Attachment 2 - Warehouse Sample Project SOW

View the file

Other files

File Type Posted
Amendment_0002.pdf PDF
ID2_(set_2).pdf PDF
ID2_(set_1).pdf PDF
ID2_(set_3).pdf PDF
ATTACHMENT_16.xlsx XLSX spreadsheet
AMENDMENT_0001.pdf PDF
Revised_Warehouse_Submittal_Register.xlsx XLSX spreadsheet
Pre-proposal_conf_slideshow.pdf PDF
Attachment_1_-_SABER_Statement_Of_Work_(SOW).pdf PDF
Attachment_9_-_WD_-_Elmore_-_ID160079_-_Highway.pdf PDF
Attachment_6_-_WD_-_Owyhee_-_ID160071_-_Heavy.pdf PDF
FA4897-16-R-0005_SABER_RFP.pdf PDF
Attachment_3_-_Past_Performance_Questionnaire.pdf PDF
Sample_Project_Attachment_4_-_Warehouse_Submittal_Register.pdf PDF
Attachment_11_-_WD_-_Elmore_-_ID160020_-_Building.pdf PDF
Attachment_5_-_WD_-_Owyhee_-_ID160099_-_Highway.pdf PDF
Attachment_4_-_SABER_Price_Evaluation_Worksheet.pdf PDF
Sample_Project_Attachment_1_-_Warehouse_Assumptions.pdf PDF
Attachment_8_-_WD_-_Elmore___Owhyee_-_ID160001_-_RESIDENTIAL.pdf PDF
Attachment_7_-_WD_-_Owyhee_-_ID160033_-_Building.pdf PDF
Sample_Project_Attachment_2_-_Warehouse_Siting.pdf PDF
Attachment_10_-_WD_-_Elmore_-_ID160048_-_Heavy.pdf PDF
Attachment_12_-_SFS_FORM_30.pdf PDF
Attachment_13_-__Notification_of_Compliance.pdf PDF
Sample_Project_Attachment_3_-_Warehouse_FloorPlan.pdf PDF
Attachment_14_-__Determination_of_Responsibility.pdf PDF
SABER_SOW_-_Draft.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4897-16-R-0005

ATTACHMENT 2

STATEMENT OF WORK

Project: QYZH 15-1234 Title: Construct Warehouse Project Manager:

Facility: XYZ Period of Performance: 120 Days Liquidated Damages: Does not apply to this task order Submittals: See attached document Government Furnished Material: None The following is a list of requirements pertaining to this delivery order:

Concrete

1. Foundation will be in accordance with building manufacturer’s requirements

2. FFE shall be 2996.0

3. Flatwork shall be designed per “Warehouse Assumptions”

4. Warehouse shall be sealed concrete. Smooth trowel finish.

5. Include landings outside exterior doors

Masonry

6. Masonry walls shall extend 8’ above floor elevation and consist of 8” CMU, split face, and fluted, running bond, water sealed at exterior, solid grouted with #5 vertical and horizontal bars

7. Screen wall near double entrance shall be same height as other masonry

Metals

8. Upper exterior walls shall be metal vertical siding, to 20’ above FFE at eaves.

Thermal and Moisture Protection

9. Roof shall be metal framed, 12/2 pitch SSM, insulated to R30

10. Insulation for the building shall be in compliance with ANSI/ASHRAE/IES Standard

90.1-2010 for Climate Zone 5

Openings

11. Install 12’x12’ electrically operated, insulated rollup door centered on gable end

12. All doors HM with HM frame, enamel paint, Best compatible cylindrical locksets

13. Exterior doors shall be insulated

14. Main exterior doors shall be 6’0” x 7’0” x 1-3/4” with vision light

15. Single exterior door shall be 3’0”x7’0” x1-3/4” with vision light

16. Double utility room doors shall be 6’0” x 7’0” x 1-3/4”

17. Double interior doors shall be 6’0” x 7’0” x 1-3/4” with vision light

18. Single interior door shall be 3’0”x7’0” x1-3/4”

19. 1.5 pr. Hinges on each door

20. Use heavy duty closers on all doors

21. Install four windows, 4’ x4’ fixed, bronze anodized, blast resistant glass

Finishes

22. Administrative section shall consist of:

Two offices ADA accessible men’s and women’s latrine Break area Mechanical room Mop closet

23. Partition walls shall be metal studs

24. Wall between administrative area and warehouse shall be full height

25. Interior walls shall be 5/8” GWB type X, taped, textured, primed and painted. Latrine and mop room will have FRP up to 4’.

26. Office areas shall be carpeted, other areas shall be VCT

27. Latrines and mechanical room have hard ceilings

28. Suspended ceilings in office and entry area shall be 2’x4’ tegular,with an 8’ interior height

Specialties

29. Install Knox box adjacent to main entrance

30. Install 10 lb. ABC extinguisher at each exterior entrance in surface mount cabinet

31. Install bathroom accessories and partitions

32. Break room shall have 6’ base and wall cabinets with sink and space for 25 c.f.

refrigerator

Fire Suppression

33. Install wet pipe fire sprinkler system throughout

Plumbing

34. Tap existing 8” concrete sewer and install new lateral

35. Tap existing 10” water main, install curb stop and new lateral

36. Male latrine has one elongated bowl flushometer toilet, one urinal, two wall hung lavatories

37. Female latrine has two elongated bowl flushometer toilets, two wall hung lavatories

38. Install tankless water heater

39. Install refrigerated drinking fountain

40. Install single basin sink in break area

41. Install floor sink in mop closet

HVAC

42. HVAC in office areas shall be natural gas fired, forced air ducted with refrigerated cooling

43. HVAC in warehouse shall be natural gas fired unit heaters and evaporative cooling

44. Evaporative coolers shall be ground level and incorporate force protection requirements

Electrical

45. Lights in office areas shall be 4’ LED troffers with occupancy sensors

46. Lights in latrines shall be 4’ surface mount LED fixtures with occupancy sensors

47. Locate LED exit/emergency lights at exterior doors

48. Install office receptacles at residential spacing

49. Electrical service shall be two 400 amp, three phase electrical panels with exterior disconnect

50. Install duplex receptacles in warehouse at 20’ intervals

51. Warehouse high bay lighting shall be LED with occupancy sensors

52. Install photo cell control light above each exterior door

Communications

53. Install one telephone board in utility room with ground and receptacle

54. Install one 48 port Ortronic cat.6 patch panels for phone and data

55. Install duct for fiber optic cable to enter building

56. Install conduit and 10 boxes with cat 6 cable

57. Provide 10 quad jacks and faceplates

Earthwork

58. Apply termiticide in accordance with U.F.C.

59. Grade native soil at 2% slope away from building for 100’ around facility, 6” below

F.F.E.

Electronic Safety & Security

60. Install conventional FACP interfaced with Monaco D-21M wireless fire alarm reporting system

61. Install horn/strobe devices as required by code

62. Install manual pull stations at each exit

Sample Project Attachments:

1. Warehouse Assumptions

2. Warehouse Siting

3. Warehouse Floor Plan

4. Warehouse Submittal Register