Questions__4.docx

DOCX document 16 KB Posted

Attached to
Renovate Command Post B-418 Federal contract opportunity
Solicitation number
FA6712-15-R-0004
Issued by
Department of the Air Force Reserve Command

About this file

Questions 4

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Command Post B-418, newest first.
File Type Posted
Question__5.docx DOCX document
Second_Site_Visit_Notice.docx DOCX document
Addendum_2_amendment.doc DOC document
27_15_00__Data_Cabling.docx DOCX document
Addendum_2_JLSS_12-0010.docx DOCX document
Questions__3.docx DOCX document
A002CPPL_REVISION_1.pdf PDF
Addendum_1_JLSS_12-0010.docx DOCX document
Amendment_One.pdf PDF
Questions__2.docx DOCX document
Question__1.docx DOCX document
Sign-In_Sheet_Site_Visit.pdf PDF
Drawings.zip ZIP file
Drawings.zip ZIP file
FA6712-15-R-0004 Rpr Command Post.doc DOC document
Past Performance Questionnaire Command Post.docx DOCX document
911 B418 Construction Bid Specifications.pdf PDF
PA1 13 Feb 15 Mod 5.txt TXT text file
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For all the potential bidders who asked about the circuit breaker issue, here is the response:

1. The intent of the A-E was to replace the existing Siemens type BLH 100A 3 Pole breaker which currently feeds Panel E-1 with a Siemens ED6 125 Amp breaker. It should fit in the same space.

2. What model of taclane-mini would we be providing or will this be provided by others?

PROVIDED BY GOVERNMENT.

3. What model of Siemens Cabinet and UPS would we be providing?

EXISTING. TO BE RELOCATED BY OTHERS.

4. Is this a plenum rated environment?

YES. REFER TO DRAWING H-1.

5. Is the CCTV cabling analog (RG-6 coax) or is it IP based (Cat 6 cable)?

CABLE BY OTHERS. CONTRACTOR TO SUPPLY AND INSTALL JUNCTION BOXES. SEE

DRAWING E-4.

6. Drawing GTP 210-166 Plate E-4, Single line Diagram 1 - appears to show a new 125 Amp breaker in panel E2-418 and a new feeder from that panel to panel EMER-1.

a. Panel E-2 does not appear to be shown on the drawings, can you provide the approximate distance to this panel ?

ANSWERED PREVIOUSLY. PANEL E2 IS IN THE MECHANICAL ROOM ON THE EAST SIDE OF

THE BUILDING.

b. If we are to be providing a new breaker to be installed in panel E2-418, could please provide the model / type of panel that E2-418 is ?

ANSWERED PREVIOUSLY. A-E BASIS OF DESIGN IS A SIEMENS ED6 125 AMP

BREAKER.

c. Are there any specs to follow for the feeder from E-2 - to EMER-1, wire # and size ? conduit type and size ?

USE EMT CONDUIT. FOLLOW NEC FOR CONDUIT SIZE, WIRE TYPE AND SIZE.

7. Drawing E21.1.c note #2, specifies provision of 100kw portable generator for the duration of the project.

a. Is this generator expected to run 24 hours a day for the entire 270 day planned project schedule ?

ANSWERED PREVIOUSLY. FOR EMERGENCY BACKUP ONLY. GOVERNMENT TO PROVIDE

FUEL.

b. Are there any restrictions on what fuel type the generator can be ?

DIESEL FUEL GENERATOR.

8. Specification section 1.12 A, B, C, D - note that the existing lighting fixtures are to be assumed to contain 'PCB's' and need to be handled and disposed of legally and properly.

a. Does this PCB section of the specifications, in fact, apply to this project ? YES.

4. Specification 01 01 00-3 paragraph 1.07 requirement for "conditioned spaces" for furniture storage however Connex box is listed please advise.

THIS IS NOT A QUESTION. SPECS CALL FOR CONDITIONED, OR "CLIMATE CONTROLLED"

STORAGE. CLIMATE CONTROLLED CONEX BOXES ARE AVAILABLE.

9. The location of door DA-104A falls in the middle of the existing wall mural. What is the expectation for painting the wall around the new door?

Drawing A-4 notes "Paint to match adjacent walls" at location of existing door filled in with CMU block. Any disturbance caused by demo for new doorways DA-104A and DE-100A should be touched up with matching solid gray paint.

10. There is an IBR repeater or LAN hub mounted on the hanger wall in the new aisle way created by moving the fence. Will this stay or will it need to be moved?

Did not see anything like that in the new aisle, although there is a PA amplifier mounted to the wall near the mural. If there is anything in the way of the two doorways being opened up, such as the amp, conduits, water lines, etc. they will need to be relocated. The new aisle created by the fence will be wide enough that anything mounted anywhere else on the wall can stay (except maybe the TV).