911 B418 Construction Bid Specifications.pdf
PDF 2 MB Posted
- Attached to
- Renovate Command Post B-418 Federal contract opportunity
- Solicitation number
- FA6712-15-R-0004
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question__5.docx | DOCX document | |
| Second_Site_Visit_Notice.docx | DOCX document | |
| Addendum_2_amendment.doc | DOC document | |
| 27_15_00__Data_Cabling.docx | DOCX document | |
| Addendum_2_JLSS_12-0010.docx | DOCX document | |
| Questions__4.docx | DOCX document | |
| Questions__3.docx | DOCX document | |
| Addendum_1_JLSS_12-0010.docx | DOCX document | |
| Amendment_One.pdf | ||
| A002CPPL_REVISION_1.pdf | ||
| Questions__2.docx | DOCX document | |
| Sign-In_Sheet_Site_Visit.pdf | ||
| Question__1.docx | DOCX document | |
| Drawings.zip | ZIP file | |
| Drawings.zip | ZIP file | |
| Past Performance Questionnaire Command Post.docx | DOCX document | |
| PA1 13 Feb 15 Mod 5.txt | TXT text file | |
| FA6712-15-R-0004 Rpr Command Post.doc | DOC document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
911th Airlift Wing Renovate Command Post, B418
JLSS 12-0010 – GTP 210-166
Construction Bid Set – December 9, 2014
Architectural Mechanical
Seals 00005-1
Construction Bid Set
SECTION 00 01 10
TABLE OF CONTENTS
SECTION NO. SECTION TITLE
DIVISION 00 - PROCUREMENT REQUIREMENTS
00 00 00 Cover Sheet 00 01 10 Table of Contents 00 01 15 List of Drawings
DIVISION 01 - GENERAL REQUIREMENTS
01 01 00 Summary of Work 01 14 00 Work Restrictions 01 32 00 Construction Progress Documentation 01 34 00 Submittal Procedures 01 40 00 Quality Requirements 01 41 00 Environmental Protection 01 50 00 Temporary Facilities and Controls 01 59 50 Safety Requirements 01 73 00 Closeout Procedures 01 73 89 Cutting and Patching 01 78 30 Project Record Documents 01 81 30 Green Procurement Requirements 01 81 30a Green Procurement Reporting Form
DIVISION 02 - EXISTING CONDITIONS
02 41 19 Selective Demolition
DIVISION 03 - DIVISION 05
NOT APPLICABLE
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 00 Thermal Insulation 07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 31 13 Access Doors and Frames 08 41 13 Aluminum-Framed Entrances and Storefronts 08 71 00 Door Hardware 08 80 00 Glazing
DIVISION 09 - FINISHES
09 21 16 Gypsum Board Assemblies 09 30 13 Ceramic Tiling
911th Airlift Wing – Renovate Command Post B418 Table Of Contents
JLSS-12-0010 00 01 10-1
SECTION NO. SECTION TITLE
DIVISION 09 - FINISHES Cont.
09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 68 13 Tile Carpeting 09 91 00 Painting
DIVISION 10 - SPECIALTIES
10 14 00 Signage 10 28 00 Toilet Accessories
10 44 13 Fire Protection Cabinets 10 44 16 Fire Extinguishers
DIVISION 11 - EQUIPMENT - NOT APPLICABLE
DIVISION 12 - FURNISHINGS
12 32 16 Manufactured Plastic-Laminate-Clad Casework 12 36 23 Plastic-Laminate-Clad Countertops
DIVISION 13 - DIVISION 21 - NOT APPLICABLE
DIVISION 22 - PLUMBING
22 00 00 Plumbing - General Provisions 22 07 00 Plumbing Thermal Insulation 22 10 00 Plumbing - Piping Systems 22 40 00 Plumbing - Fixtures and Trim
DIVISION 23 - HVAC
23 00 00 HVAC General Provisions
DIVISION 24 - DIVISION 25 - NOT APPLICABLE
DIVISION 26 - ELECTRICAL
26 00 00 Electrical General Provisions 26 05 10 Wires and Cables 600V Maximum 26 05 33 Raceway, Boxes, Fittings, and Supports 26 18 00 Wiring Devices 26 19 00 Miscellaneous Equipment 26 24 16 Panelboards 26 51 00 Lighting System
DIVISION 27 - DIVISION 49 - NOT APPLICABLE
END OF SECTION
911th Airlift Wing – Renovate Command Post B418 Table Of Contents
JLSS-12-0010 00 01 10-2
SECTION 00 01 15
DRAWING INDEX
PLATE SHEET
NUMBER TITLE
GENERAL
G-1 COVER SHEET
ARCHITECTURAL
A-1 ARCHITECTURAL EXIT PLAN AND CODE SUMMARY
A-2 ARCHITECTURAL FIRST FLOOR/ CEILING DEMOLITION PLANS
A-3 ARCHITECTURAL FIRST FLOOR/ CEILING PLAN
A-4 ARCHITECTURAL FINISH AND FURNITURE PLANS
A-5 ARCHITECTURAL INTERIOR ELEVATIONS
A-6 ARCHITECTURAL ENLARGED FIRST FLOOR TOILET PLAN AND ELEVATIONS
A-7 ARCHITECTURAL DOOR AND WINDOW SCHEDULE AND WALL TYPES
HVAC
H-1 HVAC SYMBOLS, ABBREVIATIONS AND NOTES
H-2 HVAC FIRST FLOOR DEMOLITION AND NEW WORK PLANS
H-3 HVAC FIRST FLOOR HVAC PIPING NEW WORK PLAN
H-4 HVAC EQUIPMENT SCHEDULES AND DETAILS
PLUMBING
P-1 PLUMBING SYMBOLS AND LEGEND
P-2 PLUMBING FIRST FLOOR DEMOLITION AND NEW WORK PLANS
FIRE PROTECTION
F-1 FIRE SUPPRESSION DEMOLITION FIRST FLOOR PLAN – RENOVATION FIRST
FLOOR PLAN
ELECTRICAL
E-1 ELECTRICAL SYMBOLS AND LEGEND
E-2 ELECTRICAL SYMBOLS AND LEGEND
E-3 ELECTRICAL DEMOLITION PLAN
E-4 ELECTRICAL FIRST FLOOR POWER NEW WORK PLAN
E-5 ELECTRICAL FIRST FLOOR SPECIAL SYSTEMS NEW WORK PLAN
E-6 ELECTRICAL FIRST FLOOR LIGHTING NEW WORK PLAN
END OF SECTION
911th Airlift Wing – Renovate Command Post B418 Drawing List
JLSS-12-0010 00 01 15-1
THIS PAGE INTENTIONALLY LEFT BLANK
911th Airlift Wing – Renovate Command Post B418 Drawing List
JLSS-12-0010 00 01 15-2
SECTION 01 01 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.02 TITLE OF WORK
A. Project includes work at 911th Airlift Wing/LGC, Pittsburgh IAP ARS, Moon Township, PA 15108-4495 as follows:
1. Renovate Command Post, Building B418, Government’s Project Number: JLSS 12-0010.
1.03 DEFINITIONS
A. Provide shall mean: to furnish all materials/equipment, to install all labor and services and to make the item of work or equipment fully complete, operable, and acceptable to intended use.
B. The words "Project Coordinator" used in some of these specifications shall refer to the "Contracting Officer".
C. The word “Owner” shall refer to the “Government”.
D. The word “Architect” shall refer to the “Contracting Officer.”
E. The word “Engineer” shall refer to the “Contracting Officer.”
F. The word “Inspector” shall refer to the “Contracting Officer.”
G. Any referenced standards used are to be the latest version at the time of bidding.
1.04 WORK COVERED BY CONTRACT DOCUMENTS
A. The following is a general Project Summary of the Work. Review entire set of Contract Documents for a comprehensive referencing of required work scopes. This project includes interior renovations to approximately 1,800 gross square feet at northeast corner of the First Floor of Command Post and incorporates general, fire protection, plumbing, mechanical, and electrical construction work at the existing building. A summary of Work includes:
1. Perform selective interior demolition. Demolish and remove all interior walls, wallpaper, carpeting, ceiling tiles and suspension system, HVAC ductwork and air handler unit, electrical and communications components, plumbing fixtures and piping, lighting, and existing fire sprinkler system.
2. Construct new interior wall using metal studs and drywall.
3. Interior renovation will consist of replacing ceiling assemblies, finish flooring, cove base, and walls with new materials.
911th Airlift Wing – Renovate Command Post B418 Summary of Work
JLSS-12-0010 01 01 00 - 1
4. Construct new HVAC duct system with new air handler units and emergency shutoff controls. HVAC system shall have controls that can be operated by Command Post occupants.
5. Facility will have new communications system, including wiring and outlets for television, telephone and internet. This includes installation of new outlets in floor of ICC and as required.
6. Install new lighting fixtures (fluorescent, 2’ W by 4’ L), including task/ambient lighting system for better visibility of computer screens and video wall mounted displays. Provide task lighting at work surfaces and sufficient ambient lighting for personnel to safely move about Command Post.
7. Replace all doors in the Command Post, excluding hallway door.
8. Install two plexiglass windows (in walls between EOC and main area, and ICC and main area), maintaining requirement to visually isolate ICC from Main area.
9. Install plywood borders inside walls of SIPRnet room, from floor to true ceiling. Install plywood (3 ft AFF to 7 ft AFF) around perimeter of Comm Equip room.
10. Install new fire detection system and fire sprinkler system. Install a new security alarm system.
11. Facility requires all new electrical wiring, outlets, and two new electrical panels. This includes installation of conduit and outlets in floor of EOC room and ICC room.
12. Construct unisex restroom equipped with one plumbing fixtures, toilet accessories, and one floor drain. Restroom shall have ceramic floor tile, shower stall, and an exhaust system.
13. Construct one break room, equipped with a sink, counter, and base and wall cabinets.
14. Include Cable Management systems (cable tray, duct, conduit, etc) to facilitate connectivity to various systems and devices. Isolate low voltage from high voltage.
1.05 CONTRACT METHOD
A. Construct the Work under a single lump sum, fixed price contract for all project work.
1.06 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time.
D. Contractor shall be responsible for protecting installed Work and existing adjacent building materials and systems that remain.
JLSS-12-0010 01 01 00 - 2
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
F. Obtain and pay for use of additional storage or work areas needed for operations under this Contract. Refer to Division 01 Section “Temporary Facilities and Controls” for providing temporary trailers.
G. Refer to Division 01 Section “Work Restrictions” for additional project requirements.
1.07 FURNITURE LISTING
A. Furniture listed in this Article shall be moved by Contractor to Alternate Command Post, put in storage, or as identified. After construction work required by this Contract, Contractor shall move furniture back to the renovated Command Post.
B. Contractor shall provide conditioned trailers on the RRR pad location to store furniture in the following listing:
Description L x W x H Location
Modular Desk 84" x 15" x 65" B125, Alternate Command Post Wrap around modular desk 74" x 90" x 64" B125, Alternate Command Post Modular Desk 71" x 15" x 65"` B125, Alternate Command Post Modular L shape Desk 71" x 15" x 65"` B125, Alternate Command Post cabinet 35" x 13" x 41" B125, Alternate Command Post shredder 16" x 17" x 32" B125, Alternate Command Post 2 supply cabinets 36" x 23" x 65" B125, Alternate Command Post file cabinet 25" x 15" x 51" B125, Alternate Command Post 13 chairs
B125, Alternate Command Post
2 safes 28" x 20" x 52" B125, Alternate Command Post printer 22" x 22" x 42" B125, Alternate Command Post TV 40" B125, Alternate Command Post 2 Clocks
B125, Alternate Command Post table 48" x 24" x 30" Conex box desk (office) 72" x 37" x 31" Conex box drawer (office) 37" x 24" x 30" Conex box desk (office) 47" x 23" x 24" Conex box 2 office cabinets 24" x 36" x 65" Conex box 5 chairs
Conex box desk ( sorts office) 72" x 24" x 60" Conex box desk (sorts office) 72" x 24" x 30" Conex box desk (sorts office) 66" x 26" x 66" Conex box 1 single drawer safe 17" x 15" x 12.5" Conex box cabinet 22" x 22" x 28" Conex box refrigerator 28" x 28" x 63" Conex box
JLSS-12-0010 01 01 00 - 3
Desk (CAT) 143" x 71" x 30 Conex box Desk (CAT) 72" x 36" x 30" Conex box Printer (CAT) 16" x 16" x 16" Conex box Cabinet (CAT) 33" x 15" x 55" Conex box 6 - Tvs 40" Conex box projector projector screen 100" Conex box 1 clock table (kitchen) 44" x 24" x 30" Conex box cabinet (kitchen) 23" x 18" x 30" Conex box bulletin board 58" Conex box 6 - chairs
11 folding chairs
15 large desks
20 black mesh arm chairs
1 large dry erase board
3 medium dry erase boards
1 mini fridge
5 50” monitors (1 still in box) B210, basement 1 70" monitor
B210, basement
1 40" monitor
B210, basement
1.08 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Separate contracts will be processed for procuring interior furnishing after Work required by JLSS 12-0010 is completed. Interior furnishings include, but are not limited to, desks, chairs, tables, files cabinets, copiers, and various related materials.
1.09 GOVERNMENT’S OCCUPANCY REQUIREMENTS
A. Partial Government Occupancy: Government will occupy other areas of the Building B418 beyond project Area of Work during entire construction period. Government will also occupy adjacent buildings and other areas at the site. Cooperate with Contracting Officer and Government operations during construction operations to minimize conflicts and facilitate Government usage in building and around site. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, means of egress, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.
JLSS-12-0010 01 01 00 - 4
2. Provide not less than 3 working days’ notice to Contracting Officer of activities that will affect Government’s operations.
B. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Contracting Officer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied before Government occupancy.
2. Obtain a Certificate of Occupancy before Government occupancy.
3. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
4. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
JLSS-12-0010 01 01 00 - 5
JLSS-12-0010 01 01 00 - 6
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.01 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated. Cooperate with 911th Airlift Wing personnel during construction operations to minimize conflicts and facilitate 911th Airlift Wing usage.
1. Limits: Confine construction to areas indicated on construction drawings and/or as designated by the Contracting Officer. Confine storage area as designated by the Contracting Officer.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to 911th Airlift Wing employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Perform the work so as not to interfere with 911th Airlift Wing operations.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:
1. Normal work hours shall be between 0700 to 1600 (7:00 AM to 4:00 PM), Monday through Friday, with no work on federal holidays.
2. Any deviations from the normal working hours must be approved 3 working days in advance by the Contracting Officer.
D. The Contractor shall be responsible for protecting all remaining permanent equipment.
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
F. Obtain and pay for use of additional storage or work areas needed for operations under this contract.
G. Comfort stations are not provided by 911th Airlift Wing.
911th Airlift Wing – Renovate Command Post B418 Work Restrictions
JLSS-12-0010 01 14 00 - 1
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
911th Airlift Wing – Renovate Command Post B418 Work Restrictions
JLSS-12-0010 01 14 00 - 2
SECTION 01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SCOPE OF WORK
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Construction Progress Schedule.
2. Contract Progress Report.
3. Submittals Schedule.
4. Daily construction reports.
5. Field condition reports.
6. Special reports.
B. Related Sections include the following:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
2. Division 01 Section "Quality Requirements" for submitting a schedule of tests and inspections.
3. Division 01 Section "Closeout Procedures" for submitting photographic negatives as Project Record Documents at Project closeout.
1.03 SUBMITTALS
A. Submittals Schedule: Submit (4) four copies of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
911th Airlift Wing Construction Progress Documentation
JLSS-12-0010 01 32 00-1
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for Contracting Officer’s final release or approval.
B. Construction Progress Schedule: Submit original and (2) two printed copies.
C. Contract Progress Report: Submit original and (2) two printed copies.
D. Field Condition Reports: Submit (2) two copies at time of discovery of differing conditions.
E. Special Reports: Submit (2) two copies at time of unusual event.
1.04 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.01 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.
2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals required during the first 60 days of construction. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
JLSS-12-0010 01 32 00-2
2.02 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Procedures: Comply with procedures contained in The Associated General Contractor’s Construction Planning and Scheduling.
B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by modification.
C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities in time frame coordinated with Contracting Officer.
2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
4. Startup and Testing Time: Include not less than (10) ten days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Contracting Officer’s administrative procedures necessary for certification of Substantial Completion.
D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Division 01 Section "Summary of Work." Delivery dates indicated stipulate the earliest possible delivery date.
3. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible services.
d. Partial occupancy before Substantial Completion.
e. Use of premises restrictions.
f. Seasonal variations.
g. Environmental control.
JLSS-12-0010 01 32 00-3
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.03 CONSTRUCTION CONTRACT PROGRESS SCHEDULES AND REPORTS
A. AF Form 3064, Contract Progress Schedule, shall be submitted in original and two copies.
Computer generated schedules may be used at the discretion of Contracting Officer. When approved, the original shall be retained by the contracting office. Signed copies shall be provided to the Civil Engineer and the Contractor.
B. Separate progress reports (AF Form 3065, Contract Progress Report) covering the same period shall be prepared by the Civil Engineer or their designee and the Contractor, and submitted twice monthly. The periods shall be the same as stated on the Contract Progress Schedule. At the discretion of the Contracting Officer, this time period may be extended to monthly for projects of 180 days or more. This decision shall be documented in the contract file.
2.04 REPORTS
A. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a request for information.
Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
2.05 SPECIAL REPORTS
A. General: Submit special reports directly to Contracting Officer within one day of an occurrence. Distribute copies of report to parties affected by the occurrence.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report.
List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Contracting Officer in advance when these events are known or predictable.
PART 3 - EXECUTION
3.01 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
JLSS-12-0010 01 32 00-4
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
JLSS-12-0010 01 32 00-5
THIS PAGE IS INTENTIONALLY BLANK.
JLSS-12-0010 01 32 00-6
SECTION 01 34 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.01 SCOPE OF WORK
A. This Section includes administrative and procedural requirements for submitting Shop Draw-ings, Product Data, Samples, and other miscellaneous submittals.
1.02 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Condi-tions and other Division 01 Specification Sections, apply to this Section.
1.03 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of con-struction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so pro-cessing will not be delayed because of need to review submittals concurrently for coordina-tion.
B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal.
1. Initial Review: Allow fourteen (14) calendar days for initial review of each submittal. Al-low additional time if processing must be delayed to permit coordination with subsequent submittals. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Allow fourteen (14) calendar days for processing each resubmittal.
3. No extension of the Contract Time will be authorized because of failure to transmit submit-tals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Use for Construction: Use only final submittals with mark indicating action taken by Contract-ing Officer in connection with construction.
911th Airlift Wing – Renovate Command Post B418 Submittal Procedures
JLSS-12-0010 01 34 00-1
PART 2 PRODUCTS
2.01 SUBMITTALS
A. General: Prepare and submit Submittals required by individual Specification Sections.
1. Number of Copies: Submit five (5) copies of each submittal, unless otherwise indicated.
Contracting Officer will return two (2) copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Standard color charts.
e. Manufacturer's catalog cuts.
f. Wiring diagrams showing factory-installed wiring.
g. Printed performance curves.
h. Operational range diagrams.
i. Mill reports.
j. Standard product operating and maintenance manuals.
k. Compliance with recognized trade association standards.
l. Compliance with recognized testing agency standards.
m. Application of testing agency labels and seals.
n. Notation of coordination requirements.
C. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from the same material to be used for the Work, cured and finished in manner specified, and physically identical with the product proposed for use, and that show full range of col-or and texture variations expected. Samples include, but are not limited to, the following:
partial sections of manufactured or fabricated components; small cuts or containers of ma-terials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
D. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with require-ments.
E. Material Safety Data Sheets: Submit information directly to Contracting Officer.
JLSS-12-0010 01 34 00-2
PART 3 EXECUTION
3.01 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Sign submittal under a cover letter before submitting to Contracting Officer.
B. Failure of the contractor to provide any required documents under the contract may result in withholding a retainage pursuant to the Payments Under Fixed-Price Construction Clause, FAR 52.232-5.
3.02 CONTRACTING OFFICER’S ACTION
A. General: Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Contracting Officer will review each submittal, make marks to indicate corrections or modifica-tions required, and return it. Contracting Officer will mark submittal appropriately to indicate action taken.
JLSS-12-0010 01 34 00-3
JLSS-12-0010 01 34 00-4
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
SCOPE OF WORK 1.01
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's quality-control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-control services required by Contracting Officer are not limited by provisions of this Section.
RELATED DOCUMENTS 1.02
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
B. Related Sections include the following:
1. See individual Specification Sections for specific test and inspection requirements.
DEFINITIONS 1.03
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements.
C. Mockups: Full-size, physical example assemblies to illustrate finishes and materials. Mockups are used to verify selections made under Sample submittals, to demonstrate appearance and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples.
D. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
911th Airlift Wing – Renovate Command Post B418 Quality Requirements
JLSS-12-0010 01 40 00 - 1
DELEGATED DESIGN 1.04
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Contracting Officer.
SUBMITTALS 1.05
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1. Specification Section number and title.
2. Description of test and inspection.
3. Identification of applicable standards.
4. Identification of test and inspection methods.
5. Number of tests and inspections required.
6. Time schedule or time span for tests and inspections.
7. Entity responsible for performing tests and inspections.
8. Requirements for obtaining samples.
9. Unique characteristics of each quality-control service.
C. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
JLSS-12-0010 01 40 00 - 2
9. Test and inspection results and an interpretation of test results.
10. Ambient conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
D. Permits, Licenses, and Certificates: For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
QUALITY ASSURANCE 1.06
A. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance.
D. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that is similar to those indicated for this Project in material, design, and extent.
E. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions.
F. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed.
G. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:
JLSS-12-0010 01 40 00 - 3
1. Build mockups in location and of size indicated or, if not indicated, as directed by Contracting Officer.
2. Notify Contracting Officer (7) seven calendar days in advance of dates and times when mockups will be constructed.
3. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Contracting Officer’s approval of mockups before starting work, fabrication, or construction.
5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.
6. Demolish and remove mockups when directed, unless otherwise indicated.
H. Preconstruction Testing: Testing agency shall perform, preconstruction testing for compliance with specified requirements for performance and test methods.
1. Contractor responsibilities include the following:
a. Provide test specimens and assemblies representative of proposed materials and construction. Provide sizes and configurations of assemblies to adequately demonstrate capability of product to comply with performance requirements.
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Fabricate and install test assemblies using installers who will perform the same tasks for Project.
d. When testing is complete, remove assemblies; do not reuse materials on Project.
2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Contracting Officer, with copy to Contractor.
Interpret tests and inspections and state in, each report whether tested and inspected work complies with or deviates from the Contract Documents.
3. TEST SECTIONS: Before proceeding with the work, the Contractor shall demonstrate the processes and materials to be used a minimum of 24 hours prior to proceeding with the work to allow for resolution of any questions or clarifications. Test sections shall include the following:
a. Joint Cleaning and sealing. Include a minimum 50 ft length. All preparations and processes to be followed for the contract work must be demonstrated in the completion of the test section.
4. POSITIVE DRAINAGE: Any horizontal concrete surface included in this scope of work will be placed such that the surface will achieve positive drainage and water will, in accordance with existing drainage patterns, both freely flow onto the surface and will freely flow off and away from the surface to existing stormwater drainage systems and that no water shall be allowed to “pond” or collect on that surface due to the profile or grades of the surface itself or edging or joint filling treatments. Contractor shall completely remove and replace any work which does not conform to positive drainage requirements.
JLSS-12-0010 01 40 00 - 4
5. CONCRETE SURFACE DEFICIENCIES AND CORRECTIONS: Grinding or rubbing of the concrete surface once the concrete has been finished will not be allowed.
6. EXTREME TEMPERATURE CONCRETE PLACEMENT PROCEDURES: Contractor shall submit a cold and hot weather concrete placement plan in accordance with ACI requirements.
7. Any finished concrete surface will not vary more than 1/4-inch when checked with the 10 foot straightedge at any time after the slab has set up and is cured. This will not override the positive drainage requirement.
QUALITY CONTROL 1.07
A. Contractor Responsibilities: Unless otherwise indicated, provide quality-control services specified and required by Contracting Officer.
1. Engage a qualified testing agency to perform these quality-control services.
2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
3. Where quality-control services are indicated as Contractor’s responsibility, submit a certified written report, in duplicate, of each quality-control service.
4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor’s responsibility.
5. Submit additional copies of each written report directly to Contracting Officer, when they so direct.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct special tests and inspections required by Contracting Officer.
1. Testing agency will notify Contracting Officer promptly of irregularities and deficiencies observed in the Work during performance of its services.
2. Testing agency will submit a certified written report of each test, inspection, and similar quality-control service to Contracting Officer.
3. Testing agency will submit a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.
4. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
5. Testing agency will retest and reinspect corrected work.
C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor’s responsibility, provide quality-control services, including retesting and reinspecting, for construction that revised or replaced Work that failed to comply with requirements established by the Contract Documents.
JLSS-12-0010 01 40 00 - 5
D. Testing Agency Responsibilities: Cooperate with Contracting Officer and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Contracting Officer and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
3. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.
4. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work.
5. Do not perform any duties of Contractor.
E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field-curing of test samples.
5. Delete first subparagraph below if not required or common practice in Project vicinity.
6. Delivery of samples to testing agencies.
7. Preliminary design mix proposed for use for material mixes that require control by testing agency.
8. Security and protection for samples and for testing and inspecting equipment at Project site.
F. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
JLSS-12-0010 01 40 00 - 6
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
REPAIR AND PROTECTION 3.01
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Comply with the Contract Document requirements for Division 01 Section "Cutting and Patching."
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
JLSS-12-0010 01 40 00 - 7
JLSS-12-0010 01 40 00 - 8
SECTION 01 41 00
ENVIRONMENTAL PROTECTION
PART 1 - GENERAL
1.01 SUMMARY
A. The Contractor shall comply with all federal, state and local environmental rules and regulations, including all Air Force and 911th AW programs and policies. Failure to comply shall result in the Contractor reimbursing the 911th AW for any fines, fees, or additional costs incurred by the 911th AW as a result of Contractor non-compliance.
B. The Contractor shall participate in the base Hazardous Materials (HAZMAT) program whereby all
HAZMAT shall be approved by the Government prior to use and all HAZMAT use tracked.
C. The Contractor shall adhere to the Air Force requirement to use licensed pesticide applicators as per
Para. E4.1.5.2.3 of DODI 4150.7: “Contractor employees performing pest management work on a DoD installation shall be certified prior to the beginning of the contract under a State plan accepted in the State in which the work is performed.” All pesticides must be approved by the base Pest Manager prior to bringing material on base or applying. This includes pesticides that can be purchased over the counter by consumers. Pesticides include any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest including but not limited to insecticides, herbicides, fungicides, and various other substances to control pests. Any pesticide usage and reporting must be in accordance with the Pittsburgh IAP ARS Integrated Pest Management Plan.
1.02 SUBMITTALS
A. The following shall be submitted in accordance with Section 01 34 00 SUBMITTALS.
1. Environmental Protection Program:
a. Within 10 calendar days after Notice to Proceed and prior to commencement of the work at the site, the Contractor shall submit in writing his detailed proposal for implementing requirements for environmental pollution controls specified herein.
B. Preconstruction Survey:
1. Prior to start of any onsite construction activities, the Contractor and the Contracting Officer shall make a joint condition survey, after which the Contractor shall prepare a brief report indicating on a layout plan the condition of the areas immediately adjacent to the site of the work and adjacent to his assigned storage area and access routes(s) as applicable.
2. Both the Contracting Officer and Contractor will sign this report upon mutual agreement as to its accuracy and completeness.
C. Waste Disposal Scheme:
1. The Contractor shall submit a description of his scheme for disposing of waste materials resulting from the work under this contract.
911th Airlift Wing – Renovate Command Post B418 Environmental Protection
JLSS-12-0010 01 41 00-1
2. If any waste material is dumped in an unauthorized area, the Contractor shall remove the material and restore the area to the condition of the adjacent undisturbed areas.
3. Where directed, contaminated ground shall be excavated, disposed of properly, and replaced with suitable fill material at the expense of the Contractor.
D. Material Safety Data Sheets (MSDSS) & HAZMAT Usage:
1. Prior to bringing any HAZMAT on base, submit for the Contracting Officer’s review and approval three (3) copies of the most current MSDSs for each HAZMAT to be used for performance of work under the contract. The Contractor shall note the contract number, project number, and project title on each MSDS.
2. In addition, provide the container size for each item (in units of weight / volume) and the quantities used for all HAZMAT. Provide the information on the attached HAZMAT Usage Log. This information is required for the base HAZMAT program. Submit the HAZMAT Usage Log monthly, or at the completion of all project work, as determined by the Contracting Officer.
E. Location Of Contractor’s HAZMAT Storage:
1. Submit a drawing/sketch showing the location of areas designated for storage of HAZMAT for approval by the Contracting Officer.
a. The location on Government Property for the Contractor’s HAZMAT storage shall be on areas designated by the Contracting Officer.
2. Storage areas for HAZMAT shall comply with Paragraph 3.13, Hazardous Materials.
F. Pesticides (Including Herbicides)
1. Submit the Pesticide Application Business License to the Contracting Officer.
2. Submit the Certified Commercial Pesticide Applicator license for all pesticide applicators to the Contracting Officer.
3. Submit proposed pesticide MSDS, copy of the label, intended quantity, and location of application for project to the Contracting Officer. The base Pesticide Manager will review and provide recommendation for approval or disapproval to the Contracting Officer. Material must be approved before being brought on base or applied.
4. Submit the following information of pesticide used as soon as application is complete:
a. Names of all certified applicators
b. Contractor business name
c. Date of application
d. Duration of each task in hours
e. Building, facility, or location treated
f. Room number or specific location
g. Target pest (pest to be controlled)
h. Pesticide applied and EPA Registration Number
i. Quantity applied (undiluted)
j. MSDS and product labels for each material used
JLSS-12-0010 01 41 00-2
k. Reason for application
l. Total units treated (i.e. acres, cubic feet, each, linear feet, or square feet)
m. Describe if pesticide was applied indoors or outdoors
n. Business and applicator(s) certification numbers and expiration dates
G. Solid Waste
1. Weight Receipts: As proof of proper disposal, the Contractor…