Attachment_1_Gantt_16_July_15.doc

DOC document 1 MB Posted

Attached to
Ground Control Station Conversion Federal contract opportunity
Solicitation number
FA4855-15-R-0007
Issued by
Department of the Air Force Special Operations Command

About this file

Attachment 1 Gantt Schedule 16 Jul 15

View the file

Other files for this federal contract opportunity

Other files attached to Ground Control Station Conversion, newest first.
File Type Posted
Attachment_6_Past_and_Present_Performance_Questionairre.rtf RTF text file
Attachment_2_GCS_Conversion_Proof_of_Concept_and_List_of_Materials_corrected.doc DOC document
Attachment_9_SOW.doc DOC document
Attachment_1_Gantt.pdf PDF
Attachment_3_GCS_Room_Layout.doc DOC document
Attachment_7_DD_Form_254_-_Conversions.doc DOC document
Attachment_8_Wage_Determination_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0007_Conformed_Copy.pdf PDF
Attachment_4_GFM_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0007.pdf PDF
Attachment_5_Performance_Reference_Form.doc DOC document
Attachment_10_Ground_Control_Station_Conversion_QA_Rev_Nov_24.doc DOC document
FA4855-15-R-0007_Amendment_0006.pdf PDF
Attachment_4_GFM_8_July_15.doc DOC document
Attachment_9_SOW_(Revised_16_Jul_15).doc DOC document
Attachment_8_Wage_Determination_8_July_15.doc DOC document
FA4855-15-R-0007_Amendment_0006.pdf PDF
FA4855-15-R-0007_Amendment_0005_Suspend_Contract.pdf PDF
Attachment_1_Gantt_Schedule_revised_9_Dec_14.doc DOC document
Attachment_9_Statement_of_Work_(Revised_2_Dec_14).doc DOC document
Amendment_0004_Update_PoP.pdf PDF
Attachment_9_Statement_of_Work_(Revised_24_Nov_14).doc DOC document
Ground_Control_Station_Conversion_QA_Rev_Nov_24.doc DOC document
Amendment_0003_Q_and_A_and_updated_SOW.pdf PDF
Amendment_0002_Extend_proposal_due_date.pdf PDF
Amendment_0001_Add_Q A_date.pdf PDF
FA4855-15-R-0007_GCS_Conversions.pdf PDF
Attachment_1_Gantt_Schedule.pdf PDF
Attachment_8_Wage_Determination.pdf PDF
Attachment_6_Past_and_Present_Performance_Questionnaire.pdf PDF
Attachment_9_Statement_of_Work.pdf PDF
Attachment_7_DD_Form_254_-_Conversions.pdf PDF
Attachment_5_Performance_Reference_Form.pdf PDF
Attachment_4_Government_Furnished_Materials.pdf PDF
Attachment_3_GCS_Room_Layout.pdf PDF
Attachment_2_GCS_Conversion_Proof_of_Concept_and_List_of_Materials.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID

Task Name
Scheduled Start
Scheduled Finish
Scheduled Duration
Predecessors

September 2015

July 11
September 1
October 21
Dec
6/14
7/5
7/26
8/16
9/6
9/27
10/18
11/8
11/29
1
GCS Conversion Activities
Mon 9/28/15
Tue 9/27/16
301.8 days
2
Expected Period of Performance
Mon 9/28/15
Tue 9/27/16
301.8 days
3
GCS Conversions & Installation
Mon 9/28/15
Mon 9/26/16
300.8 days

12/

4
Personnel & equipment staging
Mon 9/28/15
Fri 10/30/15
28.6 days
5
FGCS #1
Mon 11/2/15
Mon 12/7/15
27 days
6
De‐mod add‐ons
Mon 11/2/15
Fri 11/6/15
5 days
4
7
Remove & relocate flight systems
Fri 11/6/15
Thu 11/19/15
10 days
6
8
Re‐install add‐ons
Thu 11/19/15
Wed 11/25/15
5 days
7
9
Connect to C2 & FMV networks
Wed 11/25/15
Thu 12/3/15
5 days
8
10
Flight tests
Thu 12/3/15
Mon 12/7/15
2 days
9
11
Operational Date
Mon 12/7/15
Mon 12/7/15
0 days
10
12
FGCS #2
Wed 12/16/15
Wed 1/20/16
27 days
13
De‐mod add‐ons
Wed 12/16/15
Tue 12/22/15
5 days
11FS+8 days
14
Remove & relocate flight systems
Tue 12/22/15
Tue 1/5/16
10 days
13
15
Re‐install add‐ons
Tue 1/5/16
Mon 1/11/16
5 days
14
16
Connect to C2 & FMV networks
Mon 1/11/16
Fri 1/15/16
5 days
15
17
Flight tests
Tue 1/19/16
Wed 1/20/16
2 days
16
18
Operational Date
Wed 1/20/16
Wed 1/20/16
0 days
17
19
FGCS #3
Fri 1/29/16
Wed 3/2/16
27 days
20
De‐mod add‐ons
Fri 1/29/16
Thu 2/4/16
5 days
18FS+8 days
21
Remove & relocate flight systems
Thu 2/4/16
Wed 2/17/16
10 days
20
22
Re‐install add‐ons
Wed 2/17/16
Tue 2/23/16
5 days
21
23
Connect to C2 & FMV networks
Tue 2/23/16
Mon 2/29/16
5 days
22
Project: GCS Conversions
Task

External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start‐only Summary Inactive Summary Finish‐only Project Summary Manual Task Deadline External Tasks Duration‐only Progress

ID
Task Name
Scheduled Start Scheduled

Finish

Scheduled Duration
Predecessors
July 11
September 2015 September 1
October 21
Dec
48
De‐mod add‐ons
Thu 7/14/16
Wed 7/20/16
5 days
46FS+8 days
6/14
7/5
7/26
8/16
9/6
9/27
10/18
11/8
11/29
49
Remove & relocate flight
Wed 7/20/16
Mon 8/1/16
10 days
48

systems

50
Re‐install add‐ons
Mon 8/1/16
Fri 8/5/16
5 days
49
51
Connect to C2 & FMV
Mon 8/8/16
Fri 8/12/16
5 days
50

networks

52
Flight tests
Fri 8/12/16
Mon 8/15/16
2 days
51
53
Operational Date
Mon 8/15/16
Mon 8/15/16
0 days
52
54
FGCS #8
Wed 8/24/16
Mon 9/26/16
27 days
55
De‐mod add‐ons
Wed 8/24/16
Tue 8/30/16
5 days
53FS+8 days
10/1
56
Remove & relocate flight
Tue 8/30/16
Mon 9/12/16
10 days
55

systems

57
Re‐install add‐ons
Tue 9/13/16
Mon 9/19/16
5 days
56
58
Connect to C2 & FMV
Mon 9/19/16
Fri 9/23/16
5 days
57

networks

59
Flight tests
Fri 9/23/16
Mon 9/26/16
2 days
58
60
Operational Date
Mon 9/26/16
Mon 9/26/16
0 days
59
61
Quality Control Inspection
Thu 10/1/15
Mon 9/19/16
290.2 days

Schedule

62
FGCS 1 Inspection
Thu 10/1/15
Thu 10/1/15
0 days
63
FGCS 2 Inspection
Mon 1/11/16
Mon 1/11/16
0 days
15
64
FGCS 3 Inspection
Tue 2/23/16
Tue 2/23/16
0 days
22
65
FGCS 4 Inspection
Mon 4/4/16
Mon 4/4/16
0 days
29
66
FGCS 5 Inspection
Fri 5/13/16
Fri 5/13/16
0 days
36
67
FGCS 6 Inspection
Fri 6/24/16
Fri 6/24/16
0 days
43
68
FGCS 7 Inspection
Fri 8/5/16
Fri 8/5/16
0 days
50
69
FGCS 8 Inspection
Mon 9/19/16
Mon 9/19/16
0 days
57

Project: GCS Conversions

Task Split Milestone Summary Project Summary External Tasks

External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only

Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress

ID

Task Name Scheduled Start Scheduled Finish

Scheduled Duration

Predecessors

January 2016 May 2016 ember 11 February 1 March 21 May 11 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 1 GCS Conversion Activities Mon 9/28/15 Tue 9/27/16 301.8 days 2 Expected Period of Performance

Mon 9/28/15 Tue 9/27/16

301.8 days 3 GCS Conversions & Installation Mon 9/28/15 Mon 9/26/16 300.8 days 4 Personnel & equipment staging Mon 9/28/15 Fri 10/30/15 28.6 days

FGCS #1

Mon 11/2/15 Mon 12/7/15 27 days 6 De‐mod add‐ons Mon 11/2/15 Fri 11/6/15 5 days 7 Remove & relocate flight systems

Fri 11/6/15 Thu 11/19/15 10 days 8 Re‐install add‐ons Thu 11/19/15 Wed 11/25/15 5 days 9 Connect to C2 & FMV networks

Wed 11/25/15 Thu 12/3/15 5 days 10 Flight tests Thu 12/3/15 Mon 12/7/15 2 days 11 Operational Date Mon 12/7/15 Mon 12/7/15 0 days

FGCS #2

Wed 12/16/15 Wed 1/20/16 27 days 13 De‐mod add‐ons Wed 12/16/15 Tue 12/22/15 5 days 11FS+8 days 14 Remove & relocate flight systems

Tue 12/22/15 Tue 1/5/16 10 days 15 Re‐install add‐ons Tue 1/5/16 Mon 1/11/16 5 days 16 Connect to C2 & FMV networks

Mon 1/11/16 Fri 1/15/16 5 days 17 Flight tests Tue 1/19/16 Wed 1/20/16 2 days 18 Operational Date Wed 1/20/16 Wed 1/20/16 0 days

FGCS #3

Fri 1/29/16 Wed 3/2/16 27 days 20 De‐mod add‐ons Fri 1/29/16 Thu 2/4/16 5 days 18FS+8 days

1/20 21 Remove & relocate flight systems

Thu 2/4/16 Wed 2/17/16 10 days 22 Re‐install add‐ons Wed 2/17/16 Tue 2/23/16 5 days 23 Connect to C2 & FMV networks

Task Split

Tue 2/23/16 Mon 2/29/16 5 days External Milestone Inactive Task

Manual Summary Rollup Manual Summary Project: GCS Conversions

Milestone Summary Project Summary External Tasks

Inactive Milestone Inactive Summary Manual Task Duration‐only

Start‐only Finish‐only Deadline Progress

ID

Task Name Scheduled Start Scheduled Finish

Scheduled Duration

Predecessors

January 2016 May 2016 ember 11 February 1 March 21 May 11 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 24 Flight tests Mon 2/29/16 Wed 3/2/16 2 days

3/2 4/12 5/23

Project Summary External Tasks

External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only

Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress

ID
Task Name
Scheduled Start Scheduled

Finish

Scheduled Duration
Predecessors
January 2016 ember 11
February 1
March 21
May 2016

May 11

48
De‐mod add‐ons
Thu 7/14/16
Wed 7/20/16
5 days
46FS+8 days
12/20
1/10
1/31
2/21
3/13
4/3
4/24
5/15
6/5
49
Remove & relocate flight
Wed 7/20/16
Mon 8/1/16
10 days
48

systems

50
Re‐install add‐ons
Mon 8/1/16
Fri 8/5/16
5 days
49
51
Connect to C2 & FMV
Mon 8/8/16
Fri 8/12/16
5 days
50

networks

52
Flight tests
Fri 8/12/16
Mon 8/15/16
2 days
51
53
Operational Date
Mon 8/15/16
Mon 8/15/16
0 days
52
54
FGCS #8
Wed 8/24/16
Mon 9/26/16
27 days
55
De‐mod add‐ons
Wed 8/24/16
Tue 8/30/16
5 days
53FS+8 days
56
Remove & relocate flight
Tue 8/30/16
Mon 9/12/16
10 days
55

systems

57
Re‐install add‐ons
Tue 9/13/16
Mon 9/19/16
5 days
56
58
Connect to C2 & FMV
Mon 9/19/16
Fri 9/23/16
5 days
57

networks

59
Flight tests
Fri 9/23/16
Mon 9/26/16
2 days
58
60
Operational Date
Mon 9/26/16
Mon 9/26/16
0 days
59
61
Quality Control Inspection
Thu 10/1/15
Mon 9/19/16
290.2 days

Schedule

62
FGCS 1 Inspection
Thu 10/1/15
Thu 10/1/15
0 days
63
FGCS 2 Inspection
Mon 1/11/16
Mon 1/11/16
0 days
15
1/11
64
FGCS 3 Inspection
Tue 2/23/16
Tue 2/23/16
0 days
22

2/23

65
FGCS 4 Inspection
Mon 4/4/16
Mon 4/4/16
0 days
29

4/4

66
FGCS 5 Inspection
Fri 5/13/16
Fri 5/13/16
0 days
36

5/13

67
FGCS 6 Inspection
Fri 6/24/16
Fri 6/24/16
0 days
43
68
FGCS 7 Inspection
Fri 8/5/16
Fri 8/5/16
0 days
50
69
FGCS 8 Inspection
Mon 9/19/16
Mon 9/19/16
0 days
57

Project Summary External Tasks

External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only

Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress

ID

Task Name Scheduled Start Scheduled Finish

Scheduled Duration

Predecessors

September 2016 July 1

August 21

October 11

December 1 6/26 7/17 8/7

8/28 9/18

10/9 10/30 11/20 12/11 1 GCS Conversion Activities Mon 9/28/15 Tue 9/27/16 301.8 days 2 Expected Period of Performance

Mon 9/28/15 Tue 9/27/16

301.8 days 3 GCS Conversions & Installation Mon 9/28/15 Mon 9/26/16 300.8 days 4 Personnel & equipment staging Mon 9/28/15 Fri 10/30/15 28.6 days

FGCS #1

Mon 11/2/15 Mon 12/7/15 27 days 6 De‐mod add‐ons Mon 11/2/15 Fri 11/6/15 5 days 7 Remove & relocate flight systems

Fri 11/6/15 Thu 11/19/15 10 days 8 Re‐install add‐ons Thu 11/19/15 Wed 11/25/15 5 days 9 Connect to C2 & FMV networks

Wed 11/25/15 Thu 12/3/15 5 days 10 Flight tests Thu 12/3/15 Mon 12/7/15 2 days 11 Operational Date Mon 12/7/15 Mon 12/7/15 0 days

FGCS #2

Wed 12/16/15 Wed 1/20/16 27 days 13 De‐mod add‐ons Wed 12/16/15 Tue 12/22/15 5 days 11FS+8 days 14 Remove & relocate flight systems

Tue 12/22/15 Tue 1/5/16 10 days 15 Re‐install add‐ons Tue 1/5/16 Mon 1/11/16 5 days 16 Connect to C2 & FMV networks

Mon 1/11/16 Fri 1/15/16 5 days 17 Flight tests Tue 1/19/16 Wed 1/20/16 2 days 18 Operational Date Wed 1/20/16 Wed 1/20/16 0 days

FGCS #3

Fri 1/29/16 Wed 3/2/16 27 days 20 De‐mod add‐ons Fri 1/29/16 Thu 2/4/16 5 days 18FS+8 days 21 Remove & relocate flight systems

Thu 2/4/16 Wed 2/17/16 10 days 22 Re‐install add‐ons Wed 2/17/16 Tue 2/23/16 5 days 23 Connect to C2 & FMV networks

Task Split

Tue 2/23/16 Mon 2/29/16 5 days External Milestone Inactive Task

Manual Summary Rollup Manual Summary Project: GCS Conversions

Milestone Summary Project Summary External Tasks

Inactive Milestone Inactive Summary Manual Task Duration‐only

Start‐only Finish‐only Deadline Progress

ID

Task Name Scheduled Start Scheduled Finish

Scheduled Duration

Predecessors

December 1 6/26 7/17 8/7

8/28 9/18

10/9 10/30 11/20 12/11 24 Flight tests Mon 2/29/16 Wed 3/2/16 2 days 25 Operational Date Wed 3/2/16 Wed 3/2/16 0 days

FGCS #4

Thu 3/10/16 Tue 4/12/16 27 days 27 De‐mod add‐ons Thu 3/10/16 Wed 3/16/16 5 days 25FS+8 days 28 Remove & relocate flight systems

Thu 3/17/16 Tue 3/29/16 10 days 29 Re‐install add‐ons Tue 3/29/16 Mon 4/4/16 5 days 30 Connect to C2 & FMV networks

Mon 4/4/16 Fri 4/8/16 5 days 31 Flight tests Fri 4/8/16 Tue 4/12/16 2 days 32 Operational Date Tue 4/12/16 Tue 4/12/16 0 days

FGCS #5

Thu 4/21/16 Mon 5/23/16 27 days 34 De‐mod add‐ons Thu 4/21/16 Wed 4/27/16 5 days 32FS+8 days 35 Remove & relocate flight systems

Wed 4/27/16 Mon 5/9/16 10 days 36 Re‐install add‐ons Mon 5/9/16 Fri 5/13/16 5 days 37 Connect to C2 & FMV networks

Fri 5/13/16 Thu 5/19/16 5 days 38 Flight tests Thu 5/19/16 Mon 5/23/16 2 days 39 Operational Date Mon 5/23/16 Mon 5/23/16 0 days

FGCS #6

Thu 6/2/16 Tue 7/5/16 27 days 41 De‐mod add‐ons Thu 6/2/16 Wed 6/8/16 5 days 39FS+8 days 42 Remove & relocate flight systems

Wed 6/8/16 Mon 6/20/16 10 days 43 Re‐install add‐ons Mon 6/20/16 Fri 6/24/16 5 days 44 Connect to C2 & FMV networks

Fri 6/24/16 Thu 6/30/16 5 days 45 Flight tests Fri 7/1/16 Tue 7/5/16 2 days 46 Operational Date Tue 7/5/16 Tue 7/5/16 0 days

FGCS #7

Thu 7/14/16 Mon 8/15/16 27 days

7/5

Project Summary External Tasks

External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only

Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress

ID

Task Name Scheduled Start Scheduled Finish

Scheduled Duration

Predecessors

December 1 6/26 7/17 8/7

8/28 9/18

10/9 10/30 11/20 12/11 48 De‐mod add‐ons Thu 7/14/16 Wed 7/20/16 5 days 46FS+8 days 49 Remove & relocate flight systems

Wed 7/20/16 Mon 8/1/16 10 days 50 Re‐install add‐ons Mon 8/1/16 Fri 8/5/16 5 days 51 Connect to C2 & FMV networks

Mon 8/8/16 Fri 8/12/16 5 days 52 Flight tests Fri 8/12/16 Mon 8/15/16 2 days 53 Operational Date Mon 8/15/16 Mon 8/15/16 0 days

FGCS #8

Wed 8/24/16 Mon 9/26/16 27 days 55 De‐mod add‐ons Wed 8/24/16 Tue 8/30/16 5 days 53FS+8 days

8/15 56 Remove & relocate flight systems

Tue 8/30/16 Mon 9/12/16 10 days 57 Re‐install add‐ons Tue 9/13/16 Mon 9/19/16 5 days 58 Connect to C2 & FMV networks

Mon 9/19/16 Fri 9/23/16 5 days 59 Flight tests Fri 9/23/16 Mon 9/26/16 2 days 60 Operational Date Mon 9/26/16 Mon 9/26/16 0 days

9/26 61 Quality Control Inspection Schedule

Thu 10/1/15 Mon 9/19/16 290.2 days 62 FGCS 1 Inspection Thu 9/28/15 Thu 11/2/15 0 days 63 FGCS 2 Inspection Mon 1/11/16 Mon 1/11/16 0 days

64 FGCS 3 Inspection Tue 2/23/16 Tue 2/23/16 0 days

65 FGCS 4 Inspection Mon 4/4/16 Mon 4/4/16 0 days

66 FGCS 5 Inspection Fri 5/13/16 Fri 5/13/16 0 days

67 FGCS 6 Inspection Fri 6/24/16 Fri 6/24/16 0 days

68 FGCS 7 Inspection Fri 8/5/16 Fri 8/5/16 0 days

69 FGCS 8 Inspection Mon 9/19/16 Mon 9/19/16 0 days

6/24

8/5

9/19

Task Split Milestone Summary Project Summary External Tasks

External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only

Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress Attachment 1 Gantt Schedule, 8 Pages, Dated 16 Jul 15

25� Operational Date� Wed 3/2/16� Wed 3/2/16� 0 days� 24� 26�

FGCS #4�

Thu 3/10/16� Tue 4/12/16� 27 days� 27� De‐mod add‐ons� Thu 3/10/16� Wed 3/16/16� 5 days� 25FS+8 days� 28� Remove & relocate flight systems� Thu 3/17/16� Tue 3/29/16� 10 days� 27� 29� Re‐install add‐ons� Tue 3/29/16� Mon 4/4/16� 5 days� 28� 30� Connect to C2 & FMV networks� Mon 4/4/16� Fri 4/8/16� 5 days� 29� 31� Flight tests� Fri 4/8/16� Tue 4/12/16� 2 days� 30� 32� Operational Date� Tue 4/12/16� Tue 4/12/16� 0 days� 31� 33�

FGCS #5�

Thu 4/21/16� Mon 5/23/16� 27 days� 34� De‐mod add‐ons� Thu 4/21/16� Wed 4/27/16� 5 days� 32FS+8 days� 35� Remove & relocate flight systems� Wed 4/27/16� Mon 5/9/16� 10 days� 34� 36� Re‐install add‐ons� Mon 5/9/16� Fri 5/13/16� 5 days� 35� 37� Connect to C2 & FMV networks� Fri 5/13/16� Thu 5/19/16� 5 days� 36� 38� Flight tests� Thu 5/19/16� Mon 5/23/16� 2 days� 37� 39� Operational Date� Mon 5/23/16� Mon 5/23/16� 0 days� 38� 40�

FGCS #6�

Thu 6/2/16� Tue 7/5/16� 27 days� 41� De‐mod add‐ons� Thu 6/2/16� Wed 6/8/16� 5 days� 39FS+8 days� 42� Remove & relocate flight systems� Wed 6/8/16� Mon 6/20/16� 10 days� 41� 43� Re‐install add‐ons� Mon 6/20/16� Fri 6/24/16� 5 days� 42� 44� Connect to C2 & FMV networks� Fri 6/24/16� Thu 6/30/16� 5 days� 43� 45� Flight tests� Fri 7/1/16� Tue 7/5/16� 2 days� 44� 46� Operational Date� Tue 7/5/16� Tue 7/5/16� 0 days� 45� 47�

FGCS #7�

Thu 7/14/16� Mon 8/15/16� 27 days�