Bldg._503_Solicitation.docx
DOCX document 86 KB Posted
- Attached to
- Bldg. 503 Repair/Minor Const/Equipment Federal contract opportunity
- Solicitation number
- FA8201-16-B-0009
About this file
B503 Solicitation KRSM 092001 (ABC)
View the file
Other files for this federal contract opportunity
Show all 50
Bldg. 503 Repair/Minor Const/Equipment has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8201-16-B-0009
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
REPAIR B503
FFP
Repair existing real property Bldg.503: The contractor shall repair safety related exterior items to include roof/flashing, replace/repair concrete walkway and hand rail, install anti-slip stair coating, repair and repave parking lot to include restriping, repair masonry on exterior of building 503, remove landscaping, repair HVAC insulation, repair metal awning, in accordance with all attachments in section J.
FOB: Destination
PROJECT: KRSM092001A
SIGNAL CODE: A
NET AMT
FSC CD: Z2EB
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
CONSTRUCTION B503
Construct MISC Items Bldg. 503 New Minor Construction: The contractor shall construct new 6-inch concrete retaining wall, new fencing and gates, install new landscaping trees and shrubs, install new storm drainage, catch basin and sump, install new steel structured canopy, in accordance with all attachments in Section J.
FOB: Destination
PROJECT: KRSM092001B
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lot |
EQUIPMENT/INSTALL B503
Install Equip Items Bldg. 503 New Equipment: The contractor shall Install new picnic tables, smoke shelter, light post/fixtures/cover for the card reader, snow/de-icing tracer wire cables, vindicator card reader and equipment in accordance with all attachments in Section J.
FOB: Destination
PROJECT: KRSM092001C
NET AMT
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
| 0002 |
| Destination |
| Government |
| Destination |
| Government |
| 0003 |
| Destination |
| Government |
| Destination |
| Government |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC |
| 0001 |
| 180 dys. ADC |
| 1 |
| 75 CE |
RON SPAGNUOLO
5713 LAHM LANE BLDG 593 S
HILL AFB UT 84056-5410
586-8469 FOB: Destination
F2D0AC
| 0002 |
| 180 dys. ADC |
| 1 |
| (SAME AS PREVIOUS LOCATION) |
F2D0AC
| 0003 |
| 180 dys. ADC |
| 1 |
| (SAME AS PREVIOUS LOCATION) |
F2D0AC
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
| 52.202-1 |
| Definitions |
| NOV 2013 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| MAY 2014 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| SEP 2006 |
| 52.203-7 |
| Anti-Kickback Procedures |
| MAY 2014 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| MAY 2014 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| MAY 2014 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| OCT 2010 |
| 52.204-4 |
| Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
| MAY 2011 |
| 52.204-7 |
| System for Award Management |
| JUL 2013 |
| 52.204-10 |
| Reporting Executive Compensation and First-Tier Subcontract Awards |
| OCT 2015 |
| 52.204-13 |
| System for Award Management Maintenance |
| JUL 2013 |
| 52.204-16 |
| Commercial and Government Entity Code Reporting |
| JUL 2016 |
| 52.204-17 |
| Ownership or Control of Offeror |
| JUL 2016 |
| 52.204-18 |
| Commercial and Government Entity Code Maintenance |
| JUL 2016 |
| 52.204-19 |
| Incorporation by Reference of Representations and Certifications. |
| DEC 2014 |
| 52.204-20 |
| Predecessor of Offeror |
| JUL 2016 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| OCT 2015 |
| 52.209-7 |
| Information Regarding Responsibility Matters |
| JUL 2013 |
| 52.209-9 |
| Updates of Publicly Available Information Regarding Responsibility Matters |
| JUL 2013 |
| 52.211-13 |
| Time Extensions |
| SEP 2000 |
| 52.214-3 |
| Amendments To Invitations For Bids |
| DEC 1989 |
| 52.214-4 |
| False Statements In Bids |
| APR 1984 |
| 52.214-5 |
| Submission Of Bids |
| MAR 1997 |
| 52.214-6 |
| Explanation To Prospective Bidders |
| APR 1984 |
| 52.214-7 |
| Late Submissions, Modifications, and Withdrawals of Bids |
| NOV 1999 |
| 52.214-12 |
| Preparation Of Bids |
| APR 1984 |
| 52.214-18 |
| Preparation of Bids-Construction |
| APR 1984 |
| 52.214-19 |
| Contract Award-Sealed Bidding-Construction |
| AUG 1996 |
| 52.214-26 |
| Audit and Records--Sealed Bidding |
| OCT 2010 |
| 52.214-27 |
| Price Reduction for Defective Certified Cost or Pricing Data - Modifications - Sealed Bidding |
| AUG 2011 |
| 52.214-28 |
| Subcontracting Certified Cost Or Pricing Data--Modifications--Sealed Bidding |
| OCT 2010 |
| 52.214-29 |
| Order Of Precedence--Sealed Bidding |
| JAN 1986 |
| 52.219-6 |
| Notice Of Total Small Business Set-Aside |
| NOV 2011 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| OCT 2014 |
| 52.219-14 |
| Limitations On Subcontracting |
| NOV 2011 |
| 52.219-28 |
| Post-Award Small Business Program Rerepresentation |
| JUL 2013 |
| 52.222-1 |
| Notice To The Government Of Labor Disputes |
| FEB 1997 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards- Overtime Compensation |
| MAY 2014 |
| 52.222-6 |
| Construction Wage Rate Requirements |
| MAY 2014 |
| 52.222-7 |
| Withholding of Funds |
| MAY 2014 |
| 52.222-8 |
| Payrolls and Basic Records |
| MAY 2014 |
| 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| MAY 2014 |
| 52.222-12 |
| Contract Termination-Debarment |
| MAY 2014 |
| 52.222-13 |
| Compliance With Construction Wage Rate Requirements and Related Regulations |
| MAY 2014 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| MAY 2014 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| APR 2015 |
| 52.222-26 |
| Equal Opportunity |
| APR 2015 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| APR 2015 |
| 52.222-29 |
| Notification Of Visa Denial |
| APR 2015 |
| 52.222-35 |
| Equal Opportunity for Veterans |
| OCT 2015 |
| 52.222-36 |
| Equal Opportunity for Workers with Disabilities |
| JUL 2014 |
| 52.222-37 |
| Employment Reports on Veterans |
| FEB 2016 |
| 52.222-40 |
| Notification of Employee Rights Under the National Labor Relations Act |
| DEC 2010 |
| 52.222-50 |
| Combating Trafficking in Persons |
| MAR 2015 |
| 52.222-54 |
| Employment Eligibility Verification |
| OCT 2015 |
| 52.222-55 |
| Minimum Wages Under Executive Order 13658 |
| DEC 2015 |
| 52.223-2 |
| Affirmative Procurement of Biobased Products Under Service and Construction Contracts |
| SEP 2013 |
| 52.223-3 |
| Hazardous Material Identification And Material Safety Data |
| JAN 1997 |
| 52.223-5 |
| Pollution Prevention and Right-to-Know Information |
| MAY 2011 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-10 |
| Waste Reduction Program |
| MAY 2011 |
| 52.223-11 |
| Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons. |
| JUN 2016 |
| 52.223-12 |
| Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners. |
| JUN 2016 |
| 52.223-15 |
| Energy Efficiency in Energy-Consuming Products |
| DEC 2007 |
| 52.223-17 |
| Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts |
| MAY 2008 |
| 52.223-18 |
| Encouraging Contractor Policies To Ban Text Messaging While Driving |
| AUG 2011 |
| 52.223-19 |
| Compliance with Environmental Management Systems |
| MAY 2011 |
| 52.223-20 |
| Aerosols |
| JUN 2016 |
| 52.223-21 |
| Foams |
| JUN 2016 |
| 52.224-1 |
| Privacy Act Notification |
| APR 1984 |
| 52.224-1 |
| Privacy Act Notification |
| APR 1984 |
| 52.224-2 |
| Privacy Act |
| APR 1984 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| JUN 2008 |
| 52.227-1 |
| Authorization and Consent |
| DEC 2007 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| DEC 2007 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.228-7 |
| Insurance--Liability To Third Persons |
| MAR 1996 |
| 52.228-11 |
| Pledges Of Assets |
| JAN 2012 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| MAY 2014 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| NOV 2014 |
| 52.228-15 |
| Performance and Payment Bonds--Construction |
| OCT 2010 |
| 52.229-3 |
| Federal, State And Local Taxes |
| FEB 2013 |
| 52.232-1 |
| Payments |
| APR 1984 |
| 52.232-2 |
| Payments Under Fixed-Price Research And Development Contracts |
| APR 1984 |
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| MAY 2014 |
| 52.232-16 |
| Progress Payments |
| APR 2012 |
| 52.232-17 |
| Interest |
| MAY 2014 |
| 52.232-18 |
| Availability Of Funds |
| APR 1984 |
| 52.232-23 |
| Assignment Of Claims |
| MAY 2014 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| MAY 2014 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--System for Award Management |
| JUL 2013 |
| 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| JUN 2013 |
| 52.232-99 |
| Providing Accelerated Payment to Small Business Subcontractors (DEVIATION) |
| AUG 2012 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-1 |
| Performance of Work by the Contractor |
| APR 1984 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-4 |
| Physical Data |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-13 Alt I |
| Accident Prevention (Nov 1991) - Alternate I |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-21 |
| Specifications and Drawings for Construction |
| FEB 1997 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.242-4 |
| Certification of Final Indirect Costs |
| JAN 1997 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| JUN 2016 |
| 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
| 52.246-13 |
| Inspection--Dismantling, Demolition, or Removal of Improvements |
| AUG 1996 |
| 52.248-3 |
| Value Engineering-Construction |
| OCT 2015 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I |
| SEP 1996 |
| 52.249-2 Alt III |
| Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate III |
| SEP 1996 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 52.252-1 |
| Solicitation Provisions Incorporated By Reference |
| FEB 1998 |
| 52.252-2 |
| Clauses Incorporated By Reference |
| FEB 1998 |
| 52.252-3 |
| Alterations in Solicitation |
| APR 1984 |
| 52.252-6 |
| Authorized Deviations In Clauses |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DoD Officials |
| SEP 2011 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.203-7002 |
| Requirement to Inform Employees of Whistleblower Rights |
| SEP 2013 |
| 252.203-7005 |
| Representation Relating to Compensation of Former DoD Officials |
| NOV 2011 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7006 |
| Billing Instructions |
| OCT 2005 |
| 252.204-7007 |
| Alternate A, Annual Representations and Certifications |
| JAN 2015 |
| 252.204-7008 |
| Compliance with Safeguarding Covered Defense Information Controls |
| AUG 2015 |
| 252.204-7012 |
| Safeguarding Covered Defense Information and Cyber Incident Reporting. |
| DEC 2015 |
| 252.204-7015 |
| Notice of Authorized Disclosure of Information for Litigation Support |
| MAY 2016 |
| 252.205-7000 |
| Provision Of Information To Cooperative Agreement Holders |
| DEC 1991 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism |
| OCT 2015 |
| 252.222-7006 |
| Restrictions on the Use of Mandatory Arbitration Agreements |
| DEC 2010 |
| 252.223-7001 |
| Hazard Warning Labels |
| DEC 1991 |
| 252.223-7004 |
| Drug Free Work Force |
| SEP 1988 |
| 252.223-7006 |
| Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials |
| SEP 2014 |
| 252.223-7008 |
| Prohibition of Hexavalent Chromium |
| JUN 2013 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| FEB 2013 |
| 252.225-7048 |
| Export-Controlled Items |
| JUN 2013 |
| 252.226-7001 |
| Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns |
| SEP 2004 |
| 252.227-7033 |
| Rights in Shop Drawings |
| APR 1966 |
| 252.232-7004 |
| DOD Progress Payment Rates |
| OCT 2014 |
| 252.232-7010 |
| Levies on Contract Payments |
| DEC 2006 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.236-7001 |
| Contract Drawings, and Specifications |
| AUG 2000 |
| 252.236-7006 |
| Cost Limitation |
| JAN 1997 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| DEC 2012 |
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 Calendar Days * The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $496.46 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)
(a) Definitions. As used in this clause--
Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall--
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to Ron Spagnuolo 75CEG/CENMP.
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... ___ ........ ....... ………. ___ ................ ........ ___ Domestic construction material... ........ ___ ............... .............. ___ .................. ...... ___ Item 2 Foreign construction material.... ......... ___ ............. ........ ……. ___ ............... ......... ___ Domestic construction material... ....... ___ .................. ............. ___ ................. ....... ___ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
52.228-7 INSURANCE--LIABILITY TO THIRD PERSONS (MAR 1996)
(a)(1) Except as provided in subparagraph (a)(2) of this clause, the Contractor shall provide and maintain workers’ compensation, employer’s liability, comprehensive general liability (bodily injury), comprehensive automobile liability (bodily injury and property damage) insurance, and such other insurance as the Contracting Officer may require under this contract.
(2) The Contractor may, with the approval of the Contracting Officer, maintain a self-insurance program; provided that, with respect to workers' compensation, the Contractor is qualified pursuant to statutory authority.
(3) All insurance required by this paragraph shall be in a form and amount and for those periods as the Contracting Officer may require or approve and with insurers approved by the Contracting Officer.
(b) The Contractor agrees to submit for the Contracting Officer's approval, to the extent and in the manner required by the Contracting Officer, any other insurance that is maintained by the Contractor in connection with the performance of this contract and for which the Contractor seeks reimbursement.
(c) The Contractor shall be reimbursed—
(1) For that portion (i) of the reasonable cost of insurance allocable to this contract, and (ii) required or approved under this clause; and
(2) For certain liabilities (and expenses incidental to such liabilities) to third persons not compensated by insurance or otherwise without regard to and as an exception to the limitation of cost or the limitation of funds clause of this contract. These liabilities must arise out of the performance of this contract, whether or not caused by the negligence of the Contractor or of the Contractor's agents, servants, or employees, and must be represented by final judgments or settlements approved in writing by the Government. These liabilities are for--
(i) Loss of or damage to property (other than property owned, occupied, or used by the Contractor, rented to the Contractor, or in the care, custody, or control of the Contractor); or
(ii) Death or bodily injury.
(d) The Government's liability under paragraph (c) of this clause is subject to the availability of appropriated funds at the time a contingency occurs. Nothing in this contract shall be construed as implying that the Congress will, at a later date, appropriate funds sufficient to meet deficiencies.
(e) The Contractor shall not be reimbursed for liabilities (and expenses incidental to such liabilities)--
(1) For which the Contractor is otherwise responsible under the express terms of any clause specified in the Schedule or elsewhere in the contract;
(2) For which the Contractor has failed to insure or to maintain insurance as required by the Contracting Officer; or
(3) That result from willful misconduct or lack of good faith on the part of any of the Contractor's directors, officers, managers, superintendents, or other representatives who have supervision or direction of--
(i) All or substantially all of the Contractor's business;
(ii) All or substantially all of the Contractor's operations at any one plant or separate location in which this contract is being performed; or
(iii) A separate and complete major industrial operation in connection with the performance of this contract.
(f) The provisions of paragraph (e) of this clause shall not restrict the right of the Contractor to be reimbursed for the cost of insurance maintained by the Contractor in connection with the performance of this contract, other than insurance required in accordance with this clause; provided, that such cost is allowable under the Allowable Cost and Payment clause of this contract.
(g) If any suit or action is filed or any claim is made against the Contractor, the cost and expense of which may be reimbursable to the Contractor under this contract, and the risk of which is then uninsured or is insured for less than the amount claimed, the Contractor shall--
(1) Immediately notify the Contracting Officer and promptly furnish copies of all pertinent papers received;
(2) Authorize Government representatives to collaborate with counsel for the insurance carrier in settling or defending the claim when the amount of the liability claimed exceeds the amount of coverage; and
(3) Authorize Government representatives to settle or defend the claim and to represent the Contractor in or to take charge of any litigation, if required by the Government, when the liability is not insured or covered by bond. The Contractor may, at its own expense, be associated with the Government representatives in any such claim or litigation.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15% percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
52.243-4 CHANGES (JUN 2007)
(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes--
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) In the Government-furnished property or services; or
(4) Directing acceleration in the performance of the work.
(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating
(1) the date, circumstances, and source of the order and
(2) that the Contractor regards the order as a change order.
(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.
(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.
(e) The Contractor must assert its right to an adjustment under this clause within 30 days after
(1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of the proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.
(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
252.204-7004 ALTERNATE A, SYSTEM FOR AWARD MANAGEMENT (FEB 2014)
(a) Definitions. As used in this provision—
“System for Award Management (SAM) database” means the primary Government repository for contractor information required for the conduct of business with the Government.
“Commercial and Government Entity (CAGE) code” means—
(1) A code assigned by the Defense Logistics Information Service (DLIS) to identify a commercial or Government entity; or
(2) A code assigned by a member of the North Atlantic Treaty Organization that DLIS records and maintains in the CAGE master file. This type of code is known as an “NCAGE code.”
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see FAR 32.11) for the same parent concern.
“Registered in the System for Award Management (SAM) database” means that—
(1) The contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, and Contractor and Government Entity (CAGE) code into the SAM database; and
(2) The contractor has completed the Core Data, Assertions, Representations and Certifications, and Points of Contact sections of the registration in the SAM database;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for TIN validation to the Government as part of the SAM registration process; and
(4) The Government has marked the record “Active.”
(b) (1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) Offerors may obtain information on registration at https://www.acquisition.gov.
(End of Provision)
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS (JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
CONSTRUCTION
(Contracting Officer: Insert applicable document type(s). Note: If a “Combo” document type is identified but not supportable by the Contractor's business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
GOVERNMENT INSPECTION/ACCEPTANCE
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF
| Pay Official DoDAAC | F03000 | ||
| Issue By DoDAAC | FA8201 | ||
| Admin DoDAAC | FA8201 | ||
| Inspect By DoDAAC | F2D0AC | ||
| Ship To Code | ____ | ||
| Ship From Code | ____ | ||
| Mark For Code | ____ | ||
| Service Approver (DoDAAC) | ____ | ||
| Service Acceptor (DoDAAC) | ____ | ||
| Accept at Other DoDAAC | ____ | ||
| LPO DoDAAC | ____ | ||
| DCAA Auditor DoDAAC | ____ | ||
| Other DoDAAC(s) | ____ |
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
don.mattonen@us.af.mil and shelly.karcheski.2@us.af.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
don.mattonen@us.af..mil
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
252.247-7023 TRANSPORTATION OF SUPPLIES BY SEA (APR 2014)
(a) Definitions. As used in this clause --
"Components" means articles, materials, and supplies incorporated directly into end products at any level of manufacture, fabrication, or assembly by the Contractor or any subcontractor.
"Department of Defense" (DoD) means the Army, Navy, Air Force, Marine Corps, and defense agencies.
"Foreign-flag vessel" means any vessel that is not a U.S.-flag vessel.
"Ocean transportation" means any transportation aboard a ship, vessel, boat, barge, or ferry through international waters.
"Subcontractor" means a supplier, materialman, distributor, or vendor at any level below the prime contractor whose contractual obligation to perform results from, or is conditioned upon, award of the prime contract and who is performing any part of the work or other requirement of the prime contract.
"Supplies" means all property, except land and interests in land, that is clearly identifiable for eventual use by or owned by the DoD at the time of transportation by sea.
(i) An item is clearly identifiable for eventual use by the DoD if, for example, the contract documentation contains a reference to a DoD contract number or a military destination.
(ii) "Supplies" includes (but is not limited to) public works; buildings and facilities; ships; floating equipment and vessels of every character, type, and description, with parts, subassemblies, accessories, and equipment; machine tools; material; equipment; stores of all kinds; end items; construction materials; and components of the foregoing.
"U.S.-flag vessel" means a vessel of the United States or belonging to the United States, including any vessel registered or having national status under the laws of the United States.
(b)(1) The Contractor shall use U.S.-flag vessels when transporting any supplies by sea under this contract.
(2) A subcontractor transporting supplies by sea under this contract shall use U.S.-flag vessels if--
(i) This contract is a construction contract; or
(ii) The supplies being transported are--
(A) Noncommercial items; or
(B) Commercial items that--
(1) The Contractor is reselling or distributing to the Government without adding value (generally, the Contractor does not add value to items that it contracts for f.o.b. destination shipment);
(2) Are shipped in direct support of U.S. military contingency operations, exercises, or forces deployed in humanitarian or peacekeeping operations; or
(3) Are commissary or exchange cargoes transported outside of the Defense Transportation System in accordance with 10 U.S.C. 2643.
(c) The Contractor and its subcontractors may request that the Contracting Officer authorize shipment in foreign-flag vessels, or designate available U.S.-flag vessels, if the Contractor or a subcontractor believes that --
(1) U.S.-flag vessels are not available for timely shipment;
(2) The freight charges are inordinately excessive or unreasonable; or
(3) Freight charges are higher than charges to private persons for transportation of like goods.
(d) The Contractor must submit any request for use of foreign-flag vessels in writing to the Contracting Officer at least 45 days prior to the sailing date necessary to meet its delivery schedules. The Contracting Officer will process requests submitted after such date(s) as expeditiously as possible, but the Contracting Officer's failure to grant approvals to meet the shipper's sailing date will not of itself constitute a compensable delay under this or any other clause of this contract. Requests shall contain at a minimum --
(1) Type, weight, and cube of cargo;
(2) Required shipping date;
(3) Special handling and discharge requirements;
(4) Loading and discharge points;
(5) Name of shipper and consignee;
(6) Prime contract number; and
(7) A documented description of efforts made to secure U.S.-flag vessels, including points of contact (with names and telephone numbers) with at least two U.S.-flag carriers contacted. Copies of telephone notes, telegraphic and facsimile message or letters will be sufficient for this purpose.
(e) The Contractor shall, within 30 days after each shipment covered by this clause, provide the Contracting Officer and the Maritime Administration, Office of Cargo Preference, U.S.