Attachment 17 - Draft CLIN Structure for Task Order 5 GBSD Enterprise.pdf

PDF 193 KB Posted

Attached to
Integration Support Contract (ISC) 2. 0 Federal contract opportunity
Solicitation number
FA8207-20-ISC-2
Issued by
Department of the Air Force Materiel Command Nuclear Weapons Center

About this file

This document provides a draft statement of work for Task Order 5 under the Ground Based Strategic Deterrent Engineering Enterprise contract. It outlines cost-plus-award-fee contract line item numbers for engineering, technical, and management services across multiple program areas. Deliverables include full-time equivalents in engineering, configuration management, security, demonstration and validation, and weapon system components. Travel and other direct costs are also reimbursable without fee. Data items and rights are priced separately. The period of performance is from April 2022 through September 2023 with award fee evaluation periods. Option years and additional contract line items extend work through April 2027.

View the file

Other files for this federal contract opportunity

Other files attached to Integration Support Contract (ISC) 2. 0, newest first.
File Type Posted
Updated H001 OCI Clause.docx DOCX document
Attachment 15 - Draft CLIN Structure for Task Order 3 MMIII Acquisition.pdf PDF
Draft RFP FA820721R0001.pdf PDF
Attachment 10 - Appendix C Safety Plan.pdf PDF
Attachment 21 - ISC2.0 PWS TO4 MMIII INTEG.pdf PDF
Attachment 20 - ISC2.0 PWS TO3 MMIII ACQ.pdf PDF
Attachment 4 - Labor Categories and Qualifications.xlsx XLSX spreadsheet
Attachment 7 - GRIDS.docx.pdf PDF
Attachment 18 - ISC2.0 PWS TO1 MMIII DIRSUP.pdf PDF
Attachment 24 - Section M.pdf PDF
Attachment 3 - Labor Quantity Workbook.xlsx XLSX spreadsheet
Attachment 19 - ISC2.0 PWS TO2 MMIII SUST.pdf PDF
ISC 2.0 Strategy Updates 9-Sept-20.pptx PPTX presentation
ISC 2.0 Draft TO 3 MMIII Acquisition.docx DOCX document
ISC 2.0 Draft Small Business H Clause.docx DOCX document
ISC 2.0 Draft TO 1 MMIII Directorate Support.docx DOCX document
ISC 2.0 Draft Labor Rate Adjustment H Clause.docx DOCX document
ISC 2.0 Draft TO 2 MMIII Sustainment.docx DOCX document
ISC 2.0 Draft Award Fee Plan.docx DOCX document
Draft RFP Package - Attachment 2 - Suggested Labor Matrix Workbook.xlsx XLSX spreadsheet
Draft RFP Package - Attachment 4 - Labor Category Mapping.xlsx XLSX spreadsheet
Draft RFP Package - Attachment 7 - Appendix C Safety Plan.docx DOCX document
Draft RFP Package - TO 3 MMIII Acquitision Support PWS.docx DOCX document
Draft RFP Package - Basic PWS.docx DOCX document
Draft RFP Package - Attachment 1 - GRIDS.docx DOCX document
Draft Special H Clause - Joint Cyber Information Tracking System.docx DOCX document
Draft RFP Package - Attachment 9 - CDRL (list).docx DOCX document
Draft RFP Package - TO 1 Directorate Support PWS.docx DOCX document
Draft RFP Package - Attachment 6 - GFP list.xlsx XLSX spreadsheet
ISC_2_L_comp v1.2.docx DOCX document
ISC_2_M_comp v1.2.docx DOCX document
Industry Day 3 Updated Slides.pptx PPTX presentation
ICBM Governance Model.pptx PPTX presentation
ISC_2_M_Intro and Factor 1 - v2.0.docx DOCX document
ISC 2.0 Draft OCI Clause.pdf PDF
ISC 2.0 Industry Day 2 Map.pdf PDF
ISC 2.0 Industry Day 2 Additional Timeslots.docx DOCX document
MMIII INTEG DRAFT v1.16.pdf PDF
Updated DIR Support DRAFT PWS v1.19.pdf PDF
Updated MMIII Acquisition DRAFT PWS v1.12.pdf PDF
Updated MMIII Sust DRAFT v2.1.pdf PDF
ISC 2.0 Industry Day 2 Timeslots.docx DOCX document
ISC 2.0 PWS Comment Resolution Matrix_CONTRACTOR NAME.xlsx XLSX spreadsheet
ISC_2_L_Factor 1 v2.8.docx DOCX document
ISC_2_M_Factor 1 v2.2.docx DOCX document
ISC_2_M_intro v2.2.docx DOCX document
ISC 2.0 Draft Award Fee Plan.docx DOCX document
19 November Industry Day Slides - Final.pptx PPTX presentation
General Session Attendance.pdf PDF
INDUSTRY Q&A RESPONSE 1.0.docx DOCX document
Show all 50

Integration Support Contract (ISC) 2. 0 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORDER FOR SUPPLIES OR SERVICES RS

1. CONTRACT/PURCH ORDER/AGREEMENT NO.

FA820720D9999

2. DELIVERY ORDER/CALL NO.

FA8207-20-F-2005

3. DATE OF ORDER/CALL

(YYYYMMMDD)

4. REQUISITION/PURCH REQUEST NO. 5. PRIORITY

DX: A2

6. ISSUED BY CODE

DEPARTMENT OF THE AIR FORCE, DIRECTORATE OF CONTRACTING

AFNWC PZBC

6008 WARDLEIGH ROAD BLDG 1580

HILL AIR FORCE BASE UT 84056-5837

BUYER: Stephen Gacioch/AFLCMC stephen.gacioch@us.af.mil

Phone: (801) 586- 8042

7. ADMINISTERED BY (If other than 6) CODEFA8207 8. DELIVERY FOB

DESTINATION

OTHER

(See Schedule if other)

X

9. CONTRACTOR CODE FACILITY 10. DELIVER TO FOB POINT BY (Date)

(YYYYMMMDD)

SEE SCHEDULE

12. DISCOUNT TERMS

11. X IF BUSINESS IS

SMALL

SMALL

DISAD-VANTAGED

WOMEN-OWNED

13. MAIL INVOICES TO

SEE BLK 15

14. SHIP TO CODE

SEE LINE ITEM SCHEDULE

15. PAYMENT WILL BE MADE BY CODE

(SEE ESP CLAUSE 252.232-7003.) MARK ALL

PACKAGES AND

PAPERS WITH

IDENTIFICATION

NUMBERS IN

BLOCKS 1 AND 2.

16.

TYPE

OF

ORDER

DELIVERY/

CALL

PURCHASE

X This delivery order/call is issued on another Government agency or in accordance with and subject to terms and conditions of above numbered contract.

Reference your Dated: furnish the following terms specified herein.

NAME OF CONTRACTOR SIGNATURE TYPED NAME AND TITLE DATE SIGNED

If this box is marked, supplier must sign Acceptance and return the following number of copies: (YYYYMMMDD)

18.

ITEM NO.

19.

SCHEDULE OF SUPPLIES/SERVICES

(SEE SCHEDULE)

20. QUANTITY

ORDERED/

ACCEPTED*

21.

UNIT

22.

UNIT PRICE

23.

AMOUNT

ROUTINE FAST PAY PROCEDURES APPLY

* If quantity accepted by the Government is same as quantity ordered, indicate by X. If different, enter actual quantity accepted below quantity ordered and encircle.

24. UNITED STATES OF AMERICA

BY: Kyle G. Chase kyle.chase@us.af.mil

CONTRACTING/ORDERING OFFICER - -

25. $

26.

DIFFERENCES

27a. QUANTITY IN COLUMN 20 HAS BEEN:

INSPECTED RECEIVED ACCEPTED, AND CONFORMS TO

THE CONTRACT EXCEPT AS NOTED:

28. SHIP. NO.

PARTIAL

FINAL

29. D.O. VOUCHER NO.

36. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT.

31. PAYMENT

COMPLETE

PARTIAL

FINAL

32. PAID BY

30.

INITIALS

33. AMOUNT VERIFIED CORRECT FOR

34. CHECK NUMBER

35. BILL OF LADING NO.

37. RECEIVED AT 38. RECEIVED BY (Print) 39. DATE RECEIVED

(YYYYMMMDD)

40. TOTAL CONTAINERS 41. S/R ACCOUNT NUMBER 42. S/R VOUCHER NO.

DD FORM 1155, DEC 2001 PREVIOUS EDITION IS OBSOLETE

17. ACCOUNTING AND APPROPRIATION DATA/LOCAL USE

SEE SCHEDULE

SCD:A

EFT:T

ACCEPTANCE. THE CONTRACTOR HEREBY ACCEPTS THE OFFER REPRESENTED BY THE NUMBERED PURCHASE ORDER AS IT MAY PREVIOUSLY HAVE BEEN OR IS NOW MODIFIED, SUBJECT TO ALL OF THE TERMS AND CONDITIONS SET FORTH, AND AGREES TO PERFORM THE SAME.

b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE c. DATE

(YYYYMMMDD)

d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

f. TELEPHONE NUMBER g. E-MAIL ADDRESS

a. DATE

(YYYYMMMDD)

b. SIGNATURE AND TITLE OF CONTRACTING OFFICER

Total

FA8207-20-F-2005

SUPPLIES OR SERVICES AND PRICES/COSTS

GBSD Engineering - FTE

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

II XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

The Total Award Fee amounts are held in Contingent Liability

GBSD IT Support - FTE

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

GBSD IT Support - FTE

COST PLUS AWARD FEE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD A&AS - FTE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD Security - FTE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Dem/Val - FTE

Item No.

Cost Plus Award Fee

Dem/Val - FTE

COST PLUS AWARD FEE

Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

MK21A - FTE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection

MK21A - FTE

COST PLUS AWARD FEE

Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Fuze - FTE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 SEP 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD Engineering - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD IT Support - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

GBSD IT Support - CME

COST PLUS AWARD FEE

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD A&AS - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

GBSD A&AS - CME

COST PLUS AWARD FEE

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD Security - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Dem/Val - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

MK21A - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook

MK21A - CME

COST PLUS AWARD FEE

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Fuze - CME

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of

1 LO 21 APR 2022 20 APR 2023

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

I XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

GBSD Engineering - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

GBSD IT Support - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Limitations of Liability: Other Than High Value Item

GBSD IT Support - Travel & ODC

COST REIMBURSEMENT - NO FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

GBSD A&AS - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

GBSD Security - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

GBSD Security - Travel & ODC

COST REIMBURSEMENT - NO FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

Dem/Val - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

MK21A - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

MK21A - Travel & ODC

COST REIMBURSEMENT - NO FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

Fuze - Travel & ODC

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

DATA - CDRL DELIVERABLES FOR CLINS 0001 - 0072

NOT SEPARATELY PRICED

Item No.

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

DATA - CDRLs in support of CLINs 0001 - 0072 DATA IAW DD 1423 - Attached in Section J Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination

DATA - CDRL DELIVERABLES FOR CLINS 0001 - 0072

NOT SEPARATELY PRICED

Exhibit: A Quality Assurance: IAW Section J CDRLs and PWS Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

DATA RIGHTS

NOT SEPARATELY PRICED

Item No.

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

DATA IAW DD 1423-1 ATTACHED HERE TO

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2022 20 APR 2023

GBSD Engineering - FTE Option Year 1

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required

Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

GBSD Engineering - FTE Option Year 1

COST PLUS AWARD FEE

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

IV XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Option Year 1

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

GBSD Security - FTE Option Year 1

COST PLUS AWARD FEE

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Fuze - FTE Option Year 1

COST PLUS AWARD FEE

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J..

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination

GBSD Engineering - CME Option Year 1

COST PLUS AWARD FEE

Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

GBSD Security - CME Option Year 1

COST PLUS AWARD FEE

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required

Dem/Val - CME Option Year 1

COST PLUS AWARD FEE

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

III XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

GBSD Engineering - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

GBSD IT Support - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

GBSD A&AS - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

GBSD A&AS - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

GBSD Security - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

Dem/Val - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Dem/Val - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

MK21A - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

Fuze - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Fuze - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

DATA - CDRL DELIVERABLES FOR CLINS 0001 - 0072

Option Year 1

NOT SEPARATELY PRICED

Item No.

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

DATA - CDRLs in support of CLINs 0001 - 0072 DATA IAW DD 1423 - Attached in Section J Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: IAW Section J CDRLs and PWS Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

DATA RIGHTS

Option Year 1

NOT SEPARATELY PRICED

Item No.

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

DATA IAW DD 1423-1 ATTACHED HERE TO

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination

Exhibit: A

DATA RIGHTS

Option Year 1

NOT SEPARATELY PRICED

Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2023 20 APR 2024

GBSD Engineering - FTE Option Year 1

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

VI XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee

GBSD IT Support - FTE Option Year 1

COST PLUS AWARD FEE

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of

GBSD A&AS - FTE

Option Year 1

COST PLUS AWARD FEE

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

Dem/Val - FTE Option Year 1

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

MK21A - FTE

Option Year 1

COST PLUS AWARD FEE

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

FTE

Engineering Services The Contractor shall provide FTEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

GBSD IT Support - CME Option Year 1

COST PLUS AWARD FEE

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required

GBSD A&AS - CME

Option Year 1

COST PLUS AWARD FEE

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

MK21A - CME

Option Year 1

COST PLUS AWARD FEE

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST PLUS AWARD FEE

Item No.

Cost Plus Award Fee Quantity U/I Est Unit Cost Award Fee Total Estimated Cost

1 LO

R425

CME

Engineering Services The Contractor shall provide CMEs for engineering/technical services IAW PWS 5 and the Labor Quantity Workbook attached in section J.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required

Fuze - CME Option Year 1

COST PLUS AWARD FEE

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

The available Award Fee is established in the amount of $XX,XXX.XX

Evaluation Period Amount Available Amount Earned

V XX XXX XXXX - XX XXX XXXX $XX,XXX.XX $XX,XXX.XX (XX.XX%)

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

GBSD IT Support - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

GBSD IT Support - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

GBSD A&AS - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

GBSD Security - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

GBSD Security - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Place of Perf Quantity (U/I) Specified Date Specified Date Req No / Pri

Required Period of Performance

1 LO 21 APR 2024 20 APR 2025

Dem/Val - Travel & ODC Option Year 1

COST REIMBURSEMENT - NO FEE

Item No.

Cost Reimbursement - No Fee Quantity U/I Est Unit Cost Total Estimated Cost

1 LO

R425 Travel & ODCs Travel & ODCs in support of Engineering Services IAW Section 3.10 & 3.17 of the Basic PWS and Awardable Tasks

PWS.

Priority: R ROUTINE

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required…