Q A_-_13_Sep_13.pdf

PDF 239 KB Posted

Attached to
Forward Operating Location - Base Operating Support (FOL-BOS) Curacao Federal contract opportunity
Solicitation number
FA4890-13-R-0117
Issued by
Department of the Air Force Air Combat Command

View the file

Other files for this federal contract opportunity

Other files attached to Forward Operating Location - Base Operating Support (FOL-BOS) Curacao, newest first.
File Type Posted
Q_and_A_16_Jan_14_(corrected_from_15_Jan_14_post).pdf PDF
Appx_M_Certification_15Jan14.docx DOCX document
Appx_A_DefinitionsAbbreviationsAcronyms_8Jan14 1 .docx DOCX document
FA489013R0117_PWS_10Jan14.docx DOCX document
Q_and_A_10_Jan_14.pdf PDF
Appx_C_PublicationForms_8Jan14.docx DOCX document
Amendment_0002.pdf PDF
App_E_FOL_BOS-MOU_Postal_Support_Curacao.pdf PDF
FA4890-13-R-0117-Amendment_0001.doc DOC document
Appx_C_PublicationForms_20Dec13.docx DOCX document
Q A_20_Dec_13.pdf PDF
PICT2200.jpg JPG image
PICT2202.jpg JPG image
Appx_J_RealProperty_20_Dec_13.docx DOCX document
FOL-BOS_Site_Visit_Itinerary_19-20_Nov.pdf PDF
FA4890-13-R-0117_DD254_Atch_1.pdf PDF
Appx_A_DefinitionsAbbreviationsAcronyms_5_Dec_13.docx DOCX document
Appx_C_PublicationForms_5_Dec_13.docx DOCX document
Appx_K_GovernmentFurnishedProperty_5_Dec_13.docx DOCX document
Appx_J_RealProperty_5_Dec_13.docx DOCX document
Appx_M_Certification_5_Dec_13.docx DOCX document
Final_FOL-BOS_Industry_Site_Visit_Attendees_List_27_Nov.pdf PDF
Appx_N_KeyPersonnelQualifications_5_Dec_13.docx DOCX document
Appx_H_TransientLodging_5_Dec_13.docx DOCX document
FOL-BOS_Site_Visit_Itinerary_19-20_Nov.pdf PDF
PreSolicitation_Notice.docx DOCX document
Appx_M_Certification(18Sep13)DRAFT.docx DOCX document
Appx_P_COMSPOT-COMSTAT(13Sep13)DRAFT.docx DOCX document
Appx_I_C4I-PerformanceIndicators(13Sep13)DRAFT.docx DOCX document
Appx_C_PublicationForms(13Sep13)DRAFT.docx DOCX document
Appx_B_CDRLs(13Sep13)DRAFT.pdf PDF
Appx_O_ContractInclusions(13Sep13)DRAFT.docx DOCX document
Appx_H_TransientLodging(13Sep13)DRAFT.docx DOCX document
Appx_K_GovernmentFurnishedProperty(13Sep13)DRAFT.docx DOCX document
Format_for_Potential_Offerors_Questions_.docx DOCX document
Request_for_Additional_Information_-_Potential_Small_Business_Set-Aside_Determination_ —
FA4890-13-R-0117-_DRAFT_SECTIONS_L M.docx DOCX document
Appx_N_KeyPersonnelQualifications-DRAFT.pdf PDF
Appx_M_Certifications-DRAFT.pdf PDF
Appx_G_EstimatedWorkload_9Jan14.docx DOCX document
FOL-BOS_Industry_Day_Attendees.pdf PDF
Appx_O_ContractInclusions-DRAFT.pdf PDF
Appx_H_TransientLodging-DRAFT.pdf PDF
FOL-BOS_Industry_Day_Announcement.docx DOCX document
FOL-BOS-Industry_Day_Govt_Questions.docx DOCX document
FOL-BOS_Sources_Sought_28_Jun_13.docx DOCX document
Appx_P_COMSPOT-COMSTAT-DRAFT.pdf PDF
Appx_I_C4I-PerformanceIndicators_DRAFT 1 .docx DOCX document
Appx_C_PublicationForms-DRAFT.pdf PDF
Amendment_0002.pdf PDF
Show all 50

Forward Operating Location - Base Operating Support (FOL-BOS) Curacao has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION No. FA4890-13-R-0117, FORWARD OPERATING LOCATION – BASE OPERATING SUPPORT (FOL-BOS)

GOVERNMENT RESPONSES TO INDUSTRY QUESTIONS

13 September 2013

No Question Reference COMMENT/QUESTION RESPONSE

1 Appendix M, Certifications

Can the FOL Site Manager and CE Manager be duel hatted? Would the government have a problem with that?

There is no technical reason why dual-hatting such as this could not be accomplished given that the overall structure addresses the inherit issues and associated risk with this approach.

2 Appendix M, Does the government expect the Sr Contract Manger and

Quality Mgt Rep be assigned to the PMO office or not?

There is no contractual requirement for a PMO office; the contractor can locate the Quality Mgt Rep where they believe the position will be most effective to meet the requirements of

ISO 9001:2008.

3 Appendix M, Will the government repost the qualifications for the

Airfield Liaison as it appears some of it was cut off when converted to PDF?

Yes, we will post an updated Appendix M with the Airfield

Liaison’s position.

4 Appendix G, Estimated Workload

Can the government post the summary pages for M-32

Cumulative from CY Sept 11, 12 and 13 when it becomes available?

The government will post the summary pages of the M-32 from CY Sept 11, 12, and 13 when available.

5 Appendix G, Can the government provide workload for the Fitness and

Recreation area (PWS 4.3.3) as in number of personnel using fitness center on a monthly basis like done in previous RFPs as Appendix G, Section 1.7 only provide purchases of items?

Work load data in this particular area will not be useful and potentially misleading since use of the fitness center is wildly divergent depending on number of deployed units, OPTEMPO of those units, and other factors. As a result, this type of workload data will not be provided.

6 Appendix G, Can the government provide the workload for Postal

Operations (PWS 4.5 thru 4.5.2.2) as in the number of incoming and outgoing pieces of mail, mail volume by weight incoming and outgoing like done in previous

RFPs?

Yes, we have updated Appendix G with postal service historical workload.

Appendix G, Will the government provide the workload data for PWS

4.1.2 thru 4.1.2.9 so we can staff and price this section?

Workload data has been updated in Appendix G & K.

Transportation requests:

2011: 1245 Transports

2012: 1681 Transports

2013: 663 Transports through 22 Aug13

8 Appendix G, Will the government provide the square footage of cleanable space by carpet and tile by facility for PWS

4.2.1.16?

See the as-built drawings in Appendix J for this information.

9 Appendix G, Will the government provide the number of restrooms and locker rooms by facility that are to be maintained for PWS

4.2.1.16?

See the as-built drawings in Appendix J for this information.

10 Appendix G, Are the trash trucks GFV or CFV as we didn’t see any in

Government Furnished Property List (1.3) for PWS

4.2.1.17?

No, there are no GFV/CFV trash trucks. Contractor establishes a local subcontract to accomplish this function.

11 Appendix G, Are the dumpster GFP or CFP as we didn’t see any in the

Government Furnished Property List (1.3) for PWS

4.2.1.17?

No, dumpsters are part of the subcontract mentioned above.

12 Appendix G, What is the average number of Personal Property

Shipments a year or month as they are not called out in

Para 1.1 of Appendix G?

Personal Property Shipments average 10 shipments per year of not more than 800 lbs. per shipment.

13 PWS Section A, Para 4.2.1.15

How much perimeter fence line must be maintained with the 30 foot clearance zone in Liner Feet?

14 PWS Section A, Para 4.2.1.13.7

How many Fire Protection and Detection Systems must be maintained per PWS 4.2.1.13.7?

See the as-built drawings in Appendix J for this information.

15 PWS Section A, Para 4.2.1.13.5

How many Interior Electric Systems must be maintained per PWS 4.2.1.13.5?

See the as-built drawings in Appendix J for this information.

16 PWS Section A, Para 4.2.1.13.4

How many HVAC systems and sizes must be maintained

Per PWS 4.2.1.13.4?

See the as-built drawings in Appendix J for this information.

17 PWS Section A, Para 4.2.1.12

How many Cathodic Protection Systems must be maintained per PWS 4.2.1.12?

See the as-built drawings in Appendix J for this information.

18 PWS Section A, Para 4.2.1.11

How many grounding points must be maintained per PWS

4.2.1.11?

See the as-built drawings in Appendix J for this information.

19 PWS Section A, Para 4.2.1.11

How many Exterior Electrical Distribution systems must be maintained and capacity of the system per PWS

4.2.1.11?

See the as-built drawings in Appendix J for this information.

20 PWS Section A, Para 4.2.1.9

What is the capacity sanitary sewer system and linear feet to be maintained per PWS 4.2.1.9?

See the as-built drawings in Appendix J for this information.

21 PWS Section A, Para 4.2.1.3

What is the mileage of street and liner footage of sidewalks and pad to be maintained per PWS 4.2.1.3?

22 PWS Section A, Para 4.2.1.2

What is the liner footage of the storm water system that is to be maintained per PWS 4.2.1.2?

23 PWS Section A, Para 4.2.1.6

What are the number and sizes of the Generators to be maintained per PWS 4.2.1.6 as they are not listed in

Appendix G, 1.3?

24 PWS Section A, Para 4.3.2

How many MRE must be stored per PWS 4.3.2? Are they currently stored in refrigerated conditions?

Total quantity is 192 MRE cases. They are not currently refrigerated.

25 PWS Section A, Para 4.1.9.6

How many customers are serviced monthly or yearly by the PPPO per PWS 4.1.9.6?

Personal Property Shipments average 10 shipments per year of not more than 800 lbs. per shipment.

26 PWS Section D Para

2.2.3 and 2.2.4

Will the government provide the contractor the USF and

SOUTHCOM regulations and directives per PWS Section

D, para 2.2.3 and 2.2.4 along with HN laws, regulations and directives?

Government directives are available via websites or will be available if not obtainable via web in the bidder’s library. HN laws, regulation and directives are the offeror’s responsibility to obtain and adhere to.

27 PWS Section D, Para 3.1

What are the normal duty hours for other than Fire

Department, JOC, POL and Airfield Services, M-F 8 hrs, M – Sat 8 or 10 hr, please clarify?

The government specified duty hours in Section D, para 3.1.

for mandatory coverage. Offerors are requested to establish normal duty hours as appropriate to meet PWS requirements.

28 PWS Section A, Para 2.11.3

How many current Equipment and Component Warranty are being managed per PWS 2.11.3?

Warranty information is contained in Appendix G, 1.3.

Government Furnished Equipment List.

29 PWS Section A, Para 2.13.1

How many FOL/CC and Detachment Staff work group centers are to be supported by Administrative staff per

PWS 2.13.1?

The administrator supports the commander and immediate staff.

30 PWS Section A, Para 4.3.4

How many day rooms and fitness centers require cable/satellite TV service per Para 4.3.4?

The dayroom and the fitness center in C-700 require cable/satellite service. In addition there is a break area in C-

600 that requires cable/satellite service.

31 PWS Section A, Para 4.3.2

How many MRE are stored and how many are issued if any on monthly or yearly basis?

Total quantity is 192 Cases are stored. No MRE issued to date.

32 PWS Section A, Para 4.2.1.5

How many utility meters there to be validated monthly? There is one electrical meter and one water meter for the Fire

Department Complex and one electrical meter and one water meter for the operations area.