8_-_Amend_0002_list_of_changes_9_26_16.pdf

PDF 81 KB Posted

Attached to
Launch Operations Support Contract (LOSC)
Solicitation number
FA4610-15-R-0002
Issued by

About this file

Amend 0002 8 - List of Changes 26 Sep 16

View the file

Other files

File Type Posted
Released_ _Signed_FA4610-15-R-0002_Amend_0003.pdf PDF
FA4610-15-R-0002_Amend_0003.pdf PDF
8_-_Amend_0002_list_of_changes_9_26_16_R2.pdf PDF
6_-_Appendix_N_Equipment_List_for_Appendix_A_Bldgs_9_26_16.xlsx XLSX spreadsheet
7_-_3 _CDRL_A025_RCM_Plan.pdf PDF
2_-_0_RFP_Sol_FA4610-15-R-0002_9_26_16_Amend_0002.pdf PDF
7_-_2 _CDRL_A011_Quality_Management_Plan.pdf PDF
2_-_1_Sec_L_M _26_Sep_16.pdf PDF
7_-_1 _CDRL_A009_Program_Management_Plan.pdf PDF
5_-_Appendix_I_-_Service_Summary_Items_ _Objectives.pdf PDF
4_-_Appendix_A_-_Building_Listing_13Sept16.xlsx XLSX spreadsheet
9_-_Atch_10 _DB_WD_CA1600023_(Rev_12).pdf PDF
1_-_Amendment_0002.pdf PDF
7_-_5 _CDRL_A008_P_E_Responsibility_List.pdf PDF
3_-_Atch_1__LOSC_PWS_9_27_16.pdf PDF
7_-_4 _CDRL_A029_System_Safety_Program_Plan.pdf PDF
QAs_LOSC_Ind_day_26_Sep_16_final.pdf PDF
26_-_Bidders_Library _Crane_Hook_Inspections_3.pdf PDF
25_-_Bidders_Library _Crane_Hook_Inspections_2.pdf PDF
24_-_Bidders_Library _Crane_Hook_Inspections_1.pdf PDF
27_-_Bidders_Library _Crane_Hook_Inspections_4.pdf PDF
1_-_List_of_Changes_to_L_M_9_13_16.pdf PDF
2_-_List_of_Changes_to_the_PWS_9_13_16.pdf PDF
23_-_LOSC_Industry_Day_Slides_18_Aug_16.pdf PDF
18_-_Atch_9 _CBA_WD_2005-3169 _2_pgs.pdf PDF
14_-_Atch_10 _DB_WD_CA160023 _rev_10.pdf PDF
5_-_Appendix_C _D _E _F _G.xlsx XLSX spreadsheet
20_-_Bidders_Library_LOSC_Workload_Data_r1.xlsx XLSX spreadsheet
1_-_Amend_0001_FA4610-15-R-0002.pdf PDF
7_-_Appendix_J_-_MDA_Launch_Communication_Systems.xlsx XLSX spreadsheet
12_-_Amendment_0001 _Atch_2 _CDRLs _A003 _A008 _A009 _A011 _A025_A029.pdf PDF
19_-_Atch_10 _DB_WD_CA160023 _rev_10.pdf PDF
22_-_Appendix_A_-_Building_Listing_13Sept16.xlsx XLSX spreadsheet
15_-_Atch_14 _LOSC_QASP_19_Aug_16_fixed_pg_numbers.pdf PDF
3_-_Atch_1_DRAFT_LOSC_PWS_9_12_16.pdf PDF
16_-_Atch_9 _CBA _2005-3169 _with_Appendix_A _51_pgs _redacted.pdf PDF
4_-_Appendix_B_-_Equip_List_Other_Than_Appendix_A_Bldgs.xlsx XLSX spreadsheet
21_-_Bidders_Library _LOSC _Boiler_PMI_-_PM040024.pdf PDF
10_-_Appendix_N_Equipment_List_for_Appendix_A_Bldgs.xlsx XLSX spreadsheet
17_-_Atch_9 _APPENDIX_B_-_Wage_Rate_Tables_(2014-2019)_Redacted _2_pgs.pdf PDF
List_of_Documents_posted_to_FBO_Solicitation.pdf PDF
13-1 _Amendment_0001 _Atch_4 _LOSC_DD254_Continuation_Page.pdf PDF
9_-_Appendix_M_Real_Property_Report.xlsx XLSX spreadsheet
2_-1 _Sec_L_M_12_Sep_16_lh_ntc_r2.pdf PDF
8_-_Appendix_L_-_Government_Furnished_Equipment.xlsx XLSX spreadsheet
13_-_Amendment_0001 _Atch_4 _LOSC_Solicitation_FA4610-15-R-0002_DD254_7Sep16.pdf PDF
11_-_Appendix_O_-_Glossary.pdf PDF
2_-_Final_RFP_Solicitation_FA4610-15-R-0002_12_Sep_16.pdf PDF
6_-_Appendix_I_-_Service_Summary_Items_Objectives.pdf PDF
Atch_3_DIDs _LOSC.pdf PDF
Show 40 more

Latest 50 of 128 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA4610-15-R-0002, LOSC, List of Changes in Documents, Amendment 0002

# Document Changes

1. RFP, Sections A-M, 22 Sep 16 Section A, Number of pages changed from 91 to 100

2. Block 9, offers due date is changed from 04 Oct 16 to 11 Oct 16

3. Pg 48, Section I Contract Clauses added 52.203-14, 52.204-2, 52.204-2 Alt II, 52.215-2, Alt II & Alt III,

4. Pg 50, added clause 52.233-1, Alt I

5. Pg 51, added clauses 252.203-7998 (Dev), 252.204-7005, 252.222-7006.

Deleted clause 252.244-7000.

6. Pg 57, added clause 52.222-35.

7. Pg 58, added clause 52.222-36.

8. Pg 76, added clause 5352.204-9000

9. Pg 77, added clause 5352.223-9000

10. Pg 78, added clauses 5352.223-9001, 5352.242-9000

11. Pg 79, added clause 5352.242-9001

12. Pg 81, Section J, Atch 1, date for PWS changed from 9/12/16 to 9/16/16

13. Pg 82, Section K, added clause 52.204-17

14. Pg 83, added clause 52.204-8

15. Pg 98, Section L, deleted clause 52.222-46; added clause 252.209-7992 (Dev)

16. All pages, added Amendment 0002 with the page numbering

17. Sections L&M, 26 Sep 16 Para L-4.2, ** Page limit………., deleted Property Management Plan.

18. Para L-6.2 Deleted “A Technical Reference Library has been set up at Vandenberg AFB. The Technical Reference Library contains an in depth paper on the South Vandenberg Power Plant (SVPP) and additional information concerning equipment and specifications listed under paragraph L-6.6, Sub Factor 2— Operations Approach.”

19. Para L-6.4.2(2), changed “….please provide a subcontractor plan.” to “…..please submit your subcontractor’s information, if applicable.”

20. Added Amendment 0002 to footer

21. Atch 1, PWS, 22 Sep 16 Cover Page: Updated date from 15 August to 27 Sept 2.3.7: Removed reference to contract Work Request 2.6.2: Updated ISO reference to 9001-2015 5.1: Typo corrected 6.13.1: Updated acronym from Interim to Integrated 6.13.4: Corrected numbering, previously had two 6.13.3s 6.14.5: Corrected numbering, previously was 6.15.5

7.2 Section: Updated Title, restructured sub-numbering scheme to better clarify requirements 7.2.1.1: Added MDA specific Response and Restoral times

Solicitation FA4610-15-R-0002, LOSC, List of Changes in Documents, Amendment 0002

# Document Changes

7.2.1.8: Added IMDS requirement 7.2.1.9: Removed photography support 8.2: Removed GMD quality program requirement 8.8.1.2: Removed BOSWAM reference 8.8.2: Removed ‘and cost’ requirement 9.1: Removed old PTO references, added PTO 13968

22. Atch 2, CDRLs A009, submission date changed from 15 May to 60 DAC

23. A011, first submission has been changed from See Block 16 to 60 DAC with a frequency of One time and revisions.

24. A025, Block 12 has been revised from See Block 16 to 365 Days After Contract (award). Blk 16, Blk 8, has been updated to remove the inadvertent reference to the EPP.

25. A029, frequency has been changed from Weekly to One time and revisions

26. A008, Block 11 changed from 30 Jun to N/A.

27. Appendix A Updated cover page date, removed B974, removed repetitive listings of 763, removed B1777 from CLIN 1

28. Appendix I Updated cover page date, updated PWS para reference for performance objective B, C, D, E, F, G, and H

29. Appendix N Cypress Ridge asset was moved from Appendix N to Appendix B.

All Ewa Beach references were removed.

Lions Hd was relocated from Appendix N to Appendix B.

Miguelito Canyon Antenna support structure and wind hut were relocated from appendi N to appendix B.

Molokai Station was removed from Appendix N.

Oak Mountain facilities not listed in Appendix A were moved to Appendix B.

Point Conception asset was removed from Appendix N, already listed in B.

Purisma Point removed from Appendix N, already listed in B.

San Luis Light Station was removed from Appendix N, already listed in B.

All B731 assets moved from Appendix N to Appendix B.

Tran Peak assets moved from Appendix N to Appendix B.

X-37 Mob Recov Ops Cnter moved from Appendix N to appendix B.

Removed Load Weight Yard and SLC-3 “Facility” from Appendix N