Attachment_1_Gantt_16_July_15.doc
DOC document 1 MB Posted
- Attached to
- Ground Control Station Conversion Federal contract opportunity
- Solicitation number
- FA4855-15-R-0007
About this file
Attachment 1 Gantt Schedule 16 Jul 15
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID
| Task Name |
| Scheduled Start |
| Scheduled Finish |
| Scheduled Duration |
| Predecessors |
September 2015
| July 11 |
| September 1 |
| October 21 |
| Dec |
| 6/14 |
| 7/5 |
| 7/26 |
| 8/16 |
| 9/6 |
| 9/27 |
| 10/18 |
| 11/8 |
| 11/29 |
| 1 |
| GCS Conversion Activities |
| Mon 9/28/15 |
| Tue 9/27/16 |
| 301.8 days |
| 2 |
| Expected Period of Performance |
| Mon 9/28/15 |
| Tue 9/27/16 |
| 301.8 days |
| 3 |
| GCS Conversions & Installation |
| Mon 9/28/15 |
| Mon 9/26/16 |
| 300.8 days |
12/
| 4 |
| Personnel & equipment staging |
| Mon 9/28/15 |
| Fri 10/30/15 |
| 28.6 days |
| 5 |
| FGCS #1 |
| Mon 11/2/15 |
| Mon 12/7/15 |
| 27 days |
| 6 |
| De‐mod add‐ons |
| Mon 11/2/15 |
| Fri 11/6/15 |
| 5 days |
| 4 |
| 7 |
| Remove & relocate flight systems |
| Fri 11/6/15 |
| Thu 11/19/15 |
| 10 days |
| 6 |
| 8 |
| Re‐install add‐ons |
| Thu 11/19/15 |
| Wed 11/25/15 |
| 5 days |
| 7 |
| 9 |
| Connect to C2 & FMV networks |
| Wed 11/25/15 |
| Thu 12/3/15 |
| 5 days |
| 8 |
| 10 |
| Flight tests |
| Thu 12/3/15 |
| Mon 12/7/15 |
| 2 days |
| 9 |
| 11 |
| Operational Date |
| Mon 12/7/15 |
| Mon 12/7/15 |
| 0 days |
| 10 |
| 12 |
| FGCS #2 |
| Wed 12/16/15 |
| Wed 1/20/16 |
| 27 days |
| 13 |
| De‐mod add‐ons |
| Wed 12/16/15 |
| Tue 12/22/15 |
| 5 days |
| 11FS+8 days |
| 14 |
| Remove & relocate flight systems |
| Tue 12/22/15 |
| Tue 1/5/16 |
| 10 days |
| 13 |
| 15 |
| Re‐install add‐ons |
| Tue 1/5/16 |
| Mon 1/11/16 |
| 5 days |
| 14 |
| 16 |
| Connect to C2 & FMV networks |
| Mon 1/11/16 |
| Fri 1/15/16 |
| 5 days |
| 15 |
| 17 |
| Flight tests |
| Tue 1/19/16 |
| Wed 1/20/16 |
| 2 days |
| 16 |
| 18 |
| Operational Date |
| Wed 1/20/16 |
| Wed 1/20/16 |
| 0 days |
| 17 |
| 19 |
| FGCS #3 |
| Fri 1/29/16 |
| Wed 3/2/16 |
| 27 days |
| 20 |
| De‐mod add‐ons |
| Fri 1/29/16 |
| Thu 2/4/16 |
| 5 days |
| 18FS+8 days |
| 21 |
| Remove & relocate flight systems |
| Thu 2/4/16 |
| Wed 2/17/16 |
| 10 days |
| 20 |
| 22 |
| Re‐install add‐ons |
| Wed 2/17/16 |
| Tue 2/23/16 |
| 5 days |
| 21 |
| 23 |
| Connect to C2 & FMV networks |
| Tue 2/23/16 |
| Mon 2/29/16 |
| 5 days |
| 22 |
| Project: GCS Conversions |
| Task |
External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start‐only Summary Inactive Summary Finish‐only Project Summary Manual Task Deadline External Tasks Duration‐only Progress
| ID |
| Task Name |
| Scheduled Start Scheduled |
Finish
| Scheduled Duration |
| Predecessors |
| July 11 |
| September 2015 September 1 |
| October 21 |
| Dec |
| 48 |
| De‐mod add‐ons |
| Thu 7/14/16 |
| Wed 7/20/16 |
| 5 days |
| 46FS+8 days |
| 6/14 |
| 7/5 |
| 7/26 |
| 8/16 |
| 9/6 |
| 9/27 |
| 10/18 |
| 11/8 |
| 11/29 |
| 49 |
| Remove & relocate flight |
| Wed 7/20/16 |
| Mon 8/1/16 |
| 10 days |
| 48 |
systems
| 50 |
| Re‐install add‐ons |
| Mon 8/1/16 |
| Fri 8/5/16 |
| 5 days |
| 49 |
| 51 |
| Connect to C2 & FMV |
| Mon 8/8/16 |
| Fri 8/12/16 |
| 5 days |
| 50 |
networks
| 52 |
| Flight tests |
| Fri 8/12/16 |
| Mon 8/15/16 |
| 2 days |
| 51 |
| 53 |
| Operational Date |
| Mon 8/15/16 |
| Mon 8/15/16 |
| 0 days |
| 52 |
| 54 |
| FGCS #8 |
| Wed 8/24/16 |
| Mon 9/26/16 |
| 27 days |
| 55 |
| De‐mod add‐ons |
| Wed 8/24/16 |
| Tue 8/30/16 |
| 5 days |
| 53FS+8 days |
| 10/1 |
| 56 |
| Remove & relocate flight |
| Tue 8/30/16 |
| Mon 9/12/16 |
| 10 days |
| 55 |
systems
| 57 |
| Re‐install add‐ons |
| Tue 9/13/16 |
| Mon 9/19/16 |
| 5 days |
| 56 |
| 58 |
| Connect to C2 & FMV |
| Mon 9/19/16 |
| Fri 9/23/16 |
| 5 days |
| 57 |
networks
| 59 |
| Flight tests |
| Fri 9/23/16 |
| Mon 9/26/16 |
| 2 days |
| 58 |
| 60 |
| Operational Date |
| Mon 9/26/16 |
| Mon 9/26/16 |
| 0 days |
| 59 |
| 61 |
| Quality Control Inspection |
| Thu 10/1/15 |
| Mon 9/19/16 |
| 290.2 days |
Schedule
| 62 |
| FGCS 1 Inspection |
| Thu 10/1/15 |
| Thu 10/1/15 |
| 0 days |
| 63 |
| FGCS 2 Inspection |
| Mon 1/11/16 |
| Mon 1/11/16 |
| 0 days |
| 15 |
| 64 |
| FGCS 3 Inspection |
| Tue 2/23/16 |
| Tue 2/23/16 |
| 0 days |
| 22 |
| 65 |
| FGCS 4 Inspection |
| Mon 4/4/16 |
| Mon 4/4/16 |
| 0 days |
| 29 |
| 66 |
| FGCS 5 Inspection |
| Fri 5/13/16 |
| Fri 5/13/16 |
| 0 days |
| 36 |
| 67 |
| FGCS 6 Inspection |
| Fri 6/24/16 |
| Fri 6/24/16 |
| 0 days |
| 43 |
| 68 |
| FGCS 7 Inspection |
| Fri 8/5/16 |
| Fri 8/5/16 |
| 0 days |
| 50 |
| 69 |
| FGCS 8 Inspection |
| Mon 9/19/16 |
| Mon 9/19/16 |
| 0 days |
| 57 |
Project: GCS Conversions
Task Split Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only
Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress
ID
Task Name Scheduled Start Scheduled Finish
Scheduled Duration
Predecessors
January 2016 May 2016 ember 11 February 1 March 21 May 11 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 1 GCS Conversion Activities Mon 9/28/15 Tue 9/27/16 301.8 days 2 Expected Period of Performance
Mon 9/28/15 Tue 9/27/16
301.8 days 3 GCS Conversions & Installation Mon 9/28/15 Mon 9/26/16 300.8 days 4 Personnel & equipment staging Mon 9/28/15 Fri 10/30/15 28.6 days
FGCS #1
Mon 11/2/15 Mon 12/7/15 27 days 6 De‐mod add‐ons Mon 11/2/15 Fri 11/6/15 5 days 7 Remove & relocate flight systems
Fri 11/6/15 Thu 11/19/15 10 days 8 Re‐install add‐ons Thu 11/19/15 Wed 11/25/15 5 days 9 Connect to C2 & FMV networks
Wed 11/25/15 Thu 12/3/15 5 days 10 Flight tests Thu 12/3/15 Mon 12/7/15 2 days 11 Operational Date Mon 12/7/15 Mon 12/7/15 0 days
FGCS #2
Wed 12/16/15 Wed 1/20/16 27 days 13 De‐mod add‐ons Wed 12/16/15 Tue 12/22/15 5 days 11FS+8 days 14 Remove & relocate flight systems
Tue 12/22/15 Tue 1/5/16 10 days 15 Re‐install add‐ons Tue 1/5/16 Mon 1/11/16 5 days 16 Connect to C2 & FMV networks
Mon 1/11/16 Fri 1/15/16 5 days 17 Flight tests Tue 1/19/16 Wed 1/20/16 2 days 18 Operational Date Wed 1/20/16 Wed 1/20/16 0 days
FGCS #3
Fri 1/29/16 Wed 3/2/16 27 days 20 De‐mod add‐ons Fri 1/29/16 Thu 2/4/16 5 days 18FS+8 days
1/20 21 Remove & relocate flight systems
Thu 2/4/16 Wed 2/17/16 10 days 22 Re‐install add‐ons Wed 2/17/16 Tue 2/23/16 5 days 23 Connect to C2 & FMV networks
Task Split
Tue 2/23/16 Mon 2/29/16 5 days External Milestone Inactive Task
Manual Summary Rollup Manual Summary Project: GCS Conversions
Milestone Summary Project Summary External Tasks
Inactive Milestone Inactive Summary Manual Task Duration‐only
Start‐only Finish‐only Deadline Progress
ID
Task Name Scheduled Start Scheduled Finish
Scheduled Duration
Predecessors
January 2016 May 2016 ember 11 February 1 March 21 May 11 12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 24 Flight tests Mon 2/29/16 Wed 3/2/16 2 days
3/2 4/12 5/23
Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only
Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress
| ID |
| Task Name |
| Scheduled Start Scheduled |
Finish
| Scheduled Duration |
| Predecessors |
| January 2016 ember 11 |
| February 1 |
| March 21 |
| May 2016 |
May 11
| 48 |
| De‐mod add‐ons |
| Thu 7/14/16 |
| Wed 7/20/16 |
| 5 days |
| 46FS+8 days |
| 12/20 |
| 1/10 |
| 1/31 |
| 2/21 |
| 3/13 |
| 4/3 |
| 4/24 |
| 5/15 |
| 6/5 |
| 49 |
| Remove & relocate flight |
| Wed 7/20/16 |
| Mon 8/1/16 |
| 10 days |
| 48 |
systems
| 50 |
| Re‐install add‐ons |
| Mon 8/1/16 |
| Fri 8/5/16 |
| 5 days |
| 49 |
| 51 |
| Connect to C2 & FMV |
| Mon 8/8/16 |
| Fri 8/12/16 |
| 5 days |
| 50 |
networks
| 52 |
| Flight tests |
| Fri 8/12/16 |
| Mon 8/15/16 |
| 2 days |
| 51 |
| 53 |
| Operational Date |
| Mon 8/15/16 |
| Mon 8/15/16 |
| 0 days |
| 52 |
| 54 |
| FGCS #8 |
| Wed 8/24/16 |
| Mon 9/26/16 |
| 27 days |
| 55 |
| De‐mod add‐ons |
| Wed 8/24/16 |
| Tue 8/30/16 |
| 5 days |
| 53FS+8 days |
| 56 |
| Remove & relocate flight |
| Tue 8/30/16 |
| Mon 9/12/16 |
| 10 days |
| 55 |
systems
| 57 |
| Re‐install add‐ons |
| Tue 9/13/16 |
| Mon 9/19/16 |
| 5 days |
| 56 |
| 58 |
| Connect to C2 & FMV |
| Mon 9/19/16 |
| Fri 9/23/16 |
| 5 days |
| 57 |
networks
| 59 |
| Flight tests |
| Fri 9/23/16 |
| Mon 9/26/16 |
| 2 days |
| 58 |
| 60 |
| Operational Date |
| Mon 9/26/16 |
| Mon 9/26/16 |
| 0 days |
| 59 |
| 61 |
| Quality Control Inspection |
| Thu 10/1/15 |
| Mon 9/19/16 |
| 290.2 days |
Schedule
| 62 |
| FGCS 1 Inspection |
| Thu 10/1/15 |
| Thu 10/1/15 |
| 0 days |
| 63 |
| FGCS 2 Inspection |
| Mon 1/11/16 |
| Mon 1/11/16 |
| 0 days |
| 15 |
| 1/11 |
| 64 |
| FGCS 3 Inspection |
| Tue 2/23/16 |
| Tue 2/23/16 |
| 0 days |
| 22 |
2/23
| 65 |
| FGCS 4 Inspection |
| Mon 4/4/16 |
| Mon 4/4/16 |
| 0 days |
| 29 |
4/4
| 66 |
| FGCS 5 Inspection |
| Fri 5/13/16 |
| Fri 5/13/16 |
| 0 days |
| 36 |
5/13
| 67 |
| FGCS 6 Inspection |
| Fri 6/24/16 |
| Fri 6/24/16 |
| 0 days |
| 43 |
| 68 |
| FGCS 7 Inspection |
| Fri 8/5/16 |
| Fri 8/5/16 |
| 0 days |
| 50 |
| 69 |
| FGCS 8 Inspection |
| Mon 9/19/16 |
| Mon 9/19/16 |
| 0 days |
| 57 |
Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only
Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress
ID
Task Name Scheduled Start Scheduled Finish
Scheduled Duration
Predecessors
September 2016 July 1
August 21
October 11
December 1 6/26 7/17 8/7
8/28 9/18
10/9 10/30 11/20 12/11 1 GCS Conversion Activities Mon 9/28/15 Tue 9/27/16 301.8 days 2 Expected Period of Performance
Mon 9/28/15 Tue 9/27/16
301.8 days 3 GCS Conversions & Installation Mon 9/28/15 Mon 9/26/16 300.8 days 4 Personnel & equipment staging Mon 9/28/15 Fri 10/30/15 28.6 days
FGCS #1
Mon 11/2/15 Mon 12/7/15 27 days 6 De‐mod add‐ons Mon 11/2/15 Fri 11/6/15 5 days 7 Remove & relocate flight systems
Fri 11/6/15 Thu 11/19/15 10 days 8 Re‐install add‐ons Thu 11/19/15 Wed 11/25/15 5 days 9 Connect to C2 & FMV networks
Wed 11/25/15 Thu 12/3/15 5 days 10 Flight tests Thu 12/3/15 Mon 12/7/15 2 days 11 Operational Date Mon 12/7/15 Mon 12/7/15 0 days
FGCS #2
Wed 12/16/15 Wed 1/20/16 27 days 13 De‐mod add‐ons Wed 12/16/15 Tue 12/22/15 5 days 11FS+8 days 14 Remove & relocate flight systems
Tue 12/22/15 Tue 1/5/16 10 days 15 Re‐install add‐ons Tue 1/5/16 Mon 1/11/16 5 days 16 Connect to C2 & FMV networks
Mon 1/11/16 Fri 1/15/16 5 days 17 Flight tests Tue 1/19/16 Wed 1/20/16 2 days 18 Operational Date Wed 1/20/16 Wed 1/20/16 0 days
FGCS #3
Fri 1/29/16 Wed 3/2/16 27 days 20 De‐mod add‐ons Fri 1/29/16 Thu 2/4/16 5 days 18FS+8 days 21 Remove & relocate flight systems
Thu 2/4/16 Wed 2/17/16 10 days 22 Re‐install add‐ons Wed 2/17/16 Tue 2/23/16 5 days 23 Connect to C2 & FMV networks
Task Split
Tue 2/23/16 Mon 2/29/16 5 days External Milestone Inactive Task
Manual Summary Rollup Manual Summary Project: GCS Conversions
Milestone Summary Project Summary External Tasks
Inactive Milestone Inactive Summary Manual Task Duration‐only
Start‐only Finish‐only Deadline Progress
ID
Task Name Scheduled Start Scheduled Finish
Scheduled Duration
Predecessors
December 1 6/26 7/17 8/7
8/28 9/18
10/9 10/30 11/20 12/11 24 Flight tests Mon 2/29/16 Wed 3/2/16 2 days 25 Operational Date Wed 3/2/16 Wed 3/2/16 0 days
FGCS #4
Thu 3/10/16 Tue 4/12/16 27 days 27 De‐mod add‐ons Thu 3/10/16 Wed 3/16/16 5 days 25FS+8 days 28 Remove & relocate flight systems
Thu 3/17/16 Tue 3/29/16 10 days 29 Re‐install add‐ons Tue 3/29/16 Mon 4/4/16 5 days 30 Connect to C2 & FMV networks
Mon 4/4/16 Fri 4/8/16 5 days 31 Flight tests Fri 4/8/16 Tue 4/12/16 2 days 32 Operational Date Tue 4/12/16 Tue 4/12/16 0 days
FGCS #5
Thu 4/21/16 Mon 5/23/16 27 days 34 De‐mod add‐ons Thu 4/21/16 Wed 4/27/16 5 days 32FS+8 days 35 Remove & relocate flight systems
Wed 4/27/16 Mon 5/9/16 10 days 36 Re‐install add‐ons Mon 5/9/16 Fri 5/13/16 5 days 37 Connect to C2 & FMV networks
Fri 5/13/16 Thu 5/19/16 5 days 38 Flight tests Thu 5/19/16 Mon 5/23/16 2 days 39 Operational Date Mon 5/23/16 Mon 5/23/16 0 days
FGCS #6
Thu 6/2/16 Tue 7/5/16 27 days 41 De‐mod add‐ons Thu 6/2/16 Wed 6/8/16 5 days 39FS+8 days 42 Remove & relocate flight systems
Wed 6/8/16 Mon 6/20/16 10 days 43 Re‐install add‐ons Mon 6/20/16 Fri 6/24/16 5 days 44 Connect to C2 & FMV networks
Fri 6/24/16 Thu 6/30/16 5 days 45 Flight tests Fri 7/1/16 Tue 7/5/16 2 days 46 Operational Date Tue 7/5/16 Tue 7/5/16 0 days
FGCS #7
Thu 7/14/16 Mon 8/15/16 27 days
7/5
Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only
Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress
ID
Task Name Scheduled Start Scheduled Finish
Scheduled Duration
Predecessors
December 1 6/26 7/17 8/7
8/28 9/18
10/9 10/30 11/20 12/11 48 De‐mod add‐ons Thu 7/14/16 Wed 7/20/16 5 days 46FS+8 days 49 Remove & relocate flight systems
Wed 7/20/16 Mon 8/1/16 10 days 50 Re‐install add‐ons Mon 8/1/16 Fri 8/5/16 5 days 51 Connect to C2 & FMV networks
Mon 8/8/16 Fri 8/12/16 5 days 52 Flight tests Fri 8/12/16 Mon 8/15/16 2 days 53 Operational Date Mon 8/15/16 Mon 8/15/16 0 days
FGCS #8
Wed 8/24/16 Mon 9/26/16 27 days 55 De‐mod add‐ons Wed 8/24/16 Tue 8/30/16 5 days 53FS+8 days
8/15 56 Remove & relocate flight systems
Tue 8/30/16 Mon 9/12/16 10 days 57 Re‐install add‐ons Tue 9/13/16 Mon 9/19/16 5 days 58 Connect to C2 & FMV networks
Mon 9/19/16 Fri 9/23/16 5 days 59 Flight tests Fri 9/23/16 Mon 9/26/16 2 days 60 Operational Date Mon 9/26/16 Mon 9/26/16 0 days
9/26 61 Quality Control Inspection Schedule
Thu 10/1/15 Mon 9/19/16 290.2 days 62 FGCS 1 Inspection Thu 9/28/15 Thu 11/2/15 0 days 63 FGCS 2 Inspection Mon 1/11/16 Mon 1/11/16 0 days
64 FGCS 3 Inspection Tue 2/23/16 Tue 2/23/16 0 days
65 FGCS 4 Inspection Mon 4/4/16 Mon 4/4/16 0 days
66 FGCS 5 Inspection Fri 5/13/16 Fri 5/13/16 0 days
67 FGCS 6 Inspection Fri 6/24/16 Fri 6/24/16 0 days
68 FGCS 7 Inspection Fri 8/5/16 Fri 8/5/16 0 days
69 FGCS 8 Inspection Mon 9/19/16 Mon 9/19/16 0 days
6/24
8/5
9/19
Task Split Milestone Summary Project Summary External Tasks
External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration‐only
Manual Summary Rollup Manual Summary Start‐only Finish‐only Deadline Progress Attachment 1 Gantt Schedule, 8 Pages, Dated 16 Jul 15
25� Operational Date� Wed 3/2/16� Wed 3/2/16� 0 days� 24� 26�
FGCS #4�
Thu 3/10/16� Tue 4/12/16� 27 days� 27� De‐mod add‐ons� Thu 3/10/16� Wed 3/16/16� 5 days� 25FS+8 days� 28� Remove & relocate flight systems� Thu 3/17/16� Tue 3/29/16� 10 days� 27� 29� Re‐install add‐ons� Tue 3/29/16� Mon 4/4/16� 5 days� 28� 30� Connect to C2 & FMV networks� Mon 4/4/16� Fri 4/8/16� 5 days� 29� 31� Flight tests� Fri 4/8/16� Tue 4/12/16� 2 days� 30� 32� Operational Date� Tue 4/12/16� Tue 4/12/16� 0 days� 31� 33�
FGCS #5�
Thu 4/21/16� Mon 5/23/16� 27 days� 34� De‐mod add‐ons� Thu 4/21/16� Wed 4/27/16� 5 days� 32FS+8 days� 35� Remove & relocate flight systems� Wed 4/27/16� Mon 5/9/16� 10 days� 34� 36� Re‐install add‐ons� Mon 5/9/16� Fri 5/13/16� 5 days� 35� 37� Connect to C2 & FMV networks� Fri 5/13/16� Thu 5/19/16� 5 days� 36� 38� Flight tests� Thu 5/19/16� Mon 5/23/16� 2 days� 37� 39� Operational Date� Mon 5/23/16� Mon 5/23/16� 0 days� 38� 40�
FGCS #6�
Thu 6/2/16� Tue 7/5/16� 27 days� 41� De‐mod add‐ons� Thu 6/2/16� Wed 6/8/16� 5 days� 39FS+8 days� 42� Remove & relocate flight systems� Wed 6/8/16� Mon 6/20/16� 10 days� 41� 43� Re‐install add‐ons� Mon 6/20/16� Fri 6/24/16� 5 days� 42� 44� Connect to C2 & FMV networks� Fri 6/24/16� Thu 6/30/16� 5 days� 43� 45� Flight tests� Fri 7/1/16� Tue 7/5/16� 2 days� 44� 46� Operational Date� Tue 7/5/16� Tue 7/5/16� 0 days� 45� 47�
FGCS #7�
Thu 7/14/16� Mon 8/15/16� 27 days�
File details come from the government source that posted it. Updated .