER BLOCK UPGRADE (LCCBU)

PROGRAM

A8.1. LCCBU DESCRIPTION

The LCCBU program will design, develop, procure, fabricate, integrate, test, and document design solutions for four components in the Launch Control Center and the associated trainers and support equipment. The program will mitigate supply chain risks for the Floppy Disk Drive

(FDD), Journal Memory Loader (JML), Oxygen Regeneration Unit (ORU), and the Weapon

System Control Console (WSCC) Printer.

A8.2. Security Requirement

A8.3. Program-Specific Requirements

APPENDIX 9: PAYLOAD TRANSPORTER REPLACEMENT (PTR) PROGRAM

A9.1. PTR PROGRAM DESCRIPTION

The PTR program is a replacement MMIII Payload Transporter. The objective of the program is to provide a replacement payload transport capability with security upgrades. The security upgrades include an armored crew cab and an armored protection system for the Re-entry

System (RS).

A9.2. Security Requirement

Contractor resources supporting the PTR shall possess and maintain a Top Secret (SSBI) security clearance.

A9.3. Program-Specific Requirements

A9.3.1. The contractor shall serve as the PTR Deputy Program Manager

A9.3.2. Contractor support shall encompass all Integrated Logistics Support (ILS) elements necessary to allow the Program Manager and Engineer to maintain

Operational Safety, Suitability, and Effectiveness (OSS&E) of the PTR system.

A9.3.3. The contractor shall develop program documentation, support milestone decision reviews, and oversee Prime contractors. (CDRL)

A9.3.4. The contractor shall provide Program Management and Weapon System

Sustainment support to sustain legacy Transportation and Handling (T&H) equipment items that will be used in the PTR acquisition program.

A9.3.5. The contractor shall have access to engineering software at their duty location.

A9.3.6. The contractor shall support both Government and Contractor engineers as a technical consultant for test and evaluation activities.

A9.3.6.1. The contractor shall review, comprehend, and assess test documentation. (CDRL)

A9.3.6.2. The contractor shall modify test and evaluation plans and procedures

(CDRL)

A9.3.6.3. The contractor shall witness PTR testing as directed by the government, A9.3.6.3.1. The contractor shall develop, and coordinate associated test reports.

(CDRL)

A9.3.7. In the EMD Phase, the contractor shall:

Assess readiness for production.

Support development of a detailed production design.

Support design and evaluation of design producibility.

Analyze manufacturing processes and equipment.

Evaluate producibility engineering and production planning.

A9.3.8. In the P&D Phase, the contractor shall:

Maintain production surveillance.

Support quality assessment determinations.

Perform engineering analysis in support of depot maintenance, product support, or sustainment engineering.

Accomplish second sourcing/component breakout.

Complete industrial preparedness planning.

Assist in planning for the accomplishment system transition from acquisition to sustainment.

A9.3.9. The contractor shall submit an informal monthly cost report to assist the government Program Manager with forecast of planned contractor obligations and expenditures (CDRL)

APPENDIX 10: STRATEGIC AUTOMATED COMMAND CONTROL SYSTEM

REPLACEMENT (SACCS-R) PROGRAM

A10.1. SACCS-R PROGRAM DESCRIPTION

The SACCS provides a capability to compose, transmit, receive, process, readdress, and acknowledge Emergency Action Messages (EAMs), Force Direction Messages (FDMs), Force

Status Reporting (FSR), Nuclear Executing and Reporting Plan, and non-nuclear Emergency

Action Messages.

The Air Force has initiated a replacement effort to address obsolescence issues, diminished manufacturing sources, challenges interfacing with advancing telecommunication and enterprise networks, and sustainment costs. The replacement effort is known as SACCS-R.

A10.2. Security Requirement

A10.3. Program-Specific Requirements

APPENDIX 11: T-41 PROGRAM

A11.1. T-41 PROGRAM DESCRIPTION

The T-41 trainer is a half-hole realistic operational Launch Facility (LF) environment used for operations and maintenance training at Malmstrom AFB. T-41 is currently located within an aircraft hangar and simulates the appearance and function of a launch equipment room and upper launch tube of an operational launch facility. The separate T-9 effort will provide Malmstrom

AFB with a full LF trainer, allowing the T-41 trainer to be moved and utilized by another wing.

This effort entails design and construction of a new T-41 superstructure at VAFB to meet

California building codes and additional PT semitrailer weight and Center of Gravity. The existing electrical, mechanical, and Government Furnished Equipment would then be removed, shipped, and reinstalled at VAFB. If determined to be a funded program, expectation would be to initiate effort in FY22.

A11.2. Security Requirement

A11.3. Program-Specific Requirements

APPENDIX 12: TRANSPORTATION ERECTOR REPLACEMENT PROGRAM (TERP)

A12.1. TERP DESCRIPTION

TERP is a replacement MMIII solid rocket booster Transportation Erector (TE) tractor trailer truck. The TE is the Air Force’s single system capable of removing and emplacing MMIII solid rocket booster at the launch facility. The objective of ACAT III TERP is to deliver an obsolescence-free, technology refreshed, sustainable TE system.

The TERP P&D phase consists of Acceptance Testing and Full-Rate Production and Deployment

(FRP&D). The purpose of this phase is to achieve operational capability in sufficient quantities to satisfy full mission need.

A12.2. Security Requirement

Contractor resources supporting the TERP shall possess and maintain a Secret security clearance.

A12.3. Program-Specific Requirements

A12.3.1. The contractor shall provide Program Management and Weapon System

Sustainment support to sustain legacy Transportation and Handling (T&H) equipment items (e.g. hoists, actuators, etc.) that will be used in the TERP acquisition program.

A12.3.2.The contractor shall serve as the Deputy TERP Program Manager

A12.3.2.1.The contractor shall develop program documentation, support milestone decision reviews, and oversee Prime contractors. (CDRL)

A12.3.2.2. The contractor shall develop plans, execute daily activities, and report status to the TERP PM. (CDRL)

A12.3.4. The contractor shall serve in the capacity of Deputy TERP Program

Engineer/T&H Subsystems Engineer.

A12.3.4.1. The contractor shall manage sustainment for Tractors, Trailers, and commodity handling support equipment items (e.g. hoists, winches, carriages, jacks, test equipment, environmental control systems, generators, etc.).

A12.3.5. The contractor shall provide reach-back support for the TERP Program as needed, performing work under the guidance of the Lead TERP Program

Engineer.