Attch_5_-_Schedule_of_Material_Submittals.xls

XLS spreadsheet 88 KB Posted

Attached to
Repair Apron & Trench Drain and Install Mooring Points
Solicitation number
FA4621-17-R-0003
Issued by

About this file

Attachment 5 - Schedule of Material Submittals

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
Repair Apron & Trench Drain - Install Mooring Points
(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATATEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
1Work Site Review Plan (Specs 01000-1.05-A)4Within 15 days after NTP
2Environmental Plans, Permits, Etc. (Specs 01000-1.06-A)415 days after NTP If Required
3Dust Control Plan (Specs 01000-1.06-B)4Within 15 days after NTP
4Material Safety Data Sheets (Specs 01000-1.06-D)4Within 15 days after NTP
5Recycled/Reclaimed Materials (Specs 01000-1.06-F)4At final inspection
6Quality Control Plan & Procedures (Specs 01000-1.09)4Within 15 days after NTP
7Record Drawings - Redlines Set (Specs 01000-1.10A)12 weeks prior to final inspection
8Record Drawings - Final CADD Electronic Record Set (Specs 01000-1.10C)3At final inspection
9Record Drawings - 22"x34" Mylars & 11"x18" Black-Line Paper Print (Specs 01000-1.10C)1At final inspection
10Geospatial Data (Specs 01000-1.11)1At final inspection
11Lockout/Tagout Procedures (Specs 01000-1.17)4Within 15 days after NTP
12Construction Site Plan (Specs 01000-1.22-B)4Within 15 days after NTP
13Demolition Procedures (Specs 02050-2 & 02051-2)415 days after NTP
14Field Soil Moisture-Density Tests (Specs 02221-3)41 day after testing
15Material Certification (Specs 02501-2.)415 days after contract award
16Equipment Approval (Specs 02501-4.)415 days after contract award
17Plant, Equpment (Specs 02513-2.3.)4415 days after contract award
18Mixing Plant (Specs 02513-2.4)4415 days after contract award
19Composition of Mixture & Aggregate Gradation (Specs 02513-2.1 thru 2.2.3.1)4415 days after contract award
20Aggregate Certification (Specs 02513-1.4.2)415 days after contract award
21Bituminous Materials Certification (Specs 02513-1.5)415 days after NTP
22Asphalt Cement Samples (Specs 02513-1.5)3As Required
23Q. C. Lab Qualification Statement (Specs 02513-1.6.1)4415 days after NTP
24Sampling & Testing (Specs 02513-1.2.6)4As Required
25Test Lab Certification (Specs 02515-1.3.2)415 days after contract award
26Aggregate Certifications (Specs 02515-1.4.1)415 days after contract award
27Portland Cement Certification (Specs 02515-1.4.1.3)415 days after contract award
28Admixture Certification (Specs 02515-1.4.1.4)415 days after contract award
29Curing Compound Certification (Specs 02515-1.4.1.5)415 days after contract award
30Epoxy-Resin Certification (Specs 02515-1.4.1.6)415 days after contract award
31Plant & Equipment (Specs 02515-1.6.1)415 days after contract award
32Cold Weather Requirements (Specs 02515-1.6.2.1)4Within 15 days after NTP
33Hot Weather Requirements (Specs 02515-1.6.2.2)4Within 15 days after NTP
34Alkali-Silica Reactivity (Specs 02515-2.1.3.1)415 days after contract award
35Mix Design, Tests & Certifications (Specs 02515-2.2)415 days after contract award
36Reinforcement & Tie Bars (Specs 02515-2.3.1)4Within 15 days after NTP
37Dowel Bars (Specs 02515-2.3.2)415 days after contract award
38Epoxy-Resin (Specs 02515-2.3.3)415 days after contract award
39Joint Filler (Specs 02515-2.3.4)415 days after contract award
40Curing Materials (Specs 02515-2.3.5)4Within 15 days after NTP
41Cement Bonding Grout (Specs 02515-2.3.6)415 days after contract award
42Lean Concrete or Econocrete (Specs 02515-2.3.7)415 days after contract award
43Quality Control Field Testing (Specs 02515-3.12)41 day after testing
44Installation Procedure & Equipment (Specs 02581-3.)44Within 15 days after NTP
45Samples & Certifications (Specs 02581-3.)4115 days after contract award
46Installation Procedure & Equipment (Specs 02582-3.)44Within 15 days after NTP
47Samples & Certifications (Specs 02582-3.)4115 days after contract award
48Manufacturer Product Description (Specs 02600-2.)44415 days after contract award
49MSPS Sheets (Specs 02600-2.)4415 days after contract award
50Personnel Certification (Specs 02600-2.)4415 days after contract award
51Certified Material Tests (Specs 02600-2.)415 days after contract award
52VOC Compliance & Certification (Specs 02600-2.)415 days after contract award

&CPage &P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

Enter any comments pertaining to the submittal