J85 IPE.pdf

PDF 58 KB Posted

Attached to
J85 MISTR REPAIR Federal contract opportunity
Solicitation number
FA8122-10-R-0012
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

About this file

Attachment One - Initial Production Evaluation

View the file

Other files for this federal contract opportunity

Other files attached to J85 MISTR REPAIR, newest first.
File Type Posted
J85 SECTION M.pdf PDF
J85 Additional Requirements.pdf PDF
FA812210R0012_______0005.pdf PDF
J85 IPE 0005.pdf PDF
J85 PWS.pdf PDF
FA812210R0012_______0004.pdf PDF
FA812210R0012_______0003.pdf PDF
Amendment 0001.pdf PDF
J85 App B CAV_AF_(GFM).pdf PDF
Amendment 0002.pdf PDF
Appendix B.pdf PDF
J85 Packaging.pdf PDF
J85 CAR for PP.pdf PDF
J85 Safety Appendix C.pdf PDF
J85 SECTION M.pdf PDF
J85 PWS.pdf PDF
J85 RFP 2.pdf PDF
J85 RFP 5.pdf PDF
J85 RFP 3.pdf PDF
J85 RFP 1.pdf PDF
Destination.docx DOCX document
J85 DELIVERY REQUIREMENTS.docx DOCX document
Update to SAR approval.pdf PDF
J85 MISTR Items Identified for breakout for SB set aside.docx DOCX document
J85 Pre-solicitation Attendees.pdf PDF
J85 Formal Q A.docx DOCX document
J85_PreSolicitation Conference Slides.pptx PPTX presentation
MAP.pdf PDF
Form for Foreign Participants.pdf PDF
ATTACHMENT L.docx DOCX document
Exhibit A - CDRL -2.pdf PDF
Attachment ONE - IPE.pdf PDF
Form 158 - SPI -1.pdf PDF
Exhibit A - CDRL -1.pdf PDF
Performance Plan.pdf PDF
Form 158 - SPI.pdf PDF
FA8122-10-R-0012 - 2.pdf PDF
J85 SECTION M.docx DOCX document
J85 SECTION L.docx DOCX document
FA8122-10-R-0012 - 3.pdf PDF
PWS.pdf PDF
FA8122-10-R-0012 - 1.pdf PDF
RQR NSNs for Follow-on.pdf PDF
J85 RFI.docx DOCX document
NSNs QDR RQ.xlsx XLSX spreadsheet
Sources Sought Synopsis.doc DOC document
Industry Day - Q A.pdf PDF
J85 Industry Day Dec 15 2009 FINAL as of Dec 11.pptx PPTX presentation
J85 RQR-1.pdf PDF
J85 RQR-2.pdf PDF
Show all 50

J85 MISTR REPAIR has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8122-10-D-0012

ATTACHMENT ONE

INITIAL PRODUCTION EVALUATION (IPE)

(a) An IPE is to be conducted on one each of the master NSNs selected by the Government from the initial production quantity for each line item of the basic contract period. The purpose of the IPE is to ensure the Contractor’s clear understanding of the technical requirements and to evaluate the Contractor’s capability to produce a serviceable item as set forth in this contract. It is accomplished through item inspection, observing tests and a complete review of production procedures and processes. All IPE work will be performed by the Contractor under the precise production conditions and processes that will be used to repair the scheduled delivery quantities on the contract. The Contractor must assure the Government representatives witnessing the IPE, that the contractor is capable of performing all levels of testing, repair and/or modifications that may be required for compliance with the Performance Work Statement (PWS), even though each level of testing, repair or modification may not be required on each item in its actual overhaul/repair. The Contractor must have all test fixtures and production fixtures described in the tech order for each item or an acceptable substitute. An acceptable substitute must be approved in writing by the PCO prior to its use on any item.

(b) At least ten (10) working days prior to the availability of the required quantity of line items for the IPE, the contractor shall furnish written notice to the Procuring Contracting Officer (PCO). The Contractor will schedule the IPE far enough in advance to be able to deliver the first delivery increment on schedule upon receipt of approval from the PCO.

( c) The PCO shall, by written notice to the contractor within ten work days after the IPE is conducted, approve, conditionally approve, or disapprove such IPE. Continued production by the contractor piror to receipt of formal notification of IPE results will be at the Contractor’s risk. The notice of approval or conditional approval shall state any further action required of the contractor. A notice of disapproval shall cite the reasons therefore.

(d) If the IPE is disapproved by the Government, the contractor may be required, at the option of the Government, to repeat any part of or all of the IPE. After each notification by the Government of the requirement for an additional IPE, the contractor shall at no additional cost to the Government make any necessary changes, modifications, or repairs to the items overhauled/repaired. Therefore, the contractor shall perform the required additional IPE under the terms and conditions and within the time specified by the Government. All costs related to additional IPE shall be borne by the contractor. The Government reserves the right to require an equitable reduction of contract price for any extension of delivery or any additional costs to the Government related to an additional IPE.

(e) If the contractor fails to perform the tasks required for the IPE within the times or time specified, or if the PCO disapproves the IPE, the contractor shall be deemed to have failed to make progress within the meaning of the “Default” clause of the contract, and this contract shall be subject to termination for default: provided, that failure of the Government in such an event to terminate this contractor default shall not relieve the contractor of his responsibility to meet the specific work and quality requirements and delivery schedule for production quantities.

(f) If the item used in the IPE is not consumed or destroyed in testing, and unless otherwise provided in this contract, it may be delivered as part of the contract quantity if it meets all terms and conditions of acceptance. The Government has not identified any specific destructive testing requirements;

however, destructive testing may be required to investigate significant quality deficiencies identified during the IPE.

(g) In the event that the PCO does not approve, conditionally approve or disapprove the IPE within the time specified in (c) above, the PCO shall, upon timely written request from the contractor, make a determination of the delay incurred by the contractor thereby, and shall equitably adjust delivery or performance data or the contract price, or both, and any other contractual provision affected by such delay, in accordance with the procedures provided in the “Changes” clause. Failure to agree to any adjustments shall be a dispute concerning a question of “fact” within the meaning of the clause of this contract entitled “Disputes”.

File details come from the government source that posted it. Updated .