FA8101-15-R-0001 Questions / Answers
Dated: 24-Mar-15 Q&A 1 through 5 Numbering Question Government Response
Q&A - 1
Details A-1, A-2, A-3 and A-4 typical section shows 6" scarified and compacted subgrade while note#3 of these details sheet refers to a modified subgrade. Please verify if the CLINs associated with these details should include modified subgrade.
Details A-1 through A-4 have been revised by deleting Note 3.
Q&A - 2
CLIN #22 is 2" Asphalt Sidewalk Construction with 4" aggregate base IAW Detail A-11.
However Detail A-11 shows 4" asphalt with no aggregate base. Please clarify if this is to be 2" asphalt with 4" aggregate base or 4" asphalt without aggregate base.
Detail A-11 is correct. Please delete the words "4" of stabilized aggregate and" following the word of in CLIN #22.
Q&A - 3 CLIN#54 unit of measure is LB. Should this be LF?
Yes. Please change LB to LF on CLIN #54.
Q&A - 4
The Synopsis on FBO states "Proposal packages are due by 3:00 p.m. CST on 30 March 2015." However, page 3 of the Amendment states that "The required response date/time has changed from 12- Mar-15 03:00 PM to 30-Mar-2015 12:00 AM." Please clarify the proposal due time.
This was a typo and will be corrected on Amendment 0002.
Q&A - 5
Paragraph I. of the Past Performance Information Sheet, states "For each of the applicable subfactors under the technical factor in the "Evaluation Criteria for Award, illustrate how your experience on this program applies to that subfactor, if you are to perform the same effort on the proposed contract." The technical factor of Section M is paragraph 3.0 with two subfactors "Project Development and Execution of Sample Project" and "Bonding". As this attachment has to do with past performance, should we be referring to paragraph 4 "Past Performance" of Section M (and more specifically all of paragraph 4.2) or paragraph
3.0 of Section M "Technical"?
Offerors should submit as it relates to Section M, paragraphs 4.2 and 4.2.2.
Questions and Answers for FA8101-15-R-0001 TAFB Paving IDIQ