Attachment 1 Gantt Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Ground Control Station Conversion, newest first.
File Type Posted
Attachment_6_Past_and_Present_Performance_Questionairre.rtf RTF text file
Attachment_2_GCS_Conversion_Proof_of_Concept_and_List_of_Materials_corrected.doc DOC document
Attachment_9_SOW.doc DOC document
Attachment_3_GCS_Room_Layout.doc DOC document
Attachment_7_DD_Form_254_-_Conversions.doc DOC document
Attachment_8_Wage_Determination_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0007_Conformed_Copy.pdf PDF
Attachment_4_GFM_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0007.pdf PDF
Attachment_5_Performance_Reference_Form.doc DOC document
Attachment_10_Ground_Control_Station_Conversion_QA_Rev_Nov_24.doc DOC document
FA4855-15-R-0007_Amendment_0006.pdf PDF
Attachment_4_GFM_8_July_15.doc DOC document
Attachment_9_SOW_(Revised_16_Jul_15).doc DOC document
Attachment_8_Wage_Determination_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0006.pdf PDF
Attachment_1_Gantt_16_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0005_Suspend_Contract.pdf PDF
Attachment_1_Gantt_Schedule_revised_9_Dec_14.doc DOC document
Attachment_9_Statement_of_Work_(Revised_2_Dec_14).doc DOC document
Amendment_0004_Update_PoP.pdf PDF
Attachment_9_Statement_of_Work_(Revised_24_Nov_14).doc DOC document
Ground_Control_Station_Conversion_QA_Rev_Nov_24.doc DOC document
Amendment_0003_Q_and_A_and_updated_SOW.pdf PDF
Amendment_0002_Extend_proposal_due_date.pdf PDF
Amendment_0001_Add_Q A_date.pdf PDF
FA4855-15-R-0007_GCS_Conversions.pdf PDF
Attachment_1_Gantt_Schedule.pdf PDF
Attachment_8_Wage_Determination.pdf PDF
Attachment_6_Past_and_Present_Performance_Questionnaire.pdf PDF
Attachment_9_Statement_of_Work.pdf PDF
Attachment_7_DD_Form_254_-_Conversions.pdf PDF
Attachment_5_Performance_Reference_Form.pdf PDF
Attachment_4_Government_Furnished_Materials.pdf PDF
Attachment_3_GCS_Room_Layout.pdf PDF
Attachment_2_GCS_Conversion_Proof_of_Concept_and_List_of_Materials.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Scheduled Start

Scheduled Finish

Scheduled Duration

Predecessors

1 GCS Conversion Activities Mon 9/28/15 Tue 9/27/16 301.8 days

2 Expected Period of Performance Mon 9/28/15 Tue 9/27/16 301.8 days

3 GCS Conversions & Installation Mon 9/28/15 Tue 9/27/16 302 days

4 Personnel & equipment staging Mon 9/28/15 Mon 11/2/15 30 days

5 FGCS #1 Tue 11/3/15 Tue 12/8/15 27 days

6 De‐mod add‐ons Tue 11/3/15 Mon 11/9/15 5 days 4

7 Remove & relocate flight systems

Mon 11/9/15 Fri 11/20/15 10 days 6

8 Re‐install add‐ons Fri 11/20/15 Mon 11/30... 5 days 7

9 Connect to C2 & FMV networksMon 11/30... Fri 12/4/15 5 days 8

10 Flight tests Fri 12/4/15 Tue 12/8/15 2 days 9

11 Operational Date Tue 12/8/15 Tue 12/8/15 0 days 62

12 FGCS #2 Thu 12/17/... Thu 1/21/16 27 days

13 De‐mod add‐ons Thu 12/17/15 Wed 12/23... 5 days 11FS+8 days

14 Remove & relocate flight systems

Wed 12/23/15

Wed 1/6/16 10 days 13

15 Re‐install add‐ons Wed 1/6/16 Tue 1/12/16 5 days 14

16 Connect to C2 & FMV networksTue 1/12/16 Tue 1/19/16 5 days 15

17 Flight tests Wed 1/20/16 Thu 1/21/16 2 days 16

18 Operational Date Thu 1/21/16 Thu 1/21/16 0 days 63

19 FGCS #3 Mon 2/1/16 Thu 3/3/16 27 days

20 De‐mod add‐ons Mon 2/1/16 Fri 2/5/16 5 days 18FS+8 days

21 Remove & relocate flight systems

Fri 2/5/16 Thu 2/18/16 10 days 20

22 Re‐install add‐ons Thu 2/18/16 Wed 2/24/16 5 days 21

23 Connect to C2 & FMV networksWed 2/24/16 Tue 3/1/16 5 days 22

24 Flight tests Tue 3/1/16 Thu 3/3/16 2 days 23

25 Operational Date Thu 3/3/16 Thu 3/3/16 0 days 64

26 FGCS #4 Fri 3/11/16 Wed 4/13/16 27 days

27 De‐mod add‐ons Fri 3/11/16 Thu 3/17/16 5 days 25FS+8 days

28 Remove & relocate flight systems

Fri 3/18/16 Wed 3/30/16 10 days 27

29 Re‐install add‐ons Wed 3/30/16 Tue 4/5/16 5 days 28

30 Connect to C2 & FMV networksTue 4/5/16 Mon 4/11/16 5 days 29

31 Flight tests Mon 4/11/16 Wed 4/13/16 2 days 30

32 Operational Date Wed 4/13/16 Wed 4/13/16 0 days 65

33 FGCS #5 Fri 4/22/16 Tue 5/24/16 27 days

34 De‐mod add‐ons Fri 4/22/16 Thu 4/28/16 5 days 32FS+8 days

35 Remove & relocate flight systems

Thu 4/28/16 Tue 5/10/16 10 days 34

36 Re‐install add‐ons Tue 5/10/16 Mon 5/16/16 5 days 35

37 Connect to C2 & FMV networksMon 5/16/16 Fri 5/20/16 5 days 36

38 Flight tests Fri 5/20/16 Tue 5/24/16 2 days 37

12/8

1/21

3/3

4/13

9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 5 Nov 1, '15 Jan 1, '16 Mar 1, '16 May 1, '16 Jul 1, '16 Sep 1, '16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Project: GCS Conversions

Attachment 1 Gantt Schedule, 2 Pages, Dated 28 Jul 15

ID Task Name Scheduled Start

Scheduled Finish

Scheduled Duration

Predecessors

39 Operational Date Tue 5/24/16 Tue 5/24/16 0 days 66

40 FGCS #6 Fri 6/3/16 Wed 7/6/16 27 days

41 De‐mod add‐ons Fri 6/3/16 Thu 6/9/16 5 days 39FS+8 days

42 Remove & relocate flight systems

Thu 6/9/16 Tue 6/21/16 10 days 41

43 Re‐install add‐ons Tue 6/21/16 Mon 6/27/16 5 days 42

44 Connect to C2 & FMV networksMon 6/27/16 Fri 7/1/16 5 days 43

45 Flight tests Tue 7/5/16 Wed 7/6/16 2 days 44

46 Operational Date Wed 7/6/16 Wed 7/6/16 0 days 67

47 FGCS #7 Fri 7/15/16 Tue 8/16/16 27 days

48 De‐mod add‐ons Fri 7/15/16 Thu 7/21/16 5 days 46FS+8 days

49 Remove & relocate flight systems

Thu 7/21/16 Tue 8/2/16 10 days 48

50 Re‐install add‐ons Tue 8/2/16 Mon 8/8/16 5 days 49

51 Connect to C2 & FMV networksTue 8/9/16 Mon 8/15/16 5 days 50

52 Flight tests Mon 8/15/16 Tue 8/16/16 2 days 51

53 Operational Date Tue 8/16/16 Tue 8/16/16 0 days 68

54 FGCS #8 Thu 8/25/16 Tue 9/27/16 27 days

55 De‐mod add‐ons Thu 8/25/16 Wed 8/31/16 5 days 53FS+8 days

56 Remove & relocate flight systems

Wed 8/31/16 Tue 9/13/16 10 days 55

57 Re‐install add‐ons Wed 9/14/16 Tue 9/20/16 5 days 56

58 Connect to C2 & FMV networksTue 9/20/16 Mon 9/26/16 5 days 57

59 Flight tests Mon 9/26/16 Tue 9/27/16 2 days 58

60 Operational Date Tue 9/27/16 Tue 9/27/16 0 days 69

61 Quality Control Inspection Schedule

Tue 12/8/15 Tue 9/27/16 245 days

62 FGCS 1 Inspection Tue 12/8/15 Tue 12/8/15 0 days 10

63 FGCS 2 Inspection Thu 1/21/16 Thu 1/21/16 0 days 17

64 FGCS 3 Inspection Thu 3/3/16 Thu 3/3/16 0 days 24

65 FGCS 4 Inspection Wed 4/13/16 Wed 4/13/16 0 days 31

66 FGCS 5 Inspection Tue 5/24/16 Tue 5/24/16 0 days 38

67 FGCS 6 Inspection Wed 7/6/16 Wed 7/6/16 0 days 45

68 FGCS 7 Inspection Tue 8/16/16 Tue 8/16/16 0 days 52

69 FGCS 8 Inspection Tue 9/27/16 Tue 9/27/16 0 days 59

70 Final Project Management Review Tue 9/27/16 Tue 9/27/16 0 days 69

5/24

7/6

8/16

9/27

12/8 1/21

3/3 4/13

5/24 7/6

8/16 9/27 9/27

9/27 10/25 11/22 12/20 1/17 2/14 3/13 4/10 5/8 6/5 7/3 7/31 8/28 9/25 5 Nov 1, '15 Jan 1, '16 Mar 1, '16 May 1, '16 Jul 1, '16 Sep 1, '16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Project: GCS Conversions

Attachment 1 Gantt Schedule, 2 Pages, Dated 28 Jul 15