Amendment #1 to the solicitation (SF30) to update phasing and add new static ground rod effort.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Changes to SF 1442 Block 11:
- Period of performance increased to 215 days to address the new phasing.
Changes to Section F - Deliveries or Performance:
- CLIN delivery dates updated to 225 days ADC (includes 10 days to begin performance). FAR Clause 52.211-10 updated to reflect new period of performance of 215 days.
Changes to Section I - Contract Clauses:
- Added 2 new FAR Clauses: FAR 52.222-62 and FAR 52.224-3.
Changes to Section J - List of Documents, Exhibits and Other Attachments:
- Attachment 1 - Price Schedule updated to include the additional static ground rod effort.
- Attachment 2 - Statement of Work updated to address phasing changes and include replacement of static ground rods. Sections changed/added are 1.2, 2.2, 2.6, 9.1, and 13.6.1. All changes/additions are in red font.
- Attachment 4 - Draw ings pages 13-16 updated to address the phasing changes.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Mar-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA4621-17-R-0003
X 9B. DATED (SEE ITEM 11)
03-Mar-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Mar-2017
CODE
22D CONTRACTING SQUADRON - FA4621
53384 KANSAS ST STE 121
MCCONNELL AFB KS 67221-3702
FA4621 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA4621-17-R-0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The contractor period of performance end date has increased by 5 days from 210 days to 215 days.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
220 dys. ADC 1 22 CES/CENMP - F2Z39C
KEVIN WHALEN
BLDG 948
(PROGRAMS AND PLANS)
MCCONNELL AFB KS 67221
316-759-3871
FOB: Destination
F2Z39C
To:
225 dys. ADC 1 22 CES/CENMP - F2Z39C
BLDG 948
(PROGRAMS AND PLANS)
MCCONNELL AFB KS 67221
316-759-3871
The following Delivery Schedule item for CLIN 0002 has been changed from:
220 dys. ADC 1 22 CES/CENMP - F2Z39C
BLDG 948
(PROGRAMS AND PLANS)
MCCONNELL AFB KS 67221
316-759-3871
To:
225 dys. ADC 1 22 CES/CENMP - F2Z39C
BLDG 948
(PROGRAMS AND PLANS)
MCCONNELL AFB KS 67221
316-759-3871
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 215 calendar days thereafter. The time stated for completion shall include final cleanup of the premises.
(End of clause)
SECTION I - CONTRACT CLAUSES
The following have been added by reference:
52.222-62
52.224-3
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Price Schedule 1 17-FEB-2017
Attachment 2 Statement of Work 37 21-FEB-2017
Attachment 3 Specifications 43 23-FEB-2017
Attachment 4 Drawings 23 23-FEB-2017
Attachment 5 Schedule of Material
Submittals
3 17-FEB-2017
Attachment 6 Past Performance
Questionnaire (PPQ)
5 17-FEB-2017
Attachment 7 Wage Determination -
KS170020
5 06-JAN-2017
Attachment 8 Wage Determination -
KS170035
9 06-JAN-2017
to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Price Schedule 1 20-MAR-2017
Attachment 2 Statement of Work 39 20-MAR-2017
Attachment 3 Specifications 43 23-FEB-2017
Attachment 4 Drawings 23 20-MAR-2017
Attachment 5 Schedule of Material
Submittals
3 17-FEB-2017
Attachment 6 Past Performance
Questionnaire (PPQ)
5 17-FEB-2017
Attachment 7 Wage Determination -
KS170020
5 06-JAN-2017
Attachment 8 Wage Determination -
KS170035
9 06-JAN-2017
(End of Summary of Changes)