Addendum_2_JLSS_12-0010.docx
DOCX document 17 KB Posted
- Attached to
- Renovate Command Post B-418 Federal contract opportunity
- Solicitation number
- FA6712-15-R-0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question__5.docx | DOCX document | |
| Second_Site_Visit_Notice.docx | DOCX document | |
| Addendum_2_amendment.doc | DOC document | |
| 27_15_00__Data_Cabling.docx | DOCX document | |
| Questions__4.docx | DOCX document | |
| Questions__3.docx | DOCX document | |
| A002CPPL_REVISION_1.pdf | ||
| Addendum_1_JLSS_12-0010.docx | DOCX document | |
| Amendment_One.pdf | ||
| Questions__2.docx | DOCX document | |
| Question__1.docx | DOCX document | |
| Sign-In_Sheet_Site_Visit.pdf | ||
| Drawings.zip | ZIP file | |
| Drawings.zip | ZIP file | |
| Past Performance Questionnaire Command Post.docx | DOCX document | |
| FA6712-15-R-0004 Rpr Command Post.doc | DOC document | |
| 911 B418 Construction Bid Specifications.pdf | ||
| PA1 13 Feb 15 Mod 5.txt | TXT text file |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 2
TO JLSS 12-0010
Renovate Command Post, B418
1. Add Specification Section 27 15 00, Communications Horizontal Cabling, attached.
2. Drawing A-3,First Floor/Ceiling Plan, Floor Plan General Notes and Drawing E-5, First Floor Special Systems New Work Plan, Notes – add note “EMSEC inspection is required prior to drywall placement. Coordinate with Contracting Officer.”
3. Drawing E-5, First Floor Special Systems New Work Plan, Keyed Note 3 – All SIPRnet cabling between the TACLANE and each SIPR terminal shall be run exposed and visible-not in conduit, and not behind walls or above suspended ceiling. Use appropriate hangers to suspend cable.
4. Drawing A-2, First Floor Ceiling/Demolition Plans – Add to end of Keyed Note 9 – Reroute or relocate any obstruction on the hangar side of the new door as required, such as pipes, conduits, etc.
5. Drawing E-6, First Floor Lighting New Work Plan, and Specification Section 26 51 00, Lighting System – Disregard any reference to fluorescent lighting for new lights in the Spec Section. Follow the Lighting Fixture Schedule on Drawing E-6. Lighting shall be LED type.
END OF ADDENDUM
7 April 2015